Agile Project Management (or Burning Your Gantt Charts) ESC-267 Michael Karlesky & Mark VanderVoord

Transcript of (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart...

Page 1: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Agile Project Management(or Burning Your Gantt Charts)

ESC-267 Michael Karlesky & Mark VanderVoord

Page 2: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

The Zen Of “Done”

Page 3: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

3 Things

Page 4: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

1. Define Done

Page 5: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

2. Feature Done

Page 6: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

3. Project Done

Page 7: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Define “Done”

Page 8: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. The code has been written according to the developers' interpretation of the spec (delivered 9 months ago). It can now be tested.

Page 9: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. The code has been written but may require an unspecified amount of “cleanup” before shipping.

Page 10: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. It works on a developer's machine.

Page 11: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. Gantt chart progress has reached 100%

2. (more often) Gantt chart progress has reached 95% introducing a secondary state: “almost done”

Page 12: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. The developers have stepped through the code with the debugger.

Page 13: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. The debug build runs.

Page 14: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. The state immediately preceding “done done”

Page 15: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 16: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like continuation where the mind is at peace and the soul is at one with code, coworker, contractor, and customer alike

Page 17: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like continuation where the mind is at peace and the soul is at one with code, coworker, contractor, and customer alike

Page 18: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state whereinall customer-specified features have been implemented to glowing accolades

Page 19: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state whereinall customer-specified features have been implemented to glowing accolades

Page 20: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state whereinall customer-specified features pass a vast (comprehensive) suite of unit, system, and acceptance tests

Page 21: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state whereinall customer-specified features pass a vast (comprehensive) suite of unit, system, and acceptance tests

Page 22: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) all customer-specified features pass unit, system, and acceptance tests(b) ...

Page 23: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) ...(b) It works on more than just my machine

Page 24: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) ...(b) It works on more than just my machine

Page 25: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) ...(b) builds are reproducible, identical, and machine independent

Page 26: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) all customer-specified features pass unit, system, and acceptance tests(b) builds are reproducible, identical, and machine independent

Page 27: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Define “Feature Done”

Page 28: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature?

Page 29: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer can actually define in a concrete way, crossing that mystical gap between geek and non-geek.

Page 30: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer can actually define in a concrete way, crossing that mystical gap between geek and non-geek.

Page 31: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can know when it has been done correctly and is properly Awesome

Page 32: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can know when it has been done correctly and is properly Awesome

Page 33: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can verify

Page 34: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can verify (c) feels is worth some kind of money or compensation to develop

Page 35: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can verify (c) feels is worth some kind of money or compensation to develop

Page 36: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature | ˈfē ch ər |noun.

1. Something that a customer (a) can explain (b) can verify (c) will pay for

Page 37: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer?

Page 38: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

Page 39: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

2. Engineering Department

Page 40: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

2. Engineering Department

3. Marketing

Page 41: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

2. Engineering Department

3. Marketing

4. Sales

Page 42: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

2. Engineering Department

3. Marketing

4. Sales

5. Production

Page 43: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Customer noun. synonyms:

1. End User

2. Engineering Department

3. Marketing

4. Sales

5. Production

6. Technical Support

Page 44: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Since We Understand Feature

Page 45: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Now For A Round Of

“Is That A Feature?”

Page 46: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?SPI Interface Driver

Page 47: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?Application should calculate

and display the air-speed velocity of an unladen swallow

Page 48: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?Application Should Initialize

ADC asPulse Convert Mode

Page 49: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?Application Should Filter Results Before Display

Page 50: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?Application Should Look

Awesome

Page 51: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

?Application Should Blink A

Warning Light Before It Crashes

Page 52: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know Features

Page 53: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

So When Is The Feature Done?

Page 54: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done | dәn |adjective.

1. A Zen-like state wherein(a) all customer-specified features pass unit, system, and acceptance tests(b) builds are reproducible, identical, and machine independent

Page 55: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

unit, system, acceptance

Page 56: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

unit, system, acceptanceprove pieces of code work

Page 57: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

unit, system, acceptanceprove the release build works

Page 58: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

unit, system, acceptanceproves to customer the features work

Page 59: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

development team

Page 60: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

now also develops tests

Page 61: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

strangely

Page 62: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

does NOT

Page 63: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

take more time

Page 64: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

does NOT

Page 65: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

make the project more complex

Page 66: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

plus

Page 67: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

encourages good design

Page 68: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

encourages modular code

Page 69: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

and

Page 70: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(obviously?)

