Olswang 3rd Annual Construction Law Conference

52
4 February 2016 Construction Law Conference 2016

Transcript of Olswang 3rd Annual Construction Law Conference

Page 1: Olswang 3rd Annual Construction Law Conference

4 February 2016

Construction Law Conference 2016

Page 2: Olswang 3rd Annual Construction Law Conference

Francis Ho, Head of [email protected] | +44 20 7067 3505 | @fkyh

Construction Law Conference 2016 4 February 2016

Developments in Construction Insurance

Page 3: Olswang 3rd Annual Construction Law Conference

|

Current Trends

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance3

• Building Information Modelling

• Integrated Project Insurance

• Inherent Defects Insurance (Latent Defects Insurance)

Page 4: Olswang 3rd Annual Construction Law Conference

|

Building Information Modelling

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance4

• 3D digital representation of a facility or building

• Information on physical and functional aspects

• Data shared and manipulated between project participants

• Government deadline of April 2016 for adoption of Level 2 BIM

Page 5: Olswang 3rd Annual Construction Law Conference

|

BIM: 4 Levels of Maturity

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance5

• Level 0: No BIM (e.g. 2D drawings)

• Level 1: Partial BIM (e.g. some CAD, some 2D drawings)

• Level 2: Federated BIM model (but separate 3D models from each participant)

• Level 3: True BIM; single model

Page 6: Olswang 3rd Annual Construction Law Conference

|

BIM and Professional Indemnity Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance6

• Building magazine/Zurich Insurance BIM and insurance survey in 2013• 43% of contractors believe BIM will lead to increased PII premiums

• 87% of insurers believed BIM made no difference but 8% reluctant to insure

• What about Level 3?

• Potential issues• Who is liable for what?

• Who owns the intellectual property in data?

• Is application of design being extended?

• Cyber liability

• Should premiums reduce?

Page 7: Olswang 3rd Annual Construction Law Conference

|

Integrated Project Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance7

• 2011 Government Construction Strategy

• Latham (1994) and Egan (1998)

• Moving away from “blame game” and towards better integration

• IPI covers losses for whole project not liabilities

Page 8: Olswang 3rd Annual Construction Law Conference

|

Integrated Project Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance8

• Replaces PI, CAR, Public and Latent Defects (possibly also consequential loss and late completion)

• For every £5 spent on costs, £1 spent by insurers (Griffiths & Armour)

• Excess shared by project team members under pain-share

• Cost fixed at 2.5% of construction cost

• Covers all team (including supply chains)

Page 9: Olswang 3rd Annual Construction Law Conference

|

Integrated Project Insurance – Different measures of success

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance9

• Performance is measured against agreed success criteria

• Creates roles of Independent Facilitator, Technical Independent Risk Assuror and Financial Independent Facilitator

• Project board takes control of project. Client sits on project board

• Target cost and project solution are insured and insurer has recourse to TIRA and FIRA

• An end to collateral warranties and third party rights

Page 10: Olswang 3rd Annual Construction Law Conference

|

Integrated Project Insurance – Thoughts

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance10

• Alliancing model

• Insurer becomes active project participant

• Insurer covenant is critical

• Project team has to be competitively appointed

• Beware of exclusions

Page 11: Olswang 3rd Annual Construction Law Conference

|

Integrated Project Insurance – Thoughts

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance11

• Savings on duplicated insurance cover

• First trial project commenced April 2015 (Dudley College (Centre for Advanced Building Technologies))

• Private sector has adopted wait and see approach

• Viable for projects within £10m to £25m range but larger projects may be suited in future

• Only solution to insuring BIM Level 3

Page 12: Olswang 3rd Annual Construction Law Conference

|

Inherent Defects Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance12

• What does an IHD policy cover?• Latent Defects Act 1980:

“defects that are not immediately apparent and which cannot be discovered by a reasonable inspection of the property”

• On top of buildings insurance

• What is it procured?• Purchaser expectation

• Tenant expectation

• Problems/concerns with collateral warranty/third party rights package

Page 13: Olswang 3rd Annual Construction Law Conference

|

Inherent Defects Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance13

• Cover up to a specified level of indemnity

• Are they available retrospectively?

