On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur...

38
Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 1 Masyhur Irsyam* *President - Indonesian Society for Geotechnical Engineering *Member - Indonesian Academy of Sciences *Chair - Team for Revision of Seismic Hazard Maps of Indonesia 2010 and 2017 BAMBOO PILE-MATTRESS SYSTEM AS AN ALTERNATIVE OF SOFT GROUND IMPROVEMENT FOR COASTAL EMBANKMENT IN INDONESIA Acknowledgement: On behalf of: The Indonesian Society for Geotechnical Engineering (HATTI) The Organizing Committee Part of this material has ben presented in: Content: 1. Ground Improvement Methods for Recent Major Infrastructure Projects in Indonesia 2. Previous Experiences Using the Bamboo Pile-Mattress System 3. Utilization of Bamboo Pile-Mattress System for Soil Improvement: a. For Railway Embankment b. For Container Yard 4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System 5. Conclusions

Transcript of On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur...

Page 1: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 1

Masyhur Irsyam**President - Indonesian Society for Geotechnical Engineering*Member - Indonesian Academy of Sciences*Chair - Team for Revision of Seismic Hazard Maps of Indonesia 2010 and 2017

BAMBOO PILE-MATTRESS SYSTEM AS AN ALTERNATIVE OF SOFT GROUND IMPROVEMENT

FOR COASTAL EMBANKMENT IN INDONESIA

Acknowledgement:

On behalf of:

The Indonesian Society for Geotechnical Engineering (HATTI)

The Organizing Committee

Part of this material has ben presented in:

Content:1. Ground Improvement Methods for Recent Major Infrastructure Projects in

Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:

a. For Railway Embankment

b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Page 2: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 2

TRANS SUMATERA TOLL ROAD 2015 Geotechnical and Hydrological Condition

Soil Surface Condition

• Swampy area, with about 1.5m to 2m depth of water (STA 0+000 to STA 17+000)

• Flooding (5 years return period), the water level increase about 1m from initial elevation

• Total area of submerged zone until STA 18+000

Soil Stratification Profiling

PalembangInderalaya

Fill Height : 1m – 6m

Consolidation > 90% Settlement < 20 mm/year< 100 mm

Technical Requirement for Improvement of Soft Soils for Toll Road Construction(Department of Public Works 2002 and 2013)

Subgrade level:qall 110 kPa from

Plate Loading Test (1m x 1m)

Safety Factor againts Slope Stability SF> 1.5

qfinalSurcgarge load during preloading > 1.2qfinal

Page 3: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 3

VACUUM PRELOADING

Chu Jian, Guo Wei, Yan Shuwang, 2015

SELECTED SOLUTION

Masse et al, 2001 Geotekindo, 2015

• Negative pressure from vacuum will generates negative pore water pressure, increase effective stress in the soils, and results in accelerating consolidation process

• Much smaller amount of fill material that is needed

• There is no slope instability problem because the soil is in isotropic consolidation condition

