Operation Thekgo - Principals Driving Total System Reliability & Capacity AMUE Convention 16 October...
-
Upload
gregory-morris -
Category
Documents
-
view
218 -
download
0
Transcript of Operation Thekgo - Principals Driving Total System Reliability & Capacity AMUE Convention 16 October...
Operation Thekgo - Principals Driving Operation Thekgo - Principals Driving Total System Reliability & CapacityTotal System Reliability & Capacity
AMUE Convention
16 October 2007
Greg Tosen
Operation Thekgo
2
Contents
• Key Demand & Supply Side Challenges facing South Africa
• Total System Capacity & Reliability (TSC&R) – the Thekgo Approach
• TSC&R Journey (last 18 months)
– Emergency Preparedness
– Short-term Reliability
– Reliability Enhancement & Role out
• Conclusions
Operation Thekgo
3
South African Electricity Situation
Operation Thekgo
4
Electricity Demand and Supply – key challenges
• South Africa has reached the end of its surplus generation capacity
• 1st challenge: Avoiding mismatch between demand and supply
– Excess capacity - stranded resources
– Capacity shortage - constrained economic growth
• 2nd challenge: Correct choice of capacity to be constructed from an array of available options that differ dramatically in terms of:
– Cost (construction and operating)
– Lead time to construction
– Environmental impact
– Operating characteristics
Operation Thekgo
5
National + Foreign long term forecasts plus Position line
30000
40000
50000
60000
70000
80000
90000
100000
110000
120000
130000
2005 2010 2015 2020 2025
MW
Electricity growth - 6%
Position - 4%
High forecast - 3.2%
Moderate forecast - 2.3%
Long Term Demand forecast
Eskom position based on 4% electricity growth
supporting 6% economic growth
Operation Thekgo
6
Diversify Primary Energy Mix
Coal OCGT
Nuclear Renewable Energy
Imports Pumped Storage
Existing Mix by 2025
Operation Thekgo
7
Total System Capacity & Reliability Action Centre Mandate
The action centre will:
• Co-ordinate and integrate total system capacity and reliability of the business over the next 36 months
– Oversight of the overall capacity and reliability targets
Develop the targets
Develop RACIs addressing Action Centre and Line
– Oversight over all processes across the value chain to ensure the achievement of targeted capacity and reliability
– Identify, mitigate risks and implement contingencies
– Be the integration point across the value chain to ensure total systems capacity and reliability
– Implement measures across all areas of the business to address the long term capacity requirements and reliability of the total system
– Address all people, culture and stakeholder management issues pertaining to capacity and reliability
– Ensure focus across the organisation on reliability and capacity as fundamental priorities.
– Align existing initiatives and optimise resources and effort
• Implement a robust emergency response process
Operation Thekgo
8
VulnerabilityAdaptive
Capacity
Reduction Readiness Response Recovery
System adaptive capacity
System vulnerability
time
KPI
Shock
Resilient Organisation
•Ability to rebound•Ability to recover easily & quickly from adversity
Operation Thekgo
9
Key Initiatives and Objectives – 36 months
• Ensure required level of total system capacity and reliability for the next 36 months.
• Immediate focus on Western Cape & Eastern
• Implement an interim and end-state emergency response process including a command centre
• Enhance and Institutionalise Eskom’s current reliability management Framework.
• Feedback Learning from the Short Term initiatives into the existing business and long term initiatives
• Reliability and capacity is positioned as a top business priority
• Operation Thekgo is effectively positioned.
• Ensure consistent and proactive communication with all stakeholders regarding capacity and reliability.
• A robust and reliability culture supported by the correct HR processes, quality and quantity of skills.
