OPSM 501: Operations Management Week 11: The Newsvendor Problem-ways to avoid mismatch Koç...
-
Upload
makenna-meigs -
Category
Documents
-
view
212 -
download
0
Transcript of OPSM 501: Operations Management Week 11: The Newsvendor Problem-ways to avoid mismatch Koç...
OPSM 501: Operations Management
Week 11:
The Newsvendor Problem-ways to avoid mismatch
Koç University Graduate School of BusinessMBA Program
Zeynep [email protected]
Hammer 3/2 timeline and economics
Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Generate forecast of demand and submit an order
to TEC
Receive order from TEC at the
end of the month
Spring selling season
Left overunits are
discounted
Economics:• Each suit sells for
p = $180• TEC charges
c = $110 per suit• Discounted suits
sell for v = $90
The “too much/too little problem”:
– Order too much and inventory is left over at the end of the season
– Order too little and sales are lost.
Marketing’s forecast for sales is 3200 units.
The demand-supply mismatch cost
Definition – the demand supply mismatch cost includes the cost of left over inventory (the “too much” cost) plus the opportunity cost of lost sales (the “too little” cost):
The maximum profit is the profit without any mismatch costs, i.e., every unit is sold and there are no lost sales:
The mismatch cost can also be evaluated with
saleslost ExpectedC
inventory over left ExpectedC cost Mismatch
u
o
cpprofit Maximum
Mismatch cost = Maximum profit – Expected profit
Revisit Example 3:
Manufacturing cost=60TL,
Selling price=80TL, Discounted price (at the end of the season)=50TL
Market research gave the following probability distribution for demand.
Find the optimal q, expected number of units sold for this orders size, and expected profit, for this order size.
Demand Probability500 0.10600 0.2700 0.2800 0.2900 0.101000 0.101100 0.10
P(D<=n-1)00.10.30.50.70.80.9
Cu=20 Co=10P(D<=n-1)<=20/30=0.66
<=0.66 q=800
For q=800:E(units sold)=710E(profit)=13,300Max profit=20*770=15400
When is the mismatch cost high? Hammer 3/2’s mismatch cost as a percentage of the maximum profit is
$31,680/$223,440 = 14.2%
Mismatch cost as a percent of the maximum profit increases as …
– (1) the coefficient of variability of demand increases
– (2) the critical ratio decreases
Coefficientof variation 0.4 0.5 0.6 0.7 0.8 0.9
0.10 10% 8% 6% 5% 3% 2%0.25 24% 20% 16% 12% 9% 5%0.40 39% 32% 26% 20% 14% 8%0.55 53% 44% 35% 27% 19% 11%0.70 68% 56% 45% 35% 24% 14%0.85 82% 68% 55% 42% 30% 17%1.00 97% 80% 64% 50% 35% 19%
Critical ratio
Options to reduce the mismatch cost
Make to order Reactive Capacity
– Unlimited– Limited
7
Make-to-Stock Model
ConfigurationAssemblySuppliers
8
Assemble-to-Order Model
ConfigurationAssemblySuppliers
Unlimited, but expensive reactive capacity
Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Generate forecast of demand and submit 1st order to TEC
Receive 1st order from TEC at the end of Jan Spring selling season
(Feb – Jul)
Left overunits are
discounted
Oct
Receive 2nd
order from TEC at the end of Apr
Observe Feb and Mar sales and
submit 2nd order to TEC
Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Generate forecast of demand and submit 1st order to TEC
Receive 1st order from TEC at the end of Jan Spring selling season
(Feb – Jul)
Left overunits are
discounted
Oct
Receive 2nd
order from TEC at the end of Apr
Observe Feb and Mar sales and
submit 2nd order to TEC
TEC charges a premium of 20% per unit ($132 vs. $110) in the second order.
There are no restrictions imposed on the 2nd order quantity. O’Neill forecast of total season sales is nearly perfect after observing
initial season sales. How many units should O’Neill order in October?
