Oil pipeline 42 inch by 455 km

90
Baku - Tbilisi - Ceyhan (BTC) Oil Pipeline The Azerbaijan Section of the Project’s Oil Pipeline including valve and pig trap stations, laying of Fiber Optic cable and tie-ins at pumping stations. Much of the terrain is flat and semi-arid. The Pipeline links the Caspian sea oil wells with the Mediterranean Sea ship tankers port. The capacity is1 million barrels of crude oil flow per day Oil Pipeline 42” by 450km. Photographic Record of Construction 19 th June David H Moloney

Transcript of Oil pipeline 42 inch by 455 km

Page 1: Oil pipeline 42 inch by  455 km

Baku - Tbilisi - Ceyhan (BTC) Oil Pipeline

The Azerbaijan Section of the Project’s Oil Pipeline including valve and pig trap stations, laying of Fiber Optic cable and tie-ins at pumping stations. Much of the terrain is flat and semi-arid.

The Pipeline links the Caspian sea oil wells with the Mediterranean Sea ship tankers port.

The capacity is1 million barrels of crude oil flow per day

Oil Pipeline 42” by 450km.

Photographic Record of Construction

19th June David H Moloney

Page 2: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Contents

Overview Surveying & Setting OutClearing & GradingDouble Jointing i.e. welding 2 pipes togetherStringing out PipesBend Pipes for changes in direction sideways and up & downWelding Pipes into a string, Test Weld by X Ray.Anti-corrosion Coat to JointsTrenching i.e. excavate trenchLowering pipe string into trenchBackfilling TrenchReinstatement of Pipeline ROW (Right-of-Way)Reinstatement of River BanksCrossing - Horizontal Directional DrillingCrossing - Thrust BoringCrossing - River Hydrotest & PiggingTie-in i.e. connect to existing pipelineMiscellaneous

Pause Slides to Read

Page 3: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Overview Construction Sequence

A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and reinstating the land to its original condition..

Crossing Railway, Roads, Rivers, etc.Pump Station

Page 4: Oil pipeline 42 inch by  455 km

Overview Pipeline Construction Animation

To see animations, view YouTube film.

Page 5: Oil pipeline 42 inch by  455 km

Overview Pipeline Crossings Construction Animation

Page 6: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out

Page 7: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out

Page 8: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Surveying & Setting Out

FCI-ROW Set Out

Page 9: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading ROW (Right of Way)

Page 10: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading

Foreign Service Detection

Concrete Slabs Installed For

Foreign Services Protection

Page 11: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading

Page 12: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Clearing & Grading

Page 13: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing Facility

Welding 2 nr 12m long pipes together prior to stringing out.Located at Pipe Storage areas.

Page 14: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing Facility

Outline Process

1. Single piles 12m long are delivered and stacked.2. At the Bevelling Station. The ends of the pipes are

bevelled. Two pipes are aligned using an internal clamp, the joint is preheated and the root pass weld is done.

3. At the Hot Pass Station. The fill and cap passes will be carried out using Submerged Arc Welding (SAW)

4. The joints will be x-rayed 5. The double pipes 24m long are stored ready for

transportation to the site6. Purpose made dollies will transport the pipes

Page 15: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Double Jointing i.e. welding two pipes together

66

Phase 7: Rolling Pipe

Page 16: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes

Page 17: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes

Page 18: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Stringing out Pipes

Final Product

Page 19: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes

Page 20: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes

Toolbox Talk

Pipe Will Be Lifted Using Choker

Belts

Choker Belts Placed On

Pipe

Preparation For Lifting

Pipe

Loading Pipe On Bending

Machine

The Bending Machine Uses A

Series Of Clamps And Hydraulic

Pressure To Make A Very

Smooth, Controlled Bend

Bending Start

Page 21: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Bending Pipes

Bending

Clamps Pulled Through The Pipe

Maximum Bend angle Is 1.3

Degrees Per Meter

Completed Bends

Page 22: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding

Page 23: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding

Beveling

Fit-Up

Page 24: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

Welding

Page 25: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC,

X Ray Pipeline Crawler for testing joint welds

Page 26: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating for Anti-corrosion

Page 27: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating

1. Toolbox Talk

Preparation For Grit Blasting

Wearing Special Coverall

Page 28: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Joint Field Coating

Page 29: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Trenching i.e. excavate trench.