Short Term Reliability
Emergency Response Command Centre
Reliability Enhancement
Stakeholder & Communications
Culture and Change
Operation Thekgo
10
The TSC&R Journey for the next 36 months
Phase 2: Operationalisation Phase 3: Instituitionalisation
Dec 2006Dec 2006 June 2007June 2007 Dec 2007Dec 2007 June 2008June 2008 Dec 2008Dec 2008
Eskom’s Journey in the next 36 months
Summer2006
Summer2006
Winter2007
Winter2007
Summer2007
Summer2007
Winter2008
Winter2008
Summer2008
Summer2008
June 2006June 2006
Winter2006
Winter2006
Establish Emergency Response
Command Centre
Establish Emergency Response
Command Centre
Early Warning Monitoring and Response
Early Warning Monitoring and Response
Aug 2006Aug 2006
Create and ValidateReliability Enhancement
Strategy
Winter and Summer AssessmentsWinter and Summer Assessments
Readiness Action PlansReadiness Action Plans
Reliability Readiness Audit
Reliability Readiness Audit
Short Term Reliability Initiatives
Continuous ImprovementImplement Strategy
- Background and Information
EstablishInterim
EmergencyResponse
End StateDesign & Implement
May2007
and 5 yr plan
Operation Thekgo
11
Imperatives for Establishing the Emergency Response Command Centre
Integrated Emergency Response
StrategicManagement
of Stakeholders
Strategic and Tactical Emergency Response
• Create a central co-ordination point that can respond to any event in an integrated manner
• Reduce duplicated effort and drive alignment
• Focus will mostly be on events or issues with an Eskom-wide or multiple division impact
• Create a central co-ordination point that can respond to any event in an integrated manner
• Reduce duplicated effort and drive alignment
• Focus will mostly be on events or issues with an Eskom-wide or multiple division impact
• Focus on communications between divisions and regions in an integrated manner
• Foster consistency in communication of messages to stakeholder groups in an
emergency situation
• Focus on communications between divisions and regions in an integrated manner
• Foster consistency in communication of messages to stakeholder groups in an
emergency situation
• Leadership driven response to emergencies
• Strategic responses to emergencies, aligned with divisional operational response plans
• Leadership driven response to emergencies
• Strategic responses to emergencies, aligned with divisional operational response plans
Addressing the Addressing the need to react differentlyneed to react differently to an emergency from an Eskom national perspective to an emergency from an Eskom national perspective
Operation Thekgo
12
Gx (where applicable)
Gx (where applicable)
TxTx
DxDx
KSACsKSACs
Other Divisions as requiredOther Divisions as required
ERCC Operating Model – Regional Joint Command Centres (RJCC)
ERCCMegawatt Park
ERCCMegawatt Park
Eastern RJCC
Mkondeni
Eastern RJCC
Mkondeni
North East RJCC
Witbank/Nelspruit
North East RJCC
Witbank/Nelspruit
Northern RJCC
Pretoria/Polokwane
Northern RJCC
Pretoria/Polokwane
Central RJCC
Simmerpan
Central RJCC
Simmerpan
North West RJCC
Bloemfont.
North West RJCC
Bloemfont.
Western RJCC
Bellville
Western RJCC
Bellville
Southern RJCCEast
London
Southern RJCCEast
London
NATIONALNATIONALCONTROLCONTROLCENTRECENTRE
NATIONALNATIONALCONTROLCONTROLCENTRECENTRE
NationalNationalEmergencyEmergency
CentresCentres
NationalNationalEmergencyEmergency
CentresCentres
Gx JOC
Tx JOC
Dx JOC
KSACs
Other
Gx JOC
Tx JOC
Dx JOC
KSACs
Other
Gx JOC
Tx JOC
Dx JOC
KSACs
Other
Gx JOC
Tx JOC
Dx JOC
KSACs
Other
Tx JOC
Dx JOC
KSACs
Other
Gx JOC
Tx JOC
Dx JOC
KSACs
Other
Tx JOC
Dx JOC
KSACs
Other
Operation Thekgo
13
Emergency Response Protocols
Further ActionsFurther Actions
MobiliseRecovery Team
MobiliseRecovery Team
Status ReportingStatus Reporting
Emergency Response ProtocolsEmergency Response Protocols
Determine Initial Response
Determine Initial Response
Event Trigger
ActivationActivation
Convene Initial Response Team
