OIL INDIA LIMITED (A Government of India Enterprise)
P.O. Duliajan – 786602, Assam, India Website: www.oil-india.com
Corrigendum No. 2 to IFB No. CPI9724P19
Engineering, Fabrication and Supply of Modular Electrical Packages respectively for OCS at Nadua and GGS at East Khagorijan in Dibrugarh
district, Assam
1. This Corrigendum is issued to notify the following: a) In view of queries received from bidders in matter corresponding to
technical SOW, the final OIL’s responses to the queries are generated. All the bidders are requested to refer to Annexure- I attached herewith.
b) Revised Electrical single line diagram for OCS at Nadua and GGS at E. Khagorijan are attached herewith as Attachment – 1&2 respectively.
c) Hazardous area classification drawing for OCS at Nadua and GGS at E. Khagorijan are attached herewith as Attachment – 3&4 respectively.
d) Specification for Lighting Transformer for OCS at Nadua and GGS at E.
Khagorijan are attached herewith as Attachment – 5&6 respectively.
e) Specification for Lighting Fixure and Distribution Board for OCS at Nadua
& GGS at E. Khagorijan are attached as Attachment – 7&8 respectively. f) Revised Price Bid format/SOR is attached herewith as Attachment – 9.
g) Revised Electrical Substation Layout is uploaded separately under
“Technical attachment” tab in e-Tender portal. 2. Extension of the Bid Closing/Technical Bid Opening date as under:-
i) Bid Closing Date & Time : 04.01.2019, 11:00 hrs. IST.
ii) Technical Bid Opening Date & Time : 04.01.2019, 14:00 hrs. IST.
3. All other terms and conditions of the tender remain unaltered.
4. All the prospective bidders are requested to regularly visit OIL’s
website: www.oil-india.com and e-procurement portal https://etender.srm.oilindia.in/irj/portal for further announcements/latest information related to this tender.
5. Bidder to submit this Corrigendum No. 02 along with Annexure – I and
Attachments 1-9 duly signed & stamped in all pages as token of acceptance and shall upload this document in the un-priced folder of the e- bid.
Annexure – I
SUMMARY OF CONSULTANT/OIL’s RESPONSE TO PRE-BID QUERIES
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
1 CPI9724P19 General
Bidder has not received Technical Specifications for LV Switchboard
for NAUDA Site. Please provide the same
Bidder shall refer specification document no KIP-17039-E-SP-
9001, page 49 of 193 in technical part IV
2 CPI9724P19 General
For Equipments where there is no
detailed Specifications , Bidder shall Supply Equipments in line
with the details available in
17039-ND-E -DB-9001 & 17039-ND-E -DB-9001 - DESIGN BASIS
Noted
3
Bidder Presumes DATA SHEET
FOR CLARIFIED WATER DISPOSAL PUMP MOTOR is not
relevant for this Package.
Please confirm
Confirmed
4
Bidder understands that various
PIPING & INSTRUMENTATION
DIAGRAM enclosed along with Electrical Package Documents are
only for Information purpose and
the same wont form the basis for any Scope of Supply and/or
Service for MPC-9. Please Confirm
P&ID is provided for reference to
identify the electrical equipments and the control scheme/
associated signals which bidder
may use it along with SLD for the MCC, interface signal design.
5 VOLUME-
II_TECHNICAL
The Scope of supply is not limited to the below mentioned items, MPC
Contractor shall supply all required
items for the satisfactory operation of the plant.
Bidder wishes to clarify that that their Scope is limited to "MPC-9
MODULAR PACKAGE
CONSTRUCTION Supply and Installation of Electrical Systems”.
Bidder understanding is correct.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Clause 2, page 8 of 37 Which further is detailed out in
2.1 TABLE-1: Electrical Scope of
supply for Nadua site, TABLE-2: Electrical Scope of supply for East
Khagorijan site & ELECTRICAL
SOR for each site. However any Component, Sub-component,
Associated hardware, Accessories
etc., forming part of the Main equipment and are required for
satisfactory operation , will be part
of the Scope, regardless of whether such items are specifically
mentioned in the tender or not.