• Take effect 12 months after practical completion

• Insurers will wish to be able to subrogate against construction team

Page 14: Olswang 3rd Annual Construction Law Conference

|

Advantages and disadvantages

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance14

IHD Collateral Warranties/Third Party Rights

No fault Need to prove loss

Endure 10/12 years 6 or 12 year duration

Freely assignable to successors Limited assignments

Insurer offers stronger covenant Contractor covenant less certain

Extent of cover narrow Broader protection offered

Premiums can be high Costs are well-known

Policy excess applies No deductibles

Page 15: Olswang 3rd Annual Construction Law Conference

|

Inherent Defects Insurance

constructiveblog.comConstruction Law Conference 2016: Developments in Construction Insurance15

• Must remember to treat as an insurance policy

• Is there increased demand for IHD insurance?

• Is it just laziness or is there a genuine need for IHD on projects?

Page 16: Olswang 3rd Annual Construction Law Conference

Ben Worthington, Senior [email protected] | +44 20 7067 3541 | @disputes_lawyer

Construction Law Conference 2016 4 February 2016

Payment in Construction Contracts

Page 17: Olswang 3rd Annual Construction Law Conference

|

Payment regime – the basic principles

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 17

• The employer must pay the notified sum

• The notified sum is the sum stated in the payment notice

• The payment notice can be given by (or on behalf of) the employer or by the contractor

• If the employer is required to give a payment notice and doesn’t, the notified sum is that stated in the contractor’s payment application

• If the employer wants to pay less than the notified sum, it can issue a pay less notice

• Right to adjudication

Page 18: Olswang 3rd Annual Construction Law Conference

|

Failure to serve payment and pay less notices

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 18

(1) ISG Construction Ltd v Seevic College (2014)

• If E fails to serve any valid notices, it must be taken to be agreeing the value stated in the application

• contractor becomes entitled to the amount stated in the interim application irrespective of the true value of the work actually carried out

• E cannot start a second adjudication on the same interim payment application

(2) Galliford Try Building Ltd v Estura Ltd (2015)

• E cannot bring a second adjudication to determine the value of the work at the valuation date of the interim application in question

• But there was nothing to prevent the E challenging the value of the work on the next application

Page 19: Olswang 3rd Annual Construction Law Conference

|

Interim applications and overpayment

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 19

• Many contracts do not allow for a negative valuation - an overpaid contractor cannot be compelled to repay money to the employer on the next valuation date

• If E fails to serve a valid notice it may be able to adjust for any overpayment in the next payment cycle

• BUT whether this will work depends upon the timing and amount of the application

• E may have to wait until the final account stage then issue proceedings to recover any overpayment

• It might be possible to challenge the contractor’s application

• In summary, serve the notices !!!

Page 20: Olswang 3rd Annual Construction Law Conference

|

Final accounts - Harding t/a MJ Harding Contractors v Paice (Court of Appeal) (2015)

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts20

• Failure to serve valid pay less notice did not mean E was deemed to have agreed the value of C’s termination account

• E was entitled to adjudicate in order to determine the correct value of Harding’s claims and their counterclaims in the termination account

• ISG v Seevic and Galliford Try v Estura do not apply to final accounts

Page 21: Olswang 3rd Annual Construction Law Conference

|

What constitutes a valid application for payment?

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 21

(1) The Timing of the Application

Leeds City Council v Waco UK Ltd (2015):

• Applications had to made on the dates set out in the contract but parties had established through conduct of CA that applications made 3 – 4 days late would be processed

• Applications could not be made early – they must "state the financial position as at that date" (i.e. at the date stated in the contract)

• E had certified and paid one application that had been made early - that was a one-off / no waiver

• As the application was made earlier than the valuation date, the application was invalid

Page 22: Olswang 3rd Annual Construction Law Conference

|

What constitutes a valid application for payment?

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 22

(2) It must be sufficiently clear that the document is an application for payment

Caledonian Modular Ltd v Mar City Developments Ltd (2015) • C made interim applications in the same format at the end of each month

• On 13 February it issued a “final account application summary” and supporting documents during final account negotiations

• No pay less notice served against these documents – adjudicator considered the documents constituted a payment application and awarded C £1.5m

Held:

• C’s interim application was invalid because the documents did not identify themselves as a new application for payment

• Further, it was made two weeks early – a valid interim application was made at the end of January, and no further application could be made until 28 February

• C’s interim application “... must be clear that it is what it purports to be so that the parties know what to do about it andwhen.”