• Shorter time for construction

Comparison: Soil Preloading and Vacuum Preloading

Soft Clay

VerticalDrain

Surcharge

Sand Blanket Berm

Soft Clay

VerticalDrain

Surcharge

Berm

Soft Clay

VerticalDrain

Surcharge

Sand Blanket Berm

Soft Clay

VerticalDrain

Surcharge

ROW ROW

Soft Clay

Vertical

Drain

Surcharge

Sand Blanket Berm

Soft Clay

Vertical

Drain

Surcharge

Soft Clay

Vertical

Drain

Surcharge

Sand Blanket Berm

Soft Clay

Vertical

Drain

Surcharge

Soft Clay

VerticalDrain

Surcharge

Sand Blanket Berm

Soft Clay

VerticalDrain

Surcharge

Soft Clay

VerticalDrain

Surcharge

Sand Blanket Berm

Soft Clay

VerticalDrain

Surcharge

Soft Clay

Vertical

Drain

Surcharge

Sand Blanket Berm

Soft Clay

Pavement

Soft Clay

Vertical

Drain

Surcharge

Sand Blanket Berm

Soft Clay

Vertical

Drain

Surcharge

Berm

Soil Preloading Vacuum Preloading

• Wide ROW

• High soil surcharge

• Need thick horizontal drain

• Lower Stability

• Greater Lateral Movement

• Longer Construction Time

• Narrow ROW

• Lower or no soil surcharge

• Relatively thin horizontal drain

• Better Control of Stability

• Lesser Lateral Movement

• Shorter Construction Time

CONSTRUCTION OF VACUUM PRELOADING

1. Geotextile 2. Sand Filling

3. PVD Installation 4. PHD Installation

5. Geo Membrane Installation 6. Instrumentation

7. Vacuum Process 8. Backfilling during vacuum

CONSTRUCTION OF VACUUM PRELOADING

Page 4: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 4

CPT TEST : ZONE 1

Map of Earthquake Sources for Indonesia 2017Subduction Megathrust

Earthquake Hazard:- Tsunami- Ground Shaking- Liquefaction

TYPICAL SOIL PROFILE

Kedalaman ▪ 0 – 3 m = Very Loose to Loose SAND▪ 3 – 7 m = Loose to Medium SAND▪ > 7 m = Dense to V Dense SAND

Long Section Pararel TaxiwayPavement surface

Ground water surface

Long Section RunwayPavement surface

Ground water surface

Page 5: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 5

PAVEMENT FOR AIR SIDE AREA

Design Criteria:

•Safety Factor for Liquefaction >1.30 based on NCEER method with PGA 0.4g.

•Settlement < 10cm in future 10 years

•Post Improvement requirements:

Dynamic Compaction for Counter Measure of Liquefaction

Relationship between limiting epicentral distance of sites at which liquefaction has been observed and moment magnitude for shallow earthquakes (Ambrassey, 1988)

Liquefaction Susceptibility Historical Criteria

Palu

Necessary Conditions:

1. Potentially liquefiable soil (soil type, condition)

2. Saturation

3. Undrained loading:

-Earthquake

-Blasting

-Pile driving

-Trains, etc

Liquefaction Susceptibility Compositional criteria

1. Sands (and Silty Sands and Clayey Sands),

if fine content < 15%

2. Silt:

Low Plasticity (PI < 15%) Higher Plasticity

3. Clays:

-Fraction finer than 0.005 mm < 15%

-Liquid limit, LL < 35%

-Natural water content > 0.9 LL

Page 6: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 6

0

20

40

60

80

100

0.001 0.01 0.1 1 10 100Particle Size (mm)

Pe

rce

nt

fin

er

by w

eig

ht

Most likely to be liquefied

Likely to be liquefied

D50 range per JRA

Gradation Range for Potentially Liquefiable Sand (Hatanaka et al., 1997)

0.001 0.01 0.1 1 10 1000

10

20

30

40

50

60

70

80

90

100

0

10

20

30

40

50

60

70

80

90

100

Tsuchida (1970) boundaries for:

Potentially liquefiable soils

Most liquefiable soils

Palu soils:

Jl. Kenduri (Balaroa)

Soccer Field Jl. Lasoso

Residential Jl. Kedondong

Noodle Factory Jl. Kedondong

S A N D

C O A R S EM E D I U M F I N E

C L A Y S I L T G R A V E L

Sieve no: 270 200 100 60 40 20 10 4 3/4"

Per

cent

finer

by w

eigth

(%

)

Grain size (mm)

Sieve no: 270 200 100 60 40 20 10 4 3/4"

Corrected SPT Blow Counts, (N1)60 or (N1)60CS

Cyc

lic S

tre

ss R

atio

, (C

SR

7.5)

or

Cyc

lic R

esi

sta

nce

Ra

tio (

CR

R7.5) 1

atm

Correction Due to Fine Content(Seed et al., 1985 and Youd et al., 2001)