6 VOLUME-
II_TECHNICAL
30 kVA AC UPS (HOLD-1)
Clause 2.1 -05, page 10 & 17 of 37
Bidder understands that rating (30 kVA) is on HOLD. However the
rating will remain valid during the bidding process and suitable
commercial & time extension
provisions will be made available in the contract to accommodate
any change in the rating at the
time of detailed engineering.
Noted
7 VOLUME-
II_TECHNICAL
5 kVA Telecom UPS (HOLD-1),
Clause 2.1 -07, page 10 & 17 of 37
Bidder understands that rating (5
kVA) is on HOLD. However the
rating will remain valid during the bidding process and suitable
commercial & time extension
provisions will be made available in the contract to accommodate
any change in the rating at the
time of detailed engineering
Noted
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
8 VOLUME-
II_TECHNICAL
Variable quantity
Clause 2.1 -15,17,18,19,20,21, page 8 to 22 of 37
We presume that quantities are to
be quoted as per ELECTRICAL
SOR during the Bidding process. Please confirm.
Quantities indicated in SOR are
tentative. Bidder to estimate the
quantity required and quotes accordingly.
9 VOLUME-
II_TECHNICAL
Prefabricated substation - Set -1
Clause 16, page 12 of 37
Bidder Assumes that 1 Set
consists one number of
i) Switchgear Containerized room,
ii) Emergency Switchgear Containerized room
iii) UPS Containerized room
iv) Battery Containerized room. v) CCR Containerized room.
Please confirm.
Control room will be supplied by
other.
10 VOLUME-
II_TECHNICAL
Prefabricated substation - Set -10
Clause 16, page 19 of 37
Please clarify if each set contains
One number of
i) Switchgear Containerized room,
ii) Emergency Switchgear Containerized room
iii) UPS Containerized room
iv) Battery Containerized room. v) CCR Containerized room.
Also ELECTRICAL SOR FOR EAST
KHAGORIJAN mentions the quantity as "EA -1"
Each set contains One number of
i) Switchgear Containerized room, ii) Emergency Switchgear
Containerized room
iii) UPS Containerized room iv) Battery Containerized room.
11 VOLUME-II_TECHNICAL
Common Lifting kit including Slings,
Spreader Bar, Shackles and Certifications.
Clause 24, page 19 of 37
Please clarify this requirement
This lifting Kit is required for
lifting prefabricated substation. Bidder shall design and supply
lifting kits based on the weight of
the prefabricated substation and
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
shall be part of the pre fabricated
substation line item.
12 VOLUME-II_TECHNICAL
The design of the modular package
shall not exceed the package size specified in the overall plot plan.
Clause 4 g), page 25 of 37
Please clarify if the dimensions mentioned in the DWG No. 17039-
ND-E-DW-9012 ELECTRICAL
SUBSTATION LAYOUT & DWG No. 17039-EK-E-DW-8012
ELECTRICAL SUBSTATION
LAYOUT are limiting Dimensions. Bidder understands that suitable
commercial & time extension
provisions will be made available in the contract in case number of
standard containers increase due
to detailed engineering requirement
Layout specified in the drawing is
only a guideline and bidder shall
recheck based on the dimension of the equipments which will be
supplied and decide the no of
containers.
13 VOLUME-
II_TECHNICAL
The fabrication of panels/ containers shall be carried out at MPC
Contractor’s fabrication yard.
Clause 11 a), page 30 of 37
The fabrication of panels/ containers shall be carried out at
MPC Contractor’s fabrication yard
or Sub-Vendors Fabrication yard
Tender condition prevails.
14 VOLUME-II_TECHNICAL
MPC Contractor shall install and
complete Factory Acceptance Test for
all electrical equipment modeled inside the containerized electrical
substation.
