Outline Terms of Reference for Design and Supervision ... · Outline Terms of Reference for Design...

27
Government of Sri Lanka MINISTRY OF LOCAL GOVERNMENT AND PROVINCIALCOUNCILS Outline Terms of Reference for Design and Supervision Consultants PURA NEGUMA Local Government Enhancement Sector Project (LGESP) (Asian Development Bank Assisted Loan No. 2790 SRI) Project Office Project Management Unit, 27/2, Rosmead Place Colombo 07 Email: [email protected]

Transcript of Outline Terms of Reference for Design and Supervision ... · Outline Terms of Reference for Design...

Government of Sri Lanka

MINISTRY OF LOCAL GOVERNMENT AND PROVINCIALCOUNCILS

Outline Terms of Reference for Design and Supervision Consultants

PURA NEGUMA Local Government Enhancement Sector Project (LGESP) (Asian Development Bank Assisted – Loan No. 2790 SRI)

Project Office Project Management Unit,

27/2, Rosmead Place Colombo 07

Email: [email protected]

OUTLINE TERMS AND REFERENCE OF DESIGN AND SUPERVISION CONSULTANTS – PURA NEGUMA (LOCAL GOVERNMENT ENHANCEMENT

SECTOR PROJECT) (Indicative) 1. Background:

The outcome of the project will be improved local infrastructure and services delivered effectively by local authorities in less-developed areas of Sri Lanka. Under the project, about 108 local authorities selected in seven provinces (excluding the Northern and Eastern provinces), whose reform plans would be reviewed and confirmed by the government will implement subprojects for roads and bridges, water supply and sanitation, drainage, solid waste management, and other basic facilities, including building or enhancing health-care centers and public markets. The project will also support the institutional strengthening of the local authorities for improved and sustainable service delivery through business process reengineering and the development of their information technology (IT) systems. To achieve the aims and objectives, the project addresses to support the selected local authorities through three components. Viz., Component 1: Local Government Infrastructure and Service Delivery Improvement Component 2: Local Government Policy Reform and Capacity Building Support Component 3: Project Management and Administration Support As part of project preparatory work, based on the selection criteria1 for sub projects and through an inclusive planning and consultative process, a set of financially sustainable priority infrastructure projects have been identified and indicative costs estimated. The indicative list of sub-projects identified as mentioned above is given vide Annexure 1. However, it should be noted that these projects have to be got formally concurred by ADB with justification wherever necessary and likely to change. The support for investment is linked to commitment to a set of reforms by the Local Authorities. This will be facilitated by administrative and management reforms by the Government. The Project also supports project design and management through consulting services. The scope of the consulting services is to support the LA’s as in Annexure 1 in design and implementation / construction of investments in this sector.

2. Objective:

The objectives of the consultancy are:

Assess

i. With regard to sub projects identified, update the present status of the service sector (s) in the local authority area;

ii. the technical feasibility inclusive of financial, economic, environmental and social analysis;

Prepare:

iii. based on prefeasibility, Prepare feasibility report, detailed design, drawings, cost estimates and bidding documents for planning and implementation of subprojects including environmental management measures, resettlement/ indigenous people and other social actions if any.

1 Eligible subprojects include (i) environmental infrastructure such as water supply and sanitation

(including sewerage), drainage, and solid waste management; (ii) economic infrastructure such as roads and bridges (including suspension bridges); (iii) public health infrastructure such as maternity and health centers; and (iv) other local authority facilities such as public markets (pola)

Supervise:

iv. Implementation of physical work and compliance to design standards, environmental plan, resettlement plans and social/ indigenous people’s plans if any.

3. General Scope of Work

1) The scope of work mainly but not limited to includes services as indicated below for the local authorities and indicative sub project list as mentioned in Annexure 1.

2) Based on the pre-feasibility studies available, the Design and Supervision Consultant (DSC) is required to carryout a feasibility study (Sub project feasibility should include technical, financial and economic analysis, and preparation of safeguard documents in compliance with ADB requirements) and detailed engineering design, Prepare Detailed Project Report including environmental and social and financial /economic feasibility and prepare bidding documents for the project in compliance with ADB requirements. If the Local Authorities change the sub-projects due to the change in their preferences, it is the responsibility of the DSC to even conduct a pre-feasibility studies of the new projects and prepare prefeasibility report and then proceed with the other work as indicated in this ToR.

3) The overall design would cater for a period of over 30 years/ horizon as defined as

per national planning norms and a projected population as determined by the consultant based on appropriate projection techniques. The designs shall conform to relevant/ latest applicable National Standards and CEA requirements. Wherever such standards are not available, appropriate standards shall be followed in discussion with the PMU.

4) In addition, the DSC shall follow the requirements of the following documents in

carrying out the services:

a) Resettlement Framework and Environmental Assessment and Review Framework of the project; and

b) Standard Bidding Documents for Procurement of goods and Works by

ADB and of the Project

c) Checklists – Feasibility Checklists, Sector Specific Checklists and Detailed Design Checklist designed for the Project

d) Consultation Plan prepared for the project

5) The DSC needs to check that the subprojects selected meet the sub project selection criteria for the Project and reflect priorities and action in relation to the consultation and planning guideline of the Project and take into account the budget availability of each local authority.

6) Collect and update information regarding service levels in the study area including

inventory of existing systems.

7) Collect necessary data for design and implementation. The details given in the pre-feasibility study, is only a reasonable preliminary basis.DSC shall be wholly responsible for all the details provided in their reports on physical and site conditions, the execution methodology, and various other parameters etc. All data utilized in preparation of the reports shall be presented indicating the sources of the data and also the basis of assumptions, if any. i.e The consultant shall be responsible for all the data or designs and drawings given by them.

8) Carry out topographical survey with reference to specified datum as required for the service up gradation and necessary geotechnical investigations. The local body shall indicate the Project sites and their measurements. The consultant shall be responsible for its verification and mapping. Soil tests as per relevant National Standards have to be conducted and necessary reports prepared by consultants to arrive at design parameters.

9) Prepare Detailed Project Report (DPR) inclusive of detailed cost estimates using the

latest schedule of rates of the Province. Estimate associated costs such as road restoration charges/ shifting of utilities, resettlement etc. There should not be any lump sum items in the bill of quantities. For items not covered under schedule of rates, market rates to be assessed.(Necessary documents on quotations received should be made for assessment of market rates) and also prepare contract packaging plan.

10) For the given purpose and functional use of the respective sub-projects, proper

design has to be developed. The consultants have freedom to choose the type of sub structure and superstructure, provided National code specifications and standards are met. The drawings and designs shall include a general arrangement drawing and a detailed longitudinal section drawing of all components in size A1 or A2. The level of detailing shall be such so as to enable check of conformance with code provisions, including detailed construction drawings and bar bending schedules. The responsibility of the preparation and issue of detailed construction drawings is that of the Design and Supervision Consultants.

11) Assist completely in bidding, bid evaluation and award process in procurement of

works, goods and materials in accordance to guidelines of ADB.

12) DSC needs to prepare project Implementation schedule and budget with monthly targets, furnish network analysis such as Critical Path Matrix/ Program Evaluation and Review Technique (CPM / PERT) for purposes of effective project monitoring and regular reports.

13) Carrying out social impact assessments of proposed development including land acquisition and its financial implication, and if found necessary, prepare a Resettlement Plan and/or an indigenous peoples plan in accordance with the resettlement framework (RF) and indigenous peoples planning framework (IPPF) agreed upon between the Government of Sri Lanka and ADB;

14) If found necessary, prepare necessary environmental assessment reports such as an

Initial Environmental Examination or Environmental Impact Assessment, in compliance with the environmental assessment and review framework (EARF) agreed upon between the government and ADB;

15) Prepare community development and public awareness programs, and identify

training requirements if any as necessary for the subproject construction, operation and maintenance.