Page 23: Olswang 3rd Annual Construction Law Conference

|

What constitutes a valid application for payment?

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 23

(3) The application must be free from ambiguity

Henia Investments v Beck Interiors Limited (2015)• The IA issue number and valuation date indicated that it related to April, but it was served too late for the

April due date

• Court considered that it was not a valid application in respect of the May date - E could not reasonably have understood the application to relate to the April due date (as it was too late) or the May due date (as it was early and only referred to April )

• “the document relied upon as an Interim Application… must be in substance, form and intent an Interim Application stating the sum considered by the Contractor as due at the relevant due date and it must be free from ambiguity.”

Severfield (UK) Ltd v Duro Felguera UK Ltd (2015)

A valid application for payment must:

• Set out the total sum said to be due

• Set out the basis on which that sum has been calculated

• Be clear and free from ambiguity

Page 24: Olswang 3rd Annual Construction Law Conference

|

Taking control of the payment process

constructiveblog.comConstruction Law Conference 2016: Payment in Construction Contracts 24

• Do not get caught out by lack of notices !!!

• Consider contract term that allows any overpayment on an interim payment to be repayable on the next valuation (negative valuation)

• Consider making payment due date the same date each month and synchronize payment due dates across all projects

• Do not allow contractor to submit interim applications later than the dates specified in the contract

• Make sure notices are clear, unambiguous and timely

Page 25: Olswang 3rd Annual Construction Law Conference

Louise Forbes, [email protected] | +44 20 7067 3632 | @forbes_louise

Construction Law Conference 2016 4 February 2016

Case Law Update

Page 26: Olswang 3rd Annual Construction Law Conference

|

Cavendish Square Holding BV v El Makdessi and ParkingEye Ltd v Beavis [2015]

constructiveblog.comConstruction Law Conference 2016: Case Law Update26

• Liquidated damages are a pre-determined sum which become payable by a party in the event of a specified breach of contract (for example a delay to the completion date)

• The innocent party need not establish any loss or damage, only that the circumstances triggering payment has occurred

• Parties on the receiving end of claims for liquidated damages may look at ways of avoiding them, usually by claiming that the provision is a penalty clause (English law will not enforce penalty clauses)

Page 27: Olswang 3rd Annual Construction Law Conference

| Construction Law Conference 2016: Case Law Update27

The position before Cavendish in relation to penalty clauses

• Based on a tangle of case law and has evolved over time

• Is the sum payable a genuine pre-estimate of the innocent party’s loss as a result of the specified breach? (Dunlop)

• If yes, it’s not a penalty clause

• Or is the sum extravagant and unconscionable when compared to the greatest loss that the innocent party could suffer as a result of the breach?

• If yes, it’s an unenforceable penalty clause

• However, courts do not want to interfere with the parties’ freedom to contract on whatever terms they choose, so they have in recent years adopted a more commercial approach

constructiveblog.com

Page 28: Olswang 3rd Annual Construction Law Conference

| Construction Law Conference 2016: Case Law Update28

What happened in Cavendish?

• Mr Makdessi agreed to sell to Cavendish a controlling stake in the holding company of a marketing communications group in the Middle East

• The agreement stated that if he was in breach of certain restrictive covenants against competing activities, Mr Makdessi would not be entitled to receive the final two instalments of the price paid by Cavendish

• He would also be required to sell his shares to Cavendish at a price excluding the value of the goodwill of the business

• Here, monetary compensation was not the only legitimate interest which Cavendish might have in the performance of the obligations under the agreement

• It was therefore more important that the courts looked at the commercial context of the deal rather than whether the sum payable was a genuine pre-estimate of the innocent party’s loss

constructiveblog.com

Page 29: Olswang 3rd Annual Construction Law Conference

| Construction Law Conference 2016: Case Law Update29

The new test

• The Court decided not to modify the current law surrounding penalties, but rather to better codify the test

• A clause will be a penalty where it imposes a detriment on the guilty party “out of all proportion to any legitimate interest of the innocent party” in the enforcement of the specific obligation

• How this will apply in practice:

• The courts will still consider whether the sum payable is exorbitant or unconscionable, but this will be considered in the context of a party’s legitimate interest in the proper performance of the contract (i.e. they will take a ‘commercial view’)