Clause 18, page 32 of 37
Bidder understands that Electrical
Panels like LV Switchgear Panels,
Emergency Switchgear panels, APFC, MLDB, IRP & Various DBs
etc. are manufactured, inspected
and despatched to site from respective panel manufacturers
premises. These panels will be
installed inside the containerized Substation at the site location
after installation and proper
grouting of Containerised
Company expect bidder to supply
pre installed, interface cables
wired up and tested at factory, before shipping the substation to
site. Only limited reassembly and
re installation of panels which are removed for meeting the transport
limitation. If the bidder plans to
assemble all the panels inside the ready built substation and do the
interconnection cabling at site, it
is the bidder responsibility for all
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Electrical room. Please confirm works like unloading, storing, safe
guarding , shifting to site and
installation and meet the project schedule
15 ELECTRICAL DESIGN
BASIS
SCOPE OF WORK 2 numbers of 415V Gas Engine Driven Genset (GEG) and
Generator Control Panels with
required protection and synchronization facility shall be
supplied for this Captive Power
Plant ND-Clause 7.1 to 7.4, page 13 of 46
EK-Clause 7.1 to 7.4, page 14 of 47
On the Basis of TABLE-1:
Electrical Scope of supply for Nadua site, TABLE-2: Electrical
Scope of supply for East
Khagorijan site, ELECTRICAL SOR FOR NAUDA/ EAST KHAGORIJAN
, Bidder understands that GEG
as associated equipments mentioned in the referred clauses
are not in the Scope of this
Package. Please confirm
Confirmed
16 ELECTRICAL DESIGN
BASIS
SCOPE OF WORK
A source of emergency D.G. power
shall also be considered ND-Clause 7.10, page 15 of 46
EK-Clause 7.10, page 16 of 47
On the Basis of TABLE-1:
Electrical Scope of supply for Nadua site, TABLE-2: Electrical
Scope of supply for East
Khagorijan site, ELECTRICAL SOR FOR NAUDA/ EAST KHAGORIJAN
,Bidder understands that DG
associated equipments are not in the Scope of this Package
confirmed
17 ELECTRICAL DESIGN
BASIS
SCOPE OF WORK Electrical Heat Tracer for Pipelines
along with all accessories like valves,
strainers, instrumentation etc. ND-Clause 7.29, page 18 of 46
EK-Clause 7.29, page 18 of 47
Bidder understands that their
scope is limited to providing HEAT TRACING DISTRIBUTION BOARD
consisting of EHT Transformer of
50kVA, 415V/240V AC, 50Hz, 3 phase, 3 wire, Delta/delta, 4%
impedance, Off Load Tap changer
(OCTC) with ± 5% in steps of 2.5%
Bidder shall also supply heat
tracing controller with display panel which receives RTD input
from the corresponding heat trace
pipe lines and provide output to the heat tracing circuits through
the heat tracing Distribution
board. The heat tracing line list is
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
& along with requisite number of
Outgoing Circuits fed via MCBs
with Earth Leakage Protection Please confirm
provided for the bidder to estimate
the no of circuits required. Scope
includes supply and laying of RTD cables from field to CCR, supply
and installation of power cable
from the DB to the field junction box provided by others. Further
Heat tracing specification shall be
referred.
18 ELECTRICAL DESIGN BASIS
SCOPE OF WORK
LV INDUCTION MOTORS ND-Clause 10.3, page 29 of 46
EK-Clause 10.3 page 29 of 47
On the Basis of TABLE-1:
Electrical Scope of supply for
Nadua site, TABLE-2: Electrical Scope of supply for East
Khagorijan site, ELECTRICAL SOR
FOR NAUDA/ EAST KHAGORIJAN , Bidder understands that LV
Induction motors mentioned in the referred clauses are not in the
Scope of this Package
Please confirm
Confirmed.