Page 30: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Trenching

Page 31: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench

Page 32: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench

Lifting Belts Supported by Side-Booms Will Be

Utilized For Pipe Handling And Not Placed Over Any

Field Joint Area

Page 33: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Lowering Pipe string into Trench

Page 34: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling

Page 35: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling

Page 36: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Backfilling

Page 37: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW Right-of-Way

Page 38: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW

Spreading Topsoil

Page 39: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW

Page 40: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement ROW

Final Product

Page 41: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank

Page 42: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank

Matting

Page 43: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Reinstatement River Bank

Grass Is Growing On River Banks

Final Product

Page 44: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling

Page 45: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling

Rig Anchoring System; During The

Drilling Works, The Rig Will HaveTo

Be Secured To Stop It From Moving

Page 46: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling

Page 47: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Horizontal Directional Drilling

Page 48: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring

Page 49: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring

Page 50: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing by Thrust Boring

Page 51: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing

Page 52: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing

Sediment Control

Page 53: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Pipeline Crossing - River Crossing

Lowering In

Page 54: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest, Pigging (clean out pipeline) & Dry Pipeline

Page 55: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

Block Valve Pre-Testing

Trains Of Brush Pigs With Slugs Of Flushing

Water Are Used For Cleaning The Pipeline Pigs Are Loaded Into Temporary Pig Launchers

Page 56: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

Pigs Are Received Into Temporary Pig

ReceiverPigs Are Launched With Compressed Air

The Final Pig Is Fitted With An Aluminium

Gauging Plate 95 % Of The Internal Diameter To

Check For Geometrical Defects

Pigs Are Back Loaded Into Test Headers

For Filling And Dewatering Test

Sections

Test Headers Are Then Welded To The

Ends Of Test Section

Water Used For Hydrostatic Testing Is

Filtered To 50 Microns

Water Is Then Passed Through Vented

Break Tanks And Flow Meters

Page 57: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Hydrotest

Pressurising Pumps And Instrument Control

Container

Filling Spread Showing Fill Pumps,

Chemical Dump And Break Tanks

Pressurising injection Manifold Incorporating

High Pressure Flow Meter

After Hydrotest The Test Section Is

Dewatered And Water Transferred Into The

Next Section

The Dewatered Section Is Then Dried

To -10degC Dewpoing Using

Compressed Air Passed Through

Drying Units

Page 58: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in i.e. connecting to existing pipeline

Welded Joint on the Azerbaijan and Georgia Border

Page 59: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in

Page 60: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Tie-in

Preparation For Tie-In

Tie-In: Manually Welding Joints In

Trench Between Two Sections

Final Product

Tie-In

Page 61: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

MiscellaneousContents

Time Chainage DiagramPipe Spool FabricationTank ConstructionPiperackCrane Heavy LiftSlug CatcherRoad constructionReinforced Concrete WallCrossing under Existing UtilitiesTrench ExcavationLoad & HaulRock excavationQuarry & aggregate ProductionConcrete Batching PlantTemporary Sheet Pile shaftCable LayingFencingBuildings

Page 62: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Time Chainage Diagram The chart has two axis: one for time and the other for location

A legend explains meaning of the colours, symbols and line types

Sample Only

Page 63: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

Histograms for Resources & Outputs

Page 64: Oil pipeline 42 inch by  455 km

Progress Monitoring & Reporting - Dashboard

ⓒ David H Moloney

Brief Description

Dashboard is a single page, graphical representation of current progress and historical trends

Page 65: Oil pipeline 42 inch by  455 km

Temporary Contractors Site Facilities

ⓒ David H Moloney

Brief Description

Site Offices, Camp Accommodation for 1,250 workers, Canteen, Recreation, Fabrication shops, Stores, Plant Yard. In five locations along the route.

