OTC-27597-MS SCR Life Extension through Managed Shape Change · were applied to streamline this...
Transcript of OTC-27597-MS SCR Life Extension through Managed Shape Change · were applied to streamline this...
OTC-27597-MS
SCR Life Extension through Managed Shape Change M.J. Santala, Y. Constantinides, Chevron Energy Technology Company R. Koska, C. Krapf, D.S. Walters, 2H Offshore Inc
Copyright 2017, Offshore Technology Conference This paper was prepared for presentation at the Offshore Technology Conference held in Houston, Texas, USA, 1–4 May 2017. This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not necessarily reflect any position of the Offshore Technology Conference, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright.
Abstract
Steel catenary risers (SCRs) are a cost effective option for deepwater developments. Throughout industry hundreds of SCRs
have been deployed and have proven to be highly reliable. Nevertheless, as the inventory of SCRs across industry ages and
as operators seek to extend the lives of deepwater platforms beyond their originally intended service life, strategies are
needed to ensure that SCRs can continue to operate reliably. Since touchdown point fatigue damage is a strong factor
determining the service life of an SCR, strategies to mitigate fatigue damage in this region may be required for service life
extension. One such strategy commonly adopted is platform relocation in order to shift the SCR touch down point
throughout the life of the field and hence spreading the fatigue damage along the riser touch down region; however, this
typically needs to be planned for in the original concept development. In this paper, two additional strategies based on
modifying the shape of an existing SCR are presented. These strategies reduce the fatigue damage rate in the original
touchdown point (TDP) region by managing the shape of an existing SCR either through adding buoyancy or by changing the
length of the riser such that the original segment of riser pipe in the TDP region is moved to a low stress region. The
proposed techniques also accommodate riser response during extreme environmental events. The techniques have been
examined based on case studies of a production SCR and an export SCR. Trade-offs in placement of buoyancy and the
impact that shape change has on meeting riser strength requirements are presented. It is shown that the potential exists to
roughly double the computed fatigue life in the touchdown region.
Introduction
Steel catenary risers (SCRs) have proven to be a cost effective and reliable riser system for deepwater development. As a
consequence, SCRs have become one of the most common deepwater riser systems. And, although the population of SCRs is
anticipated to continue growing further, within the next ten years a significant amount of SCRs will be reaching the end of
their planned service life. It is anticipated that in many cases there will be a desire to extend the initial service life of the
floating production platforms and their associated risers. Since touchdown point fatigue damage is a strong factor
determining the design service life of an SCR, strategies to mitigate fatigue damage in this region may be required for service
life extension.
This paper describes two methods that may be considered to mitigate accumulation of touchdown point fatigue;
Addition of buoyancy modules to the in-situ riser to create a marginal lazy wave configuration that shifts the TDP further
away from the nominal TDP.
Change in riser length by removal of joints at the top of the riser to shift the TDP further away from the nominal TDP. It
is expected this would be done should the riser need to be removed from its basket by a heavy lift vessel for replacement
of the SCR tapered stress joint or flex joint.
Learn more at www.2hoffshore.com
2 OTC-27597-MS
Because of the nature of Chevron’s SCR portfolio, it was decided to test these methods for two different size risers hosted by
two different Gulf of Mexico floating platforms in the water depth range of 5000 ft to 7000 ft. The two test cases were a 7”
oil production SCR and a 20” oil export SCR. In both cases the hang-off method was a titanium tapered stress joint (TSJ).
Both risers were fully straked and therefore VIV-induced fatigue damage was negligible compared to wave-induced or hull
vortex-induced motion (VIM)-induced fatigue. The riser / host combinations were based on designs which have been
progressed through detailed design but metocean criteria and soil conditions were updated and other minor simplifications
were applied to streamline this feasibility study. Nevertheless, each riser / host had its own Project-specific design basis and
site-specific metocean conditions*. A full fatigue life analysis was considered, along with the critical strength cases that
controlled the original design. We therefore expect the results to be broadly indicative of those that can be expected in the
same water depth range in the Gulf of Mexico. To simplify the discussion here, presented results will focus on the larger
export riser but key performance metrics will also be reported for the production riser.
Overview of Shape Change Assessment Procedure
An overview of the shape change assessment analysis is presented in the flowchart in Figure 1. The procedure began by
adding buoyancy or changing length with the objective of moving the nominal TDP location by a target distance. The
nominal TDP relocation analysis was done quasi-statically with no environmental loading or vessel offset. The general
analysis workflow was the same whether the buoyancy addition or riser length change strategy was tested.