16) Prepare action plan and report on implementing relevant part of the gender action plan of the project.

17) The consultant shall conduct his own studies and prepare estimates based on

schedule of rates. The PMU, SPCU as well as the LA concerned and Project Management Consultants shall not be responsible (except as to risks specifically accepted under the conditions of contract) for the validity of the project details and designs and estimates.

18) The consultants shall assist the Local Authority in obtaining technical sanction from competent authorities.

19) The DSC shall mobilize exclusive supervision staff for the supervision of construction including comprehensive quality checks and measurements of works including checking the invoices sent by the contractor. The DSC is also responsible for certifying the quality of works.

20) Supervision Tasks include:

a) Construction Supervision: Supervise construction of project components, monitor

construction and quality control methods, assist to record measurements in accordance with the procedures followed in the Government, certify that quality of works conform to the specifications and drawings, assess the adequacy of the contractors' inputs in material, labor and construction method, furnish all revisions and detailed construction drawings as necessary during the continuance of the contract, attend third party inspections as necessary, check contractors' design and drawings for lump sum turnkey contracts, examine contractors' claim for extension of time and extra works, etc. and prepare recommendation for approval of Local Authorities / SPCUs.

b) Check installation and commissioning, prepare measurement for works completed

and in progress and certify bills for payment to the contractors/suppliers. Ensure that works are constructed to the prescribed quality in accordance with specifications in tender documents and quality assurance system;

c) As required, assist the LAs / SPCUs in the resolution of contractual issues including

review, evaluation and confirmation of contract Variation Orders;

d) As necessary, assist the SPCUs / LAs with overall contract management and approving of the ''as built" drawings as prepared by the Contractors.

e) Prepare inception report, monthly/quarterly progress reports and project completion

report;

f) Conduct and supervise the implementation of training programs, in collaboration with the contractors, to strengthen the capacity of staff involved in operation and management of the new system, including the operation of facilities and equipment.

g) Provide necessary advisory support to the local authority about the institutional

arrangement for Operation and Management.

h) Assist SPCUs in the preparation of plan of action for the subprojects for presentation to Local Authorities and get their consent.

i) Prepare a simplified quality control manual for use of the field staff;

j) Assist SPCU to undertake other tasks as assigned by the PMU

k) Preparation of O & M plans for all the assets created in the project.

l) Preparation of the sub project completion report in the format provided by the PMU.

4. Data, services and facilities to be provided by the client

The maps and other data related to this work, to the extent available in the town office will be provided.

5. Schedule of completion of tasks

All feasibility and designs work including the Detailed Project Reports and the Bid documents to be completed within 6 months of the assignment with the atleast one subproject completed within one month of award of contract. The supervision work should commence after award of work. The project closing period is 30 June 2015 and all works to be completed atleast 2 months before the project completion period to facilitated completion work and processing of final bills and payments to be made within the project closing period.

6. Procedure for Technical Sanction and Administrative Approval:

The Technical Evaluation Committee of the province under the project scrutinize the designs and estimates and finally give technical sanction for the sub-project and the Procurement Committee under the chairmanship of the Chief Secretary will issue the Administrative Approval for the Project.

Annexure 1 Local Authorities Covered under the Project and Initial Subproject Identified

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

Central Province (For Package DSC - 01)

1 Gurudeniya, Gangawata Korale, Kandy 1

Construction of a multi-purpose building for auditorium, library, Montessori, clinic and Ayurvedha with a children’s park

50

Total 50

2 Barigama, Harispattuwa, Kandy 1

Construction of PS office Building including auditorium and Library

43

Total 43

3 Theldeniya, Medadumbara, Kandy 1 Development of Daily fair 48.5

Total 48.5

4 Hasalaka, Minipe, Kandy 1 Multipurpose building 48.5

Total 48.5

5 Panwila, Panvila, Kandy

1 Huluganga Bridge 19

2 Health Centre 16

3 Construction of 2nd Phase of PS Building including Auditorium and Library

13.5

Total 48.5

6 Galaha, Pathahewaheta, Kandy 1

Construction of Multipurpose buildig including PS office and Library and Auditorium

50

Total 50

7 Udadumbara, Udadumbara, Kandy

1 Improvemntg to existing water supply project 11

2 Pola Hunnasgiriya 37.5

Total 48.5

8 Doluwa, Udapalatha, Kandy 1 Water supply project 48.5

Total 48.5

9 Metihakka, Ambanganga Korale, Matale 1

Construction of multi-purpose Building (Auditorium, Library, Computer centre) with a children park

46.5

Total 46.5

10 Kalu Ganga Nuwara Kadey, Laggala-Pallegama, Matale

1 Construction of public toilet facilities 2.5

2 Construction of a weekly fair 10.5

3 Construction of Internal Road and Drainage System 13

4 Water supply project 22.5

Total 48.5

11 Naula, Naula, Matale 1

Improvements to PS office building with Ayuruweda medical centre, IT centre

48.5

Total 48.5

12 Raththota, Rattota, Matale

1 Construction of Library Building 23.5

2 Construction of the Bus stand (land to be transferd fron PRDA)

10

3 Development of Pola 15

Total 48.5

13 Hettipola, Wilgamuwa, Matale

1 Construction of a water supply project for the Hettipola Town

10

2 Development of the weekly fair 10

3 Construction of crematorium 10

4 Improvemnts to the PS office building (Auditorium) 18.5

Total 48.5

14 Elakkaraya, Yatawatta, Matale

1 Construction of PS Building upper floor 25

2 Construction of Library Building 21.5

Total 46.5

15 Maskeliya, Ambagamuwa, Nuwara Eliya

1 Construction of the Internal Roads under the PS area (Maskeliya town)

25

2 Development of Public Toilet 8

3 Construction of sub office and Library 14.3

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

Total 47.3

North Central Province (For Package DSC - 02)

1 Galenbindunuwewa, Galenbindunuwewa,Anuradhapura

1 Construction of a multipurpose building city hall with a podium,Library,Montisoory with a Children's Park

20.4

2 Construction of bus stand 8

3 Costruction of Ps building 6

4 Improvements to existing water supply 14

Total 48.4

2 Bulnewa Galnewa 1 Construction of Drainage System & pavement 14

Total 14

4 Mahailluppallama Ipalogama Anuradhapura

1 Multipurpose Building 44.5

Total 44.5

3 Horoupathana, Horoupathana, Anuradhapura

1 Construction of a multipurpose building with a Children's Park

24

2 Development of busstand 21.84

Sub total 45.84

5 Kebithigollawa Kebithigollawa Anuradhapura

1 Construction of a multipurpose building with a Children's Park (Auditorium with a podium,Day care centre,Montisoory )

29.4

2 Development oftheWeekly Pola 16

Total 45.4

6 Parakramapura, padaviya, Anuradhapura

1 Construction of a multipurpose building with a Children's Park (PS Sub Office Auditorium with a podium,Day care centre,Montisoory,Library )

16

3 Construction of Internal roads leading to Apayapura Janapadaya from Prakramapurawith drainagesystem

30.5

Total 46.5

7 Andiyagala,Palagala, Anuradhapura

1 Construction of a multipurpose building city hall with a podium,Montisoory with a Children's Park

28.3

2 Development oftheWeekly Pola 18

Total 46.3

8 Pahekanuwa, Rajangane,Anuradhapura

1 Construction of Drainage System & pavement 18

2 Development oftheWeekly fair in a new land 30.5

Total 48.5

9 Rambewa,Rambewa,Anuradhapura

1 Construction of a multipurpose building ( Auditorium with a podium,Library )

30

2 Development of the Weekly fair with toilet facility 20

Total 50

10 Thiappane, Thirappane,Anuradhapura 1 Construction of a city hall with a podium,Library 45.77

Total 45.77

11 Aralaganwila, Dibulagala,Polonnaruwa

1 03 Water projects, Nuwaragala WS-22,Wehangala WS-11, Siripura WS11

45.77

2 Development of the Weekly fair with toilet facility 6

Total 51.77

12 Thalpotha,Lankapura,Polonnaruwa

1 Development of busstand & public toilet facility 21.4

2 Construction of Internal roads infront of Rathnasal vidyalaya

10.5

3 Development oftheWeekly Pola 15

Total 46.9

North Western Province (For Package DSC - 03)