Liquefied

N-SPT

Non-Liquefied

CSR=t

sn

Percepatan gempa

Muka air tanah

Kedalaman yg ditinjau

Magnitude gempa

Kandungan butir halus

Page 7: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 7

Hammer weight: 15, 17, dan 23 Ton

Drop height: 15 m to 17 m

TRIAL TEST OF OF DYNAMIC COMPACTION

THE PROCESS

HW

Fase 1

Fase 2

Fase 3

Zona Zona Zona

DC Phase 1

DC Phase 2(if necessary)

VC Ironing

• Pelaksanaan dilakukan dengan menentukan konfigurasi jumlah pukulan yang harus dilakukan melalui tahapan percobaan.

• Dari proses tersebut, jumlah pukulan jika diperlukan dapat dibagi menjadibeberapa tahap pemukulan dan fase ironing.

Fase 1

Fase 2

Fase 3

Zona Zona Zona

Fase 1

Fase 2

Fase 3

Zona Zona Zona

Result of Dynamic Compaction

Proses Trial (Percobaan) menghasilkan konfigurasi pemukulan sebagai berikut:1. Berat tamper: 17 Ton2.Tinggi jatuh: 15 m3.Jumlah pukulan: 6 pukulan

0

1

2

3

4

5

6

7

8

0 10 20 30 40 50 60

Dep

th (m

)

N-SPT

Zona B - 6 Pukulan

Kriteria Desain

Pre-SPT

Post-SPT

Hasil Uji SPT

specification

before

after

Hasil Uji CPT

specification

before

after

New Yogyakarta International Airport Rapid Impulse Compaction for Land Site Area, 2018

Page 8: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 8

Impulse Compaction for Land Site AreaNew Yogyakarta International Airport

Liquefaction → Stone ColumnConsolidation → PVD

CONSTRUCTION OF RUNWAY 3

SOEKARNO – HATTA INTERNATIONAL AIRPORT SECTION 1

JAKARTA 2018

`

Kolam retensi

RUNWAY 2

RUNWAY 3

TAXIWAY

Saluran-1

Saluran-2

Saluran-3

Jalan PerimeterJalan InspeksiSaluranGardu Catu daya listrik

KETERANGAN

P-401 AC-WC, t = 5 cmP-401 AC-BC, t = 10 cmP-304 Cement Treated Base course, CBR >100%, t = 30 cmP-209 Crushed Agregate Subbase, CBR >80%, t = 42 cmControl Fill CBR 6%, t = 165 cmSand Blanket, t = 60 cm

27,50 17,50SHOULDER

25,00MAIN LINE

27,5017,50SHOULDER

CL

60,00

TIMBUNAN TIMBUNAN

P-401 AC-WC, t = 5 cmP-401 AC-BC, t = 5 cm

P-304 Cement Treated Base course, CBR >100%, t = 13 cm

P-209 Crushed Agregate Subbase, CBR >80%, t = 20 cmControl Fill CBR 6%, t = 165 cm

Sand Blanket, t = 60 cm

Stone Column Pola Segitiga spasi 1,5m, t = 4,5m & 5m

Preloading, t = 228 cmControl Fill CBR 6%, t = 165 cm

Sand Blanket, t = 60 cm

Stone Column Pola Segitiga spasi 1,5m, t = 4,5m & 5m

PVD Pola Segitiga spasi 1m, t = 8 – 16 m

PVD Pola Segitiga spasi 1m, t = 8 – 16 m

TYPICAL POTONGAN LAPISAN PERKERASAN

TYPICAL POTONGAN SOIL IMPROVMENT

TIPIKAL MELINTANG TAXIWAY

1.50 m

0.50 m

Page 9: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 9

2nd Trial, 11 April 2018

East Connection TaxiwaySoekarno Hatta International AirportJakarta – Indonesia 2018

Application of Full Displacement Column f 32 cm for solving Bearing Capacity and Consolidation problems

