On-grid PV Opportunities in University Campuses: A case study at Nazarbayev University in Astana,...
-
Upload
luis-ram-rojas-sol -
Category
Food
-
view
20 -
download
0
Transcript of On-grid PV Opportunities in University Campuses: A case study at Nazarbayev University in Astana,...
On-Grid PV Opportunities in University Campuses: A Case Study at Nazarbayev University in Astana, Kazakhstan
AITKULOV, Daniyar
ASSYLOVA, Zhuldyz
SUANBEKOVA, Elnara
ROJAS-SOLORZANO, Luis
Split-Croatia May 14-17, 2017
ContentIntroduction
2
IntroductionRelated Work
Assessment Methodology (LCCA)
Feasibility Analysis Scenario I
Scenario II
Scenario III
LCCAInitial Costs
Annual Costs
Periodic Costs
Conclusions
IntroductionRelated work
3
Total capacity: 28 MW
Aims to:
545 MWh/year by 2017
Many university campuses around the world are installing PV systems in theirpremises as fully operative projects to demonstrate their commitment withcurrent environmental issues using viable technologies.
Substantial encouragement coming from the government:US Renewable Energy Incentive Program that helps to cut up to half the cost of thesolar system.
Total capacity: 23.6 MW
Total capacity: 17.4 MW
IntroductionRelated work
4
System aims to generate 10% of total
Campus demand.
Expected output: 240 MWh/year
RE incentives program initiated by
government of Malaysia
State University of New Jersey
The total capacity of 17,417 kW
Many projects ongoing to implement mid-size photovoltaic plants
integrated into main university buildings to “teach by example”.
• Gained experience is valuable in further
analysis and future projects around the
world.
• What about Nazarbayev University?
Is it viable?
Introduction5
Nazarbayev University: Astana-Kazakhstan
• Founded: June 2010 in the “heart of Eurasia”.
• Research university aiming to develop as a prestigiousworld-class university combining education, researchand innovation.
https://monitor-cdn5.icef.com/wp-content/uploads/2014/09/Kazakhstan-map.jpg
• 3268 students.
• Academic Excellence: Integration of educationand research in a common ecosystem.
• Clean Energy Technologies: one StrategicResearch and Technology area.
• Kazakhstan EXPO-2017: “Future Energy”
Nazarbayev University is a suitable candidate
Introduction6
Economic-technical
evaluation of the project
Natural resources assessment
Technology selection
Life Cycle Cost Analysis on
Proposed Case vs. Base Case
Base case: Grid electricity (72% from coal-fired power plants)*
Proposed case: On-grid PV FIT / On-grid PV FIT + Grant / On-Grid PV FIT++
Assessment Methodology/LCCA
Assessment Methodology (LCCA)
RETScreen 4.0 platform
(*) https://www.export.gov/article?id=Kazakhstan-Electrical-Power-Generation
Introduction7
Assessment Methodology (LCCA)/ Natural Resources Assessment
• 87.5% electricity from fossil fuels, 12.3%hydro and 0.2% others. 72% of electricityfrom coal-fired power plants.
• Solar energy is abundant. 2200-3000sunny hours per year.
• 6x50MW solar plants in construction insourthern region Zhambyl 2016-17.
• 1300-1800kWh/m2/year solar insolation.
source: http://www.reegle.info/policy-and-regulatory-overviews/KZ Based on REEEP Policy Database
http://solargis.com/assets/graphic/free-map/GHI/Solargis-Kazakhstan-GHI-solar-resource-map-en.png
LocationEngineering Block 6
Deployment
Ground location was discarded becauseof ongoing construction an potentialuncontrolled shadowing.
Accessibility issues
Roof offers difficulties for maintenance work.
Where in NU campus is it possible to install PV?
8
Block 8 Block 6 Block 4 Block 2
Close up of Block 6
IntroductionAssessment Methodology (LCCA)/ Technology Selection
9
Parameters for energy model
Technical specifications of PV panels (as extracted from RETScreen)
PV Capacity 24 kWp
Solar tracking mode Fixed
Slope 30 °
Azimuth 0 °
Electricity Export
Rate (FIT) (KZT/MWh)
36,410
Capacity Factor 14.7%
Astana Solar PV Panels KZ PV 230M60, efficiency: 12.4%, 100 units, total 24 kWp on 194 m2
IntroductionAssessment Methodology (LCCA)/ Technology Selection
Life Cycle Cost Analysis (LCCA)Initial costs
10
Contract negotiations, permits & approvals, site survey & land rights,
GHG validation & registration, project financing, legal & accounting. Free
consulting from NU.