1 Giribawa, Giribawa, Kurunegala 1 Construction of Bus stand and drainage 18

Total 18

2 Kithalawa,Kuliyapitiya, Kurunegala 1 PS office with Library and Health Clinics 48.5

Total 48.5

3 Polpithigama, Polpithigama, Kurunegala 1 Multipurpose Building 18.8

Total 18.8

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

4 Udubaddawa, Udubaddawa, Kurunegala 1 Multipurpose Building 50

Total 50

5 Arachchikattuwa, Arachchikattuwa, Puttalam

1 Development of weely fair and drainage system 38

2 Construction of Library 12

Total 50

6 Madampe, Chilaw, Puttalam 1

Construction of multipurpose building Maternity Centre and health service centre

25.5

Total 25.5

7 Norochcholai, Kalpitiya, Puttalam

1 Construction of Library building 19

2 Development of drainage system and pavement 4

3 Development of Public Toilet facility 3.2

4 Community Hall 16.8

Total 43

8 Nawagathegama, Nawagathegama, Puttalam

1 Development of weekly fair and drainage system 10

2 Construction of multipurpose building 20

3 Development of bus stand and public toilet 20

Total 50

9 Wanathavilluwa, Wanathavilluwa, Puttalam

1 Construction of water supply scheme 22.7

Total 22.7

Sabaragamuwa Province (For Package DSC - 04)

1 Dippitiya, Aranayaka, Kegalla

1 Construction of a Multi Purpose building (Pradeshiya Sabha office, Library, Ayuruweda)

35.3

2 Development of Weekly Fair 10

3 Development of Public Toilet facilities 2

Total 47.3

2 Bulathkohupitiya, Bulathkohupitiya, Kegalla

1 Construction of weekly fair 10

2 Improvements to the Internal roads leading to compost Plant

6

3 Development of Public Toilet facility 4

4 Construction of a Multi Purpose Building (Clinic, Ayuruweda, Montessori)

30

Total 50

3 Dehiowita, Dehiovita, Kegalla 1 New Projects to be identified 50

Total 50

4 Deraniyagala, Deraniyagala,Kegalla

1 Development of the Drainage system & the Pavementand entrance road

10

2 Construction of a Multi -purpose building (Library, Montessori, Day Care centre along with a children park)

40

Total 50

5 Galigamuwa, Galigamuwa, Kegalla

1 Development of the Drainage system & the Pavement 8

2 Development of Weekly Fair 5

3 Improvement to the Bus stop (shelters) on Ratnapura road

5

4 Construction of PS Building 16

5 Improvements to crematorium(entrance road) 10

6 Solid Waste management(compost plant) 6

Total 50

6 Moronthota, Kegalla, Kegalla

1 Construction of weekly fair (Only Pola recommended in ground floor)

15

2 Construction of a Multi -purpose building (Library, Montessori, clinic

35

Total 50

7 Yatiyantota(Kithulgoda), Yatiyanthota, Kegalla

1 Construction of weekly fair & public toilet for 50 Million 45.8

Total 45.8

8 Ayagma, Ayagama, Ratnapura 1 Development of Public Toilet facility 2

2 Construction of a Multi -purpose building 38

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

Total 40

9 Waylioya, Balangoda, Ratnapura

1 Construction of a Multi -purpose building (community hall - event & conference room, Library, ayuruweda clinic, stores in the lower level)

27

2 Compost Project 5

3 Development of the Drainage system & the Pavement 14

4 Improvement to the bus stand 4

Total 50

10 Udawalawa, Embilipitiya, Ratnapura

1 Construction of Internal roads within the town 10.5

2 Construction sub office and library 20

Total 30.5

11 BelihulOya, Imbulpe, Ratnapura

1 Construction of a Multi -purpose building. (library, clinic, ayuruweda, Montessori)

39

2 Construction of Internal roads with drainage systems. 3

3 Construction of weekly fair 8

Total 50

12 Kahawaththa, Kahawatta, Ratnapura 2 Development of the Drainage system 18

Total 18

13 Kolonne, Kolonna, Ratnapura

1 Construction of a Multi Purpose building (PS office , library in upstairs and a few shops)

34.5

2 Development of Public Toilet facility 2

3 Construction of weekly fair 10

Total 46.5

14 Pelmadulla, Pelmadulla, Ratnapura 1 Construction of a Multi -purpose building with weekly fair 46.5

Total 46.5

15 Ratnapura New Town, Ratnapura, Ratnapura

1 Drainage System 2

2 Multipurpose building 42

3 Three wheel park 2.5

Total 46.5

Southern Province (For Package DSC - 05)

1 Urugasman handiya, Karandiniya, Galle

1 Community Building 12.5

2 Multipurpose Building 25

3 Drainage System 8

4 Toilet Complex 3

Total 48.5

2 Udugama, Nagoda, Galle

1 Multipurpose Building 24

2 Development of Weekly fair 25.5

Total 49.5

3 Neluwa, Neluwa, Galle

1 Construction of multipurpose building 20

2 Internal Roads 10

3 Development of weekly fair 10

4 Development of three wheel park 6.5

Total 46.5

4 Ethkandura, Welivitiya-Divithura, Galle 1 Multipurpose Building 45

Total 45

5 Kirama, Katuwana, Hambantota

1 Construction of Bus Stand(Bulding with upstairs) 40.5

2 Improvement to Solid waste management system 6

Total 46.5

6 Thibbatuwaawa, Athuraliya, Matara

1 Thibbotuwawa Weekly Fair 20

2 Construction of suspension bridge(Haranamulla) 30

Total 50

7 Hakmana, Hakmana, Matara

1 Develpoment of the drainage system & the pavement 12

2 Development of the roads leading out of the town up to agreed distance(Only the roads which belong to PS)

26.5

3 Construction of compost plant 5

4 Meella Water Supply 5

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

Total 48.5

8 Deniyaya, Kotapola, Matara 1 Improvements to the PS building 48.5

Total 48.5

9 Malimbada, Malimbada, Matara 1

Construction of PS office building along with the library and an auditorium

50

Total 50

10 Pitabeddara, Pitabeddara, Matara

1 Improvement to the water supply project 5

2 Weekly fair 32

3 Construction of multi-purpose building( HR development Center)

8

Total 45

11 Thihagoda, Thihagoda, Matara

1 Construction of the weekly fair 23.5

2 Construction of new PS office building 23

3 Construction of Public Toilet Facility 2

Total 48.5

12 Thawalama Western, Thawalama, Galle 1

Bus Stand 30

Development of Weekly fair and related roads 20

Total 50

Uva Province (For Package DSC - 06)

1 Udawela, Badulla, Badulla 1

Construction of a Multi Purpose Building ( PS office , Library, Ayuruweda, )

