Outcome of the Review and Response to Recommendations

38
1 4 November 2013 Holger Witte Brookhaven National Laboratory Advanced Accelerator Group Outcome of the Review and Response to Recommendations

description

Outcome of the Review and Response to Recommendations. Overview. Outcome of review meeting Comments and recommendations Update on PRY. Review Meeting. 23 rd /24 th of September Presented solution: Partial Return Yoke Findings Recognition: intensive programme of FE modelling - PowerPoint PPT Presentation

Transcript of Outcome of the Review and Response to Recommendations

Page 1: Outcome of the  Review  and  Response  to  Recommendations

14 November 2013

Holger WitteBrookhaven National Laboratory

Advanced Accelerator Group

Outcome of the Review and Response to Recommendations

Page 2: Outcome of the  Review  and  Response  to  Recommendations

24 November 2013

• Outcome of review meeting

• Comments and recommendations

• Update on PRY

Overview

Page 3: Outcome of the  Review  and  Response  to  Recommendations

34 November 2013

• 23rd/24th of September • Presented solution: Partial Return Yoke• Findings

– Recognition: intensive programme of FE modelling– The team is to be congratulated on the effort

that has gone into this work– The design of the PRY shielding and the

procedure for installation are basically sound– The ISIS Group is satisfied with the work being

done by the MICE Collaboration to control the level of stray field

Review Meeting

Page 4: Outcome of the  Review  and  Response  to  Recommendations

44 November 2013

• The strategy of improving the shielding now to reduce the risk of losing running time later is sound

• less attention has been paid as to the effect of the presence of the new PRY shielding on the coil

• Design improvements: – Symmetrize support structure– Compatibility with Step VI

Comments

Page 5: Outcome of the  Review  and  Response  to  Recommendations

54 November 2013

• Platform on the north side of the experiment• Ensure that PRY does not increase risk of coil

failure– Forces and coil quenches

• Modify PRY: independent of mezzanine• Compatibility of PRY with Step VI• Commissioning plan for Step IV• Validate results of Step IV with measurements• Steve Plate: UK visit• Watch schedule

Recommendations

Page 6: Outcome of the  Review  and  Response  to  Recommendations

64 November 2013

• Quenches• Forces

– Variation in material parameters– Offsets

Effect of PRY on Solenoids

Page 7: Outcome of the  Review  and  Response  to  Recommendations

74 November 2013

• Superconducting state: fct (B, J, T)• Effect of PRY: changes B• Simulation 1:

– Step IV configuration with PRY• Simulation 2:

– Extrusion coupling: use magnetization of Simulation 1

– No coil currents• Done for 240 MeV flip and solenoid mode• (MICE: NbTi, Cu:Sc = 4)