Convene Initial Response Team
Plan ActionsPlan Actions
Stand Down
Assess SituationAssess
Situation
Develop Strategic Options & Priorities
Develop Strategic Options & Priorities
Further ActionsFurther Actions
MobiliseRecovery Team
MobiliseRecovery Team
Status ReportingStatus Reporting
Emergency Response ProtocolsEmergency Response Protocols
Determine Initial Response
Determine Initial Response Team
Event Trigger
ActivationActivation
Convene Initial Response Team
Convene Initial Response Team
Plan ActionsPlan Actions
Stand Down
Info Request
Assess SituationAssess
Situation
Develop Strategic Options & Priorities
Develop Strategic Options & Priorities
Communications and Stakeholder Management
Alert
Nw
Operation Thekgo
14
The TSC&R Journey for the next 36 months
Phase 2: Operationalisation Phase 3: Instituitionalisation
Dec 2006Dec 2006 June 2007June 2007 Dec 2007Dec 2007 June 2008June 2008 Dec 2008Dec 2008
Eskom’s Journey in the next 36 months
Summer2006
Summer2006
Winter2007
Winter2007
Summer2007
Summer2007
Winter2008
Winter2008
Summer2008
Summer2008
June 2006June 2006
Winter2006
Winter2006
Establish Emergency Response
Command Centre
Establish Emergency Response
Command Centre
Early Warning Monitoring and Response
Early Warning Monitoring and Response
Aug 2006Aug 2006
Create and ValidateReliability Enhancement
Strategy
Winter and Summer AssessmentsWinter and Summer Assessments
Readiness Action PlansReadiness Action Plans
Reliability Readiness Audit
Reliability Readiness Audit
Short Term Reliability Initiatives
Continuous ImprovementImplement Strategy
EstablishInterim
EmergencyResponse
End StateDesign & Implement
May2007
and medium-term outlook
Operation Thekgo
15
Short-term Reliability
• Ensure required total system capacity and reliability for next 5 yrs Ensure proper alignment
and coordination of all capacity and reliability related initiatives across all functions and
areas within Eskom
• Establish reliability assessment and reliability readiness
Equip the organisation to live with an increase of power system risk
Operation Thekgo
16
Short Term Reliability – Approach
Enhance the preparedness of Eskom to address total system reliability for
key periods
AssessEffectiveness
Action Solution
Identify
Reliability Risk Assessments
Ongoing Coordination of Reliability Initiatives
Reliability Readiness Audit
18 month plan
5 yr plan
Regional Reliability Teams
Operation Thekgo
17
Short Term Reliability – Approach
Enhance the preparedness of Eskom to address total system reliability for
key periods
AssessEffectiveness
Action Solution
Identify
Reliability Risk Assessments
Ongoing Coordination of Reliability Initiatives
Reliability Readiness Audit
18 month plan
5 yr plan
Regional Reliability TeamsRisks
Operation Thekgo
18
Key Power System RisksRisk Comment
Extended Outage of a large coal fired thermal unit or of a nuclear unit (600 to 900 MW) impacting on stock pile levels, creating capacity shortages (needing extended use of demand side resources) and increased vulnerability to large scale interruptions based on location of generation (as transmission corridors become heavily loaded)
•While there have been a number of short duration generator outages, there has been no extended outage of any of the large units
Outages of one or two lines and/or transformers in major transmission corridors resulting in large scale interruptions and possible rolling load shedding if recovery times are long
•No major transmission risks have materialised.
•The risk remains unchanged
Operation of special protection systems are not effective leading to cascading outages and increased vulnerability to large scale interruptions and blackout.
•No incidents have occurred
•The risk remains unchanged
Dramatic reduction in coal stockpiles resulting in units having to shut down. Vulnerability has increased to this risk due to the low level of stockpiles currently.
