7/26/2019 OSH Risk Assessment
1/12
Chapter 6:
RISK ASSESSMENT
By:
Dr. Mior Ahmad Khushairi Bin Mohd ZahariLecturer, FKKSA, UMP09-5492837/[email protected];[email protected]
BKB3533
OSH in Chemical Biotechnology
Industries
-
7/26/2019 OSH Risk Assessment
2/12
Objectives
Describe risk assessment
Construct Fault Tree diagram
-
7/26/2019 OSH Risk Assessment
3/12
INTRODUCTION
The term risk assessment comes from the insuranceindustry & was one stage in their process of determiningand spreading liabilities they carried.
Objective:
to identify hazards so that action can be taken toeliminate, reduce or control them before accident
that cause damage or injury occur.
-
7/26/2019 OSH Risk Assessment
4/12
What is Risk Assessment ?
Risk assessment is the process where you: identify hazards,
analyze or evaluate the risk associated with that hazard, and
determine appropriate ways to eliminate or control the hazard.
In practical terms, a risk assessment is a thorough look at yourworkplace to identify those things, situations, processes, etc that maycause harm, particularly to people. After identification is made, you
evaluate how likely and severe the risk is, and then decide whatmeasures should be in place to effectively prevent or control the harmfrom happening.
-
7/26/2019 OSH Risk Assessment
5/12
Why is Risk Assessment important?
Risk assessments are very important as they form anintegral part of a good occupational health and safetymanagement plan.They help to:
create awareness of hazards and risks,
identify who may be at risk (employees, cleaners, visitors,contractors, the public, etc),
determine if existing control measures are adequate or ifmore should be done,
prevent injuries or illnesses when done at the design orplanning stage, and
prioritize hazards and control measures.
-
7/26/2019 OSH Risk Assessment
6/12
What is a goal of Risk Assessment ?
The aim of the risk assessment process is to remove a hazardor reduce the level of its risk by adding precautions orcontrol measures, as necessary. By doing so, you have
created a safer and healthier workplace.
-
7/26/2019 OSH Risk Assessment
7/12
Fault Tree Analysis
Fault Tree is a method by which a particular undesiredsystem failure mode can be expressed in terms ofcomponent failure modes and operator actions.
The system failure mode to be considered is termed thetop event and fault tree is developed in branches belowthis event showing it causes.
-
7/26/2019 OSH Risk Assessment
8/12
Fault Tree Procedure
1. Draw the top event2. Determine major events that contribute to the top event
3. ParallelAND; SeriesOR
4. Consider the intermediate events, what events must occurto contribute to that intermediate event?
5. Continue until all the branches terminated by basic,undeveloped or external events.
-
7/26/2019 OSH Risk Assessment
9/12
Flat Tire
Flat Tire
Tire FailureRoad
Debris
DefectiveTire
Worn Tire
Well defined
accidents/Topevent
Basic/Intermediate
events
Basic events
-
7/26/2019 OSH Risk Assessment
10/12
Process Plant FireWell defined
accidents/Top
event
Basic/Intermediate
events
Basic events
Fire
Fuel
Leakingjoint
Oxygen
Drainvalveopen
Ignition
Weldingin
progress
Electricmotor
-
7/26/2019 OSH Risk Assessment
11/12
Fault Tree Logic Transfer Components
BASICevent
A fault event that needs no further definition
INTERMEDIATEevents
An event that results from the interaction of anumber of other events
UNDEVELOPED
eventAn event that cannot be developed further dueto lack of suitable information
EXTERNALevent
An event that is a boundary condition to the faulttree
Expandedevent
Used to transfer the fault tree into and out of asheet of paper
-
7/26/2019 OSH Risk Assessment
12/12
Advantages Disadvantages
It begins with a top event
Its specific Used to determine min cut
sets
Computer application withreference libraries
For complicated
processes, FT will beenormous
Will take a long time
Not all failure modesmight have been
considered Possibility of a partial
failure
Different structures if
developed by differentindividual