Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the...
Transcript of Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the...
![Page 1: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/1.jpg)
![Page 2: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/2.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Method Statement
Demolition of Workshop & Stores
METHOD STATEMENT REGISTER/ISSUE RECORD SHEET.
No. Method Statements
1. Original Method Statement
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Status
Distribution
Client::
Client Representative:
CDM Co-ordinator:
Site:
File:
Status : I - Information, C - Comment, A - Approval, W – Working
![Page 3: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/3.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
HEALTH & SAFETY METHOD STATEMENT BRIEFING SHEET
Please complete the section below – In completing and signing this sheet you are demonstrating that you have read, understood and been briefed onto your safe system of work contained within your method statement and activity specific risk assessment Reference Method Statement: Demolition of Workshop & Stores
Surname
First name
Employer
Briefed By
Date
Signature
![Page 4: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/4.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Section Content
1.0 Method Statement
2.0 Method and Sequence
3.0 Documentation Required Prior to Work Commencing
4.0 Identified Hazards – General
5.0 Programme
6.0 Resources
7.0 Personal Protective Equipment
![Page 5: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/5.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
1.0 Method Statement
1.1 Scope of the works
The works are to be executed safely and diligently in accordance with all current legislation. The scope of the work involves the asbestos removal, environmental clean, soft strip of all
deleterious materials, structural demolition & processing of all materials
Workshop & Stores Building
1.2 The Surrounding Area The area surrounding the Workshop & Stores is made up of structures within the Didcot A
site, to include the Turbine Hall & Didcot B to the west & National Grid sub-station to the North.
2.0 Method and Sequence The method & sequence will be as follows: 1. Exclusion Zone
2. Asbestos Removal 3. Environmental Control 4. Soft Strip 5. Demolition of Structure
a. Canopies b. Crane c. Columns
6. Processing & Removal
![Page 6: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/6.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Exclusion Zone The site will be kept clean and tidy to eliminate slips, trips and falls. Heras fence panels,
feet, clips and warning signs will be clearly displayed. Transit routes for plant and pedestrians will be set up for the separate activities happening
within the demolition boundary, these may change as work progresses. There will be a need & requirement to isolate working areas or prohibit access; this will be
through the use of Heras fencing or barriers, erected, and appropriate warning signs erected.
Appropriate signs will delineate the barriers and traffic and pedestrian routes. When operations are being undertaken the whole area will be enforced as an exclusion
zone for non-demolition personnel Sentries/banksmen will be in attendance during operations to ensure that no unauthorised
access into the working area during the works Any pre-existing voids or openings that have no protection will have fencing or barriers
erected Heras fencing will be erected across any opening within the perimeter walls (doorways) to
prevent unauthorised access during the works Prior to starting any works the site supervisor will walk the site with Mechanical & Electrical
RWE team and inspect the structures to understand that the building has been disconnected of all known services
Entrance to Workshop & Stores secured with Heras Fencing
Access to Workshop & Stores
![Page 7: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/7.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Heras fencing will be erected to prohibit access to the working area during the demolition
works. All Heras fencing will be erected in accordance with manufacturers instructions. Firstly an operative will place the feet along the proposed fencing line at the approximate
distance required to accept the fencing panels. Two operatives will pick up the fence panel and begin the placing of the fence into the
positioned feet. Each fence panel will be fixed to the next, progressively throughout the erection, with two
number clips using handheld tools.
Finally back stays will be connected to every foot and adjoining fence panel to ensure support.
The site will be kept clean and tidy to eliminate slips, trips and falls. The following materials will be used; Heras fence panels, feet, clips and warning signs clearly displayed on the fence.
Transit routes for plant and pedestrians will be set up for the separate activities happening
within the demolition boundary. These may change as work progresses, therefore will be labelled.
Doorway to Workshop
Heras fencing placed across doorway to prohibit access to working area
![Page 8: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/8.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Yellow route Vehicle Access
Asbestos Removal A series of Demolition & Refurbishment Surveys have been completed to identify all
Asbestos Containing Materials. A fully licensed sub contractor will undertake the asbestos removal works
Using the ESG Asbestos surveys (ASO3509 -015) all notifiable asbestos materials will be
marked up with a RED cross / A and all non notifiable asbestos will be marked up with Orange cross / A.