Figure 1 – Basic Shape Change Assessment Analysis
* Metocean conditions at both sites are representative of deepwater Central Gulf of Mexico conditions in RP-2MET [3].
SCR Design Data
and Fatigue Results
Adjust SCR Configuration (add buoyancy
or add/remove riser joints at hang-off)
TDP Location
Shifted by Target
Distance?
YES
NO
Re-evaluate SCR Fatigue Performance
Target Fatigue
Life Improvement
Factor Achieved?
Re-evaluate Extreme Strength
Performance
Adequate Strength
Performance
Maintained?
Target Distance
to Shift TDP
YES
YES
NO
NO
Assessment Complete
Learn more at www.2hoffshore.com
OTC-27597-MS 3
Since the strategies outlined here change the configuration of the riser during its life, the damage rates for both the original
and modified configurations needed to be computed. Fatigue life was maximized based on study of fatigue critical locations
(typically the TDP, buoyancy section and TSJ). The optimal time for the change from the original to the modified shape was
found through an interactive procedure based on an initial assumed transition time. The transition time was successively
adjusted until the overall fatigue life was maximized at the most critical location (Figure 2). The resulting overall fatigue life
of the system was compared to the fatigue life of the original SCR configuration to determine the fatigue life improvement
factor for the modified configuration.
Figure 2 – Example Fatigue Damage at Critical Locations (addition of 54 buoyancy modules)
After determining the touchdown point fatigue improvement, the strength performance of the modified SCR configuration
was assessed. The most onerous extreme or survival operating condition identified from the original work was assessed for
the modified configuration.
Modeling Assumptions
The wave-induced fatigue analysis (WIF), vortex-induced vessel motion (VIM) fatigue analysis and extreme storm strength
analysis were carried out using non-linear time domain analysis programs.† The SCRs were modeled using beam elements
based on nominal wall thickness and material properties. Appropriate seabed stiffness was considered for the riser section
that lies on the seabed.
The bare pipe, straked pipe and TSJ sections were modeled with the appropriate physical and hydrodynamic properties
consistent with normal design practice. The SCRs were modeled as fully straked from the TSJ to approximately 500 ft
beyond the nominal TDP. With the high VIV suppression efficiency of the strakes, the original analyses showed that for both
of these SCRs, VIV-induced fatigue damage was negligible compared to wave-induced and VIM-induced fatigue damage.
As such, for this feasibility study, VIV analysis was not included.‡
Actual implementation of the buoyancy addition strategy would entail adding a number discrete buoyancy modules over a
length of the riser. The outside diameter (ODDBM), the length (LDBM) and the space between the modules (SpaceDBM) all have
a very comparable length scale. From a modeling standpoint, an equivalent continuous buoyancy section was developed.
The equivalent length (LECB) and equivalent outer diameter (ODECB) of the equivalent continuous buoyancy section were
determined in order to achieve the same amount of total up-thrust and added mass applied to the riser as the discrete
buoyancy modules (Figure 3).
† Flexcom [5] was used for analysis of the export riser and OrcaFlex [4] was used for the analyses of the production riser.
The choice of program was based on the format of pre-existing files from previous work. ‡ VIV forcing on the buoyancy elements was not thought to be an important driver to fatigue life in the cases studied, but in
an actual design, this contribution would need to be explicitly assessed.
0.0
0.2
0.4
0.6
0.8
1.0
1.2
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
Fa
tig
ue
Da
ma
ge
Accu
mu
lati
on
Time / Original Design Life (Fatigue Improvement Factor)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FATIGUE DAMAGE ACCUMULATION300ft TDP Shift, 54 Buoyancy Modules Added 775ft above Nominal TDP
TSJ Buoyancy Original TDP New TDP
- 54 buoyancy modules added for
300ft TDP shift after 99% of original
design life is used- Critical fatigue locations are original
TDP & new TDP, fatigue damage accumulation of 1.0 at a time of 1.93
multiplied by the original design life (fatigue improvement factor of 1.93)
Fatigue Damage Accumulation Reaches Limit of 1.0
Original SCR Configuration
Modified SCR Configuration
Learn more at www.2hoffshore.com
4 OTC-27597-MS
Figure 3 – Modeling Discrete Buoyancy Modules with Equivalent Continuous Buoyancy
Fatigue Analysis
Time domain random sea analyses were conducted to assess wave-induced fatigue (WIF) using three hour vessel motion time
traces (which include vessel offsets) and the associated current profiles. Vortex-induced vessel motion (VIM) fatigue
analyses were conducted to assess the riser fatigue damage that occurs due to low frequency motions of the vessel from
currents. The VIM response was simulated in the time domain as a harmonic motion about the mean offset vessel position
with the associated low frequency transverse motion natural period (Figure 4). The VIM analysis simulation time was
selected to be at least 10 times the average transverse motion natural period of the vessel undergoing VIM.
