Organized by: Department of Civil Engineering Sponsors: 31 st May to 3 rd June 2010.
-
Upload
rosalind-lane -
Category
Documents
-
view
213 -
download
0
Transcript of Organized by: Department of Civil Engineering Sponsors: 31 st May to 3 rd June 2010.
Organized by: Department of Civil Engineering
Sponsors:
31st May to 3rd June 2010
Structural TopicThe goal of the project is to design a transformable bridge-like walkway consisting of two half-circles, which can be connected to form both an S-shape and a circle of the walkway.
Both configurations will be tested and assessed. The fabricated model must follow the structural design report submitted.
Non-compliance with the instructions and use of materials not provided by the organizer will lead to disqualification.
Grand Challenge (S-Shape walkway)
An example of timber structural model of the bridge walkway.
Geometric Requirements
Plan view of the S-shape walkway and circle configuration with dimension and clearance requirements.
Plan
Geometric Requirements
Horizontal view of a part of the walkway with dimension and clearance requirements.
Geometric Requirements for Loading
Horizontal view of the end of the walkway with load application and clearance requirements.
Elevation
Material and Tools Materials
Balsa wood slat (15 pieces for each team) with dimension of 1mmx75mmx1000mm
Nylon cord (maximum 3 meters for each team) with diameter of 1 mm.
Adhesive (UHU Hart Balsa cement) Screws (Aluminum, M6)Note: Screws can be used to fix one of the columns
and they are not allowed inside the structure.
Tools Ruler, triangle ruler, protractor, compass, pencils,
cutter knives, sand papers, scissors.Note: Installation of tools in the structure is not allowed.
Structural Requirements The transformable bridge-like walkway has to
be fabricated using wood slat, adhesive and, optionally, nylon rope.
The structure must consist of two half-circles, which can be connected to both an S-shape and a circle of the walkway.
The two parts must be detachable from one another so that both configurations can be tested and assessed.
Structural Requirements
Maximum three columns are allowed to support the walkway.
The type of structure is not specified and not limited but clearance requirement must be satisfied.
Only one of the columns will be rigidly connected to the ground. This column will be fixed to the base by two or four adjustable aluminum brackets. The cross-section of the built-in column must be rectangular over the first 50 mm from the ground.
The bases of the remaining columns are only provided with supports for only horizontal and compressive forces.
Clamped Support
Base construction for clamped column.
Plan
Clamped Support
A typical connection at the bottom of the clamped column.
Simply Supported Base
Base construction for non-clamped columns.
Plan
Other Requirements
The model may be limited to the load-carrying components.
The following parts should be properly designed for load application:The longest free end of the walkway in the S-
shape configurationThe sections in the middle of the longest
span between the columns in both the S-shape and circular-shape configurations.
Load Tests
Both the S-shape and the circle configurations of the model are tested.
Load testing will include both static and impact loads applied in vertical direction:The longest free end of the walkway in the S-
shape configuration In the middle of the longest span between
the columns in both configurations. The static load tests will be carried out
first and those models that pass static tests will be admitted to the impact load tests.
Loading Apparatus
Loading constructions.
Elevation
Load Tests Static load test
The model will be loaded incrementally with three masses of 2.0 kg each.
The final mass is 6.0 kg plus the mass of the load-carrying construction.
The displacement limit is l/100 for the load between two columns and l/50 for the load at the end points of the walkway. Where, l is the distance between the load point and the axis of the next column, measured along the axis of the walkway.
The test will be terminated upon collapse of the model.
Impact load test The final mass of 6.0 kg plus the mass of the load-carrying
construction remains unchanged. Then, the upper mass segment of 2.0 kg is lifted to a height of 80 mm
above its idle position and suddenly released. The test will be considered successful if the model does not collapse
within the first 10 seconds after application of the impact load.
Tentative Schedule for GEM1505C
Time Event
16th or 17th March 2010 Submission of the design report
23rd or 24th March 2010 Fabrication of the S-shape bridge
30th or 31st March 2010 Fabrication of the S-shape bridge
6th or 7th April 2010 Testing of structure
13th or 14th April 2010 Testing of structure
1st – 4th June 2010 6th Inter-University Invitational Civil Engineering Competition
Model appearance The model appearance is focused on the design idea,
innovation, proportion and elegance, realistic layout, and technical elaboration of the construction.
Structural behavior The marks are collected step-by-step during the tests. The lightest model which satisfy all static load tests will be
awarded 25% marks. Load to weight ratios will indicate the rank the larger L/W will get 1% point less consecutively but not less than 13%.
The lightest model to satisfy all impact load tests will be awarded 25% marks. Load to weight ratios will indicate the rank the larger L/W will get 1% point less consecutively but not less than 13%. Those passing the impact load test will receive higher marks than the failed ones.
Assessment
Grand Challenge (S-Shape walkway)
An example of timber structural model of the bridge walkway.