Effect of PRY on Quenches

Page 8: Outcome of the  Review  and  Response  to  Recommendations

84 November 2013

Effect of PRY on Quenches

240 MeV Flip Mode

28.5 mT Spectrometer+End coil 2

Page 9: Outcome of the  Review  and  Response  to  Recommendations

94 November 2013

Effect of PRY on Quenches

240 MeV Solenoid Mode

23 mT End coil 2

Page 10: Outcome of the  Review  and  Response  to  Recommendations

104 November 2013

Tc End Coil 2

L. Bottura, “A practical fit for the critical surface of Nb–Ti”. DOI: 10.1109/77.828413

240 MeV Flip

Page 11: Outcome of the  Review  and  Response  to  Recommendations

114 November 2013

ΔTc End Coil 2

Assume ΔB of 30 mT everywhere

ΔTc < 0.02 K

Page 12: Outcome of the  Review  and  Response  to  Recommendations

124 November 2013

Spectrometer Solenoid, B

240 MeV Flip

Page 13: Outcome of the  Review  and  Response  to  Recommendations

134 November 2013

Spectrometer Solenoid

Note: steps due to Bisection method

ΔTc < 0.02 K

Page 14: Outcome of the  Review  and  Response  to  Recommendations

144 November 2013

240 MeV Solenoid, End Coil 2

Tc ΔTc

ΔTc < 0.02 K

Page 15: Outcome of the  Review  and  Response  to  Recommendations

154 November 2013

Variation of Material Properties

Air

Iron

Half PRY Simulation

Page 16: Outcome of the  Review  and  Response  to  Recommendations

164 November 2013

Magnetization 240 MeV Flip

Page 17: Outcome of the  Review  and  Response  to  Recommendations

174 November 2013

FC M1 M2 E1 SS E2

240 MeV Sol -587 494 39 -254 -6253 -3048

240 MeV Flip -4273 -2835 -2673 -2315 -10344 -3414

Half PRY Simulation

Fx

FC M1 M2 E1 SS E2

240 MeV Sol -596 87 140 53 -159 -155

240 MeV Flip -1935 174 576 50 -243 -167

Fy

PRY1 (Sol/Flip): Fx=19776 N / 52317 N

Acceptable force: 1/3 of longitudinal force

Tracker: 50 tonsFC: 20-30 tons

Forces in Newton

Page 18: Outcome of the  Review  and  Response  to  Recommendations

184 November 2013

Forces – Simple Study

Page 19: Outcome of the  Review  and  Response  to  Recommendations

194 November 2013

Result

Page 20: Outcome of the  Review  and  Response  to  Recommendations

204 November 2013

Solenoid Mode - Forces

Page 21: Outcome of the  Review  and  Response  to  Recommendations

214 November 2013

Flip Mode - Forces

Page 22: Outcome of the  Review  and  Response  to  Recommendations

224 November 2013

• Discrepancy: MICE hall model predicts larger stray fields

• Increased stray field– Differences in coil geometries/currents– Differences in PRY geometry

• Position of Virostek disc

Update on PRY - Stray field

Page 23: Outcome of the  Review  and  Response  to  Recommendations

234 November 2013

M1 (TRD) M1 M2 (TRD) M2R1 (mm) 255 258 255 258

R2 (mm) 355 302.7 312 287.8

Z1 (mm) 3752 3711.6 4193 4150.8

Z2 (mm) 3550 3510.4 3991 3951.3

J (A/mm2) 71.31 71.6 65.6 66

Coil Geometry

Difference in coil cross-section: M1: 20200/8993.64 = 2.25M2: 11514/5945.1 = 1.94

Page 24: Outcome of the  Review  and  Response  to  Recommendations

244 November 2013

New Solenoid Currents

Old New

Page 25: Outcome of the  Review  and  Response  to  Recommendations

254 November 2013

PRY Geometry – Backing Plates

Updated model, including centre section

Page 26: Outcome of the  Review  and  Response  to  Recommendations

264 November 2013

Residual Field

Page 27: Outcome of the  Review  and  Response  to  Recommendations

274 November 2013

Residual Field

Page 28: Outcome of the  Review  and  Response  to  Recommendations

284 November 2013

PRY Geometry – Lap Joint

Stray field looks ok, but…

Page 29: Outcome of the  Review  and  Response  to  Recommendations

294 November 2013

Lap Joint Design - Forces

94 kN

94 kN

190 kN

N S N S N SAnalogy:

Page 30: Outcome of the  Review  and  Response  to  Recommendations

304 November 2013

Solenoid Mode

Page 31: Outcome of the  Review  and  Response  to  Recommendations

314 November 2013

Flip Mode

Page 32: Outcome of the  Review  and  Response  to  Recommendations

324 November 2013

• Review: very positive feedback• MICE solenoids: not affected by PRY• Engineering suggestions: underway • Compatibility with Step VI• Lap joint design

– Not considered anymore

Summary

Page 33: Outcome of the  Review  and  Response  to  Recommendations

334 November 2013

Additional Slides

Page 34: Outcome of the  Review  and  Response  to  Recommendations

344 November 2013

• Preliminary survey in controlled area– No dose rate above background: move steel to

low background area• Survey on 8” grid pattern using hand held

meter• Examination with High Purity Germanium

(HPGe) gamma spectroscopy unit– only Naturally Occurring Radioactivity Material:

release for free use

Process for Releasing Steel

Page 35: Outcome of the  Review  and  Response  to  Recommendations

354 November 2013

EVA Magnet Steel

Page 36: Outcome of the  Review  and  Response  to  Recommendations

364 November 2013

EVA Magnet Steel• Unknown pedigree

– C 0.3%?– Measurements:

1 month• Controlled area

– Release process: 2 months?

– Risk: only naturally occurring radiation allowed

• Engineering– Additional weight– Space

Page 37: Outcome of the  Review  and  Response  to  Recommendations

374 November 2013

Magnetization – 240 MeV

Flip Mode Solenoid Mode

Page 38: Outcome of the  Review  and  Response  to  Recommendations

384 November 2013

Stray Field JFE-EFE Steel