Where it is not possible to see or reach the asbestos materials for spraying the wall or floor
adjacent to the material will be sprayed with an ‘A’ and arrow pointing to the location. The method, scope & plan of works will be covered under a separate Method Statement A copy of the Asbestos Removal Contractor’s Plan of Work shall be forwarded to RWE
Npower & HSE prior to commencement of the works; these works will be carried out by an approved competent sub contractor.
Prior to the removal of Notifiable Asbestos a Fourteen-Day Notice to the HSE (Form ASB5)
will be in place. A licensed sub contractor will remove Notifiable Asbestos under The CAR 2012.
![Page 9: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/9.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Asbestos identified prior to soft strip
All Non-Notifiable Asbestos will be removed whole where possible. The material will be kept
damp using a fine water spray. ACM’s will be removed from the building at regular intervals, thus ensuring that hazardous
substances are not accumulating on site causing risk to operatives or trespassers. The material will be disposed of into suitable containers, with the material removed in
accordance with Duty of Care Regulations. All Notifiable non-licensed ACM will be notified to the HSE prior to works commencing (this
may be undertaken on the day, but must be before works commence) using form ASBNNLW1.
All ACM’s (Notifiable licensed asbestos; Notifiable non-licensed; and non-notifiable
asbestos) will be removed by suitably trained personnel equipped with the required P.P.E and R.P.E –Disposal overalls Cat 3 type 5/6 / Half face masks and P3 Filters which will be face fitted by a competent person to the specified model
All Asbestos Air Clearance Certificates shall be forwarded promptly to the office for inclusion
within the Health and Safety File. A temporary storage area will be clearly identified, marked out, segregated and sealed at all
times. Transit routes for the movement of the asbestos must be clearly advised to all personnel
working on site. Environmental Clean Coleman & Company will look to adopt a tiered system of approach to dealing with the
removal of oils or lubricants that remain with pipework or machinery.
![Page 10: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/10.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
The first stage will be to try and remove the oil under controlled conditions with specialist
contractors.
Existing Environmental Spillages
A contractor would contain & remove the oil from plant, machinery or pipework with trained
& competent operatives by approved techniques If wholesale removal was not possible then the next stage would be containment of the oils. This would involve the cutting of pipework or plant and removing it to a “contamination area”
where it can then be dealt with The containment area will be sheeted & bunded off to prevent uncontrolled leaks, and the oil
would be removed from the equipment through gravity and the equipment removed from the area once classed as clean.
The oils will then be removed from the contamination area by trained & competent
operatives using approved techniques. The next stage would deal with un-controlled release of oils onto the Workshop floor. The
containment procedure would be to deal with the immediate incident with granules & absorption mats to contain, limit the spread of oil & to clean the area.
The last stage of containment would be if there was a release of oils into the existing
drainage system, they would ultimately be retained within catch pits 1 (oil loop) Once at the catch pits the oils would be separated from the water and the oils cleared from
the top with the oil mops and suitably disposed off through a licenced contractor. Fluorescent Lights All fluorescent tube strip lights will need to be removed from all of the structures before
works can commence.
![Page 11: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/11.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
An operative will access the light fitting by means of a scaffold tower or a podium, from
which the tubes will be carefully removed by hand, taking care not to break the tubes. All lighting tubes will be placed unbroken as far as reasonably practicable into a centrally
located bin. Once the recycling box is full it will be removed from site and taken to a reclaim yard for
disposal. All necessary certification for the safe disposal of the lights will be issued and copies
retained on site & issued to RWE.
Storage of Fluorescent Lights
Soft Strip All services will be made redundant/isolated before the soft stripping works commence
including the existing lifts. Prior to any works commencing isolation certs will be in place, with all isolations carried out
by RWE Npower. A handover document (DCH 2013-CHRRR-0039) has been produced & issued to C&C
detailing all certification. The isolation certificate will be attached and issued as part of the Task Briefing to the
operatives involved with the works Any isolation certificates should be checked and confirmed prior to demolition commencing
![Page 12: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/12.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Stores Structure
All services both above and underground to this area have been disconnected by RWE asset development team.
The works comprise of the removal and subsequent disposal off site of all residual soft
furnishing, rubbish, mechanical and electrical fixtures, internal plasterboard walls and stud work, and insulation materials.
All materials will be stripped back to the structure, they will be separated for recycling
purposes, and loaded into bins for removal off site.