19 ELECTRICAL DESIGN
BASIS
SCOPE OF WORK
CATHODIC PROTECTION SYSTEM
ND-Clause 10.16, page 44 of 46 EK-Clause 10.16, page 45 of 47
On the Basis of TABLE-1:
Electrical Scope of supply for
Nadua site, TABLE-2: Electrical Scope of supply for East
Khagorijan site, ELECTRICAL SOR
FOR NAUDA/ EAST KHAGORIJAN , Bidder understands that
CATHODIC PROTECTION
SYSTEM mentioned in the referred clauses are not in the Scope of
this Package. Please confirm
confirmed
20 ELECTRICAL DESIGN SCOPE OF WORK On the Basis of TABLE-1: confirmed
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
BASIS MOTOR OPERATED VALVES
ND-Clause 10.17, page 45 of 46
EK-Clause 10.17, page 46 of 47
Electrical Scope of supply for
Nadua site, TABLE-2: Electrical
Scope of supply for East Khagorijan site, ELECTRICAL SOR
FOR NAUDA/EAST KHAGORIJAN
, Bidder understands that MOTOR OPERATED VALVES mentioned in
the referred clauses are not in the
Scope of this Package. Please confirm
21 ELECTRICAL DESIGN
BASIS
The residual current monitoring
system (RCMS) shall be provided with a minimum 12 inputs from outgoing
feeders.
ND-Clause 7.15, page 15 of 46 EK-Clause 7.15, page 16 of 47
Considering the given Distribution
Scheme. 6 Channel RCM Modules are sufficient. Kindly Accept
Tender condition prevails.
22 ELECTRICAL DESIGN
BASIS
SHORT CIRCUIT LEVELS 240 V Systems: 16 kA (rms) for 1 sec
ND-Clause 9.1, page 21 of 46
EK-Clause 9.1, page 21 of 47
Short Circuit levels for 240 V System is 10 kA for I Sec as per
ELECTRCIAL SINGLE LINE
DIAGRAM. We presume that the SLD will supersede this
requirement in Design Basis
16 KA for 1 sec short cicruit level
shall be considered for 240 V
system
23 ELECTRICAL DESIGN
BASIS
Bidder shall design adequate number & size of portable modularized ISO
container to house electrical
equipment. If required ISO containers readily available can be combined and
modified suitably to have sufficient
space for installing electrical equipments. The suggested
number of container based systems
are,
Containers specified here does not match with DWG No. 17039-ND-
E-DW-9012 ELECTRICAL
SUBSTATION LAYOUT/ DWG No. 17039-EK-E-DW-8012
ELECTRICAL SUBSTATION
LAYOUT. Bidder understands that
1) Containers are to be supplied in
line with DWG No. 17039-ND-E-
Confirmed.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
(a) Containerized substation for
Normal LV Switchgear. (b) Container for Emergency LV
Switchgear.
(c) Container for UPS system and container for batteries.
(d) Container for installing gas engine
generator and its accessories including control panel.
(e) Container for installing emergency
switchboard and EDG control panel. ND-Clause 9.4.1, page 22 of 46
EK-Clause 9.4.1, page 22 of 47
DW-9012 ELECTRICAL
SUBSTATION LAYOUT & DWG No.
17039-EK-E-DW-8012 ELECTRICAL SUBSTATION
LAYOUT
2) Containers for installing gas engine generator and its
accessories including control
panel are in the Scope of GEG Supplier.
Please confirm
24 ELECTRICAL DESIGN
BASIS
VFD units shall be employed for the process pump motors where required
ND-Clause 10.1.5, page 25 of 46 EK-Clause 10.1.5, page 25 of 47
Bidder shall follow the Load List (ETP LOADS &
OWS+CRWS+RWTP LOADS) as the basis for Consideration of
VFDs
Revised load list for water
treatment package will be
provided. Revised SOR will be provided.
25 ELECTRICAL DESIGN
BASIS
Motor Protection: • Motors rated up to 12.5hp shall be
equipped with Direct On Line starters.
• Motors rated above 12.5hp and upto 40hp shall be equipped with Star-
Delta starters.
• Motors rated above 40hp shall be provided with soft starter and
numerical motor protection relays.