50

Total 50

2 Heeloya, Bandarawela, Badulla

1 Construction of Weekly Fair 6.6

2 Construction of water Project near office 2.00

3 Construction of PS office Building with Library 36.9

4 Construction of Public Toilet Facilty 3.00

Total 48.50

3 Haal Atutenna, Haldummulla, Badulla 1 Completion of Multipurpose Building 15

Total 15.00

4 Kandekeitya, Kandaketiya, Badulla

1 Construction of a PS Office Building with a Library 25

2 Development to the Weekly Fair 25

Total 50.00

5 Meegahakivula, Meegahakivula, Badulla 1 Bus stand 30

Total 30

6 Ingurukaduwa, Badalkumbura, Monaragala

1 Construction of a PS Sub office 25

2 Construction of a Weekly Fair 23.5

Total 48.5

7 Madulla, Madulla, Monaragala

1 Bus stand with Three wheel park 26.5

2 Development of Drainage and Pavement System 12

3 Public Toilet and Childern Play area 10

Total 48.5

8 Medagama, Medagama, Monaragala

1 Construction of the Library Building 10

2 Development of the Weekly Fair with side walls 11

3 Construction of the Public toilet facilities ( in the Bus stand area)

2

4 Multipurpose Building 25

Total 48

9 Siyambalaanduwa, Siyambalanduwa, Monaragala

1 Bus stand 15

Total 15

10 Thanamalwila, Thanamalvila, Monaragala

1 Construction of a PS Office Building with a Library 35

2 Weekly Fair 15

Total 50

Western Province (For Package DSC - 07)

1 Baduraeliya, Palindanuwara, Kalutara 1 Construction of a Bus stand & Three wheeler park 45

Total 45

2 Iththapana, Walallawita, Kalutara 1 Construction of a Multi-Purpose Building ( Library, 30.25

S/No LA S/No List of Indicative Sub Projects Initial

Estimate

Montessori, )

2 Development of the weekly fair & a construction of a public toilet facility

19.75

Total 50

3 Pallewela, Mirigama, Gampaha 1 Construction of a water supply in the market area. 12

Total 12

Annexure 2 2.1 Scope of Work- Improvement to Storm Water Drains – Specific Tasks Specific tasks of the design and supervision consultancy on works related to Storm Water Drainage improvement apart from the general tasks described earlier are:

a) Using available maps, topographic sheets and by reconnaissance and detailed survey of the catchment and sub-catchment areas, determine storm water flow and show on a plan in the form of modules each module covering the catchment area.

b) Analyze rainfall data of the previous years (no. of years would be in accordance with the standard practice followed in the country) and estimate storm run-off per unit area for various storm frequencies;

c) Prepare an outline drainage plan for the area and identify missing links and prioritized program of improvement works.

d) For priority drainage area, carryout detailed topographic survey and leveling to prepare longitudinal sections of the system and cross sections of important rivers, major channels and drains covering a width of 15 m on either bank generally at intervals of 10 m along with L-sections and detailing all the temporary and permanent structures met within that width. All the structures and encroachments will also be marked with enough details.

e) Indicate the details of other underground services, mainly sewers and water mains (electrical cables) which are in the vicinity of the storm water drainage system and show their distance from storm water drains with a view to know about the possibility of providing by-pass storm water drain and for deciding their location.

f) Indicate the inundation area clearly, showing probable depth of water accumulation in case of intensity of rainfall as agreed with the SPCU.

g) Locate all ponds and flood water holding ponds/zones in part portions of open gardens or playgrounds – showing therein probable size duly dimensioned should be shown on plan along with various arrangements / devices to dispose off the accumulated water to nearest outfall or conserve the water so as to reduce the shortage of water supply and to be shown in a tabular proforma.

h) Carry out analysis of existing situation of storm water drains to identify deficiencies and develop alternative strategies and options for expansion / augmentation of the existing system to address system deficiencies.

i) Prepare detailed cost estimates for priority drainage area. Estimate necessary road restoration charges wherever needed.

j) Prepare a traffic diversion plan as necessary and incorporate in bidding documents. 2.2 Scope of work- Water Supply – Specific Tasks

a) Based on feasibility, the Consultant is required to carry out a detailed engineering design including environmental and social studies and prepare, Detailed Project Reports and bidding documents for all the identified water supply sub-projects .

b) The overall design would cater for a period of over 30 years/ horizon as defined as

per national planning norms and a population as determined by the consultant based on appropriate projection techniques. The designs shall conform to relevant/ latest applicable National Standards, NWSDB guidelines and CEA requirements. Wherever such standards are not available, appropriate standards shall be followed in discussion with SPCU/PMU.

c) Based on the pre-feasibility reports, ,the work involved and the study/output shall

include, but not necessarily limited to the following as necessary:

(i) Designs for development/ rehabilitation of works at source and transmission and distribution for selected Local Authority(s);

(ii) Designs for development/ rehabilitation of constructing treatment plants (as necessary;

(iii) Designs for development/ rehabilitation of Internal distribution lines with adequate regulations to ensure equitable water supply;

(iv) O&M mechanism including a plan and staffing requirements and

(v) A tariff system and a mechanism to update tariff periodically

(vi) Suggest proper zoning and block regulations if any, in order to give equitable water supply with optimal utilization of existing infrastructure facilities.

(vii) Identify potential options for the long-term system improvements with recommendations for addressing environmental, institutional and regulatory issues if any.

(viii) Estimate the investments required including O & M for various identified options with financial analysis taking into consideration the water tariff to be levied for capital and operation and maintenance requirements

(ix) Support LA in preparing actions required for staffing of the water unit and in establishing tariff mechanism

(x) Based on cost-benefit analysis and cost projections, prioritize the investment proposals based on economy and efficiency. t.

d) Soil Investigation: Soil tests as per relevant National/ NWSDB Standards have to be done by consultants to arrive at design parameters for the formation and safe bearing capacity. At locations proposed for important installations such as pump house, OHT/sumps etc., at least one bore hole for every such installation, should be made to determine the SPT N values at depth specified in the relevant codes. Soil samples taken from bore holes should be visually classified, index properties determined and presented in along with the final report. The subsurface water at each bore hole be sampled and a chemical analysis carried out, to recommend appropriate cement/admixture for use in concrete mixed for the foundations. Recommendations of a geo-technical expert should be furnished in the soil report and should cover aspects like appropriate soil stabilization measures if required, bearing capacity of the founding strata etc.

e) Instrumentation: All necessary instrumentation such as flow meters, energy meters

etc shall be arranged and operated by the consultants at their own cost.

f) For the given purpose and functional use of the respective projects, proper design has to be developed. The consultants have freedom to choose the type of substructure and superstructure provided code specification / National/ NSWDB stipulations are met. The drawings and designs shall include a general arrangement drawing and detailed drawings of all components in standard size. . The level of detailing shall be such as to enable check of conformance with code provisions, including detailed construction drawings and bar bending schedules.

g) Prepare a traffic diversion plan as necessary and incorporate in bidding documents

2.3 Scope of work - Roads and Bridges. – Specific tasks 2.3.1 Investigation of Project Road Alignments:

a) Review the requirement of improvement of the road improvements prioritized after the consultation and requirement assesment to be taken up under the Project.

b) The consultant needs to assess the following before undertaking the feasibility studies and detailed design

(i) Type of terrain / topography of the existing alignment, improvement requirements based on existing condition and requirement of any road re-alignment.(if any)

(ii) Land use including existing settlements / structures (location and structural condition) and identify any bypass requirements (if any)

(iii) Hydrological and drainage characteristics to identify risk of flooding. The Consultant shall undertake hydrological and hydraulic studies for all drainage catchments with careful analysis of topographic maps and field investigations. The calculation of catchment run off and channel discharge characteristics shall be based on rainfall intensity and duration for a return periods identified in the Drainage Design Manual for the various drainage elements and bridges. The capacity of existing waterways and drainage structures shall be checked and their deck levels shall be compared with anticipated flood levels. Slopes and capacity of side drains and turnouts shall be surveyed in areas where erosion or flooding presently occurs, in order to ensure adequate design of side and catch drains, erosion control measures and the protection of side slopes. Detailed site investigation and surveys shall be carried out for areas susceptible to flooding or landslide, and at all proposed new or replacement drainage structure locations, including a sufficient length up stream and downstream to the structures. Preliminary structural design shall be undertaken with a view to fixing vertical and horizontal alignments at those structures.

(iv) Environmental effects and Social impacts. (v) Assessment and projection of traffic volume and type based on one day traffic

counts or as necessary in line with the standards on required section as necessary. The forecasts should include best estimate of likely demand (based on economic activity, past growth trends, growth in vehicle population, planned developments, etc). The forecasts should also include the impact on the project area during and after the construction period.