The contributions from WIF-induced fatigue damage (DWIF) and VIM-induced fatigue damage (DVIM) were computed
separately, but the procedures working from the time domain simulations were the same for each process. For each fatigue
environment (wave or VIM current condition), stress time histories were extracted along the length of the riser and stress
histograms were generated using the rainflow cycle counting method. Fatigue damage was then estimated using the design
S-N curves and SCFs with Miner’s rule to sum the damages from the probabilistically weighted environmental design
conditions.
The factored and combined fatigue life includes a 5% allowance for installation damage and was determined as:
𝐹𝑎𝑐𝑡𝑜𝑟𝑒𝑑 𝐶𝑜𝑚𝑏𝑖𝑛𝑒𝑑 𝐿𝑖𝑓𝑒 = 0.95
10 × 𝐷𝑊𝐼𝐹 + 10 × 𝐷𝑉𝐼𝑀
The two risers studied did have a different sensitivity to wave and VIM damage. In their original configurations the ratio of
separately computed WIF-fatigue life over VIM-fatigue life for the export riser was 2.6 whereas for the production riser the
ratio was 0.29; so the export riser was more sensitive to VIM-induced fatigue and the production riser was more sensitive to
WIF-induced fatigue damage.
Figure 4 – Dynamic Hull VIM Analysis Methodology
Learn more at www.2hoffshore.com
OTC-27597-MS 5
Shifting TDP through Added Buoyancy or Removing Joints
For the 20” export riser the outside diameter of the discrete buoyance elements modeled was 1.85 m (6.07 ft) with a net uplift
of 17.6 kN (3.95 kips) per module. The overall effect of adding the buoyancy elements was that, while in the straked region
the SCR had a wet weight per unit length of 2.40 kN/m (0.164 kips/ft), in the buoyancy region the average wet weight per
unit length was -2.35 kN/m (-0.161 kips/ft). As part of this feasibility study, the efficacy of adding buoyancy to the export
riser starting either 325 ft or 775 ft from the original nominal TDP was tested.§ As shown in Figure 5, the amount of TDP
shift that was achieved per unit buoyancy element was greater when the buoyancy added closer to nominal TDP. This figure
also shows the TDP shift per (40’ length) riser joint removed.
Figure 5 – Amount of Export Riser TDP Shift Achieved Versus Number of Buoyancy Elements Added or Joints Removed
Mitigating TDP Fatigue through Buoyancy Addition
Figure 6 and Figure 7 show the shape of the export riser near the TDP with varying amounts of buoyancy added 325 ft and
775 ft from the original touch down region. Since the basic premise presented here is that life can be extended by using
buoyancy to shift the TDP, Figure 5 might lead one to believe that adding buoyancy at the closer offset would be the most
effective way to achieve this result. For large amounts of buoyancy this was shown to be true. However, as shown in Figure
8, when less buoyancy was used the fatigue life improvement factor was higher when the buoyancy was placed further from
the original TDP. The reason for this is that the buoyancy modules themselves create a new elevated stress cycle region in
the sag- and hog-bend region that they create. If a modified configuration sag- or hog-bend elevated stress cycle region
overlaps the original TDP region then little or no benefit may be achieved by adding buoyancy. Indeed, as shown in Figure
9, though adding either 10 or 14 modules starting at 325 ft from the original TDP significantly shifts the nominal TDP, it
actually led to a worse fatigue damage accumulation rate in the region of the original TDP.**
Adding the buoyancy at the
further offset was shown to have two benefits, the sag- and hog-bend elevated stress cycle was less severe than when the
buoyancy was added at closer offset, and the sag- and hog-bend elevated stress cycle region was further removed from the
original TDP high stress cycle region.
§ For the smaller production riser, buoyancy elements with an outside diameter of 1.45 m (4.76 ft) were considered to be a
practical size that might be implemented. These were modeled as having 8.7 kN (1.95 kips) of uplift per element which
provides comparatively more buoyancy (ratio of buoyancy uplift to original wet weight) than for the export riser. For the
production riser, buoyancy was added starting at offsets of either 400 ft or 775 ft from the original TDP. **
In these cases where adding buoyancy led to worse performance at the original fatigue critical point the fatigue life
improvement factor does not drop below 1.0 since the optimized solution in this case was simply not to make the change.