•Stockpile risks
•The risk still remains
Unavailability of liquid fuel for open cycle gas turbines •Risk remains unchanged
Operation Thekgo
19
Confidence levels (2005-2006 data)
Daily UCLF and (UCLF+OCLF) Cumulative Distribution (April 2005 - February 2007)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
UCLF or UCLF+OCLF (%)
Pro
ba
bilit
y
UCLF
UCLF+OCLF
2000MW1500MW
NOTE: 36428 MW installed base
Confidence level 90%
(37 days at risk) 95%
(19 days at risk) 98%
(8 days at risk) Unplanned Allowance
1500 MW 2000 MW 2500 MW
1900 MW O.R.
Operation Thekgo
20
Short Term Reliability – Approach
Enhance the preparedness of Eskom to address total system reliability for
key periods
AssessEffectiveness
Action Solution
Identify
Reliability Risk Assessments
Ongoing Coordination of Reliability Initiatives
Reliability Readiness Audit
18 month plan
5 yr plan
Regional Reliability Teams
Plans
Operation Thekgo
21
18 Month Rolling Plan – Approach & Classification
Summer ’06Oct ’06 to Mar ‘07
Summer ’06Oct ’06 to Mar ‘07
Winter ’07Apr ’07 to Sep ‘07Winter ’07
Apr ’07 to Sep ‘07Summer ’08Oct ’07 to Mar ‘08
Summer ’08Oct ’07 to Mar ‘08
18 Month Rolling PlanUpdated every 6 months
6 Month Rolling PlanBi-Monthly
Approach PhilosophyApproach Philosophy
• Assessing the vulnerability to the organisation from an integrated perspective.
• Plan is developed using divisional input for compiling the vulnerability, and assessing the system adaptive capacity.
• Assessing the vulnerability to the organisation from an integrated perspective.
• Plan is developed using divisional input for compiling the vulnerability, and assessing the system adaptive capacity.
• Green– If the Actual Supply (AS) is greater than the Required
Supply (RS) and meets the 1900 MW reserve.
• Yellow– If the Actual Supply (AS) is greater than the Required
Supply (RS) and the deficit is less than 1000MW.
– Probably use of Contracted DMP resources and EL1.
• Orange– If Actual Supply (AS) deficit to RS is between 1000 MW
and 2000 MW.
– Probably use Interruptible loads.
Classification System• Red
– If Actual Supply (AS) deficit to RS is between 2000 MW and 3000 MW.
– Probably use interruptible loads and have some mandatory load shedding.
• Brown– If the Actual Supply (AS) deficit to RS is more than
3000MW.
– Probably have rotating mandatory load shedding
Operation Thekgo
22
Capacity Adequacy – Winter 2007
Date Week Forecast Available Capacity Less OR and UA Surplus / Deficit
04-Jun-07 22 36844 37390 33590 -3254
11-Jun-07 23 36972 37300 33500 -3472
18-Jun-07 24 37043 37881 34081 -2962
25-Jun-07 25 36386 38489 34689 -1697
02-Jul-07 26 36461 38506 34706 -1755
09-Jul-07 27 36736 39008 35208 -1528
16-Jul-07 28 36319 38583 34783 -1536
23-Jul-07 29 35823 38853 35053 -770
30-Jul-07 30 35211 37485 33685 -1526
06-Aug-07 31 34579 36660 32860 -1719
13-Aug-07 32 34540 36960 33160 -1380
20-Aug-07 33 34255 36309 32509 -1746
27-Aug-07 34 34068 35852 32052 -2016
03-Sep-07 35 34917 36397 32597 -2320
10-Sep-07 36 33443 35612 31812 -1631
17-Sep-07 37 33951 35612 31812 -2139
24-Sep-07 38 32982 34829 31029 -1953
Ver 5
Operation Thekgo
23
Short Term Reliability – Approach
Enhance the preparedness of Eskom to address total system reliability for
key periods
AssessEffectiveness
Action Solution
Identify
Reliability Risk Assessments
Ongoing Coordination of Reliability Initiatives
Reliability Readiness Audit
18 month plan
5 yr plan
Regional Reliability Teams
Teams
Operation Thekgo
24
Reliability Risk Team Structure (R.A.C.I.)
