Osceola County
Transportation&
Transit
December 10, 2019Poinciana
Presentation
![Page 2: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/2.jpg)
Responsibilities
• Traffic Engineering• Transportation Planning• Traffic Operations
o Signalso Signso Crosswalks (striping)
• Constructiono Roadso Sidewalkso Trails
![Page 3: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/3.jpg)
Osceola County Road Widening Program
![Page 4: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/4.jpg)
Simpson Road
• Widening from 2 to 4 lanes, with sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Phase 1 – Osceola Parkway to Boggy Creeko Construction FY2022
• Phases 2, 3, and 4 – Osceola Parkway to US 192
• Design advertised now• Construction FY2023
• Website -www.improvesimpsonroad.com
![Page 5: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/5.jpg)
Boggy Creek Road
• Widen from 2 to 4 lanes approximately 5.9 miles
• Simpson Road to Narcoossee Road
• Sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Design advertisement in January 2020
• Construction FY2024
![Page 6: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/6.jpg)
Bill Beck Blvd
• New 2-lane roadway approximately 0.7 mile
• Osceola Parkway to Woodcrest Blvd
• Sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Design update complete in FY2020
• Construction in FY2021
![Page 7: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/7.jpg)
Partin Settlement Road
• Widen from 2 to 4 lanes approximately 2.7 miles
• Neptune Road to E. Lakeshore Blvd
• Sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Design advertisement in January 2020
• Construction FY2024
![Page 8: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/8.jpg)
Poinciana Blvd
• Widen from 2 to 4 lanes approximately 5.8 miles
• Pleasant Hill Road to Crescent Lakes Way
• Sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Design advertisement in January 2020
• Construction FY2024
![Page 9: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/9.jpg)
Neptune Road
• Widen 3.5 miles from 2 to 4 lanes• Partin Settlement Rd to US 192• Finalizing Project Development
and Environment (PD&E) study for the widening, rehabilitation and reconstruction of Neptune Road including sidewalks, bicycle accommodations, curb and gutter, and drainage improvements
• Design advertised now• Construction FY2022• Website -
www.improveneptuneroad.com
![Page 10: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/10.jpg)
CR 532
• Widen from 2 to 4 lanes approximately 2.9 miles
• Old Lake Wilson to US 17/92• Sidewalks, bicycle
accommodations, curb and gutter, and drainage improvements
• Part of Poinciana Parkway Extension Project – Partnership with CFX
• Design advertisement Early 2020• Construction FY 2023 - FY2024
![Page 11: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/11.jpg)
I-4/CR 532 Interchange
• Design of modified interchange as a diverging diamond configuration
• Partnership with FDOT• Design complete in FY2020• Construction in FY2021• State funds
![Page 12: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/12.jpg)
Hoagland Boulevard
• From John Young Parkway to 5th Streeto 3.15 mileso approx. $39 milliono New 2.15 mile four-lane divided
roadwayo Widening 2 to 4 lane 0.91 mile divided
roadwayo 6’ bike laneso 6’-8’ sidewalks on both sides of
roadwayo Curb and guttero Bridge Over SunRail tracks and
reconstruction of Shingle Creek Bridgeo Completion anticipated 2021o https://www.osceola.org/agencies-
departments/transportation-transit/projects/hoagland-blvd/
![Page 13: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/13.jpg)
John Young Parkway
• From south of Pleasant Hill Road to West Portage Streeto Adding one lane in each directiono Adding a two-way flyovero Modifying median openingso Signalizationo Bike laneso Designo Approximately $40 million for ROW;
not yet funded in FDOT work programo Approximately $90 million to build; not
yet funded in FDOT work programo http://www.cflroads.com/project/418403-
3/SR_600_US_17_92_from_Pleasant_Hill_Road_to_Portage_Street
![Page 14: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/14.jpg)
John Young Parkway/Pleasant Hill Rd Intersection
• Interim Improvement to intersection
• Quad Road concept – disperses traffic over two intersections
• Re-aligns entrance into The Oakes Subdivision
• FDOT finalizing PD&E• Moving into Design and ROW
acquisition• Money being placed into FDOT
work program
![Page 15: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/15.jpg)
Central Florida Expressway Authority
![Page 16: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/16.jpg)
Osceola Parkway Extension
• Preferred alignment going to CFX Board – December 12, 2019• Design in 2020• Extend roadway to Nova Road
![Page 17: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/17.jpg)
Northeast Connector to Nova Road
• CFX Board approved moving forward with the PD&E for the portion of the Northeast Connector Expressway to Nova Road
• PD&E progressing
![Page 18: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/18.jpg)
Southport Connector Expressway
• CFX Board approved moving forward with PD&E for Southport Connector Expressway
• PD&E Being Advertised
![Page 19: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/19.jpg)
Poinciana Parkway Extension
• Widen existing Poinciana Parkway from 2 to 4 lanes
• Poinciana Parkway Extension from US 17/92 to CR 532
• Design contract being advertised first quarter 2020
![Page 20: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/20.jpg)
• Story Creek Boulevard: This is a connector Framework roadway that is being constructed by developers to provide a connection between Pleasant Hill Road and Reaves Road. The Reaves Road side has started, and the County is coordinating with the developer on a timeline for the portion at Pleasant Hill Road to complete the connection.
• Roundabouts• Marigold / Peabody South• Marigold / Laurel Ave• Marigold / San Lorenzo• FDOT is conducting a Safety Study to analyze for potential safety improvements and/or
roundabouts at these intersections. Potential design and construction would be funded by FDOT.
Other Projects
![Page 21: Osceola County Transportationprfsc.org/wp-content/uploads/2019/12/Poinciana-12-10-19...• From John Young Parkway to 5th Street o 3.15 miles o approx. $39 million o New 2.15 mile](https://reader033.fdocuments.us/reader033/viewer/2022042008/5e70c0ff2f37a2651f77a174/html5/thumbnails/21.jpg)
Thank you!
www.Osceola.org407-742-0552
Tawny Olore, [email protected]
October 22, 2018Rotary Club of
Kissimmee