• Motors rated for 100hp and above shall be provided with Motor
Protection Relays.
ND-Clause 10.1.9, page 25 of 46
Requirements Specified in this clause does not match with
STARTING METHOD mentioned
the Load List (ETP LOADS & OWS+CRWS+RWTP LOADS).
Bidder understands that Load list
needs to be followed. Please confirm
Revised load list for water
treatment package will be
provided. Revised SOR will be provided.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
EK-Clause 10.1.9, page 25 of 47
26 ELECTRICAL DESIGN BASIS
Protection relays for LV incomer feeders shall be of numeric type
ND-Clause 10.1.10, page 25 of 46 EK-Clause 10.1.10, page 25 of 47
As per Serial Number 2a) of ELECTRICAL SOR, Incomers
needs to be provided with μp based LSING(Overload protection
(L), short-time delayed short-
circuit protection (S), instantaneous short-circuit
protection (I) and ground-fault
protection (N)). protection having communication capability. Hence
Numerical Protection relays are
not considered by the Bidder. Please confirm
Confirmed.
27 Electrical Single Line
Diagram
The degree of protection for ratings up
to 2500 should be IP54 or better and for ratings more than 2500 it should
be IP42 or better
ND- Notes 14, page 03 of 04 EK- Notes 14, page 04 of 04
LV Switchboards shall have
ingress protection of IP42 as mentioned in ELECTRICAL SOR
page No. 3 & 4 of 12 confirmed
28 Electrical Single Line
Diagram
63A,415 VAC,50Hz,3PH,3W, 10 kA/1
Sec CU BUSBAR. MOV DB, page 04 of 04
Bidder feels that the MOV DB
needs to be fed through an Auxiliary Transformer as the Fault
levels needs to be maintained at
10 kA or less. Please re-look Bidder shall consider bus bar and
all MCCBs Fault level shall be
made suitable for 50 kA for 1 sec.
29 Electrical Single Line
Diagram
400A,415 VAC,50Hz,3PH,3W, 10
kA/1 Sec CU BUSBAR
MPDB, page 04 of 04
Bidder feels that the MPDB needs
to be fed through an Auxiliary
Transformer as the Fault levels needs to be maintained at 10 kA
or less. Alternately CU Bus bar
rating shall be made suitable for 50 kA for 1 Sec and MCCB
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Outgoings may be used. Please
suggest
30
Electrical Single Line Diagram,ETP LOADS
List,
OWS+CRWS+RWTP LOADS, ELECTRICAL
SOR
General Bidder Presumes that in case of any discrepancy among the
referred documents, Electrical
SOR Will supersede the other documents. Please confirm
This is a lump sum contract.
Quantity mentioned in SOR is
tentative. Bidders have to estimate required and quote accordingly.
31
ETP LOADS List,
OWS+CRWS+RWTP
LOADS
TAG NO. (HOLD-1) Bidder understands that ratings mentioned in Load List are
presently on HOLD, However it
will remain valid during the bidding process and suitable
commercial & time extension
provisions will be made available in the contract to accommodate
any change in the rating at the time of detailed engineering
HOLD will be removed during
detail engineering.
32
ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
a) Motor Feeders up to 40HP shall be
provided with MCCB having adjustable Thermal Magnetic
protection.
b) Motor Feeders above 40 HP shall be
provided with MCCB having μp based
protection and Numerical Motor Protection Relay having protective
functions as per OISD RP149.
Clause 2.1 a) & b), page 02 of 12
Bidder informs that MCCBs for
Motor Feeders shall be provided with Magnetic release only and the
same will be as per Type-2 Co-
ordination chart of the Switchgear OEM Tender condition prevails.
33
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
a) Motor Feeders up to 40HP shall be
provided with MCCB having
adjustable Thermal Magnetic
Bidder informs that MCCBs for
Motor Feeders shall be provided
with Magnetic release only and the
Tender condition prevails.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
protection.
b) Motor Feeders above 40 HP shall be provided with MCCB having μp based
protection and Numerical Motor
Protection Relay having protective functions as per OISD RP149.