Page 66: Oil pipeline 42 inch by  455 km

Temporary Contractors Site Facilities - Stores

Brief Description

Page 67: Oil pipeline 42 inch by  455 km

Pipes ⓒ David H Moloney

Brief Description

Pipes were manufactured in Japan, coated

with a plastic covering in Malaysia, and

shipped to the Georgian ports of Poti.

Transported by Train and trucks across land.

Japan

Georgia

Page 68: Oil pipeline 42 inch by  455 km

Pipe Spool Fabrication Animation

Page 69: Oil pipeline 42 inch by  455 km

Post Weld Heat Treatment

Non Destructive Testing

Cut

Bevel

Fit-up

Weld

NDT

PWHT

Blasting

Painting

Pipe Spool Fabrication StepsP

ipe

wo

rk

Page 70: Oil pipeline 42 inch by  455 km

Tank Construction

Page 71: Oil pipeline 42 inch by  455 km

Piperack Construction Animation

The Pipe Racks carry pipes and cables between the different processes..

Page 72: Oil pipeline 42 inch by  455 km

Cranes Heavy Lift Animation

Lift column from the horizontal and

rotate into the vertical

Page 73: Oil pipeline 42 inch by  455 km

Slug Catcher Construction Sequence Animation

Separates the Gas from the Oil & WaterAlso to dissipate any pressure surges

Page 74: Oil pipeline 42 inch by  455 km

Road Construction Sequence Animation

Page 75: Oil pipeline 42 inch by  455 km

Reinforced Concrete Wall Construction Sequence Animation

Page 76: Oil pipeline 42 inch by  455 km

Crossing Under Buried Utilities & Overhead Power Cables Animation

Page 77: Oil pipeline 42 inch by  455 km

Trench Excavation with Stepped Faces

Page 78: Oil pipeline 42 inch by  455 km

Trench Excavation with Battered Faces

Page 79: Oil pipeline 42 inch by  455 km

Excavate & Load, Cart, Tip & Return

Brief Description

Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes

Ea

rth

wo

rks

7 minutes

14 minutes

3 minutes

14 minutes 7 km

7 km

Page 80: Oil pipeline 42 inch by  455 km

Rock - Excavability

Brief Description

The excavability of rock depends

mainly on the rock strength and the

layer thickness. This diagram shows

excavation methods for rock of

various strengths and thicknesses,

with a free face.

ⓒ David H Moloney

Ea

rth

wo

rks

Page 81: Oil pipeline 42 inch by  455 km

Quarry & Aggregate Production

ⓒ David H Moloney

Co

ncre

te

Page 82: Oil pipeline 42 inch by  455 km

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Brief Description

.

The mixing is computer controlled

and has a dynamic screen display,

showing the process. The material

storage capacity is, to match two

days concrete production.

Co

ncre

te

Page 83: Oil pipeline 42 inch by  455 km

Concrete Batching Plant

ⓒ David H Moloney

Co

ncre

te

Page 84: Oil pipeline 42 inch by  455 km

Temporary Sheet-pile Shaft

Page 85: Oil pipeline 42 inch by  455 km

Cable laying 132KVa Electric

Page 86: Oil pipeline 42 inch by  455 km

Fencing

ⓒ David H Moloney

Co

ncre

te

Page 87: Oil pipeline 42 inch by  455 km

ⓒ David H Moloney

Co

ncre

te

Central Control Building for Refinery

Cross Sections Horizontal moving upwards

Page 88: Oil pipeline 42 inch by  455 km

Main Electrical Sub Station

ⓒ David H Moloney

Co

ncre

te

Cross Sections Horizontal moving upwards

Page 89: Oil pipeline 42 inch by  455 km

Main Electrical Sub Station

ⓒ David H Moloney

Co

ncre

te

Cross Sections Vertical moving along

Page 90: Oil pipeline 42 inch by  455 km

Construction of Azerbaijan Oil Pipeline 42” by 450km. Client BTC

ENDMy YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