Integrated Reliability
Risk Forum
ExcoSoS
Exco
ThekgoActionCentre
CTAD
Regional Reliability
Teams
Implementation of Reliability Risk Mitigations and
Actions(Accountable)
Custodians of Reliability Risk(Responsible)
Guidance re Mitigation &
Implementation Support(Inform)
Auditing of Action Implementation &
Mitigation Effectiveness
(Consult)
Custodian of Overall Reliability
Risk Process(Responsible)
Operation Thekgo
25
Approach to Addressing the Reliability Situation in the Regions
Network Strengthening
Network Strengthening
Load ReductionInitiatives
Load ReductionInitiatives
IntegratedCustomer Mgt
IntegratedCustomer Mgt
Stakeholder Management
Stakeholder Management
IntegratedReliability Risk Mgt
IntegratedReliability Risk Mgt
EmergencyPreparedness
EmergencyPreparedness
Skills & ResourcesSkills & Resources
Operation ThekgoOperation Thekgo
Reliability Team PMO
Reliability Team PMO
• Assessing overall reliability risks in an integrated approach for the region
• Managing and controlling the activities of the resilience team
• Risk, issue and deliverable management
Operation Thekgo
26
Approach to Addressing the Reliability Situation in the Regions
Network Strengthening
Network Strengthening
Load ReductionInitiatives
Load ReductionInitiatives
IntegratedCustomer Mgt
IntegratedCustomer Mgt
Stakeholder Management
Stakeholder Management
IntegratedReliability Risk Mgt
IntegratedReliability Risk Mgt
EmergencyPreparedness
EmergencyPreparedness
Skills & ResourcesSkills & Resources
Operation ThekgoOperation Thekgo
Reliability Team PMO
Reliability Team PMO
• Assessing overall reliability risks in an integrated approach for the region
• Managing and controlling the activities of the resilience team
• Risk, issue and deliverable management
Operation Thekgo
27
Region Risks
Unifirm Substations Single Contingency lines
R Load is shed after the loss of a single transformer.
OMomentary load shedding is required after the loss of a transformer but all load is restored after remedial actions have been implemented.
G No load shedding is required after the loss of a single transformer.
Operation Thekgo
28
Approach to Addressing the Reliability Situation in the Regions
Network Strengthening
Network Strengthening
Load ReductionInitiatives
Load ReductionInitiatives
IntegratedCustomer Mgt
IntegratedCustomer Mgt
Stakeholder Management
Stakeholder Management
IntegratedReliability Risk Mgt
IntegratedReliability Risk Mgt
EmergencyPreparedness
EmergencyPreparedness
Skills & ResourcesSkills & Resources
Operation ThekgoOperation Thekgo
Reliability Team PMO
Reliability Team PMO
• Assessing overall reliability risks in an integrated approach for the region
• Managing and controlling the activities of the resilience team
• Risk, issue and deliverable management
Operation Thekgo
29
DSM Role out
Customer Service
Board of Directors
Quality Assurance
Research & Development
ESSENTIAL SUPPORT FUNCTIONS TO ALL OF THE ABOVE
PersonnelPersonnelPersonnel
$
MICROSOFTCORPORATION
Finance
TariffsBuilding stdsAppliancelabeling
OR STICK
Warehouse
Comprehensive National Comprehensive National Demand Management Demand Management
ProgrammeProgramme
Virtual Power Station
Increased Demand Side Management target of 3000MW by 2012
Operation Thekgo
30
Conclusions
• The system remains extremely tight from a capacity point of view for the months and years ahead
– Probability of load shedding is relatively high largely due to unexpected performance changes in generation or transmission plant.
– Relief only when several new coal fired units are built and reserve margin goes over 15% (2011 to 2013)
• Focus is required on current system, as well as new build programs
– Integration of new projects is going to put the network under stress and close cooperation required between all divisions
.
Operation Thekgo
31
Integration between these elements is key for Eskom to handle their current and future challenges.
Planning Security of Supply Risk Management
Emergency Response
Event
Emergency response plan
Activ
ity
Crisis management/ communication plan
Businessrecovery plan
Time objective
Roadmap to RecoveryTM
Stage 1Stage 2
Stage 3
ER Protocol Recovery strategiesStakeholder
management / Comms
• Daily plan• Weekly Plan• Monthly Plan• 18 Month Plan• 5 Year Plan• 15 Year Plan
Life of Plant
Supply
Demand Risk / Shortfall
Probability of Risk
Thekgo value
Thank YouThank You