Clause 2.2 a) & b), page 03 of 12
same will be as per Type-2 Co-
ordination chart of the Switchgear
OEM
34
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
INTERPOSING RELAY PANEL-Location: Emergency Switchgear
Room
Clause 3.2, page 04 of 12
Even though Location for one of the Interface Relay Panel is
mentioned as Emergency
Switchgear Room, DWG No. 17039-ND-E-DW-9012
ELECTRICAL SUBSTATION
LAYOUT & DWG No. 17039-EK-E-DW-8012 ELECTRICAL
SUBSTATION LAYOUT does not show this panel as being part of
this room. Kindly re-check and
confirm
IRP panel shall be accommodated
in the emergency switchgear room Layout
35 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
Design, Engineering, Manufacturing,
Assembling, Supply, Installation,
Testing & Commissioning of 30 kVA AC UPS (UPS rating shall be
confirmed during Detailed
Engineering) Clause 4.1, page 04 of 12
Bidder understands that rating
(30 kVA) will remain valid during
the bidding process and suitable commercial & time extension
provisions will be made available
in the contract to accommodate any change in the rating at the
time of detailed engineering
Noted
36 ELECTRICAL SOR FOR
NAUDA
Battery Backup time shall be 6 hours Clause 4.1, page 04 of 12
As per Clause No. 7.17 (Page 16 of 46) of Electrical Design Basis,
back up time required is 1 Hour.
Bidder understands the back-up
Back up time shall be 1 hour
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
requirement is only for 1 hour
37 ELECTRICAL SOR FOR
NAUDA
Battery backup time shall be 2 hours Clause 4.2, page 04 of 12
As per Clause No. 7.18 (Page 16 of 46) of Electrical Design Basis,
back up time required is 1 Hour. Bidder understands the back-up
requirement is only for 1 hour
Back up time shall be 1 hour
38
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
Design, Engineering, Manufacturing, Assembling, Supply, Installation,
Testing & Commissioning of 5 kVA
Telecom UPS (UPS rating shall be confirmed during Detailed
Engineering
Clause 4.3, page 04 of 12
Bidder understands that rating (5 kVA) will remain valid during the
bidding process and suitable
commercial & time extension provisions will be made available
in the contract to accommodate
any change in the rating at the time of detailed engineering
Bidder to supply 5 kVA Telecom UPS.
39 ELECTRICAL SOR FOR NAUDA
Battery Backup time shall be 12
hours. Clause 4.3, page 04 of 12
As per Clause No. 7.19 (Page 16
of 46) of Electrical Design Basis, back up time required is 8 Hours.
Please clarify
Back up time shall be 8 hours
40
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
Design, Engineering, Manufacturing, Assembling, Supply, Installation,
Testing & Commissioning of Floor
mountable type, Security Room Utility Transformer and Utility Distribution
Board
Clause 6.4, page 05 of 12
This Distribution board is neither shown in the Electrical Single Line
Diagram nor in the 2.1.
SUMMARY SCOPE OF SUPPLY TABLE-1: Electrical Scope of
supply for Nadua site/TABLE-2:
Electrical Scope of supply for East Khagorijan site In case this is fed
from the Normal LV Switchboard ,
kindly update the same in the feeder list
Bidder shall consider transformer
feeders in Normal switchboard
41
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
Incomer : 1 No. of 32A, 240VAC, 16kA
for 1 Sec, TP MCCB Outgoing Feeders : 1. 12 Nos. of 6A,
Since the MLDB which provides
the source to these LDBs are rated for 10 kA for 1 Sec, We suggest
MLDB short circuit rating shall be 16 kA.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
240VAC, 16kA for 1 Sec, DP RCBO
with ΔIn of100mA. Clause 6.5, page
05 of 12
the fault rating for LDBs to be
maintained as 10 kA in place of 16
kA. Please confirm
42 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
Incomer : 1 No. of 32A, 240VAC, 16kA
for 1 Sec, TP MCCB
Outgoing Feeders : 1. 12 Nos. of 6A, 240VAC, 16kA for 1 Sec, DP RCBO
with ΔIn of100mA. Clause 6.6, page
05 of 12
Since the ELDB which provides
the source to these LDBs are rated
for 10 kA for 1 Sec, We suggest the fault rating for LDBs to be
maintained as 10 kA in place of 16
kA. Please confirm
ELDB short circuit rating shall be 16 kA.