Segregation of Materials
Operatives will undertake the soft strip whilst using hand tools and access equipment to gain
access to areas of the building
Temporary timber/fibre board structures will be soft stripped
![Page 13: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/13.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Soft stripping will involve the use of hand held tools including powered tools (as required to remove trunking/ducting/pipes) (PAT tested) and hand tools. Individuals will wear P3 face fit masks and disposable overalls (Cat 3, Type 5/6) as per the risk assessment or COSHH assessment requires. Type of gloves will be suitable for the task.
The noise and dust levels will be controlled to create minimal noise and dust. Records shall
be maintained of noise and vibration levels for any hand held tools. All electrical equipment shall be 110v maximum.
Should any material be uncovered that is suspected of being or containing asbestos,
all work in the immediate area will cease. C&C Site Supervisor & RWE HSQE will be immediately informed, and the area will be clearly identified and an exclusion zone established until deemed clear by the asbestos contractor.
All Soft Strip arisings will be removed from site daily to prevent the build up of materials and
to eliminate the risk of fire. Plant will be equipped with a grapple attachment for the loading of arisings. All skips will be sheeted prior to the vehicles exiting the site.
Bobcat Skidsteer loading soft strip arisings into waste bins
Coleman & Company’s Site Supervision will be responsible for the safe access and egress
of their vehicles and plant. Priority will be given to Public Vehicular/Pedestrian Traffic and Coleman & Company will
ensure that the Emergency Services can safely reach all areas of the site should an emergency arise.
The debris will be loaded into awaiting roll on/off containers for disposal to a suitably
licensed facility.
![Page 14: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/14.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Demolition of Structure Adequate protection measures shall be afforded to any existing drainage in the form of
timber plywood sheets or steel road plates. Existing drainage plans are available and these will be used to locate and seal pipes to remain.
All service isolations/disconnections will be in place prior to works commencing on site.
Coleman & Company Site Supervisor will have confirmation of isolations/disconnections and drawings of all relevant services. Any live services remaining will be adequately protected until confirmation of disconnection is received.
Existing service trench adjacent to Workshop
All demolition will be undertaken in a safe and controlled manner in accordance with BS
6187 Code of Practice for Demolition, Health & Safety Guidance Notes. Coleman & Company supervisor will walk the area to ensure there has been no change to
the local environment or works by others that may have effect on the proposed works. All personnel to be inducted, certificates inspected and a toolbox talk carried out to ensure
all persons are aware of their duties, responsibilities and any risk associated with the works. The demolition will be carried out taking full account of the buildings structural make up. The
works will be carried out starting at the top of the structure, working within structural bays, bay by bay. No structures will be left in an unstable state overnight.
![Page 15: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/15.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Demolition to Structure
External Canopies There are two steel framed canopies/structures that connects the workshop and Turbine
Hall that will need to be removed One is a steel roof canopy and the other is a walkway consisting of a steel section structure,
roof and glazed units that provided the access into the Turbine Hall that will need to be removed.
Both these structures will be removed in very similar ways to one another and will be
undertaken prior to the main demolition
Canopies to be removed
Canopies/Structures
![Page 16: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/16.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
A suitable sized excavator equipped with attachment will be placed on the external road on
timber protection mats The excavator will be positioned over the walkway and begin the demolition by munching
the roof section and glazed units The excavator will work from left to right removing the roof section and glazed units down to
the floor level, after this point the demolition will cease to allow clearing of the debris This demolition will remove weight from the structure that will assist the next stage of the
demolition process A full exclusion zone of the working area below will be established to prevent unauthorised
access to the working area. Rope seals to the glazed units will be separated from the window frames and disposed of as
hazardous waste in a sealed skip by ACMS Ltd. ACMS operatives will wear disposal overalls, Cat 3 Type 5/6, and face fitted Sundstrum face
masks with P3 filters. All ACM’s will be removed, double bagged and placed into a seal skip for removal off site. The demolition will re-commence with the excavator shearing through the steel floor section
adjacent to the Turbine Hall The connection to the Turbine Hall will be completely sheared, and at this point the structure
will be disconnected and will allow the continual shearing of the structure back to the workshop
If at any point there is a requirement for flame cutting of the steel; then trained competent
burners will use oxygen/propane cutting equipment to cut the steel Any access that would be required will be provided by a MEWP or Cherry picker operated
by a trained IPAF operative
Separation from Turbine Hall
Direction of Demolition
![Page 17: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/17.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Before any hot works are undertaken a permit system will be issued as a control mechanism
to prevent an incident. The permit will be issued on a daily basis by Site Supervisor and all necessary risks and
control measures will be identified. The permit will be authorised and the recipient will sign the permit as acceptance of its
conditions The hot works will be allowed to commence and during the works a trained fire watch will be
in attendance during the activities and will have two fully serviced fire extinguishers Upon completion of the hot works there will be a one hour “cool down” period for the works
in which the fire watch will maintain attendance and ensure that no fires ignite. The hot works permit will be closed after all hot works have ceased and the cooling down
period has expired, by the individual who took the permit out.