12-9
Revisit Example 2: Finding Cu and Co
A textile company in UK orders coats from China. They buy a coat from 250€ and sell for 325€. If they cannot sell a coat in winter, they sell it at a discount price of 225€. When the demand is more than what they have in stock, they have an option of having emergency delivery of coats from Ireland, at a price of 290.
The demand for winter has a normal distribution with mean 32,500 and std dev 6750.
How much should they order from China??
Example 2: Finding Cu and Co
A textile company in UK orders coats from China. They buy a coat from 250€ and sell for 325€. If they cannot sell a coat in winter, they sell it at a discount price of 225€. When the demand is more than what they have in stock, they have an option of having emergency delivery of coats from Ireland, at a price of 290.
The demand for winter has a normal distribution with mean 32,500 and std dev 6750.
How much should they order from China??
Cu=75-35=40Co=25F(z)=40/(40+25)=40/65=0.61z=0.28 q=32500+0.28*6750=34390
Apply Newsvendor logic even with a 2nd order option
The “too much cost” remains the same:
– Co = c – v = 110 – 90 =20.
The “too little cost” changes:
– If the 1st order is too low, we cover the difference with the 2nd order.
– Hence, the 2nd order option prevents lost sales.
– So the cost of ordering too little per unit is no longer the gross margin, it is the premium we pay for units in the 2nd order.
• Cu = 132 – 110 = 22
Critical ratio:
Corresponding z-statistic (0.05)=0.5199, (0.06)=0.5239, so z = 0.06.
5238.02220
22
uo
u
CC
C
3263118106.03192 zQ
Profit improvement due to the 2nd order option
With a single ordering opportunity:– Optimal order quantity = 4101 units– Expected profit = $191,760– Mismatch cost as % of revenue = 4.9%
The maximum profit is unchanged = $223,440
With a second order option:– Optimal order quantity = 3263 units
– Reduction in mismatch cost = 38% (19,774 vs 31,680)– Mismatch cost as % of revenue = 3.1%
666,203$
43722$50820$440,223$
quantity entreplenishm secondExpectedC
inventory over left ExpectedC- profit Maximum profit Expected
u
o
Limited reactive capacity
Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Generate forecast of demand and submit 1st order to TEC
Receive both orders from TEC at the end of Jan Spring selling season
(Feb – Jul)
Left overunits are
discounted
Oct
Submit 2nd order to TEC
Observe pre-book orders
from retailers
Units in the 2nd order are no more expensive than in the 1st order
But there is limited capacity for a 2nd order
Sample of wetsuits
1st order must be at least 10,200 suits so that there is enough capacity for the 2nd order.
Also a minimum order quantity-order once What should we produce in the 1st order?
Sport Model Price Margin Discount
DIVE DIVE COMP 3/2 FULL 1100 660 0.60 120 38% 65%DIVE WMS 7000X 7MM FULL 600 360 0.60 275 38% 65%SURF EPIC 5/3 W/HD 800 296 0.37 225 38% 50%SURF HEAT 3/2 1200 444 0.37 110 38% 50%SURF HEATWAVE 4/3 700 259 0.37 140 38% 50%SURF ZEN-ZIP 4/3 3100 1147 0.37 165 38% 50%TRIATHLON TRIATHLON 4/3 FULL 2600 1690 0.65 210 45% 65%WAKE-BOARD REACTOR 3/2 1500 750 0.50 150 45% 65%WINDSURF CYCLONE 4/3 950 665 0.70 325 45% 65%WINDSURF WMS EVOLUTION 4/3 850 595 0.70 275 45% 65% = expected demand
= standard deviation of demand
Price = wholesale priceMargin = gross margin as a % of priceDiscount = anticipated end of season discount as % of price to sell left over inventory
Profit and mismatch with only 1 ordering opportunity
Use the Newsvendor model to evaluate the optimal order quantity, expected profit, maximum profit and mismatch cost
A suits produced in the 1st order earns the Newsvendor profit but a suit produced in the 2nd order earns the maximum profit.