(vi) The Consultant shall assemble and evaluate available accident data and seek to identify principal causes and assess the potential for the project to reduce accidents through, for example, improved junction layouts or the provision of pedestrian and non-motorized facilities. The consultant should compile a list of the problem areas and his proposed approach to mitigate the problems.

(vii) Utilities: The Consultant shall obtain from concerned authorities the utilities maps showing the locations, dimensions and capacities of their existing underground and overhead apparatus within the road reserve, or potential road reserve extension. The consultant shall show all utilities and data on a draft set of utility drawings to later be incorporated into the design drawings. Where shown on the authorities maps, the data shall include the above ground height or buried depth of all services, including cross road services to adjacent properties. The accuracy of all such records shall be verified on site by the Consultant both by observation and by use of non-intrusive detection equipment. In addition, the Consultant shall obtain details of utility proposals for short and medium term service enhancement proposals, and consider the implications of these in the design. The consultant shall include in the project specification a requirement for the contractor to locate these services early on in the construction contract.

The Consultant shall prepare an Initial Assessment Report summarizing the findings from their visual assessment and Investigation of Project Road Alignments, which shall include a detailed project road inventory and photographic record. The Consultant shall liaise with the Client to agree on the actions and priorities recommended in their report.

2.3.2 Topographical Survey: The Consultant shall carryout the topographical survey using Total Station or other appropriate methods.

The width of the survey corridor shall extend past the ROW and take into account the layout of the existing alignment including the extent of embankment and cut slopes and the general ground profile beyond. The following existing over and underground features like poles, pipes trees, building lines, bus bays, culverts and drains, bridges etc in full shall be mapped for a corridor width not less than ROW required. Survey shall be carried out as per the code list required for survey data processing. Cross-section shall be taken at distances as per national standards in longitudinal direction for entire width of carriageway. For small drains across CD works, at least three cross sections shall be taken, namely one at the selected site, one upstream and one downstream. For major drains and streams across bridges, cross sections shall be taken as per national design norms The Consultant shall be fully responsible for the accuracy of the survey. 2.3.3 Soils Materials and Pavement Investigations The Consultant shall undertake extensive soils and materials testing in relation to the: (i) adequacy of sub grade materials on existing and new alignments; (ii) stability of existing embankments and cuttings and their capacity for raising or

deepening; (iii) suitability of cut materials to be utilized as fill; (iv) identification of suitable borrow pit and gravel pit location and an estimate of the

volumes of suitable material they may yield and potential water points; (v) identification of suitable sources of aggregates and an estimate of the volumes they

may yield. The consultant shall in discussion with the SPCU arrive at the tests to be conducted and conduct the same in standard laboratories acceptable to the client. 2.3.4 Culvert and Bridge Inspection and Assessment The Consultant shall undertake a detailed condition survey of all existing drainage culverts and all bridges to be retained to determine their structural adequacy and traffic load capacity. Assessments shall be made of their residual life, and the cost of repairs or reconstruction to increase capacity. The Consultant shall make recommendations as to their retention, reconstruction or replacement. The Consultant shall carry out necessary non-destructive testing of the culverts and or bridges. The Consultant shall include a draft non-destructive testing program, and structural investigations for the culverts and bridges, including provisional cost estimates in their proposal. This shall be refined and updated once the assignment commences. In cases of new bridges, the Consultant shall carry out a borehole investigation to determine the strength of soil and/or prove rock depth and strength for each bridge at the location of each abutment and alternate pier. 2.3.5 Geometric design The Consultant shall develop optimum vertical and horizontal alignments having regard to: (i) design manual criteria or such other criteria agreed with the Client; (ii) the need to balance cut and fill; (iii) the need to minimize land take beyond the existing road reserve; (iv) the need for inbuilt safety measures such as climbing lanes, right turn lanes, traffic

calming measures;

(v) the need for adequate road user facilities such as bus bays and laybys, including space for vendor services;

(vi) the need to protect vulnerable road users (vii) a requirement for accommodation works to be affordable and acceptable to

frontages; (viii) minimize the need to protect or relocate utility services; (ix) the need to avoid geological, hydrological and environmental problems; and (x) the need to avoid extensive and expensive bridge and structural works. Where alternative horizontal alignments beyond the road reserve limits are to be evaluated, the Consultant shall develop and cost options at an early stage and prepare a report for consideration by interested parties and the Client. The Consultant shall propose target dates for the presentation of such options and selection of the preferred option in their work plan in the Initial Assessment Report, ensuring sufficient time to complete the detailed design of the preferred solution within the assignment timescale. Vertical and horizontal alignment data shall be computed for the centre line at a maximum of 20m intervals and at all vertical and horizontal transition points. 2.3.6 Preliminary Engineering Design and Feasibility Study It is intended that the project road be upgraded to meet the agreed design criteria for the standard of road. The consultant shall not assume it will follow the existing alignment full length, as sections may have to be improved to meet the agreed standards and design criteria. The consultant shall consider the surveys, investigation, studies and analysis as made above and prepare a Preliminary Engineering Design along with Feasibility. The consultant shall present to the Client alternatives for improvement in alignment of the road and for improvements e.g. service roads and/or walkways, lay buys for motorized and non-motorized vehicles, where the road passes through Local Authorities and settlements. Road drawings to include: Plan drawings of appropriate scale to show alignments, vegetation type, main drainage elements, right of way and clearly show areas of landtake Profile drawings shall also be to appropriate scale to include the existing road surface or natural ground level and proposed vertical alignment. The consultant shall undertake the geometric design of the road using a modern and comprehensive (Computer Aided Design and Drafting) CADD package. This CADD software must be capable of allowing the designer to assess different alignments along the proposed route All topographical and design data shall be supplied in a format suitable for input to a road design software or similar. The design shall be referenced to a line or string which shall contain details of chainage (or station), horizontal and vertical geometry information. The consultant shall divide the road into homogenous sections in terms of traffic loading and strength, and propose at least two alternative pavement options in terms of layer type, quality and thickness of pavement considering the project traffic loadings for each section. The consultant shall take into account availability of suitable construction materials along the route. Preliminary Design of Structures: Based on the full topographic survey, geotechnical investigation, hydrological study and other studies, prepare structurally sound and cost effective design ,layouts for all major structures in the project road. Preliminary design of proposed bypasses, whether or not to be included in the works contract prepared under this consultancy

Preliminary design of proposed grade separated junctions, whether or not to be included in the works contract prepared under this consultancy The Consultant shall calculate quantities for the items of construction based on the preliminary design drawings and shall prepare a preliminary bill of quantities along with preliminary cost estimates The Consultant shall prepare a Preliminary Design Report that shall include: (i) preliminary investigation results, analyses and interpretation of findings (ii) analysis of design options and recommendation of most viable option (iii) preliminary findings with regard to environmental and social impact and road safety (iv) location maps, layout plans and profiles (v) typical cross sections showing cut and fill slopes (vi) typical cross section drawings showing pavement details (vii) drawings for cross drainage (viii) two alternative pavement designs for each homogenous road section (ix) bridge drawings (x) plans through town centres, plans for bypasses and plans for grade separated

junctions

2.3.7 Detailed engineering design As the design progresses the Consultant shall maintain close liaison with the Client and shall submit for approval from time to time, according to the work program, draft design proposals for the alignment, drainage, pavement, structures and other technical aspects of the design prior to proceeding to the detailed design drawings. Where a number of options have been considered these shall be described and analyzed in a Design Options Report. Similarly, the Consultant shall submit draft technical specifications and bills of quantities prior to producing the draft final bidding documents. 2.3.7.1 Design Standards The engineering design shall be undertaken using appropriate computer aided design software. The Consultant's proposal must state the software they intend to use, and ensure it is compatible with the Client software and IT systems in the early stages of the design assignment. All topographical and design data shall be supplied in a format suitable for input to an appropriate road design software. The design shall be referenced to a line or string which shall contain details of chainage (or station), horizontal and vertical geometry information. The Design shall be undertaken to National standards and the agreed variations. The Consultant shall prepare a Design Departures Report that clearly identifies all instances where these design standards have been deviated from in their design, with justification for the deviation. These deviations shall include instances where the Consultant considers the design standards to be lacking or inappropriate to the project.

