    Chapter 6:

    RISK ASSESSMENT

    By:

    Dr. Mior Ahmad Khushairi Bin Mohd ZahariLecturer, FKKSA, UMP09-5492837/[email protected];[email protected]

    BKB3533

    OSH in Chemical Biotechnology

    Industries

  • 7/26/2019 OSH Risk Assessment

    2/12

    Objectives

    Describe risk assessment

    Construct Fault Tree diagram

  • 7/26/2019 OSH Risk Assessment

    3/12

    INTRODUCTION

    The term risk assessment comes from the insuranceindustry & was one stage in their process of determiningand spreading liabilities they carried.

    Objective:

    to identify hazards so that action can be taken toeliminate, reduce or control them before accident

    that cause damage or injury occur.

  • 7/26/2019 OSH Risk Assessment

    4/12

    What is Risk Assessment ?

    Risk assessment is the process where you: identify hazards,

    analyze or evaluate the risk associated with that hazard, and

    determine appropriate ways to eliminate or control the hazard.

    In practical terms, a risk assessment is a thorough look at yourworkplace to identify those things, situations, processes, etc that maycause harm, particularly to people. After identification is made, you

    evaluate how likely and severe the risk is, and then decide whatmeasures should be in place to effectively prevent or control the harmfrom happening.

  • 7/26/2019 OSH Risk Assessment

    5/12

    Why is Risk Assessment important?

    Risk assessments are very important as they form anintegral part of a good occupational health and safetymanagement plan.They help to:

    create awareness of hazards and risks,

    identify who may be at risk (employees, cleaners, visitors,contractors, the public, etc),

    determine if existing control measures are adequate or ifmore should be done,

    prevent injuries or illnesses when done at the design orplanning stage, and

    prioritize hazards and control measures.

  • 7/26/2019 OSH Risk Assessment

    6/12

    What is a goal of Risk Assessment ?

    The aim of the risk assessment process is to remove a hazardor reduce the level of its risk by adding precautions orcontrol measures, as necessary. By doing so, you have

    created a safer and healthier workplace.

  • 7/26/2019 OSH Risk Assessment

    7/12

    Fault Tree Analysis

    Fault Tree is a method by which a particular undesiredsystem failure mode can be expressed in terms ofcomponent failure modes and operator actions.

    The system failure mode to be considered is termed thetop event and fault tree is developed in branches belowthis event showing it causes.

  • 7/26/2019 OSH Risk Assessment

    8/12

    Fault Tree Procedure

    1. Draw the top event2. Determine major events that contribute to the top event

    3. ParallelAND; SeriesOR

    4. Consider the intermediate events, what events must occurto contribute to that intermediate event?

    5. Continue until all the branches terminated by basic,undeveloped or external events.

  • 7/26/2019 OSH Risk Assessment

    9/12

    Flat Tire

    Flat Tire

    Tire FailureRoad

    Debris

    DefectiveTire

    Worn Tire

    Well defined

    accidents/Topevent

    Basic/Intermediate

    events

    Basic events

  • 7/26/2019 OSH Risk Assessment

    10/12

    Process Plant FireWell defined

    accidents/Top

    event

    Basic/Intermediate

    events

    Basic events

    Fire

    Fuel

    Leakingjoint

    Oxygen

    Drainvalveopen

    Ignition

    Weldingin

    progress

    Electricmotor

  • 7/26/2019 OSH Risk Assessment

    11/12

    Fault Tree Logic Transfer Components

    BASICevent

    A fault event that needs no further definition

    INTERMEDIATEevents

    An event that results from the interaction of anumber of other events

    UNDEVELOPED

    eventAn event that cannot be developed further dueto lack of suitable information

    EXTERNALevent

    An event that is a boundary condition to the faulttree

    Expandedevent

    Used to transfer the fault tree into and out of asheet of paper

  • 7/26/2019 OSH Risk Assessment

    12/12

    Advantages Disadvantages

    It begins with a top event

    Its specific Used to determine min cut

    sets

    Computer application withreference libraries

    For complicated

    processes, FT will beenormous

    Will take a long time

    Not all failure modesmight have been

    considered Possibility of a partial

    failure

    Different structures if

    developed by differentindividual