0
1
2
3
4
5
6
0
5
10
15
20
25
30
0 100 200 300 400 500 600
Nu
mb
er o
f 40
ft Ris
er J
oin
ts R
em
ove
dNu
mb
er
of
Bu
oya
ncy M
od
ule
s A
dd
ed
TDP Shift Distance (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR TDP SHIFTBuoyancy Modules: 1.85m OD, Length & Spacing, Density = 635kg/m3
Buoyancy Added 325ft above Nominal TDP Buoyancy Added 775ft above Nominal TDP
Riser Joints Removed from Hang-off
Learn more at www.2hoffshore.com
6 OTC-27597-MS
Figure 6 – Near Seafloor Export Riser Shape with Buoyancy Added 325ft from Nominal TDP
Figure 7 – Near Seafloor Export Riser Shape with Buoyancy Added 775ft from Nominal TDP
Figure 8 – Fatigue Life Improvement Factor Versus Number of Buoyancy Modules Added to Export Riser
0
100
200
300
400
500
600
700
-1,800 -1,600 -1,400 -1,200 -1,000 -800 -600 -400 -200 0 200 400
Ele
va
tio
n a
bo
ve
Se
ab
ed
(ft
)
Horizontal Distance from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR CONFIGURATIONTDP Shift with Buoyancy Modules Added 325ft above Nominal TDP
Original Configuration 7 Modules (100ft TDP Shift)
10 Modules (150ft TDP Shift) 14 Modules (200ft TDP Shift)
22 Modules (280ft TDP Shift) 32 Modules (385ft TDP Shift)
54 Modules (550ft TDP Shift)
Buoyancy Modules
Nominal TDP Location
325ft
0
100
200
300
400
500
600
700
-1,800 -1,600 -1,400 -1,200 -1,000 -800 -600 -400 -200 0 200 400
Ele
va
tio
n a
bo
ve
Se
ab
ed
(ft
)
Horizontal Distance from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR CONFIGURATIONTDP Shift with Buoyancy Modules Added 775ft above Nominal TDP
Original Configuration 7 Modules (50ft TDP Shift)
14 Modules (100ft TDP Shift) 22 Modules (150ft TDP Shift)
32 Modules (200ft TDP Shift) 54 Modules (300ft TDP Shift)
Buoyancy Modules
Nominal TDP Location
775ft
0.0
0.5
1.0
1.5
2.0
2.5
3.0
0 10 20 30 40 50 60
Fa
tig
ue
Lif
e I
mp
rove
me
nt
Fa
cto
r (-
)
Number of Buoyancy Modules Added
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FATIGUE LIFE IMPROVEMENT FACTORFatigue Life Extension by Adding Buoyancy Modules
Combined Life, Wave Fatigue + VIM Fatigue
Buoyancy Added 325ft Above TDP Buoyancy Added 775ft Above TDP
Learn more at www.2hoffshore.com
OTC-27597-MS 7
Figure 9 – Factored Fatigue Lives for Export Riser with Buoyancy Added 325ft from Nominal TDP
Figure 10 – Factored Fatigue Lives for Export Riser with Buoyancy Added 775ft from Nominal TDP
1
10
100
1,000
10,000
100,000
-1,000 -800 -600 -400 -200 0 200 400 600 800
Fa
cto
red
Fa
tig
ue
Lif
e (
ye
ars
)
Arc Length from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FACTORED FATIGUE LIFE AT TDPAPI X' in Seawater with CP, KDF=2.5, SCF=1.3, Safety Factor=10
Buoyancy Added 325ft above Nominal TDP, Wave Fatigue + VIM Fatigue
Original Configuration 7 Modules Added 10 Modules Added
14 Modules Added 22 Modules Added 32 Modules Added
54 Modules Added
1
10
100
1,000
10,000
100,000
-1,600 -1,400 -1,200 -1,000 -800 -600 -400 -200 0 200 400
Fa
cto
red
Fa
tig
ue
Lif
e (
ye
ars
)
Arc Length from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FACTORED FATIGUE LIFE AT TDPAPI X' in Seawater with CP, KDF=2.5, SCF=1.3, Safety Factor=10
Buoyancy Added 775ft above Nominal TDP, Wave Fatigue + VIM Fatigue
Original Configuration 7 Modules Added 14 Modules Added
22 Modules Added 32 Modules Added 54 Modules Added
Learn more at www.2hoffshore.com
8 OTC-27597-MS
Mitigating TDP Fatigue through Joint Removal
Removing joints from the top of the riser shifts the TDP but maintains the basic catenary shape (Figure 11) and the general
TDP fatigue damage pattern also remains similar but shifts accordingly (Figure 12). For both the risers tested here, removing
just a single 40 ft joint achieved an improvement factor on TDP fatigue life of nearly 2.0 and with three joints removed, the
fatigue life improvement factor marginally exceeded 2.0 for both risers considered. The improvement factor versus number
of joints removed for the export riser is shown in Figure 13.