43 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
Design, Engineering, Manufacturing,
Assembling, Supply, Installation,
Testing & Commissioning of Wall / Floor mountable type 240VAC ETP &
OWS Emergency Lighting Distribution
Board Clause 6.6, page 05 of 12
Quantity for this switchboard is
mentioned as "1 LOT”. Bidder
presumes that the same is to be read as “1 EA”. Please confirm
Confirmed.
44 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
Design, Engineering, Manufacturing,
Assembling, Supply, Installation, Testing & Commissioning of Floor
mountable type, Electric Heat Tracing
System complete with EHT Transformer of 50kVA, 415V/240V
AC, 50Hz, 3 phase, 3 wire,
Delta/delta, 4% impedance, Off Load Tap changer (OCTC) with ±5% in
steps of 2.5%. Clause 7.1, page 06 of
12
Bidder understands that their
scope is limited to providing HEAT TRACING DISTRIBUTION BOARD
consisting of EHT Transformer of
50kVA, 415V/240V AC, 50Hz, 3 phase, 3 wire, Delta/delta, 4%
impedance, Off Load Tap changer
(OCTC) with ±5% in steps of 2.5% & along with requisite number of
Outgoing Circuits fed via MCBs
with Earth Leakage Protection Please confirm
Bidder shall also supply heat
tracing controller with display panel which receives RTD input
from the corresponding heat trace
pipe lines and provide output to the heat tracing circuits through
the heat tracing Distribution
board. The heat tracing line list is provided for the bidder to estimate
the no of circuits required. Scope
includes supply and laying of RTD cables from field to CCR, supply
and installation of power cable
from the DB to the field junction box provided by others. Further
Heat tracing specification shall be
referred.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
45
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
Design, Engineering, Manufacturing,
Assembling, Supply, Installation,
Testing & Commissioning of Non-Segregated Phase Bus Duct enclosing
Copper bus bars
Clause 8, page 06 of 12
Bidder requests to provide DWG
No. 17039-ND-E-DW-9012
ELECTRICAL SUBSTATION LAYOUT & DWG No. 17039-EK-E-
DW-8012 ELECTRICAL
SUBSTATION LAYOUT in AutoCAD format to measure the
length of the busducts connecting
Gas Generator to LV Switchboard
AutoCAD drawing will be provided.
46 ELECTRICAL SOR FOR
NAUDA
Design, Engineering, Manufacturing,
Assembling, Supply, Installation,
Testing & Commissioning of the Complete High mast lighting system
with High mast (30m height) of double
sided arrangement Clause 9.1, page 06 of 12
Quantity of High masts motioned
in ELECTRICAL SOR FOR NAUDA
is different from the quantity mentioned in 2.1. SUMMARY
SCOPE OF SUPPLY TABLE-1:
Electrical Scope of supply for Nadua site. We presume that
"ELECTRICAL SOR FOR NAUDA” will supersede the other. Please
confirm.
High Mast quantity shall be 5 nos.
refer Corr1_CPI9724P19
47
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
Incomer : 1 No. of 32A, 240VAC, 16kA for 1 Sec, TP MCCB
Outgoing Feeders:
1. 12 Nos. of 6A, 240VAC, 16kA for 1 Sec, DP RCBO with ΔIn of100mA
Clause 10.1, page 06 of 12
Since the MLDB which provides the source to these LDBs are rated
for 10 kA for 1 Sec, We suggest
the fault rating for LDBs to be maintained as 10 kA in place of 16
kA. Please confirm.