Page 10: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 10

► DETAIL PROJECT LOCATION

TERMINAL 1

TERMINAL 2

WE

ST

CO

NN

EC

TIO

N T

AX

IWA

YTERMINAL 3

CONNECTION NP1 SECONDARY APRON

(Previous Phase 2016 – 2017)

EAST CONNECTION TAXIWAY

(Current Phase 2018)

► LONG SECTION PROFILE OF CONSTRUCTION HEIGHT

TAHAP 2TAHAP 1

1.280%

1.30%

0.92%

Hmax ≈ 10.3 m

Phase I 2016 Phase I 2018Hmax ≈ 8.6 m

BRIDGE

ON PROGRESS 2018

COMPLETED 2017

Hmax ≈ 9.4 m

TAHAP 2TAHAP 1

Phase I 2016 Phase I 2018

Hmax ≈ 8.7 m

BRIDGE

ON PROGRESS 2018

COMPLETED 2017

EAST SIDE TAXIWAY

WEST SIDE TAXIWAY

BRIDGE

q badan taxiway=5 ton/m2

q bahu taxiway=1 ton/m2

q bahu taxiway=1 ton/m2

•Minimal Subgrade CBR 6%•Settlement post construction < 100mm•FS static > 1.5 and FS earthquake > 1.0

FDC or KGM

Design Criteria:FDC = Full Displacement ColumnKGM = Kolom Grout Modular

Step 1:Positioning of FDC rig

Step 3:Installation to required founding depth

Step 4:Once the displacement tool reached the required depth, simultaneously it will extract and pump in-situ fill material (mortar) through the hollow rod. The tool is rotated in the same direction during installation phase

Step 2:Lowering the displacement tool into the ground by rotating and pushing. Soil is loosen by the auger starter and the pushed into the surrounding soil by the displacement body

► SEQUENCE OF WORK

Page 11: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 11

► FDC TYPICAL SETUP

FDC RIG

MIXER

TRUCK

MORTAR

PUMPSUPPLY LINES

MIXER

TRUCKFDC RIG

Konsep Desain

Bearing Layer/Less Compressible Soil Layer

Loading Transfer Platform (LTP)

FDC

FDC

FDC

FDC

Load

1. Pemasangan FDC dan LTP

2. Pembebanan dan distribusi tegangan oleh LTP ke FDC dan tanah sekitarnya

3. Selama proses konsolidasi. Pada saatdisplacement tanah terjadi lebih besardaripada displacement FDC, sebagiantegangan pada tanah tertransfer pada FDC akibat negative skin friction pada bagian atas FDC

4. Pada saat tercapai kondisi displacement tanah mengecil sehingga kurang dari displacement FDC pada kedalaman tertentu, terjadi transfer tegangan kembali dari FDC ke tanah sekitarnya. Hal ini memobilisir positive skin friction dantahanan ujung bawah FDC

5. FDC dan tanah sekelilingnya bersama-samamenahan beban secara komposit

Compressible Soil Layer

PERLUASAN APRON 5.8 Ha

Header Pit 2A

AREA 5.8 Ha

Header Pit 2B

GROUND IMPROVEMENT WORK FOR WEST APRON DEVELOPMENT

I GUSTI NGURAH RAI AIRPORT, BALI

Vibro-Compaction

Page 12: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 12

Map of Earthquake Sources for Indonesia 2017Subduction Megathrust

Earthquake Hazard:- Liquefaction

RENCANA DESIGN AREA 5.8 Ha

RENCANA DESIGN

POTONGAN MELINTANG PERKERASAN

SALURAN EKSISTING

RENCANA SALURAN

TANAH EKSISTING (SEBELUM VIBRO FLOATATION)

VIBRO FLOATATION 10 m

TANAH EKSISTING (SESUDAH VIBRO FLOATATION)

RENCANA PERKERASAN APRON

DESAIN PEMINDAHAN SALURAN EKSISTING

RENCANA PEKERJAAN PERKERASAN APRON BARAT

DESAIN RENCANA PEKERJAAN BREAKWATER

Working Progress

11/2/2018Presentation for PT Pembangunan Perumahan

(Persero)

