Optimized Risk in ABC Projects
Transcript of Optimized Risk in ABC Projects
Optimized Risk in ABC Projects
SH 114 Signature Bridge
Irving, Texas
Matt Paggioli, Webber, LLCSam Piland, Webber, LLC
DFWInternational
Airport
Dallas
Irving
Project Location
2
• Bid Date: June 7, 2017
• Completion Date: December 2020
• Client: TxDOT, Dallas District
• Project Award Amount: $39,547,700
SH 114 Signature Bridge
• Scope of Work: Five new bridges over SH 114
• Three vehicular bridges over main lanes and frontage roads
• Two pedestrian bridges over main lanes
• Aesthetic steel truss supported by cable-stay system and
pylons
• New exit ramps and frontage roads
3
Project Specifics
• Three vehicular bridges over tolled express lanes, main lanes and frontage roads
• Super structure designed with standard prestressed concrete U-beams and slab
• Two pedestrian bridges over tolled express lanes and main lanes
• Super structure designed as post-tensioned continuous box girder sections utilizing cast-in-place construction methods
4
TxDOT requested to open the new tolled express lanes early, but how?
• Webber proposed an ABC method to eliminate the shoring necessary for the pedestrian bridge box girder spans to be cast-in-place and allow the early opening.
• Webber had concerns for additional costs that the original pricing of the work would not cover the proposed ABC method.
So why ABC for this Project?
5
City of Irving PropertyLeased to TxDOTApproximately 80 Ac.
• Redesign of post tensioned box girder spans
• Approval process
• Casting location
• Erection of box sections
• Optional traffic routes
• Frontage Road access requirements
• Previous experience
Considerations
6
1. Safety Measures• Engineering controls• Traffic control
2. Multiple Professional Engineers (7 Firms) working on the design• DECON – Hired by Webber for multiple design scopes
• Redesign box girders• Geotechnical report on casting yard and travel path• Overhang design
• Mammoet – Heavy lift contractor used in house engineering staff to design the lifts• Webber – Coordinate design and review with in-house engineering services• Toroja – Independent final review of complete design package• TxDOT – Bridge Division review of complete redesign package• PERI Formworks – Design and manufacture of formwork• Structural Technologies (VSL) – Design and install of post tensioned system
3. Survey Control
Risk Management Strategies
7
Shoring occupying express lanes for 8 months to cast all four spans
Express Lane
Risk Management Strategies
8
• First ABC method considered. Cast box girder spans on existing newly constructed bridge and utilize sliding jack method for moving to final location• Ruled out due to risk associated with excessive loading on newly constructed bridge
Precast Box Girder SpansFirst Option Considered
9
• Post tensioned box girder spans cast off site on the ground with steel lifting girders in place
Precast Box Girder SpansSecond Option Considered
10
11
• Staging area location and transporting route
Precast Box Girder SpansSecond Option Considered
11
Precast Box Girder SpansReinforcing Section Views
12
Precast Box Girder Span Forming System
13
Precast Box Girder SpansPost Tension Tendon Location
14
Precast Box Girder SpansClosure Pour At Center Bents
15
Gantry Arrangement for Lifting Box Girder Spans
16
Precast Box Girder SpansTransport Plan
17
18
Precast Box Girder SpansPouring Top Phase
18
19
Completion of Casting Precast Box Girder Spans at Staging Area
19
Precast Box Girder SpanLifted and Loaded on SPMT
20
Precast Box Girder SpanTransported with SPMT
21
22
Precast Box Girder SpanAdjustments with SPMT
22
23
Precast Box Girder SpanBeing Set in Place
23
24
Precast Box Girder SpanInstalled
24
https://youtu.be/JxlxVwU21xQ
Transporting and Installation with SPMT
25
Thank You
26
Questions?