Page 71: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

promotes TESTABLE code

Page 72: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

when all tests

Page 73: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 74: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

we know those features

Page 75: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

DONE

Page 76: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done For Good?

Page 77: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Yes!

Page 78: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Continuous Integration

Page 79: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Every Time

Page 80: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Add A Feature

Page 81: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Every Time

Page 82: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Fix A Bug

Page 83: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Every Time

Page 84: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Change Anything

Page 85: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

ALL TESTS

Page 86: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Re-run

Page 87: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Re-validated

Page 88: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Re-verified

Page 89: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

But We Can't Work On

Features Until There Is

Infrastructure

Right?

Page 90: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Wrong

Page 91: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

“Simplest Thing That Works”

Page 92: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then

Page 93: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Refactor As Needed

Page 94: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

You Can't Guess

Page 95: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Exactly

Page 96: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How All Modules Will Be Used

Page 97: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Quite Likely

Page 98: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

“You Ain't Gonna Need It”

Page 99: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

When You're Wrong

Page 100: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Spend More Time Changing

Page 101: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Than Writing

Page 102: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

But You Skipped The Step Where We Wrote A

System Design

Specification!

Page 103: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Wrong

Page 104: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Develop Documentation

Page 105: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Like Software

Page 106: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Collaborative

Page 107: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Fast

Page 108: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Unobtrusive

Page 109: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Get the Customers Involved

Page 110: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Don't Let It Feel Rigid

Page 111: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Don't Let It Get Stale

Page 112: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Always Evolving

Page 113: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Accurate

Page 114: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

wiki

Page 115: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

That's Feature Done

Page 116: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Define “Project Done”

Page 117: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Project Done | präjˌekt dәn |noun.

Page 118: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Project Done | präjˌekt dәn |noun.

1. A Zen-like state wherein(a) all customer-specified features pass unit, system, and acceptance tests(b) builds are reproducible, identical, and machine independent

Page 119: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

anti-climactic?

Page 120: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

really want to know

Page 121: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

WHEN

Page 122: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Project Done

Page 123: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Let's Start With

Page 124: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Estimation

Page 125: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

All Features Given Points

Page 126: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points are NOT Hours

Page 127: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points are Complexity

Page 128: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

If Feature 1

Page 129: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

2x

Page 130: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature 2

Page 131: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then

Page 132: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

2x

Page 133: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points

Page 134: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Humans Better At EstimatingComplexity Than Time

Page 135: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Estimating Points

Page 136: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Factors Out

Page 137: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Page 138: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Meetings

Page 139: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

Meetings

Page 140: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

Meetings

Requirement Gathering

Page 141: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

Meetings

Requirement Gathering

Coffee Breaks

Page 142: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

Meetings

Requirement Gathering

Coffee Breaks

Phone Calls

Page 143: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

MeetingsHear Ryan's Joke

Requirement Gathering

Coffee Breaks

Phone Calls

Page 144: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

MeetingsHear Ryan's Joke

Requirement Gathering

Coffee Breaks

e-mail

Phone Calls

Page 145: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

MeetingsHear Ryan's Joke

Requirement Gathering

Coffee Breaks

e-mail

YouTube

Phone Calls

Page 146: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Overhead

Documenting

MeetingsHear Ryan's Joke

Requirement Gathering

Coffee Breaks

e-mail

YouTube

Phone Calls

less-than-productive time

Page 147: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Because The Truth Is

Documenting

MeetingsHear Ryan's Joke

Requirement Gathering

Coffee Breaks

e-mail

YouTube

Phone Calls

less-than-productive time

Page 148: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

No One Is Productive 100% Of Their Time

Page 149: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points

Page 150: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Estimate

Page 151: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Net Progress

Page 152: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

So How Do We Assign Points?