Assembly and testing of Vibro-Flotation Equipment

Content:1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:

a. For Railway Embankment

b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Page 13: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 13

Large and Uneven settlement

Very soft soil

Low bearing capacity

Very soft soil

Limited Height

Embankment on Soft Soils

For:- Embankment with limited height- Embankment in submerge area

- Embankment with tolerable settlement- Embankment in remote area

BAMBOO PILE-MATTRESS SYSTEM

Critical height

hc

Stability of Embankment Without Reinforcement

Soft Soil

Page 14: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 14

Stability of Embankment With Geotextile

It enforces the failure surface not to pass through middle of the embankment

Stability of Embankment With Bamboo Mattress

Distribute embankment load more uniformly

Reduce differential settlement due to it stiffness

Provides buoyancy

Stability of Embankment With Bamboo Pile- Mattress

However, embankment is still subjected to consolidation settlement!!!

Increase resistance due to side friction from bamboo piles

6.00 m

0.75 m

2.50 m

1.5

1

1.5

1

1

44

1

6.00 m

2.50 m

0.75 m

1

1.5 1.5

1

Consolidation Settlement

Bamboo mattress only Bamboo pile-mattress system

Page 15: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 15

Durability?

Appropriate for embankment in

coastal and swampy area where

it is always saturated

Bamboo is durable as long as it is always saturated

Very Soft-Soft ClayN-SPT = 0-1qc = 1-2 kg/cm2C = 0.65 t/m2

Stiff-Very Stiff ClayN-SPT = 16C = 9 t/m2

25 m

Coastal Embankment 1995

3 m

4 m

3 m

High Strength Woven Geotextile

Page 16: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 16

Utilization of Bamboo Mattress for Coastal Embankment at Tambaklorok - Semarang

Laboratorium GeoteknikPusat Penelitian Antar Universitas, PPAU

Institut Teknologi Bandung

Embankment for Land Reclamation on Very Soft SoilMorokrembangan-Surabaya 1999

Page 17: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 17

A

B

C

D

E

F

Dermaga dan Breakwater, Muara Angke 2003

Tipikal Potongan Sekitar Dermaga

Seabed 1:1Quarry run/kerikil/sand bags

2% 2%

Pas ir

Matras Bamboo 5 lapis

Cerucuk Bamboo

L = 6 m

Woven Geotextile

Armor: Ruble mount

W50 = 400 Kg

Seabed

W50 = 370 Kg, Ø59 - 70 cm

Fi l ter: W50 = 37 Kg

Armor: Ruble mount

Ø27 - 33 cm

Tipikal Potongan Melintang

Quarry run/kerikil/sand bagsSeabed

Cerucuk Bamboo

Matras Bamboo 5 lapis

Spasi = 1 m, L = 6 m

Seabed

Page 18: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 18

PrefabricatedSegmental Raft

Content:1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:

a. For Railway Embankment

b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Page 19: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 19

UTILIZATION OF BAMBOO PILE-MATTRESS SYSTEM FOR RAILWAY EMBANKMENT ON VERY SOFT SOIL CONDITION

SEMARANG –TAWANG, 2012-2013

Page 20: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 20

Cara Meletakkan Bambu Pada Matras

Untuk 5 lapis

Page 21: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 21

Page 22: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 22

Page 23: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 23

Page 24: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 24

Loading Test Cargo Train

Surabaya, 4 Juli 2013

Masyhur IrsyamKetua - Himpunan Ahli Teknik Tanah IndonesiaKetua - Pusat Penelitian Mitigasi Bencana ITB

Ketua - Tim Revisi Peta Gempa Indonesia Anggota - Tim Penasehat Konstruksi Bangunan DKI