• Whether this will impact on standard delay liquidated damages in construction contracts remains to be seen – but it may make challenging a liquidated damages provision on the grounds that it’s a penalty even harder

constructiveblog.com

Page 30: Olswang 3rd Annual Construction Law Conference

|

Bloomberg LP v Sandberg and Others [2015]

constructiveblog.comConstruction Law Conference 2016: Case Law Update30

• Bloomberg entered into an agreement for lease at 15 Finsbury Square

• They received collateral warranties from various contractors in relation to works carried out at the Property including from Sandberg, Buro Happold and from Malling Pre-cast Limited

• In 2001, two cladding tiles fell from the building. Investigative works were carried out, a condition survey was produced and Malling carried out remedial works to the cladding. On 8 July 2013 a soffit cladding tile fell to the pavement from the seventh floor of the Property

• Sandberg and Buro Happold had carried out certain investigative works and provided the condition survey during 2001 and 2002

Page 31: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update31

• The warranty in favour of Bloomberg from Malling contained the following limitation clause (clause 6):

“Notwithstanding the date hereof no proceedings shall be commenced against the Contractor after the expiry of twelve years from the date of issue of the last written statement by the Client that practical completion of the Project has been achieved under the Contract.”

• The ‘last written statement by the Client that practical completion of the project had been achieved’ was given on 29 August 2000

• Bloomberg out of time under the Malling warranty to bring a claim directly against Malling. They instead issued claim forms against Sandberg and Buro Happold

• Sandberg brought a claim against Malling for a contribution from Malling pursuant to the Civil Liability (Contribution) Act 1978 (the “Act”)

Page 32: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update32

• Clause 1 of the Act provides:

“(1) Subject to the following provisions of this section, any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise).

. . .

(3) A person shall be liable to make contribution by virtue of subsection (1) above notwithstanding that he has ceased to be liable in respect of the damage in question since the time when the damage occurred, unless he ceased to be liable by virtue of the expiry of a period of limitation or prescription which extinguished the right on which the claim against him in respect of the damage was based.”

• Malling resisted relying on the clause 6 wording, arguing that the words “no proceedings shall be commenced against the Contractor” was meant to be construed to mean that “no proceedings” included proceedings by any other party

Page 33: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update33

• Mr Justice Fraser noted that the words used in the clause were clear. There was no ambiguity. “No proceedings” in the context of a warranty between Bloomberg and Malling, could only mean proceedings by Bloomberg

• He noted that the overall effect of Malling’s arguments would be that parties could effectively “contract out” of the operation of the Act, an act that had been put in place by Parliament to benefit other third parties

Relevance

• Not a surprising result, but clarifies the impact of limitation clauses within appointments and collateral warranties

• Enforced principles to be adopted in the process of contractual construction stated in Arnold v Britton [2015] UKSC 36 – although commercial common sense and surrounding circumstances may be relied upon as aids to construction, they should not undervalue the importance of the language of the provision itself

• The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader

Page 34: Olswang 3rd Annual Construction Law Conference

|

MW High Tech Projects UK Ltd v Haase Environmental Consulting GmbH [2015]

constructiveblog.comConstruction Law Conference 2016: Case Law Update34

• In June 2010 MW High Tech, the contractor, was awarded an engineer, procure and construct contract to build a waste to energy plant

• HEC was engaged by the Contractor as a process engineering design consultant

• Clause 5.9.1 of the appointment required HEC to use “all the reasonable skill, care and diligence to be expected of properly qualified and competent design professional experienced in the design of works similar in size, scope, nature and complexity to the Process Technology.”

• The appointment also required HEC to design the works in accordance with the EPC output specification and the delivery plan (the “Requirements”)

Page 35: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update35

• After the contractor and HEC had entered into the formal appointment, HEC had developed the design to include features not present in the basic design. The contractor alleged that the new features were not required by the Requirements, but had caused the contractor to incur increased costs

• As the additional features would not be treated as variations under the contract, the contractor could not recover those additional costs from the employer. The contractor accordingly claimed the additional costs from HEC

• An adjudication found in HEC’s favour and so the contractor brought the issue to the TCC

• The Court held that on a proper construction of the appointment, the requirement to comply with the Requirements was “subject to the Consultant's overriding obligation to exercise reasonable skill and care as more particularly provided in clause 5.9.1.”

• Further the Court concluded that “[i]n the hierarchy of the principal obligations, the obligation to exercise reasonable skill and care is paramount.”

