ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

17
ORKA Preservation Task Force first meeting Wednesday, February 8, 2012 1 Notes by Peter H. Garbincius Notes from meeting are interspersed (Riesselmann and Sands did not participate)

description

ORKA Preservation Task Force first meeting Wednesday, February 8, 2012. Notes by Peter H. Garbincius Notes from meeting are interspersed (Riesselmann and Sands did not participate). m y interpretation and priorities:. - PowerPoint PPT Presentation

Transcript of ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

Page 1: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

1

ORKA Preservation Task Forcefirst meeting

Wednesday, February 8, 2012

Notes byPeter H. GarbinciusNotes from meeting are interspersed(Riesselmann and Sands did not participate)

Page 2: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

2

Page 3: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

3

my interpretation and priorities:• Not to immediately concentrate on costs!• Prime issues seem to be material handling

and possible interference for CDF building refurbishment for and IARC operations

• When we understand the requirements of ORKA, IARC, and their mutual interactions, then we can work on estimates what about BNL/RHIC/sPhoenix?

• Only concentrate on these ORKA/IARC issues, not on items that are independentplease humor my learning curve!

Page 4: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

4

CHANGES from ORKA proposal

S-shaped (dogleg) K+ beam dump to Tevatron tunnel

CDF solenoid remains parallel to Tevatron tunnel

5’ x 8’ door BIG door Crane hook coverage in assembly hall?Go look at it at CDF!

This area of target & K+ beam is at 710’ elevation

12’ x 26’ transporter CAN move beyond Central Detector installed in Collision Hall

radiation shielding studies

Page 5: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

5

Doug Jensen working on design of a short 14 m 0.6 GeV/c enriched K+ beam

are low-p components availability from BNL?Very likely, except for two 600 KV separators.

95 GeV from MI

to beam stopstopping target

Page 6: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

6

Page 7: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

7

What does ORKA need from CDF?What has to go? How? When?

ORKA fits here!

target position

modify plug for close-in quads note SS insert 3o-10o

BNL may wantCentral CalorimetersDecision = Fall 2012?

Tevatron beam 723’-4.25”

4’ high elevation change

Hanging steel CAN be removed with detector in place, needs engineered move

Page 8: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

8

Magnetic Circuitsmall contribution from central calorimetersno need to map B-field, plenty of K+ →π+ πo

Is flux return steel just top and bottom - YES, or does it include North and South walls? - NO

3o-10o SS plug

Page 9: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

9

comparable installation:Remove CDF

SVX & CTC intact?

Install ORKA in pieces in

collision hall?

Page 10: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

10

Can plug be modified for input beam quads while in collision hall? NO, must be done in Assembly Hall

Non-magnetic Stainless Steel Plug 3o-10o. Does removing it provide enough room for Quadrupole Magnets?

Page 11: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

11

X-5X

X-3

X-4

X-7X-1

X-3

X-4?

?

?X-2 X

X

out 1200 ton door – orderCentral Detector is #2

SVX, CTC, and Central Calorimeter Archesare removed in Assembly Hall

Page 12: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

12

questions?• When does the big Door have to be open?• How much can be done through 5’ x 8’ door?• How much access is needed to Assembly Pit,

upstairs CDF building, crane, when?• Can N/S muon walls, plug, forward toroids be

removed without removing central detector?• How does Cable Bridge get removed?• Even if we could remove roof of Collision Hall

for later installation, do we have to remove upper notch steel hung from ceiling first?

Page 13: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

13

continued…• How much space and time with big door open:– Soon to remove CDF before IARC referbishing?– Later to install ORKA during IRAC operations?

• What other massive, bulky items? – Target and 600 MeV/c beamline elements– Beam stop (in d.s. tunnel)

• What about provision for plasma wakefield test?

• next meeting: ___________ Terry E will poll

Page 14: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

14

710’ elev

706’ elev garage for door

710’ elev710’ elev

Limit of 50 ton crane coverage ~ 4.5’ from wallPHG – 4march2012

Page 15: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

15

Discussion on Feb 8, 2012

• What would be ideal schedule to minimize impact on IARC schedule & accommodate ORKA?– Feb 2014 IARC building complete, begin refurbish CDF bldg– Remove CDF components now, including cable bridge, replace

Solenoid & (modified) plug(s) into Collision Hall ~ 18 Months + $ X M (JDL will provide better estimate), then, if provisions made, public tours in CDF Collision Hall

– End of 2014 – begin IARC operations in deep pit starting from North (far) end, leaving space for 1200 ton shield door and 1 or 2 transporters for ORKA

– ORKA, if and when approved, assemble elsewhere, use just crane and 1 or 2 transporters for installation, then close shield door

– IARC can expand through Assembly Hall, but would need to allow for opening door and use of 1-2 transporters

Page 16: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

16

continued discussion• Would Fermilab invest in display/tours before

installation of ORKA? Expenses could be saved– human engineering, life safety, egress– repurposing building from experiment => public

• Even temporarily…before ORKA• Who decides this usage which implies what codes apply?• Grandfathering?

– What are these saved refurbishment costs and how do they compare to, or offset some of the investment of removing CDF components?

• Once we have cost estimate and timescale, Director must choose between ORKA investment (gamble), public tours, & impact on IARC operations

Page 17: ORKA Preservation Task Force first meeting Wednesday, February 8, 2012

17

4march2012: Peter checked

• Exact size of CDF equipment transporter: 25’ + 32” = 27’-8” x 11’-11”

• Crane coverage – carriage and south catwalk as found: hook is 12’ from I-beam + 18” from wall (upstairs). I-beam is 4’ from catwalk rail, catwalk rail is 4’ from major wall (downstairs) so I-beam is at same position as downstairs wall

• From 3rd floor, measured crane had another 90” = 7.5’ travel before reaching stop => 12’-7.5’=4.5’ from I-beam = downstairs wall.