Optimizing Natural Resource Management in KZN
by prioritizing High Altitude Clearing
of AIPs
![Page 2: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/2.jpg)
WHY IS HAT IMPORTANT?High strategic priority for DEA and WfW
We attack the major source of infestation
![Page 3: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/3.jpg)
METHODS AND SAFETY
![Page 4: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/4.jpg)
TWIN ROPE SYSTEMIRATA TRAINING
![Page 5: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/5.jpg)
HAT SUCCESSES: Setting the first standards
![Page 6: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/6.jpg)
Divider page textshowing imagery
Divider page textDivider page textGreytown
![Page 7: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/7.jpg)
S15P1000019
![Page 8: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/8.jpg)
Divider page textshowing imagery
Divider page textDivider page texteThekwini
![Page 9: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/9.jpg)
Divider page textshowing imagery
Divider page textDivider page textS15P1000021
![Page 10: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/10.jpg)
Umkamhlamba
![Page 11: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/11.jpg)
![Page 12: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/12.jpg)
SCATTERED PINUS INFESTATIONS
![Page 13: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/13.jpg)
Divider page textshowing imagery
Divider page textDivider page textRECRUITMENT IN THE BERG
![Page 14: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/14.jpg)
People EmployedPerson Days of Work Target Person Days % Person Days of Annual TargetAverage Person Days /monthWage Cost per Person Day
201323
5 3666 50483%23
R 139
201465
14 782 14 368103%
20R 153
HISTORICAL PERFORMANCE: PERSON DAYS
2015 YTD63
3 7913 90097%19
R 182
![Page 15: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/15.jpg)
HECTARES CLEAREDGreytown eThekwiniMonks CowlCathedral PeakInjasuthi TOTAL %
2013PLAN ACTUAL180 139180 242
- -- -- -
106%
HISTORICAL PERFORMANCE: PRODUCTION
2015 YTDPLAN ACTUAL
32 3260 4130 3030 2636 27
83%
2014PLAN ACTUAL124 9983 116
108 73106 80
0 3496%
![Page 16: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/16.jpg)
Total budget% Expenditure
20132 167 910
100%
20146 725 136
100%
HISTORICAL PERFORMANCE: EXPENDITURE
2015 YTD1 437 665
100%
![Page 17: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/17.jpg)
APO SUMMARY: 2015/2016Operational budget R 5 750 659
Management budget R 251 181
Total budget R 6 001 840
Management person days 240
KPI's:
Cost/hectare (excl man) R 8 444
Cost/person day (excl man) R 368
Cost/hectare (incl man) R 8 813
Cost/person day (incl man) R 384
![Page 18: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/18.jpg)
APO SUMMARY: 2015/2016Operational budget R 5 750 659
Management budget R 251 181
Total budget R 6 001 840
Management person days 240
KPI's:
Cost/hectare (excl man) R 8 444
Cost/person day (excl man) R 368
Cost/hectare (incl man) R 8 813
Cost/person day (incl man) R 384
![Page 19: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/19.jpg)
KZN TEAMS
Calendar days
Budget person days
Training days
Base duties
Production days
Number staff
Paid Person days
Productive person days
Units/hectare
240
15 600
24
46
170
60
15 600
10 200
14.50
APO SUMMARY cont…
![Page 20: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/20.jpg)
KZN TEAMS
APO SUMMARY cont…
Initial NBAL allocated hectares
Follow up NBAL allocated hectares
HELICOPTER HOURS
CAMPING DAYS
547
134
5
104
![Page 21: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/21.jpg)
HAT as preferred vehicle
to implement NRM projects• Strategically- important and visible areas• Scope for intermediate sites• Institutionally established• Well trained teams, recruited from closest community• Excellent KPIs: Expenditure, Employment, Production• Standards finalised• GIS and reporting advantage• Good partner relationships
![Page 22: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/22.jpg)
WAY FORWARD
• Aerial surveys and mapping new areas• Increase funding to optimise impact on
natural resources• Unlocking contribution potential • Implement a realistic exiting strategy
![Page 23: Optimizing Natural Resource Management in KZN by prioritizing High Altitude Clearing of AIPs.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649f355503460f94c52af9/html5/thumbnails/23.jpg)
NGIYABONGA