Page 36: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update36

• The Judge, however, found that as a matter of proper contractual construction, the obligation to comply with the EPC Requirements could be read as an independent obligation alongside the over-riding obligation to take reasonable skill and care

• The only qualification to the strict requirement to comply with the EPC Requirements would be if it would be negligent for HEC to design in accordance with a certain part of the latter they would not be obliged to comply with that part of the EPC Requirements

• This follows an earlier ruling in Costain v Haswell & Partners Ltd [2009] which related to an appointment which had a skill and care obligation and an obligation for the works designed under the appointment to meet the requirements set out in the specification

Relevance?

• A “reasonable skill and care” qualification may serve to increase the consultant’s liability rather than reducing it since compliance with a strict obligation could put the consultant in breach of its skill and care obligation

Page 37: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update37

• By the same token, a non-negligent breach of the specifications could still constitute a breach

• In order to be sure that an appointment does not impose “fitness for purpose” and other strict obligations which may not be backed by PI insurance, it is crucial to ensure that any “strict” obligations in the appointment are expressly qualified by wording such as “The Consultant shall exercise the standard of skill and care required by clause [ ] to see that...”

Page 38: Olswang 3rd Annual Construction Law Conference

|

Caterpillar Motoren GmbH & Co KG v Mutual Benefits Assurance Company [2015]

constructiveblog.comConstruction Law Conference 2016: Case Law Update38

• An on-demand bond is a primary obligation that takes the form of an undertaking from the bondsman to pay a sum of money to the employer without reference to the liability of the contractor

• As such, it tends to include phrases such as “on-demand”, payment “without proof or conditions”, and payment upon “first written demand”, all of which are indicative of on-demand bonds

• Payment guarantees, on the other hand, are secondary obligations in which the bondsman’s liability to pay the employer is contingent upon a breach by the contractor of the underlying construction contract (in other words they act as a form of insurance)

• If the employer cannot establish a breach by the contractor then the bondsman has no liability to pay. Payment guarantees may mention the words “guarantee” and “lawful claims” or include other wording that is suggestive of a secondary obligation

Page 39: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update39

Wuhan Gouyu Logistics Group C Ltd and another v Emporiki Bank of Greece SA [2013]

Presumption that a bond is an on-demand bond where:

i. It relates to an underlying transaction between parties in different jurisdictions;

ii. It is issued by a bank;

iii. It contains an undertaking to pay “on demand”; and

iv. It does not contain clauses excluding or limiting the defences that are available to a guarantor

Page 40: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update40

The Facts of the case

• Caterpillar entered into two sub-contracts for the provision of construction services in relation to two power plants. Each sub-contract (which was in materially identical terms) required the sub-contractor to procure an advance payment bond (“APB”) and a performance bond (“PB”) in favour of Caterpillar.

• The APBs were described as instruments that guaranteed the due performance by the sub-contractor for an advance payment made by Caterpillar to the sub-contractor

• The PBs were described as instruments that guaranteed the due performance of all work by the sub-contractor.

• Disputes subsequently arose between Caterpillar and the sub-contractor and Caterpillar demanded the return of advance payments and also a sum in respect of liquidated damages

Page 41: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update41

The Decision

• The Court considered the terms of each bond

APBs• “guarantees and undertakes to pay” “forthwith on demand” and “without reference

to” the contractor

• The word “guarantees” could be suggested to mean that the parties intended that bondsman would only pay where the sub-contractor had failed to perform its obligations, whereas the words “forthwith on demand” and “without reference to” the contractor suggested bondsman’s liability was to pay the sum which was demanded by Caterpillar

• Met the Wuhan requirements for an on-demand bond

Page 42: Olswang 3rd Annual Construction Law Conference

| constructiveblog.comConstruction Law Conference 2016: Case Law Update42

PBs• Ability to pay “lawful” claims which tended to suggest a payment guarantee over an

on-demand bond

• There was also an obligation upon bondsman to pay Caterpillar once Caterpillar had declared that sub-contractor was in default, but bondsman was to pay “unconditionally” “the amount of damages claimed by” Caterpillar, which was inconsistent with the concept of lawful claims and payment guarantees

• The deciding factor, however, was that any demand was expressed as being “conclusive” as regards the amount that was due from bondsman, which left no doubt that the PBs were on-demand bonds as opposed to payment guarantees

Lessons

• Look beyond the name of the instrument

• Look at the language

• Apply the Wuhan test

• Draft clearly to avoid uncertainty

Page 43: Olswang 3rd Annual Construction Law Conference

Ashley Hurst, [email protected] | +44 20 7067 3486

Construction Law Conference 2016 4 February 2016

The Role of Lawyers in a Reputational Crisis

Page 44: Olswang 3rd Annual Construction Law Conference

|

Hypothetical scenario

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis44

• Buildem High plc is a substantial player in the construction industry which has publicly denounced blacklisting.