The steel canopy will be removed in exactly the same manner, with the excavator shearing
through the steel sections The excavator will continually remove small sections of the structure allowing them to fall to
the floor below All of the steel produced will be removed to a processing area to be further reduced and
removed off site
![Page 18: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/18.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Workshop & Stores Demolition with the excavator will cut through the connections of the trusses to the
supporting columns one bay at a time. The self weight of the roof will hinge the sections of the roof to the floor in a controlled
manner assisted by the excavator and shearing attachment. No operatives will be allowed in the demolition zone during the mechanical demolition of the
roof and trusses. The sequence of demolition will take into account the stability of the existing structure and
any wind bracing. Demolition will commence from either end working towards the wind bracing, and the wind
braced sections of the structure will be removed at the end of the demolition process. The bracing will provide temporary bracing of the structure during the partial demolition
stages The wind bracing is positioned on either side of the structure and provides resistance to
lateral movement of the structure The structure will be removed in a methodical and systematic sequence allowing for areas of
the structure to be removed, processed and cleared before carrying on with the demolition works
Wind Bracing to Structure
Heras fencing will be erected around the demolition zone and the excavator will always be
set a safe distance away and will not work directly under the roof structure.
Plan Bracing to Portal Frame Steel structure
![Page 19: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/19.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
External low height brickwork walls to the building will be demolished by the excavator and loaded into a dump truck by the excavator or roll-on, roll-off skips with a skidsteer for transport to the processing area
Preparing the Crane The crane will be removed from their elevated position with the use of a excavator and
number of operatives Firstly trained operatives working from a elevated platform will access the crane to
undertake the connection of the rope Trained slinger/signallers will attach wire ropes around one of the beam sections, wrapping it
into a choke hitch located at one side of the crane to make a failsafe connection This operation will be repeated on the opposite side of the crane and the ends of the ropes
will be allowed to fall to the floor below to be connected All wire ropes used in this operation will be pre-determined by an competent person to
ensure that the correct length & capacity of rope is used. Shackles will be attached to the ends of each wire rope to provide the mode of connection to
the excavator. In order to mitigate the vibration of the crane hitting the floor; a bed of hardcore will be
placed on the floor below An excavator will be utilised to civilise the stockpile and placed the material in the desired
location to minimise impact vibration The next stage of the process would be to remove the physical stops of the crane to allow
the cranes to be pulled from the rails and onto the mat of hardcore Operatives using hot cutting techniques will begin the process of cutting the metal stops
from the crane rail using oxygen & propane burning equipment from an elevated working platform
All operatives carrying out burning & cutting operations will be required to wear respirators,
fire retardant overalls, gauntlets & protective visor All burning equipment will be inspected before use to ensure it is all in good order and fit for
use. All burning equipment will be stored in a sealed container, in a ventilated area, with cylinders
stored upright, and secured. The area directly below the cutting operations will be cleared and cordoned off as an
exclusion zone for the works Once the hot works have been completed; operatives will vacate the area and remove all
MEWPS to a safe distance Removal of Crane Once the ropes have been attached, the metal stops removed & crushed hardcore placed to
reduce the impact then the crane can be removed from its rails
![Page 20: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/20.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
The operation to remove the crane will now fall under the direction of the slinger/signaller
and the operation of the excavator driver. The area surround the drop zone will be secured with the use of heras fencing to prevent
unauthorised access during the works The signaller will commence the operation to pull the crane from the rails and onto the
crushed bed of hardcore The slinger will inspect the slings are attached correctly & safely to the excavator; and once
satisfied will direct the excavator The slinger/signaller will instruct the excavator to slowly reverse until the slack within the
ropes has been removed. The excavator will slowly track back providing the crane with enough forward movement to
place it off the end of the crane rails and safely onto the bed of hardcore below. Once the crane is placed upon the hardcore the slinger will remove the shackles from the
excavator only, which will release the excavator from the operation. The excavator will be in a position to provide mechanical support if required to remove the
crane from the hardcore and onto the floor to prevent any risk of injury Once the crane has been successfully removed from the hardcore, and shackles or ropes
can then be removed safely The crane will be removed to the processing area for further reduction in size and removal
off site All free standing columns remaining following removal of the trusses will be sheared at the
base of the column through the flanges leaving the web intact. The excavator with attachment will then lower the column to the floor and complete the
shearing cut at the base. During all demolition the appropriate dust suppression will be used. Either a hose feed from
a Fire Hydrant or our Dust Suppression Unit (fire engine).
