OMD Operations Metrics Data warehouse -Weekly update meeting 02 November, 2011

description

OMD. Operations Metrics Data warehouse -Weekly update meeting. 02 November, 2011. OMD. 2. Universe Status update (Phase 1). Signed off. In User Regression. Still to release. This weeks actions – from 23 November 2011. Remaining phase 1 universes will be moved to user regression - PowerPoint PPT Presentation

Transcript of OMD

Page 1: OMD

OMDOperations Metrics Data warehouse

-Weekly update meeting

02 November, 2011

Page 2: OMD

2

Description

OMD Migration project was commissioned to migrate the current Operations Metric Databases (OMD) from Sybase IQ to SQL Server 2008 R2. The system needs to be migrated to SQL Server before Sybase IQ license expires in December 2011.

PM Comment

Progress has been slow due to issues with IQ2 server. The volumes of data involved for universes have taken longer than expected to load into the current SQL UAT environment. Progress has been made on SQL server tuning of slow running reports within the larger results such as Memphis. There is a issue with the production server release which was due on 18 November. No agreed date from infrastructure as waiting for hardware to arrive on site in the next couple of days. Due to NYK holidays and FICC change freeze there is a possibility that full release of production will not be until beginning Jan.

PM John Ilett

IT/BTB Owner S Balasubramanian

Business Sponsor

Rpting Month/ RAG 23 Nov 11 Red

OMD

Key MilestonesKey recent Milestones Status Date Comment/Benefits

Phase 1 universe signed off by users (9 signed off, 7 in regression, 11 development) In Progress 02/11/2011 Due to issues with IQ2, production server, volume of data and tuning has pushed back our phase 1 delivery of 25/11/2011.

Production Hardware Pending 3011/2011 Considering its Thanksgiving here this week and we’re close to the FICC change freeze beginning you should be prepared for the possibility that your Prod hardware will not

be built and fully configured until Jan. We are pushing for asap but purchasing, installing and building hardware at this time of the year is always difficult

Inception Date March 2010

Project Phase Migration to SQL

Category OMD

Schedule December 11 Migration

Accomplishments this week

1. Sign off for 4 universes and release of 7.

Issues/Risks to be Addressed

Description Issue/Risk Target Resolution Date

Production Hardware Push phase 2 loading & testing

25/11/2011

Key Deliverables Schedule (for the rest of the Year)

1. End to end test of migration2. Migrate sample data to each table for review and load process3. UAT Hardware delivered by 07th October 20114. Prod Hardware delivered by 16 th November 20115. Migration commence mid September6. Migration to UAT in place by End October.7. Migration from UAT to Production by end December8. Migration of Data start beginning of December.

Resource Utilization 1. OMD: Deepali Nerkar– Oracle testing, Informatica updates for SQL, BO Universe ; Anvaya Akhouri– NFS mount;

John Ilett – SQL Server set up, BO universe.2. TCS: Senthilkumar Krishnamurthy, Manoj Sthanumalayan, Arunkumar Chandran, Jegan Vasan, Satishkumaar

Manivannan, Sathappan Muthupalaniappan, Gayathri Ramkumar, Logesh Kulasekaran, Kanimozhi Elango3. DBA: Pavan Yerra4. Infrastructure & Hardware: Derek Sheridan, William Mackenzie5. Business Users: Neil Howlin, Justin Hess, Rute Pereira, Edmun Ullman

Page 3: OMD

3

Universe Status update (Phase 1)

Phase Universe PM1.1 OMD EXPOSURE MANAGER - Arrangement Knowles, Ben: Operations (LDN)1.1 OMD EXPOSURE MANAGER - Balances Knowles, Ben: Operations (LDN)1.1 OMD EXPOSURE MANAGER - Trade Knowles, Ben: Operations (LDN)1.1 OMD EXPOSURE MANAGER - Workflow Knowles, Ben: Operations (LDN)1.3 OMD DAILY VOLUME Hess, Justin: Operations (SGP)1.3 OMD eTMS Heskins, Ed: Operations (LDN)1.3 OMD EXOTICS Heskins, Ed: Operations (LDN)1.3 OMD DMX Trade Miller, Greg: Operations (LDN)1.4 OMD CATS CREDIT Miller, Greg: Operations (LDN)

Signed off

Phase Universe PM

1.1 OMD MEMPHIS Botwinik, Craig: Operations (NYK)1.2 OMD EDG CTR Trade Knowles, Ben: Operations (LDN)1.3 OMD FISS Positions Ullman, Edmund: Operations (LDN)1.3 OMD Rates IMPACT Botwinik, Craig: Operations (NYK)1.3 OMD ARMS Soliman, JC: Operations (SGP)1.4 OMD Trident Rate Reset Soliman, JC: Operations (SGP)1.4 OMD Secondary Loans – Position Lim, Peter: Operations (SGP)