Sport ModelOrder
quantityExpected
profitMaximum
profitMismatch
costDIVE DIVE COMP 3/2 FULL 1241 $30,086 $50,160 $20,074DIVE WMS 7000X 7MM FULL 677 $37,608 $62,700 $25,092SURF EPIC 5/3 W/HD 1009 $58,048 $68,400 $10,352SURF HEAT 3/2 1514 $42,568 $50,160 $7,592SURF HEATWAVE 4/3 883 $31,604 $37,240 $5,636SURF ZEN-ZIP 4/3 3910 $164,953 $194,370 $29,417TRIATHLON TRIATHLON 4/3 FULL 3449 $164,582 $245,700 $81,118WAKE BOARD REACTOR 3/2 1877 $75,536 $101,250 $25,714WINDSURF CYCLONE 4/3 1284 $89,538 $138,938 $49,399WINDSURF WMS EVOLUTION 4/3 1149 $67,788 $105,188 $37,399Total 16993 $762,311 $1,054,105 $291,794
12-16
Produce “safer” products early, produce “risky” products with reactive capacity
Sort items by their mismatch cost to order quantity ratio. Fill the 1st order up to the minimum quantity (10,200) with the items that have the lowest mismatch – quantity ratio
The mismatch cost is reduced by 66%!
ModelOrder
quantity
Newsvendorexpected
profitMismatch
cost
Mismatch cost-order quantity
ratioFirst order
quantity ProfitHEAT 3/2 1514 $42,568 $7,592 5.0 1514 $42,568HEATWAVE 4/3 883 $31,604 $5,636 6.4 883 $31,604ZEN-ZIP 4/3 3910 $164,953 $29,417 7.5 3910 $164,953EPIC 5/3 W/HD 1009 $58,048 $10,352 10.3 1009 $58,048REACTOR 3/2 1877 $75,536 $25,714 13.7 1877 $75,536DIVE COMP 3/2 FULL 1241 $30,086 $20,074 16.2 1241 $30,086TRIATHLON 4/3 FULL 3449 $164,582 $81,118 23.5 0 $245,700WMS EVOLUTION 4/3 1149 $67,788 $37,399 32.6 0 $105,188WMS 7000X 7MM FULL 677 $37,608 $25,092 37.1 0 $62,700CYCLONE 4/3 1284 $89,538 $49,399 38.5 0 $138,938Total 16993 $762,311 $291,794 10434 $955,320
12-17
18
Push-Pull Supply Chains
Push-Pull Boundary
PUSH STRATEGY PULL STRATEGY
Low Uncertainty High Uncertainty
The Supply Chain Time Line
CustomersSuppliers
19
A new Supply Chain Paradigm
A shift from a Push System...– Production decisions are based on forecast
…to a Push-Pull System– Parts inventory is replenished based on forecasts– Assembly is based on accurate customer demand
20
Demand Forecast
The three principles of all forecasting techniques:
– Forecasts are always wrong– The longer the forecast horizon the worst is the
forecast – Aggregate forecasts are more accurate
• The Risk Pooling Concept
21
Business models in the Book Industry
From Push Systems...– Barnes and Noble
...To Pull Systems– Amazon.com, 1996-1999
And, finally to Push-Pull Systems– Amazon.com, 1999-present
• Around 40 warehouses
22
Business models in the Grocery Industry
From Push Systems...– Supermarket supply chain
...To Pull Systems– Peapod, 1989-1999
• Stock outs 8% to 10%
And, finally to Push-Pull Systems– Peapod, 1999-present
• Dedicated warehouses• Stock outs less than 2%
23
Locating the Push-Pull Boundary
24
Organizational Skills Needed
RawMaterial Customers
PullPush
Low Uncertainty
Long Lead Times
Cost Minimization
Resource Allocation
High Uncertainty
Short Cycle Times
Service Level
Responsiveness
25
Speculative Production capacity
ReactiveProduction capacity
Initial forecast Later orders
Low Risk: Push High Risk: Push-Pull
O’Neill: quick response (reactive capacity)
Announcement
Read the HP case for next week We will analyze it in-class Bring your laptops!