Development
Spare parts cost (30 % percentage of the total equipment cost): 3,312,000 KZT. Thus, total CAPEX = 16,469,200 KZT. Contingencies = 1,497,200 KZT.
Balance of system & miscellaneous“Astana Solar” LLPmanufactures PV in Kazakhstan
Feasibility study
PV panels by “Astana Solar” using Kazakhstani silicon. “KazPV” LLP (1kWp ≈ 315,000 KZT).
Power system
Low-maintenance PV system typically require little maintenancewith lifetime of 25 years
Annual costs
Support to be provided by NU.
Additional expenses of 200,000 KZT.
EngineeringInverter lifecycle = 10 years
Periodic costs
24 kWp PV array: 7,560,000 KZT
11
Current FIT in Kazakhstan: 36,410 KZT/MWh
Scenario I Scenario II Scenario III
Brief
description
Current FIT
36,410
KZT/MWh / No
incentives
Current FIT +
30% Total
CAPEX GG
Upgraded FIT
70,000
KZT/MWh
/No incentives
Scenarios to be assessed
Scenarios
Life Cycle Cost Analysis (LCCA)
Scenario I (On-grid PV FIT)Financial parameters
Inflation rate % 9.7%
Discount rate % 12.0%
Project life yr 20FinanceIncentives and grants KZTDebt ratio % 25.0%Debt KZT 4 117 300Equity KZT 12 351 900Debt interest rate % 15%
Debt term yr 20
Debt payments KZT/yr 657 786
Financial viabilityAfter-tax IRR - equity % 15.1%Simple payback yr 17.6Equity payback yr 8.8Net Present Value (NPV) KZT 4 587 237Benefit-Cost (B-C) ratio 1.37
Cumulative cash flows (as extracted from RETScreen)
12Feasibility Analysis (via LCCA)
Financial parameters
Fuel cost escalation rate % 3.0%
Inflation rate % 9.7%
Discount rate % 12.0%
Project life yr 20
Financial viability
Pre-tax IRR on equity % 20.9
Simple payback yr 12.3
Equity payback yr 7.2
Net Present Value (NPV) KZT 5 849 558
Benefit-Cost ratio 1.47
11
Scenario II (On-grid PV FIT + 30% CAPEX GG)Cumulative cash flows (as extracted from RETScreen)
Feasibility Analysis (via LCCA)
Financial parametersInflation rate % 9.7%Discount rate % 12.0%Project life yr 20Debt ratio % 25.0%Debt KZT 4 117 300Equity KZT 12 351 900Debt interest rate % 15%Debt term yr 20Debt payments KZT/yr 657 786
Financial viabilityAfter-tax IRR - equity % 28.3%Simple payback yr 8.3Equity payback yr 5.0Net Present Value (NPV) KZT 32 298 837Benefit-Cost (B-C) ratio 3.61
12
Scenario III (On-grid PV Upgraded FIT )
Cumulative cash flows (as extracted from RETScreen)
Feasibility Analysis (via LCCA)
Summary of 3 scenarios
Scenario I Scenario II Scenario III
Scenario brief description no incentives,
actual feed in
tariff 36,410
KZT/MW
30 % incentives
from government
with actual feed in
tariff
new proposed feed
in tariff 70,000
KZT/MW
Pre-tax IRR on equity (%) 15.1 20.9 28.3
Simple payback (years) 17.6 12.3 8.3
Equity payback (years) 8.8 7.2 5
Net Present Value (NPV) (KZT) 4 587 237 5 849 558 32 298 837
Benefit-Cost ratio 1.37 1.47 3.61
13Feasibility Analysis (via LCCA)
Concluding remarksFinancial impact via LCCA of On-grid PV system at Nazarbayev University campus wasexplored under 3 scenarios: (I) Current FIT; (II) Current FIT + Grant; and (III) Upgraded FIT.
Results show that:
• Scenario I, under current FIT of 36,410 KZT/MWh, is marginally attractive with largeEquity and Simple paybacks and a modest Benefit-Cost ratio of 1.37.
• Adding an incentive of 30% of CAPEX (scenario II) improves the project financial outcome,but still in a modest level, keeping Equity and Simple paybacks above 10 years.
• Nearly duplicating the current FIT (scenario III), with no grant, led to a dramatic change infinancial outcome, turning the project into a highly attractive investment.
• Results have proven that subtle changes in Kazakhstan’s FIT policy may create theappropriate scenario to bring on-grid PV systems to campuses and facilitate the “teachingby example”.
16