Page 153: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Planning Poker

Page 154: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Step 1

Page 155: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

As A Group

Page 156: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Choose a Medium-Size Feature

Page 157: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Call it 5

Page 158: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Everyone Has Deck of Cards

Page 159: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Numbered 1-10

Page 160: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(Or 1-2-3-5-8-13)

Page 161: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

For Each Feature

Page 162: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Quickly Discuss It

Page 163: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then, Everyone Chooses a Card

Page 164: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(But Does Not Show It)

Page 165: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Everyone Reveals

Page 166: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

If Points are Close

Page 167: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(within a card)

Page 168: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Use the Highest Value

Page 169: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Otherwise

Page 170: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Re-Discuss

Page 171: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(there's a difference in view)

Page 172: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(what the feature is)

Page 173: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(the risks involved)

Page 174: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(or what's unknown)

Page 175: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

After Discussion

Page 176: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Re-Select Cards

Page 177: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Repeat Until You Agree

Page 178: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Repeat Until All Features Estimated

Page 179: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

That's It?

What aboutFeatures we

don't understand yet, or high

risk Features?

Page 180: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Good Point

Page 181: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Higher Risk Features

Page 182: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Get Higher Points

Page 183: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Lack of Definition

Page 184: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Gets Higher Points

Page 185: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Some of Those Unkowns

Page 186: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Will be Easy

Page 187: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Some will be Scary

Page 188: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

In Fact,

Page 189: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Normal Features

Page 190: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Will be Easier / Harder

Page 191: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Than Estimated

Page 192: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

But That's OK

Page 193: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(we'll see why in a moment)

Page 194: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Now For A Round Of

“How Many Points?”

Page 195: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Our Features:1. Return Version Message via serial port when requested.2. Measure Filtered Battery Voltage and Return 1/sec3. Estimate Battery Life Remaining and Return 1/sec4. Blink Red LED when Battery Is Too Low5. Send Out LOW Message once when Battery Too Low

Page 196: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

So Now What?

Page 197: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

It's Time For Fancy Math

Page 198: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Sum The Points

Page 199: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

As We Work

Page 200: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Track Points From “Features Done”

Page 201: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

At Regular Intervals

Page 202: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(Iterations)

Page 203: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 204: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Burn-Down Chart

Page 205: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 206: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

VELOCITY

Page 207: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Variations in Points Completed

Page 208: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Per Iteration

Page 209: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Average Out

Page 210: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Use Points Completed

Page 211: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

In Last Iteration

Page 212: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(or Average of Last Few)

Page 213: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Calculate Velocity

Page 214: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(Points / Iteration)

Page 215: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Use Velocity

Page 216: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

From Points Remaining

Page 217: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

To Predict “Project Done”

Page 218: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 219: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

I'm Sorry

That End Date Is Not Acceptable.

Page 220: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Have Options

Page 221: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We're Tracking Velocity

Page 222: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know Effect Of Adding People

Page 223: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know Effect Of Dropping or Modifying Features

Page 224: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Can Estimate Effect Of Buy/Build Decisions

Page 225: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Huh?

Page 226: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Feature Sets Change

Page 227: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

New Features Are Requested

Page 228: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Features Were Forgotten During Estimation

Page 229: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Priorities Change

Page 230: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Each Time

Page 231: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Add / Remove

Page 232: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points to Total Points

Page 233: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points Remaining

Page 234: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Giving Us Updated Estimates

Page 235: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Automatic History

Page 236: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained
Page 237: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

De-Featuring / Feature Redesign

Page 238: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Scope Creep

Page 239: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

“Project Done”

Page 240: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What About Adding People?

Page 241: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

4 people

5 people

Page 242: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Be Careful

Page 243: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

6 people

Page 244: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

6 people

Page 245: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Because of This

Page 246: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Often Add Another Graph

Page 247: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Track Velocity

Page 248: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Now For A Round Of

“What Happened?”

Page 249: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Where Did We Add Features?

Page 250: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What Was Our Initial Estimate?

Page 251: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What Was Velocity At Iteration 4?

Page 252: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Where Did We De-Feature?

Page 253: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What Was Our Final Total?

Page 254: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Where Was A Velocity Jump?

Page 255: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Where Were We Done?

Page 256: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

So We Just Work Through

Points Until We're Done?