In User Regression

Phase Universe PM1.1 OMD MAGICS (TODAY) Botwinik, Craig: Operations (NYK)1.2 OMD IMPACT (TODAY) Botwinik, Craig: Operations (NYK)1.4 OMD TMS Botwinik, Craig: Operations (NYK)1.4 OMD TMS Journals Botwinik, Craig: Operations (NYK)1.4 OMD TriOptima (TODAY) Knowles, Ben: Operations (LDN)1.4 OMD EDG Sophis Instrument Knowles, Ben: Operations (LDN)1.4 OMD SDAPS Trade (TODAY) Lim, Peter: Operations (SGP)1.4 OMD Secondary Loans – Trade (TODAY) Lim, Peter: Operations (SGP)1.4 OMD SIM Trade (TODAY) Heskins, Ed: Operations (LDN)1.4 OMD IMPACT Trade Botwinik, Craig: Operations (NYK)1.4 OMD IMPACT Open Items Botwinik, Craig: Operations (NYK)

Still to release

Page 4: OMD

4

This weeks actions – from 23 November 2011 Remaining phase 1 universes will be moved to user regression

Phase 2 development has started

Move SecuritiesSettlment into phase 3

Performance tune

Raise all DRQs once servers on site and space required for production servers

Continue performance tuning techniques in UAT environment

Page 5: OMD

5

Old Implementation Timeline Chart

23/09/2011 30/01/2012

01/10/2011 01/11/2011 01/12/2011 01/01/2012

15/12/2011

21/10/2011TCS: SQL & Stored

Procedures migrated to UAT

23/09/2011TCS Start Development

30/01/2012SyBase Exited

14/10/2011UAT Servers in place

18/11/2011Production Servers in place

01/11/2011 - 25/11/2011TCS: Phased data load

& UAT of universes

28/10/2011TCS: Informatica

& Autosys migrated to UAT

03/01/2012

04/11/2011TCS: BO Universe

& report migrated to UAT

14/10/2011TCS: Scripts (Java, Perl,

Env Files, Unix) migrated to UAT

02/12/2011TCS: Migrate to Production

(with data)

25/11/2011UAT Test Complete

25/11/2011 - 13/12/2011Phase 2 UAT Sign off

01/11/2011 - 18/11/2011Phase 1 UAT Sign off

03/01/2012 - 19/01/2012Phase 3 UAT Sign off

15/12/2011 - 03/01/2012Year end change Freeze

01/12/2011Phase 1 Release

07/01/2012Phase 2 Release

26/01/2012Phase 3 Release

The following major bottlenecks have pushed back timelines:1. Availability of SyBase production server: We could not extract data without hampering current production. IQ2 production environment was delivered 31/10/20112. Agreed production server delivery dates have slipped due to sign off and procurement of space: Due to deliver 09/12/2012 earliest. May push into January. *Without production and necessary spacing we cannot switch of SyBase.

Page 6: OMD

6

Phase 1 Implementation Timeline Chart

23/09/2011 30/01/2012

01/10/2011 01/11/2011 01/12/2011 01/01/2012

15/12/2011

23/09/2011TCS Start Development

07/01/2012Phase 1 released

To Production

14/10/2011UAT Servers in place

09/12/2011Production Servers

in place

03/01/2012

01/11/2011 - 07/12/2011Phase 1 regression Sign off

15/12/2011 - 03/01/2012Year end change Freeze

01/11/20111.1 delivery

to users11/11/20111.2 delivery 25/11/2011

1.3 delivery

12/12/2011 - 06/01/2012Migrate phase 1 to Prod

28/11/20111.4 delivery

Page 7: OMD

7

Phase 2 Implementation Timeline Chart

23/11/2011 30/01/2012

01/12/2011 01/01/2012

15/12/2011

20/01/2012Phase 2 released

09/12/2011Production Servers

in place

03/01/2012

30/11/2011 - 11/01/2012Phase 1 UAT Sign off

15/12/2011 - 03/01/2012Year end change Freeze

30/11/20112.1 delivery

02/12/20112.2 delivery

12/01/2012 - 19/01/2012Migrate phase 2

to Prod

07/12/20112.3 delivery

Page 8: OMD

8

Phase 3 Implementation Timeline Chart

09/12/2011 30/01/2012

01/01/2012

15/12/2011

31/01/2012Phase 3 released

09/12/2011Production Servers

in place03/01/2012

04/01/2012 - 20/01/2012Phase 3 regression Sign off

15/12/2011 - 03/01/2012Year end change Freeze

04/01/20123.1 delivery

06/01/20123.2 delivery

23/01/2012 - 27/01/2012Migrate phase 2

to Prod

11/01/20123.3 delivery

13/01/20123.4 delivery

17/01/20123.5 delivery