2.3.7.2 Detailed Geometric Design The preliminary optimum vertical and horizontal alignments shall be reviewed in relation to the outcomes of the entire engineering investigation process, and in relation to progress with land acquisition issues. Adjustments shall be made as necessary and care shall be taken to retain coordinated vertical and horizontal alignments. Alignment set out details such as tangent length, curve radius, deflection angle, apex distance, transition length etc shall be prepared to ensure easy setout of the alignment. In order to ensure setting out using Total Station, coordinates of all centre line intersection

points, tangent points and straights at 100m intervals shall be determined and scheduled. Likewise horizontal and vertical curve data at 20m intervals shall also be scheduled. Cross sectional design shall take into account the need for: (i) earth works side slopes and cuttings, including the need for benching or other slope

stability measures. (ii) Extra Widening (iii) climbing lanes; (iv) bus bays, lay bys and mobile weighbridge lay-bys; (v) additional lanes or service roads in high density areas; (vi) footways and lanes for non motorized traffic; (vii) requirements for open or piped side and catchwater drains, subsurface drains; (viii) space to accommodate utility services and roadside furniture, e.g. road lighting

and ducting, guardrails, road widening, road signs and the like.

Full cross section data shall be computed at 25m intervals Where cross sectional requirements cannot be accommodated within the existing road reserve, the preliminary land acquisition proposals shall be revisited or retaining structures to limit the road reserve requirement may be considered. 2.3.7.3 Pavement Design The Consultant shall develop a range of standard pavement designs and associated maintenance regimes and economically evaluate each to determine which the lowest whole life has cost. The Consultant shall identify road sections, which may require a non standard pavement design due to a range of factors including: (i) a particularly weak sub-grade; (ii) very low traffic levels; (iii) excessive local heavy vehicles; (iv) locations, especially in urban areas and near markets, subject to long term parking of

heavy goods vehicles; (v) diesel leakages from stationary vehicles; and (vi) a lack of local pavement materials coupled with excessive haulage costs from

elsewhere. Non-standard designs shall be developed for each of these sections and presented to the Client for consideration.

In determining, the number of standard axles to be carried by the pavement during its design life the Consultant shall: (i) take into account potential regulatory changes; (ii) design on the basis of existing average axle loads, not allowable axle loads; (iii) increase the design axle loads by 5%, or more if historical and present overload data

does not indicate a progressive tightening of overload control; (iv) carry out a sensitivity analysis on the axle load and traffic ADT variation (+1-5%, +/-

10% and +/-40%) and assess how this affects the pavement designs; (v) compute standard axle numbers for low, medium and high heavy vehicle growth

predictions.

(vi) The cost implications of designing for medium and high traffic growth over and above low growth shall be evaluated in financial and economic terms and a recommendation shall be made to the Client as to the preferred option.

(vii) In determining, which existing pavements can be retained in situ and overlaid with additional materials the Consultant shall have regard to anticipated further

deterioration prior to the start of construction works; a period expected to be at least two years. Pavement materials, which cannot be retained in situ as a result of location or condition, shall be recycled as sub-base or for use in temporary diversions.

2.3.7.4 Design of Drainage Structures (Side & Cross Drains) The Consultant shall engage with roadside communities and local authorities to raise awareness of the need to offer easement rights for road drainage to run-off over adjoining land to ensure adequate drainage. Where such easement rights are required, the Consultant shall submit details for inclusion in the Resettlement Action Plan and shall design such run-off drainage in consultation with the affected landowner. In designing bridges over 6m span the Consultant should have regard to providing as much standardization as possible and offsite pre-casting or fabrication of components. The choice of design must reflect seasonal constraints to construction, whether bridges are likely to be on the construction programmer’s critical path and the cost and practicality of providing temporary bridging. 2.3.7.5 Potential Borrow Pits, Quarries and Gravel Pits

Following preliminary identification of borrow gravel pit and quarry locations the Consultant shall consult with authorities as to possible locations and legal requirements, prepare tentative proposals and plans for their opening, operation and restoration. The project specification shall specify that the final responsibility of establishing borrow pits, quarries and gravel pits are with the Contractor and the plans prepared as part of the design is only indicative. Such plans shall cover, but not be limited to: (i) precise locations and boundaries of each pit/rock source; (ii) land ownership, including haul roads; (iii) material quantities to be extracted and their location in the road works; (iv) the stockpiling of overburden; (v) necessary planning consents; and (vi) public roads to be used for haulage purposes and their protection (vii) Environmental compliance. The Consultant shall examine existing quarries and crushing plants and their capacity to supply aggregates and granular mixes to the required specifications.

2.3.7.6 Design of Ancillary Features Traffic Signals & Control Design Should the need arise for the adoption of Traffic signals/ other traffic management measures, the Consultant will submit design rational to the Client for review. Once agreed the consultant will design the traffic signal layout(s), specify the equipment, which is to be agreed with the Client to ensure it is compatible, and ease of maintenance. Roadside Furniture The Consultant shall clearly mark on design drawings the extents of the existing and proposed road reserves and design permanent signage to indicate the extents of the road reserve. The Consultant shall fully schedule necessary mandatory and informatory road signs and markings and ensure that their siting makes them highly visible yet minimizes obstruction to road users and driver sight lines. All signs shall be reflective. Best international practice shall be observed in the introduction of anti-vandal construction details. Road markings shall be fully detailed and be comprised of reflective thermo-plastic or similar durable paint.

The Consultant shall pay particular attention to the provision of safety features such as guard rails and the like, and hold consultations with the Client and road safety organizations to ensure effective provision and siting of these features. Crash barrier systems (Safety Fencing & Safety Barrier) The Consultant shall include in their design safety barriers and safety fencing, where identified as necessary and according to the findings of the Road Safety Audit. The design of crash barrier systems shall consider whole life costs and durability. The Consultant shall assess the cost and engineering considerations of providing steel, concrete or other safety barriers systems, and present their analysis and recommendations of these options to be the Client for consideration.

2.4 Designs of Bridge The consultant shall workout the Hydrological and hydraulic calculations and confirms the floods characteristics of the streams crossed, including the elevation of the water surface, the velocity of flow, for a recurrence interval of 100 years The detailed design shall take account of the bridge location and expected difficulties in constructing the bridge, lead time in importing specialist materials if proposed, maintenance of the bridge with a view to ensuring the bridge is "buildable" and "maintainable". The foundations shall be designed based on the geotechnical- data obtained at each abutment and pier location. The consultant shall use recognized structural design software and shall produce output data in a format that can be easily followed and understood. The detailed design calculations are to follow Indian/International Standards in layout and referencing. The Consultant shall prepare structural report which shall include the assumed method of construction and risk assessment of whether any elements of the structure may be overloaded through the construction process, a full set of detailed design calculations, basic design assumptions and criteria used are to be included in table and note form on the drawings. The report shall include all necessary design drawings and schedules / tables. Drawings of each structure are to be prepared in sufficient details for the bridge to be constructed.