Bangun SuciptoPT. Pembangunan Perumahan

Andi KartawiriaPT. Promisco

UTILIZATION OF BAMBOO PILE-MATTRESS SYSTEM FOR CONTAINER YARD ON VERY SOFT SOIL CONDITION

JAKARTA PORT TERMINAL, KALIBARU, 2013

New Priok Port Project:

CT 1SUPPORTI

NG

AREA

CT : Container Terminal

PT : Product Terminal

FERIALDY NOERLAN – Direktur Teknik PT PELABUHAN INDONESIA II (Persero)

Seminar HATTI, Desember 2012

Page 25: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 25

Owner : PT PELABUHAN INDONESIA II (Persero)

Konsultan : direncanakan oleh PT LAPI ITB

Kontraktor : PT Pembangunan Perumahan(Penulis terlibat sbg Geotechnical Expert PT PP)

Reklamasi:

Sebagian besar area yang

tersedia untuk reklamasi berada

di atas tanah lunak → complicated

design (matras bambu untuk

pondasi revetment);

Permasalahan ketersediaan

pasir untuk material reklamasi;

FERIALDY NOERLAN

Seminar HATTI, Desember 2012

FERIALDY NOERLAN

Seminar HATTI, Desember 2012

VERY SOFT TO SOFT CLAY

MEDIUM TO STIFF CLAY

VERY HARD CLAY

STIFF TO VERY STIFF CLAY

Panjang daerah yang diperkuat dng cerucuk matras bambu > 5.o kmJumlah matras > 360 ribu

Page 26: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 26

PT. PP (Persero)

Page 27: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 27

Alat pancang cerucuk cluster bambu dipatenkan oleh PT .PP

PT. PP (Persero)

Alat pancang cerucuk cluster bambu dipatenkan oleh PT. PP

PT. PP (Persero)

PT. PP (Persero) Alat pancang cerucuk cluster bambu dipatenkan oleh PT. PP

Page 28: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 28

PT. PP (Persero)

Page 29: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 29

PT. PP (Persero)

Page 30: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 30

PT. PP (Persero)

Demak

Kendal

SemarangGiant Sea Wall and Shoreline Belt

Shoreline Belt

Page 31: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 31

Semarang-Demak Toll Road and Sea Dyke

TITIK AWAL

Semarang-Demak Toll Road and Sea Dyke

INUNDATION DURING HIGH TIDE

124

Luas genangan ROB + 4.500 ha (2007), dan akan meningkat terus

Penyebab : penurunan muka tanah (land subsidence); abrasi pantai;

dan kenaikan muka air laut (SLR).

SEA DYKE

125

MSL = +0,00 m

Geomembran

Batu Gradasi 60 - 300 kg,

1 : 5DWL = +3,36 m

1 : 3+4.30 m +7.50m

1.00+3.50m

1 : 5

1 : 3

Crucuk bambu + Pvd

Matras Bambu 14 Lapis -1.50 m- 2.50 m

- 5.72 m

KOLAM RETENSI

1 : 3

Tetrapod

Page 32: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 32

MSL = +0,00 m

Geomembran

Batu Gradasi 60 - 300 kg,

1 : 5DWL = +3,36 m

1 : 3+4.30 m +7.50m

1.00+3.50m

1 : 5

1 : 3

Crucuk bambu + Pvd

Matras Bambu 14 Lapis -1.50 m- 2.50 m

- 5.72 m

KOLAM RETENSI

1 : 3

Tetrapod

Sea Dyke Tahapan :

Urug pasir 1 m

Pasang cerucuk cluster bamboo L = 10 m, spasi 1.0 m

Pasang matras bambu 14 lapis

Pasang PVD L = 20 m

Timbunan bertahap 1 m (termasuk batu dan tetrapod) dengan waktu konsolidasi14 hari per tahap hingga elevasi + 5.70 (as). Pada tahap akhir hingga elevasi + 7.20 as, waktu konsolidasi selama 90 hari sebelum pelaksanaan perkerasan fleksibel.