Dust Suppression Techniques
![Page 21: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/21.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
The amount of water to be used will be optimum to provide suppression of the airborne dust particles while not completely saturating the surrounding ground and causing silt run-off problems. The drains will be protected with G3 filters.
Any nearby identified gullies will be fitted with G3 silt membrane filters to avoid silt run off
into the drainage system. The windows and surround will be removed mechanically and located within a designated
area prior to removal of the asbestos rope seals under controlled conditions. Rope seals to the skylights will be separated from the window frames and disposed of as
hazardous waste in a sealed skip by ACMS Ltd. ACMS operatives will wear disposal overalls, Cat 3 Type 5/6, and face fitted Sundstrum face
masks with P3 filters. The bases of the steel columns that are connected to the concrete floor slab will be removed Trained operatives using oxygen propane burning equipment will cut the steel flush with the
concrete floor Before any hot works are undertaken a permit system will be issued as a control mechanism
to prevent an incident. The permit will be issued on a daily basis by Site Supervisor and all necessary risks and
control measures will be identified. The permit will be authorised and the recipient will sign the permit as acceptance of its
conditions
Structural Column
The hot works will be allowed to commence and during the works a trained fire watch will be
in attendance during the activities and will have two fully serviced fire extinguishers Upon completion of the hot works there will be a one hour “cool down” period for the works
in which the fire watch will maintain attendance and ensure that no fires ignite.
Cutting of columns flush with floor level
![Page 22: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/22.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
The hot works permit will be closed after all hot works have ceased and the cooling down
period has expired, by the individual who took the permit out. Process & Clear During the demolition of the building all demolition arisings generated will be progressively
removed from the working area All steelwork & concrete will be removed with the use of secondary excavators, 8 wheeled
wagons or articulated dump trucks. The material will be removed through an approved access to a processing area. This area
will be close to the working area to minimise travel distance and all material will be deposited within this area
Once the area has been established with appropriate fencing and signage the movement of
plant & equipment will be monitored by trained banksmen A series of excavators equipped with shears will begin to process the material into sections
that can be loaded onto vehicles for removal off site Composite materials will be segregated into different waste streams and will be removed
separately All vehicle movements will be covered with a consignment note and where required with a
waste transfer note. Crushing of Concrete Coleman & Company will notify the Local Authorities Environmental Health Department of
the site requiring the installation of Mobile Crushing Plant, by means of approved notification. This is to be in compliance with the Environmental Protection Act 1990.
Care will be taken to locate the plant on site to eliminate the potential for any impact on the
environment. A demarcation zone will be erected by use of heras fence panels, a minimum of 3m around
the crusher ensuring sufficient distance is given to prevent direct access to moving parts or potential ejected materials coming into contact with persons or items.
Prior to operating the plant will be inspected and guards and emergency stops checked to
ensure they are in good condition and working order. These daily checks are in addition to inspection and maintenance checks before use and
installation on site. The operator’s manual must be available on site. Access will only be allowed for machine plant being loaded and the collection of crushed
stock pile. Only Coleman & Company personnel will be allowed in this area, under the supervision of the Site Supervisor.
While the crusher is operating, the crusher operator must stand outside the exclusion zone.
The exclusion zone will be suitably signed. The crusher will be discharging the material off the belt directly in the crushing area. Dust
suppression will be supplied to the Crushing Plant via a direct water main supply.