Figure 11 – Near Seafloor Export Riser Shape with Riser Joints Removed from Top
Figure 12 – Factored Fatigue Lives for Export Riser Joints Removed from Top
0
100
200
300
400
500
600
700
-1,600 -1,400 -1,200 -1,000 -800 -600 -400 -200 0 200 400
Ele
va
tio
n a
bo
ve
Se
ab
ed
(ft
)
Horizontal Distance from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR CONFIGURATIONTDP Shift by Removing 40ft Riser Joints at Hang-off
Original Configuration 1 Riser Joint Removed 2 Riser Joints Removed 3 Riser Joints Removed
Nominal TDP Location
1
10
100
1,000
10,000
100,000
-500 -400 -300 -200 -100 0 100 200 300 400 500
Fa
cto
red
Fa
tig
ue
Lif
e (
ye
ars
)
Arc Length from Nominal TDP (ft)
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FACTORED FATIGUE LIFE AT TDPAPI X' in Seawater with CP, KDF=2.5, SCF=1.3, Safety Factor=10Riser Joints Removed from Hang-off, Wave Fatigue + VIM Fatigue
Original Configuration 1 Joint Removed 2 Joints Removed 3 Joints Removed
Learn more at www.2hoffshore.com
OTC-27597-MS 9
Figure 13 – Fatigue Life Improvement Factor Versus Number of Joints Removed from Export Riser
Verifying Design Strength Requirements of Modified Shape Risers
From previous design work on both of these riser configurations, the governing cases controlling strength had been
identified. For both risers, the governing strength case was a 100-year hurricane case with intact mooring system. For the
export riser, the ratio of peak to yield stress was higher at the TSJ than near the TDP. Adding buoyancy to the export riser
provided a modest reduction in the peak stresses at the TSJ (Figure 14) and removing joints imposed a modest increase in the
peak stresses at the TSJ (Figure 15). Near the TDP, peak stresses in the export riser varied quite modestly based on the
amount of buoyancy added or number of joints removed (Figure 14 and Figure 15).
For the production riser the ratio of peak to yield stress was higher at the TDP than TSJ and adding buoyancy helped reduce
this peak stress quite dramatically; the ratio improved by a factor greater than two when more than 33 buoyancy modules
were added (at either offset). On the other hand, when riser joints were removed from the production riser, peak stresses
increased at the TDP. The increase in peak stress near the TDP in the production riser when two or more joints were
removed was so high that this would not have been a viable option for the particular production riser studied.
As shown in Figure 8 and Figure 14, adding 22 buoyancy modules 325 ft from the nominal TDP of the export riser provides a
fatigue life improvement factor of over 1.5 and gives adequate performance from a strength standpoint. Interestingly,
however, in this case in the near offset case of the 100-year hurricane a secondary touchdown point can form (Figure 16).
Though the appearance of this secondary touchdown region does not necessarily preclude this particular solution, the
implications of designing a riser which takes on such a configuration during extreme events should carefully be considered
before doing so. Of course, such double-touchdown geometries can be avoided either by adding more buoyancy (Figure 17)
or perhaps by applying the same amount of buoyancy at a further offset.
Overall, the strength studies indicate that shifts in TDP sufficient to extend fatigue life by a factor of two can be achieved and
simultaneously meet strength requirements. However, depending on what the critical design point in the original design was
it may be that some options are precluded from use.