• An anonymous internet user "BuildemLow" has posted on an internet discussion forum that a "whistleblower" has revealed "explosive documents" which apparently show that "Buildem High engaged in blacklisting practices 4 years ago".

• The posting has been tweeted and is causing a stir on Twitter.

• The Mail on Sunday has called the press office asking for comment.

• A temporary employee called Jane, who left under a cloud several weeks ago, is suspected of being responsible for the allegations. A review of her emails has revealed that she sent an email from her work email account to her Hotmail account with a copy of confidential internal report on blacklisting.

• The report concludes that "Whilst conversations about blacklisting clearly took place at Buildem in September 2012, we are confident they were not acted upon."

Page 45: Olswang 3rd Annual Construction Law Conference

|

Issues

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis45

• How should Buildem deal with the Mail on Sunday?

• How should Buildem deal with "BuildemLow" and Twitter?

• What is the role of the legal team (internal and external) in the unfolding crisis?

• What can be done once the heat has died down to better prepare for the future?

Page 46: Olswang 3rd Annual Construction Law Conference

|

How should Buildem deal with the Mail on Sunday?

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis46

• The first call with a hostile journalist• Do not respond "no comment"

• Take contact details

• Ascertain deadline

• The twin track approach (law/PR)

• Ask for further information and ascertain the underlying allegations (preferably in writing)

• "Reynolds push back"

• Delay tactics

• On the record / off the record comments

Page 47: Olswang 3rd Annual Construction Law Conference

|

How should Buildem deal with "BuildemLow"?

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis47

• Take screen shots and analyse content

• Assess the extent of the damage (who has noticed and republished?)

• Cross-check against internal information/data

• Consider Norwich Pharmacal disclosure orders to identify BuildemLow

• Consider injunction against "persons unknown"

• Consider the impact of engaging (the "Streisand effect")

Page 48: Olswang 3rd Annual Construction Law Conference

|

How should Buildem High deal with Twitter?

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis48

• Assess extent of the damage

• Consider carefully whether to engage at all

• Timing is critical – the conversation will move on quickly

• Surgical removal if necessary

• Obtaining information from Twitter

Page 49: Olswang 3rd Annual Construction Law Conference

|

What is the role of the legal team in a crisis?

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis49

• Assessors of risk (insurance, litigation, regulatory scrutiny)

• Martials of the facts

• Work closely with communications and operations to ensure consistency with the facts

• Project managers(calls, meetings, updates)

• Set communications protocols to protect confidentiality and privilege (e.g. assign project name, encrypt documents, email restrictions)

• Instruct outside advisors (for privilege reasons)

• Auditors of steps taken

Page 50: Olswang 3rd Annual Construction Law Conference

|

What can be done to improve preparedness?

constructiveblog.comConstruction Law Conference 2016: The role of lawyers in a Reputational Crisis50

• Form a crisis team

• Brainstorm the types of crisis that might hit your company

• Draft a simple crisis plan which is accessible and can be easily updated

• Use checklists for specific subject matters (e.g. data breach) rather than prescriptive "to do lists" and flow charts

• Practice using "war games" in different scenarios

• Know who to call internally and externally

• Ascertain your online footprint and key influencers

Page 51: Olswang 3rd Annual Construction Law Conference

|

Q&Aconstructiveblog.comConstruction Law Conference 201651

Page 52: Olswang 3rd Annual Construction Law Conference

|

For more information please contact

Olswang:Changing Business.www.olswang.com

Francis Ho+44 20 7067 [email protected]

Brussels+32 2 647 4772

London+44 20 7067 3000

Madrid+34 91 187 1920

Munich+49 89 206 028 400

Singapore+65 6720 8278

Paris+33 17 091 8720

Thames Valley+44 20 7071 7300