![Page 23: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/23.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
The dust suppression is afforded through the manufacturers standard spray unit over the
hopper and discharge belt. The water will be fed directly from a licensed metered standpipe. All guards on the crushing plant are standard and are in good working order and are
checked regularly and the inspection record daily by the crusher operator.
Typical Layout of Crushing Activities
The guards must never be removed, unless for maintenance work while plant is completely
turned off and by competent persons under a permit. Upon completing any maintenance work all guards should be re-installed and a full inspection carried out and recorded.
The crushing plant is checked on a daily basis by the operator, oils, fuel water, guarding,
feed belts, safety start and emergency stop buttons etc. The operator will wear the required PPE whilst operating the machine including ear
defenders and P3 mask. The operator will control the machine from the ground outside the exclusion zone, unless there is a blockage (see note below).
360° Excavator will load the Crushing Plant with the processed concrete and masonry. If blockages occur, the plant will be stopped, keys removed, 360º excavator operator
notified, and the crusher operator will investigate and clear the blockage and a permit issued A fully trained and certified Operative will operate the Crushing Plant. A loading shovel will clear the processed material from the belt of the Crushing Plant and
transfer to the crushed material stockpile. All crushed material will be transported to an approved area for future use on the site.
Excavator loading crusher with processed materials
Banksmen in attendance during crushing operations
Crushed & graded materials from the conveyor of crusher
![Page 24: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/24.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
3.0 Documentation Required Prior to Work Commencing Refurbishment / Demolition asbestos survey to HSG264:2010 must be in place prior to
soft strip or any structural demolition.
Environmental hazard survey has been undertaken and certificates issue for any removal of materials
Residual Risk Register to identify all known risks within the structure
Project F10 Notification to the Health and Safety Executive (HSE).
Site Starter Pack including RISK and COSHH Assessments, including this Method Statement and any other relevant site documents.
If the project is for any organisation other than a local authority insert the section 81-82 document.
Stored Energy Procedure 4.0 Identified Hazards-General 4.1 All operatives on site will be inducted and advised of the contents of this method statement
and relevant associated Health and Safety and Environmental documentation within the Site Starter Pack. All operatives will sign a register to demonstrate that they have understood the relevant Site Health and Safety, Environmental Documents.
Specific The site layout should be considered to take into account the location of the drainage, this
should take into account the location of stored substances or anything else which has the potential to contaminate the drains on or adjacent to the site.
4.2 Other Staff on Site The site will be secured during the demolition works with banksmen in attendance to ensure
that unauthorised access for RWE members of staff are managed during the demolition works.
4.3 Community Relations During the demolition works the site supervisor will constantly monitor the works and assess
levels of noise, dust and vibration. The site supervisor will be appointed as the community liaison officer.
4.4 Access and Egress Access and egress to the site will be via Purchas Road from A4130. A designated
banksman will control the access and egress of all vehicles. 4.5 Traffic Management All plant and pedestrian movement will be co-ordinated by Coleman & Company including
arrangements for segregation and safe transit routes. A traffic management plan will be created prior to the works and updated, where necessary, during the works
4.6 Traffic movements, where appropriate, will be controlled by a designated banksman. Vehicle
reversing will be minimised where possible.
![Page 25: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/25.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
4.7 Pedestrian and plant routes will be clearly identified, with each delineated and protected by the use of a suitable means.
4.8 Identified Hazards-Structural Demolition 4.9 Demolition and Dismantling is a potentially hazardous operation, it is essential that
demolition works are managed by experienced personnel and executed by fully trained operatives. All personnel and operatives, who work on site, will be inducted before entering the working area. Site visitors may only enter the working area if they are accompanied by the site supervisor, members of the contract management team or their nominated deputy.
4.10 Coleman & Company will erect suitable heras fencing to the perimeter of the site, safety-
warning signs will be erected on the external face of the hoarding 4.11 All existing services, will be located, identified and noted on existing drawings. Any works,
necessary to protect the services during the works, and will be carried out prior to the works commencing. As built records will be produced at the end of the project.