Page 257: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Almost

Page 258: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

The Order Is Important

Page 259: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How Do We Set Priority?

Page 260: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Every Iteration

Page 261: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Work With Customer

Page 262: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Prioritize

Page 263: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Most Important Features First

Page 264: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Highest Risk First

Page 265: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Greatest Unknowns First

Page 266: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

(Helps Flush Out Definition)

Page 267: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Plus a Bonus

Page 268: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Stop When You Want

Page 269: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

If Customer Happy

Page 270: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Current Feature Set

Page 271: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

All Tests Pass

Page 272: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then Ship It

Page 273: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Why Wait For Low-Priority Features?

Page 274: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Ship Now.

Page 275: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Make Money.

Page 276: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Find Out What Customer Wants

Page 277: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

And Add Those Features

Page 278: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Iterations

Page 279: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We've Seen

Page 280: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Iterations

Page 281: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Help

Page 282: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

To Regularly Adjust Priorities

Page 283: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

To Accurately Track Progress

Page 284: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

They Also

Page 285: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Serve As Mini-Milestones

Page 286: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Or Mini-Releases

Page 287: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How Long Is An Iteration?

Page 288: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Usually

Page 289: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

1 or 2 weeks

Page 290: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

1 Week

Page 291: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Faster Feedback

Page 292: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

More Flexible

Page 293: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

2 Week

Page 294: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Coarse Grained Features

Page 295: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

More InterdependenciesWith Other Disciplines

Page 296: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Pick What Sounds Right

Page 297: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

You Can Always Change

Page 298: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

1 ⇨ 2Sum Pairs Of Past Iterations

Page 299: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

2 ⇨ 1Split Past Iterations Into Halves

Page 300: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What Happens When We Reach The End Of An Iteration...

With Incomplete Features?

Page 301: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

All Incomplete Features

Page 302: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Count As 0 Points

Page 303: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

If

Page 304: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Still High Priority

Page 305: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Work On It Next Iteration

Page 306: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Points Will Average Out

Page 307: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How Do We Know How Much Work To Schedule

For Next Iteration?

Page 308: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

“Yesterday's Weather”

Page 309: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Assume Our Velocity

Page 310: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Will Be Our Recent Velocity

Page 311: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then

Page 312: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Work With Customer

Page 313: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Highest Priority Features

Page 314: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Fit In As Many As We Can

Page 315: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Some Teams

Page 316: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Use Visual Reinforcement

Page 317: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Sheets of Paper

Page 318: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Size Proportional To Points

Page 319: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Large Sheet Of Paper

Page 320: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Size Proportional to Velocity

Page 321: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Then Fit Features Into Iteration

Page 322: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Intuitive

Page 323: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Visual (For Visual People)

Page 324: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

So Is That It?

Page 325: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Let's See

Page 326: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 327: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Meaning of Done

Page 328: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 329: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How To Estimate The Complexity Of Features

Page 330: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 331: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

When Features Are Done

Page 332: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 333: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

How Quickly We Get Features Done

Page 334: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 335: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

When Project Should Be Done

Page 336: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 337: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

What Our Options Are To Change When It's Done

Page 338: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 339: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

The Success Of Those Changes

Page 340: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We Know

Page 341: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

To Make Constant Corrections

Page 342: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

so

Page 343: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Yeah.

Page 344: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

We're

Page 345: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Done.

Page 346: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

This Presentation is Licensed Under a Creative Commons 3.0 Attribution,

Share-Alike License.

You may use all or part of this presentation for whatever you want, as long as you

(1) credit Michael Karlesky and Mark VanderVoord (2) release any derived works under a similar license

http://www.creativecommons.org/

Page 347: (or Burning Your Gantt Charts) · Gantt chart progress has reached 100% 2. (more often) Gantt chart ... 1 or 2 weeks. 1 Week. Faster Feedback. More Flexible. 2 Week. Coarse Grained

Images By (thanks!):Beach Zen - TanaisCosta Rica Zen Garden – Scott RobinsonFire And Water – Paul Sapiano

Zen Garden – Timothy TakMad Scientist - Zoomar

Momento Zen – Silke GerstenkornZen – Pierangelo RosatiCarnival Cruise – Josh Bousel