0.0
0.5
1.0
1.5
2.0
2.5
3.0
0 1 2 3
Fa
tig
ue
Lif
e I
mp
rove
me
nt
Fa
cto
r (-
)
Number of 40ft Riser Joints Removed at Hang-off
Chevron ETC - SCR Shape Change Assessment
BIG FOOT 20" SCR - FATIGUE LIFE IMPROVEMENT FACTORFatigue Life Extension by Removing 40ft Riser Joints at Hang-off
Combined Life, Wave Fatigue + VIM Fatigue
Learn more at www.2hoffshore.com
10 OTC-27597-MS
Figure 14 – Export Riser Peak Stresses in 100-year Hurricane vs Number Buoyancy Modules Added
Figure 15 – Export Riser Peak Stresses in 100-year Hurricane vs Number Joints Removed
Learn more at www.2hoffshore.com
OTC-27597-MS 11
Figure 16 – Export Riser 100-year Hurricane Near Offset Sag Bend with 22 Buoyancy Modules at 325ft from Nominal TDP
Figure 17 – Export Riser 100-year Hurricane Near Offset Sag Bend with 54 Buoyancy Modules at 325ft from Nominal TDP
Discussion and Conclusions
The key conclusions and recommendations from the SCR shape change assessment are as follows:
For both risers studied, TDP zone fatigue life could be roughly doubled by adding buoyancy close to the end of the
original riser design life.
o Adding a large number of buoyancy elements starting close to the TDP led to the overall greatest benefit in
fatigue life for both risers considered in this study.
o Generally, a longer buoyancy section results in a larger fatigue life compared to a shorter buoyancy section.
o If the amout of buoyancy added is to be minimized for cost or operational reasons, adding at a further
distance from the TDP may be necessary to avoid having a secondary hog-sag stress region near the orginal
TDP stress region.
o Adding a small number of buoyancy modules near the touchdown point may also cause secondary contact
of the riser with the seabed in some near offset conditions.
o For the risers studied, strength requirements could always be accomodated. Peak stresses did not
universally decrease with the addition of buoyancy so such cases would always need to be checked.
Learn more at www.2hoffshore.com
12 OTC-27597-MS
For both risers studied, TDP zone fatigue could also be nearly doubled by removing a single 40 ft joint close to the
end of the original riser design life. However, removal of joints proved more challenging from a strength
standpoint.
o For one of the cases, removing even a single joint did not pass the preliminary strength checks performed
here. For the other case, removing a single joint was acceptable but the strength case design margin was
reduced.
o The potential for removing riser joints is dependent on the specific configuration and original design
margin. The particulars of which case did and did not work here should not be generalized beyond the fact
that removing lengths from a previously optimized design may prove challanging and needs to be checked.
In summary, both methods of shifting the TDP are capable of providing improved fatigue life, but the strength response of
each specific riser needs to be evaluated on a case-by-case basis. The buoyancy approach certainly affords more opportunity
for fine adjustment/optimization in a real project scenario and there are field-proven techniques for adding buoyancy to an in
site riser. However, having two options (buoyancy addition or joint removal) increases the chance of finding a workable
solution for specific cases and further allows the costs and operational implications of the different solutions to be compared.
For example, if a riser flex joint needed to be changed out as part of life extension, the joint removal option may become
much more attractive operationally since the riser would already need to be lifted from the porch in that case. Depending on
the original SCR design, in addition to confirming adequate strength response, several items that would need to be confirmed
include the following:
If buoyancy modules are added to an SCR, then strakes would need to be removed from the buoyant section. Any
resulting changes in VIV response would need to be determined in order to confirm that the riser maintains adequate
fatigue performance including the effects of VIV;
Riser maintains adequate clearance with other risers, umbilicals and mooring lines;
The change in riser shape associated with adding buoyancy does not cause flow assurance problems, such as
slugging;
Hang-off loading on the riser porch remains within allowable limits.
Nomenclature
DVIM Fatigue damage due to vortex-induced hull motion
DWIF Fatigue damage due to wave-induced motions
SCF Stress concentration factor
SCR Steel catenary riser
TDP Touchdown point
TSJ Tapered stress joint
VIM Vortex-induced motion of platform
VIV Vortex-induced vibration (here in context of vortices shed directly by riser)
References
1. API – “Recommended Practice for Design of Risers for Floating Production Systems and TLPs”; API-RP-2RD, 1st Edition; June
1998.
2. API – “Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms – Load and Resistance
Factor Design”; API-RP-2A-LRFD, 2nd Edition; April 1994.
3. API – “Derivation of Metocean Design and Operating Conditions – ANSI/API Recommended Practice 2MET”, API-RP2MET,
First Edition, November, 2014.
4. Orcina – “OrcaFlex Reference Manual”; Version 10.0d; 2016.
5. MCS International – “FLEXCOM Three Dimensional Nonlinear Time Domain Riser Analysis Software”; Version 7.9; April
2009.
Learn more at www.2hoffshore.com