4.12 Any existing live services that remain will be protected prior to work commencing. 4.13 In the event of an emergency the following names and numbers may be used:-
Mr M A Coleman Managing Director & H&S Director
0121 3252424
Mr M Carless Contracts Director 0121 3252424 Kieran Conaty Project Director 07889-168727 John Foster Site Manager 07815-312762 Stuart Campbell Site Supervisor 07912-684645
4.14 In the event of an accident or incident on site, it will be reported immediately to the Site
Supervisor & RWE HSQ Manager Mark Pedlar; who will report to Shady Lane reception on 0121 3252424. Should the accident / incident be reportable under the Reporting of Injuries Diseases and Dangerous Occurrences Regulations, the appropriate documentation will be completed by our Health and Safety Manager and submitted to the HSE. All of Coleman & Company’s Site Supervisors are trained four-day first aiders. A complete First Aid kit will be kept on site at all times.
4.15 Coleman & Company will carry out regular safety inspections appropriate to the activities
taking place. The results of which will be recorded and kept on file. 4.16 All works will be executed in daylight hours. No operatives will work in the hours of
darkness. Unless agreed in advance 4.17 The site will be secured at all times and locked at the end of each working day. Any leading
edges will be suitably protected using suitable and sufficient edge protection for the duration of the works. The works may be sequenced to ensure that structural features of the building such as balconies may be left in place to ensure that unnecessary leading edges are not created.
4.18 Noisy operations will be minimised with breaks at regular intervals, working between the
hours of 08.00 – 17.00 Monday to Friday. 4.19 All plant conforms to current European Legislation. Percussive breakers are suitably
silenced for working in sensitive areas. Plant operators shall undertake plant and vehicle checks on a daily basis and note any defects. The plant will not be used if those defects constitute a health and safety hazard until they have been rectified and no longer present a hazard
![Page 26: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/26.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
4.20 Should dust be generated, it will be suppressed with water or other suitable method,
ensuring that it is sprayed in a fine mist controlling dust, whilst preventing silt run off. 4.21 Maintain safe access / egress to / from site at all times ensuring;
Stairways and passageways are kept clear
There is no build up of flammable materials
There are no slip trip and fall hazard
Site generated waste i.e. from welfare is contained and disposed of properly There is suitable lighting in the building
4.22 Rubbish will be removed from site as works proceed to eliminate the risk of fire. All loads will
be sheeted prior to leaving site 4.23 All waste produced at site will be treated in accordance with the Landfill (England & Wales)
Regulations 2002. 4.24 The treatment given to all waste produced will give due consideration to all recycling
opportunities which will be investigated and where possible recyclables such as wood and plastic will be recovered from waste.
4.25 Due care and attention will be taken whilst working in the vicinity of adjacent properties and
public footpaths or roadways. 4.26 The site supervisor will ensure that suitable drop and exclusion zones are used when
necessary. 4.27 The building will be demolished in a safe and controlled manner, thus ensuring falling debris
does not pose a risk of harm to personnel on site and members of the public. 4.28 Where Propane and oxygen burning equipment is used, all bottles will be secured during
use and at the end of each day. Bottles will be fitted with flash back arrestors. All hoses are correctly coloured, taped and checked daily for holes
4.29 Prior to using any scaffolding ensure that the scaffold has been handed over by the scaffold
Sub Contractor using the appropriate scaffold handover certificate 4.30 A competent person must inspect all scaffolding before the first use, after adverse weather
conditions, after substantial alteration or dismantling. Notwithstanding the above, the scaffold must be inspected every seven days by a competent person and daily visual inspections and a record of the inspection kept on site
4.31 Identified Hazards Asbestos Removal 4.32 All licensed asbestos removal works will be carried out by a licenced asbestos contractor
who will be responsible for the following. 4.33 Notification of asbestos removal to Health and Safety Executive – ASB5 Preparation of all Health and Safety documentation including the Plan of Work and
submission of the HSE – and a copy issued to Coleman & Co
Ensuring they have competent employees to undertake the works, including sufficient supervision
4.34 Executing works in accordance with legislation Air clearance approval by UKAS accredited laboratory Notification to the HSE for any non-licensed notifiable asbestos using ASBNNLW1
![Page 27: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/27.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
Keeping records of exposure and medical records for those working with non-licensed notifiable asbestos
Notification of site under the Hazardous Waste Regulations Provision of sealed lockable containers Disposal at a licensed land fill site Waste Carriers Licence/ADR trained driver 4.35 Prior to commencing any work on site a Refurbishment / Demolition asbestos survey in
accordance with HSG264:2010 must be in place. If this is not the case any work on site must not proceed. The asbestos survey will identify the asbestos containing materials present within the building. The asbestos survey has identified asbestos in the following areas;
4.36 The removal of the non-licensed asbestos will be managed in accordance with the following
procedures. 4.37 The areas where the work is taking place must be assessed, considering proximity to other
activities. Asbestos should be removed as far as possible in isolation to other activities. 4.38 Temporary storage areas will be clearly identified, marked out, segregated and sealed at all
times 4.39 Transit routes for the movement of the asbestos must be clearly advised to all personnel
working on site 4.40 Disposal routes for disposing of asbestos material must be well controlled at both points i.e.