Content:1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:

a. For Railway Embankment

b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

BAMBOO PILE-MATTRESS SYSTEM Pile-Raff Foundation

How to calculate? Coceptually, it is similar with pile-raft system for high rise buildings

2-Dimention

3-Dimention

Firmansyah, 2013

Page 33: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 33

FEM Modelling

Very Soft Soil

Node-to-Node Spring

Beam

Embankment soil

FEM 3D FEM 2D

Beam with interface

Very Soft Soil

Beam

FEM 2D

Beam dng interface element

Configuration of bamboo cluster pile

Page 34: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 34

Matt and Pile Properties

EI = E x Imatras

Imatras = Ibambu + (Ar2)

I =( )

64

DD 4

i

4

o −

- Fmax

d

0.7m

1.0m

K = Node to Node Spring/ Anchor

Beam Element

FEM 2D

MSL = +0,00 m

Geomembran

Batu Gradasi 60 - 300 kg,

1 : 5DWL = +3,36 m

1 : 3+4.30 m +7.50m

1.00+3.50m

1 : 5

1 : 3

Crucuk bambu + Pvd

Matras Bambu 14 Lapis -1.50 m- 2.50 m

- 5.72 m

KOLAM RETENSI

1 : 3

Tetrapod

Verification and Numerical ModelingBy Using

Instrumented Trial Embankmentat Tambak Oso Surabaya

Pemancangan Cerucuk Bambu

Pembuatan Matras bambu

Page 35: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 35

Pemasangan Instrumentasi di lapangan :

Pemasangan Settlemetn Plate

Pemasangan Instrumentasi di lapangan :

Pemasangan Piezometer dan tipe alat baca

5

14

18

78

85

104

Grafik Penurunan-Waktu pada Settlement Plate 4

0

10

20

30

40

50

60

70

0 20 40 60 80 100 120

Hari Pengamatan

Pe

nu

run

an

(cm

)

0

1

2

3

4

0 20 40 60 80 100 120

Tin

gg

i T

imb

un

an

(m

)

Elastic settlement

Consolidation settlement

Elastic settlement

Consolidation settlement

Elastic settlement

Consolidation settlement

Elastic settlement = 48 cm

Consolidation settlement = 17 cm

konstruksi

Page 36: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 36

(b) Arrow of Deformation(a) Shading of Deformation

Consolidation Settlement

(b) Arrow of Deformation(a) Shading of Deformation

Elastic Deformation

30.17241

0

10

20

30

40

50

60

70

80

90

100

0 20 40 60 80 100 120 140 160 180 200

Day

Se

ttle

me

nt (c

m)

Analytical Method Prediction Finite Element Method Prediction Settlement Plate 1

Settlement Plate 2 Settlement Plate 3 Settlement Plate 4

Settlement Plate 5 Settlement Plate 6 Settlement Plate 7

0

1

2

3

4

0 20 40 60 80 100 120 140 160 180 200Em

ba

nkm

en

t H

eig

ht (m

)

Analisis Stabilitas Timbunan Double Track

Tawang, Semarang

Page 37: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 37

Initial Condition Timbunan Track Baru Track Baru Opersional

Peninggian Track LamaMatras saja

Peninggian Track LamaMatras + Cerucuk

Peninggian Track LamaMatras + Cerucuk

Content:1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:

a. For Railway Embankment

b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Conclusions

•Recent major infrastructure projects in Indonesia used Vacuum Consolidation, Dynamic Compaction, Rapid Impulse Compaction, Stone Column, and Full Displacement Column etc.

• Bamboo pile-mattress system is proven to be reliable, and therefore, can be used as ground reinforcement for coastal/ swampy embankment on soft soil layer.

• Performance of the system can be predicted accurately as long as it is modeled correctly.

• Consolidation settlement has to be accounted for during the design life.

Page 38: On behalf of: BAMBOO PILE-MATTRESS SYSTEM AS AN … · SEQUENCE OF WORK. Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018 Workshop HATTI 2018 11 FDC TYPICAL SETUP FDC

Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 38

Thank You