The consultant shall prepare a provisional traffic management plan detailing how motorized and non motorized traffic and pedestrians shall be accommodated during the construction phase. The plan shall: (i) develop a phased approach to construction which minimizes road user disruption; (ii) detail which public roads shall or shall not be used for construction or diverted traffic; (iii) locate and detail temporary diversion roads; (iv) lay down conditions for one way traffic working; (v) detail required provisions for temporary bus bays and lay by facilities; (vi) ensure that frontages, particularly commercial frontages, shall have reasonable

access at all times; (vii) detail the temporary signing that must be provided and maintained; (viii) specify speed limits to be applied, and specify where and when speed humps may or

shall be provided; (ix) specify the minimum standards of riding quality to be provided on the existing and

diversion roads; and specify special facilities to be provided for pedestrians and other vulnerable road users, particularly in high density areas and near schools.

This plan shall be incorporated into bidding documents for works and bidders shall submit a lump sum price for its implementation. The Consultant shall ensure the works contract

documents make it clear that the successful bidder may present modifications to the plan during the various stages of implementation to suit precise construction requirements, but will not be permitted to over-ride the main provisions of the plan.

The Consultant shall prepare and submit contract drawings and load them onto Autocad/ standard design software and on the Client’s systems and present, the drawings are complete. The scale of presentations should be as per national standards/ international best practices. Detailed bills- of quantity shall be prepared under the following general headings: preliminary and general; clearing and earth works; drainage (culvert and protection works); sub base and base; surfacing; major structures including bridges; road furniture; ancillary works; schedule of day works. Quantities for pavement works must allow for anticipated further deterioration between the time of the consultancy and the expected start of road works. They must also allow for the ongoing maintenance of existing pavements by the contractor pending their incorporation into the works, with penalties for non conformance. The Consultant shall be advised by the Client whether any facilities provided for the purposes of the construction contract, such as offices, houses, laboratories, vehicles etc, are to be retained by the Client or are to be owned by the Contractor. In order to make a fair and reasonable estimate of the construction costs the Consultant shall prepare a unit price analysis of each major item using basic cost elements (labour, material, equipment, overhead, risks and profit) and showing separately the cost for taxation. Costs shall be broken down into foreign and local currency components. Cost comparisons shall be made in respect of both unit rates and per km costs with similar ongoing projects in the region. These comparisons will be presented in tabular form supplemented by possible explanations for significant variances. The consultant shall prepare a construction program and, in the process, identify the following:

i. list of required construction equipment with their size/capacity-which shall be also used as the basis for identifying the minimum required equipment to be stated in the prequalification documents;

ii. combination of the construction equipment assumed in estimating works production rate per major activities assumed;

iii. major activities and their duration;

iv. network program showing the proposed ordering or sequencing of the major activities;

v. duration of the entire project in the form of a bar chart; and

vi. monthly cost of each major activity and anticipated expenditure forecast;

vii. method statements; In carrying out the analysis, the consultant shall take into account the climatic conditions (rainy and dry seasons, etc) of the areas concerned. The Detailed Design Report shall include a concise Design Statement, that provides a summary of all design standards, criteria and assumptions used to prepare the design, and the dates and scope of all survey and data collection activities. This shall be prepared in tabular form and act as an Executive Summary to the design report. The main report shall fully detail:

horizontal and vertical alignment design including the identification of key constraints and considerations and mass haul calculations;

road pavement and drainage design including evaluation of whole life cost options;

Structural Reports for all bridge and structures design, covering issues of standardization, prefabrication, ease of construction and including annexed detailed design calculations for each major structure ; and

borrow pit, gravel pit and quarry identifications and design, including details of haul routes and materials distribution within the works.

Design of all roadway ancillary features (safety fencing, road marking, traffic signs, etc) Provisional Traffic Management Plan Summary of road safety audit findings and response

The report shall include a list, in each section, the relevant design standards followed and a Departures Report identifying all instances where these standards have been deviated from and the reason for such deviation. The report shall include the estimated Construction Quantities, Cost Estimate and Economic Analysis of the presented design. The report shall include a provisional traffic management plan detailing how motorized and non motorized traffic and pedestrians shall be accommodated during the construction phase. The Consultant shall prepare the General Specification and also recommend specific options, or possibly additional options, which shall be incorporated into a Special Specification. The Consultant shall further consider the sourcing of all major materials, sand, aggregates, bitumen, reinforcing steel, structural steel etc and determine whether Manufacturer's certificates concerning composition and strength will be obtainable or adequate and as such whether sampling and testing will be needed. In the latter case such testing must be covered in the Annex 2.5 Scope of Work: Sector Solid Waste Management – Specific tasks

The scope of work covers but is not limited to:

(i) To conduct a random waste characterization study in the LAs (ii) To establish current status and baseline of solid waste management in the Local

Authority (iii) Based on the above, analyze the technical, economic, environmental, financial and

social feasibility for various components of solid waste management such as source segregation, collection, transportation, treatment and disposal by composting and landfill;

(iv) To analyze the costs involved with complete breakups for the above methodologies of waste disposal for the Local Authority;

(v) To carry out on-site geological mapping of the site and investigate the topography, geomorphology, hydrogeology, stratigraphy and other geological characteristics like the porosity, permeability etc. which will have significant influence on the design criteria for various facilities to be provided in and around the area of waste disposal suggested; design of the landfill and other facilities proposed must meet the technical guidelines provided by the Central Environmental Authority (CEA);2

(vi) To identify clusters in addition to the Local Authorities mentioned for setting up common landfill facility based on cost benefit financial analysis and assess the feasibility of making such an arrangement;

(vii) To develop a financial model in order to have a cost-effective transportation solution; (viii) Based on the above, work out cost-benefit analysis of individual Local Authorities

involved in the cluster; (ix) To suggest an institutional framework for the construction, operation and

maintenance of the regional landfill if found feasible; (x) To prepare detailed designs, drawings, estimates and bid documents for the facilities

that are required for effective operation of the disposal facilities and maintaining the environmental standards.

2 Central Environmental Authority. Technical Guidelines on Solid Waste Management in Sri Lanka.

(xi) To examine the possibility of posing the project for CDM potential and assist the LAs in obtaining the same by preparing the baseline parameters, PIN etc. and to analyze the financials of the LAs taking into account the above credits.

(xii) Assist the Local Authority in obtaining clearances from various statutory authorities for developing the landfill and compost yard.

(xiii) Necessary approvals from the CEA, if required, would be obtained by the local authorities with necessary support from the consultants.

The consultants are required to carry out the following tasks in line with National Solid Waste Management Policy and CEA guidelines, others rules and regulations.

(As envisaged at present the designs of Solid Waste Management subprojects are undertaken by the National Solid Waste Management Support Centre. If required the consultant should be able to take up the design work of the solid waste management subprojects)

Annexure 2.6 Scope of Work – Public Buildings / Local Authority Facilities: Specific tasks 2.6.1 General The designs shall conform to relevant/ latest applicable National Standards3, building codes, building regulations and CEA requirements. Wherever such standards are not available,

3 The consultants shall specify the materials and workmanship based on ICTAD specifications for

Construction and Maintenance of buildings, and any other internationally accepted specifications in the event of above specifications being inadequate. The consultant is required to comply with British Standards / Codes of Practices for the designs or accepted international standards. The British Standard Codes of Practices will govern the structural designs. In case any other code of practice is used in the design, the designer is required to furnish a comparison between the British Codes provision and the code being used in the design. The British Standards will be treated as the basic minimum required and any other standard is required to be proved higher than the British Code requirements. The main applicable British Standards that the design has to conform to are listed below for easy reference. However, the design has to conform to all other non-listed British Code of practice that is relevant to the design standards.

(a) Design loads: Design loading for buildings B.S.6399 Part I

Basic data for wind loads C.P.3 Chapter V – Part 2 And manual “Design of Building to High Winds – Sri lanka” (b) RCC Structure Design: Structural use of concrete BS 8110 Parts 1, 2, 3 (c) Structural Steel Design: Structural use of steel works in Buildings BS 5950 Part 1 to

9 (d) Design of Foundations Code of practice for foundations B.S. 8004 (e) Code of practice for protection of structures Against water from the ground B.S.