entry and exit 4.41 All bonded non notifiable asbestos must be removed by suitably trained and experienced
personnel equipped with the required, additional Personal Protective Equipment and Respiratory Protective Equipment
4.42 The area where the material is being removed must be correctly set up, ensuring that there
is no risk of cross contamination. The materials must be removed whole where possible. All reasonable attempts must be made to ensure no unnecessary breaking of the material.
4.43 Where appropriate the material will be kept damp using water to ensure no excessive levels
of dust arise 4.44 The material will be disposed of into suitable containers, and removed in accordance with
Duty of Care Regulations 4.45 ACM’s will be removed from the building at regular intervals, thus ensuring that hazardous
substances are not accumulating on site. 4.46 Should any asbestos be discovered which was not foreseen or anticipated then the following
procedure should be followed: Ensure that work in that area immediately stops. This area will then be closed off and marked up as an exclusion zone. The Site Supervisor must be informed and in turn must inform his Project Manager
via Shady Lane reception noting it as an incident. Call 0121 3252424. RWE Mark Pedlar should be contacted on Tel: 07901750800
The site supervisor will assess if there are any other works, which are being conducted in similar areas, which are now suspected to contain asbestos.
If this is the case then work in those areas should also come to an immediate stop.
![Page 28: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/28.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
These areas are to be sealed off and marked up as exclusion zones. A suitable method of work and removal will then be chosen. Project manager will then advise an appropriate course of action.
4.47 Should any materials (including redundant gas bottles or fire extinguishers) be found on site
they will be collected together (stored in a suitable location) and returned to a suitably licensed facility. If there are any materials found which are unknown or suspected to be hazardous then work in that area will cease and the Project Manager will be contacted in order for a suitable method to devised for the work to continue.
5.0 Programme 6 Weeks Resources Contract Management Team
Managing Director Mark Coleman Contracts Director Mark Carless Project Director Kieran Conaty Project Manager Chris Doyle Site Manager John Foster
Site Management
Site Supervisor Sub Contractors Asbestos Company Personal Protective Equipment Mandatory Hard hat
Reflective waistcoat or jacket
Mid sole and toe protection safety boots
Light eye protection
Gloves
This methodology is to be strictly adhered to at all times. In the event of any occurrence that may necessitate a change to the method e.g
(a) Changes in the nature of the works (b) Additional works , ancillary works (c) Previously unknown / unidentified risks (asbestos/suspect material/ etc) (d) Ground/site conditions
The works will cease and an assessment will be made as to the most appropriate course of action to be taken. The revised method of work MUST be agreed by a Project Manager and approved by the HSEQ Manager / Contracts Director and the agreed method will be advised to the workforce by the Site Supervisor by means of a toolbox talk or suitable method.
![Page 29: Original Method Statement - WhatDoTheyKnow · PDF file1.0 Method Statement 1.1 Scope of the works ... deleterious materials, structural demolition & processing of all materials Workshop](https://reader031.fdocuments.us/reader031/viewer/2022021818/5aa397ef7f8b9a84398e8d50/html5/thumbnails/29.jpg)
Project: Didcot A Station Client: RWE Npower
K:\Contracts\Contracts\Current Contracts\C143 - Didcot Early works - RWE N Power\Method Statements\MS118 Workshop & Stores\Demolition of Workshop & Stores Rev 0.doc
This will require the risk assessment and method statement to be reviewed and approved as per Coleman procedures (see above) and must be signed off prior to any changes commencing. This may include the site supervisor drafting a proposed method for review and approval (refer to cover sheet for details of signing procedures) and forwarding to the PM in sufficient time for the reviews and approvals to be undertaken, and where required issue of the documents to the client / CDM-C / client’s representative. Coleman and Company accept no liability for injury to persons, damage to plant, property or materials resulting from the acts of Sub Contractors working outside the scope of their agreed method statement.