8102 (f) Earth retaining structure designs: Code of practice for earth retaining structures

B.S. 8002 (g) Aqueous liquid retaining structures- Design of concrete structures for retaining

Aqueous liquids B.S. 8007 (h) Specification for Hot Rolled Steel B.S. 4443 (i) Specification for cement B.S. 12

appropriate standards shall be followed in discussion with the PMU. The overall design would cater for a period as defined as per national planning norms. 2.6.2 Surveys and Investigations:

a) Data Collection: Collecting and updating information regarding existing levels of the

proposed subproject and ascertain the necessity of the same by carrying out an inventory of existing systems / facilities. All required data shall be collected to design and construct basic utilities such as water supply and sewer pipes, storm water pipes and drains, development of ground water source including rain water harvesting, electrical network with back up supply, fire detection / protection system, incorporating Green Building Concept etc. (The details given in the technical conditions and specifications taken in conjunction with the pre-feasibility study, is only a reasonable preliminary basis. The nature of the overall contract is such that after the proposal, the consultant shall be wholly responsible for all the details of the proposal, the physical and site conditions, the execution methodology etc. All data utilized in preparation of the proposal shall be presented indicating the sources of the data and also the basis of assumptions, if any. The consultant shall be responsible for all the data or designs and drawings given by them)

b) Topographical Survey: Detailed topographical survey of the site, along with Contour

survey at the required contour intervals, as approved by the Client, in and around the subproject site. The local body shall indicate the Project sites and their measurements. The survey shall include all necessary data related to the existing public utility services, lines of streets and pavements, building lines, adjoining properties, position of lights, restrictions, basements and boundaries to design the Sewerage and Strom water drain system. The consultant shall be responsible for the survey of the areas and preparation of necessary survey maps.

c) Soil Investigation and Tests: Soil tests as per relevant National Standards have to be

conducted and necessary reports prepared by consultants to arrive at design parameters including safe bearing capcities. Also, conduct soil test, Hydro geological survey and such other tests required to provide essential design data from sub-soil conditions. The Consultant shall interpret the soil investigations report and design the appropriate type of foundation for the Building, in consultation with the Client. The bore holes should normally be taken to a depth as acceptable to national design norms. The subsurface water at each borehole should be sampled and a chemical analysis carried out, to recommend appropriate cement mixture ratios for use in the foundations. Recommendations of a geo technical expert should be furnished in the soil report. It should cover aspects like appropriate soil stabilization measures if required.

2.6.3 Detailed Design (Architectural and Structural), estimates and Detailed Project Report

a) Prepare a site evaluation and analysis report with basic approach to circulation, activity distribution and interaction and external linkages and impact of existing and / or proposed development on its immediate environs.

b) For the given purpose and functional use of the respective sub-projects, proper

design has to be developed. The consultants have freedom to choose the type of sub structure and superstructure, provided National code specifications and standards are met. The drawings and designs shall include a general arrangement drawing and a detailed longitudinal section drawing of all components in size A1 or A2. The level of detailing shall be such so as to enable check of conformance with code provisions, including detailed construction drawings. The responsibility of the preparation and issue of detailed construction drawings is that of the Design and Supervision Consultants.

c) Prepare conceptual designs, drawings and study model with reference to requirement

definitions. Required drawings such as Architectural, structural, service drawings and design calculations for all designs shall be furnished by the consultant to the client for execution of work

d) Prepare detailed structural designs and drawings along with construction drawings

with detailed design calculation.

e) Prepare Sanitary, Plumbing, drainage, water supply and sewerage system designs and drawings including solid waste management, Electrical, electronic, communication systems and internet system design and as required Heating, ventilation and air conditioning design (HVAC) and other mechanical systems, solar water heating system, solar power system.

f) Design for Elevators, Escalators, etc if required.

g) Design for Fire detection, fire protection and Security systems and any disaster

management systems as necessary etc.

h) Design for Integrated Building Management System.

i) Development works such as external sewer, water supply, drains, and culverts Roads, Street lights, Rainwater harvesting etc. all complete.

j) Use of environmental friendly and energy conservation concepts with minimum or no

additional cost.

k) Vehicle parking layout for the entire campus including site development and other infra structural facilities.

l) Detailed Engineering drawings4 for all the designs.

m) Prepare drawings, layout etc., and necessary for submission to statutory bodies for

sanction for obtaining approval / Licenses. The client will make necessary applications. The Consultant shall carry out all the works together with the necessary drawings and other particulars for obtaining all statutory approvals from UDA/CEA etc or other agencies. in addition, shall assist the client to get necessary approvals.

n) The services will include structural, architectural designs of the buildings taking into

consideration of Earth Quake Resistance and other Disaster effects, designs of all external and internal services, including air conditioning (HVAC), lifts, escalators, electrical, mechanical, DG sets of required capacity, fire fighting and safety systems, public address system, access control, telephone exchange, communication tower, water supply, furnishing fit out, sewerage disposal, internal roads, arrangements for

4

Preparation of architectural drawings including plans, cross sections, elevation etc to a scale of 1:100 or 1:50. Preparation of structural design based on appropriate engineering analysis of loads, stresses, deflection and strength of materials, including detailed statistical scheme and calculations. Preparation of drawings for sanitary installations to a scale of 1:100 or 1:50 and detailed drawings to a larger scale as may be found necessary to enable the construction of the works. Preparation of drawings of electrical installation as required for lighting and services to a scale 1:100 or 1:50 and detailed drawings to a larger scale as may be found necessary to enable the construction of the works. Preparation of water supply, sanitary and storm sewer line drawings to a scale 1:100 or 1:50 and detailed drawings to a larger scale as may be found necessary to enable the construction of the works, as well as septic tank details (with calculations), and overhead tank, if required.

special security systems, Integrated Building Management System and monitoring of all works during the construction as required.

o) Based on the surveys and designs evolved by the consultants, within the framework

and the requirements of the project, the consultants have to prepare detailed specifications, detailed item and quantity schedules. Prepare detailed cost estimates using the latest provincial schedule of rates. Estimate associated costs such as road restoration charges/ shifting of utilities, quality tests, resettlement etc.(as applicable) There should not be any lump sum items for work related items in the bill of quantities. For items not covered under schedule of rates, market rates to be assessed.(Necessary documents on quotations received should be made for assessment of market rates. This will be subject to scrutiny and approval of client)

p) Prepare and submit complete set of working drawings for all works and details sufficient for proper execution of works during construction. All the drawings and reports, Manuals, to be furnished in both soft and hard copies, duly attested. The Consultant shall be fully responsible for accuracy of all the data, rate analyses for items of work used in the Project preparation, Cost Estimates and design irrespective of the fact whether the same has been examined and approved by the Client or not.

q) For concepts, plans of the project and preliminary project report covering various aspects of projects such as buildings and fire fighting, electrical works, air-conditioning works, roads, drainage, water supply, sewerage and pavements etc. shall be prepared by the consultant to suit requirements and meeting statutory/mandatory provisions for the project as a whole and whereas the Architectural consultant shall have meetings with SPCU and LA to finalize the general as well as specific requirements.

r) All works shall be done in conformity with relevant National Standards specification, National Building Code, Standard Specification for Roads and Bridges and to the requirements of statutory bodies, local byelaws and accepted Government procedures.

s) The consultant shall conduct his own studies and prepare estimates based on

Provincial schedule of rates. The PMU, SPCU as well as the LA concerned and Project Management Consultants shall not be responsible (except as to risks specifically accepted under the conditions of contract) for the validity of the project details and designs and estimates.

t) Prepare a Detailed Project Report incorporating all details of the Project as above.

u) The consultants shall assist the Local Authority in obtaining approval of plans and

estimates (approval of Plan and estimates and bid documents) from competent authorities like LA, TEC (Technical Evaluation Committee) etc.

Note: Please note the ToR is outline and indicative and will be fine tuned while issuing the Request For Proposal to the shortlisted Consultants.

===============