MLDB short circuit rating shall be
16 kA.
48
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
Incomer: 1 No. of 32A, 240VAC, 16kA for 1 Sec, TP MCCB
Outgoing Feeders:
1. 12 Nos. of 6A, 240VAC, 16kA for 1 Sec, DP RCBO with ΔIn of100mA
Clause 10.2, page 06 of 12
Since the ELDB which provides the source to these LDBs are rated
for 10 kA for 1 Sec, We suggest
the fault rating for LDBs to be maintained as 10 kA in place of 16
kA. Please confirm
ELDB short circuit rating shall be
16 kA.
49 ELECTRICAL SOR FOR Design, Engineering, Manufacturing, Bidder understands from DWG Air conditioners shall be
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
NAUDA / EAST
KHAGORIJAN
Assembling, Supply, Installation,
Testing & Commissioning of SPLIT /
DUCTABLE SPLIT TYPE AIR CONDITIONERS
2 Ton High Wall Split AC - 5 Star
Location: All containerized room Clause 17.1, page 08 of 12
No. 17039-ND-E-DW-9012
ELECTRICAL SUBSTATION
LAYOUT & DWG No. 17039-EK-E-DW-8012 ELECTRICAL
SUBSTATION LAYOUT that
Normal LV Switchgear Room, Emergency Switchgear room &
Battery rooms are not required to
be Air Conditioned. Please confirm
considered for CCR room,
marshalling room, UPS room,
Normal switchgear room, emergency switchgear room.
Battery room shall have exhaust
fan. Bidder shall decide the no of AC units based on the heat load of
the equipments that are supplied.
If AC unit required is more than 10 nos. it shall be included as part
of line item 1 prefabricated
substation.
In SOR a separate line item is
provided for the Air conditioning unit. Bidder shall verify the
quantity based on the heat load of supplied equipments inside the
substation and estimate the
quantities accordingly. Any addition in quantity and
Ventilation fans shall be part of
the line item of prefabricated substation
50
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
Values provided in the SOR may vary
slightly. Vendor shall round of the quantity to nearest 500/1000 mtr
drum.
Notes 2, Page 12 of 12
Please confirm that this is
applicable for Serial No. 18 CABLES. Suitable commercial &
Time extension provisions will be
made available in the contract to accommodate any increase in
quantity beyond the rounded off
quantity. Also please note that
Bidder to note that rounding off of
the quantities to nearest cable values. This is a lump sum
contract. Quantity mentioned in
SOR is tentative. Bidders have to estimate required and quote
accordingly.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
rounding off of the quantities to
nearest 500/1000 mtr will have
huge loading on the price. Hence request you to kindly revise the
round off value to nearest 100
meter
51 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General
SOR items especially for cables,
trays, earthing, other engineered
items which are quantified, whether Bidder should treat them
as "Quantity to Order" or
"Quantity to be Paid" by the Purchaser.
This is a lump sum contract. Quantity mentioned in SOR is
tentative. Bidders have to estimate
required and quote accordingly.
52 General
Bidder understands that the
Quantities wherever mentioned in SOR form the basis of offer. Any
Increase or decrease during execution will be compensated
with time & price.
This is a lump sum contract. Quantity mentioned in SOR is
tentative. Bidders have to estimate required and quote accordingly.
53 General
There is no line item for requirement of structural steel.
Bidder requests OIL to note that structural steel shall be required
for mounting panels, cable trays,
etc. Bidder requests OIL to include nominal quantity of steel in Tons
for the same.
This is a lump sum contract.
Quantity mentioned in SOR is
tentative. Bidders have to estimate required and quote accordingly.
54
Electrical &
Instrumentation Tender
Completion Period :
Eight Months (8) from the Date of
Letter of Award (LOA).
The completion period is
mentioned as 8 Months from LOA.
Looking at the volume of work &
detailing required, bidder
estimates that completion period
shall be 11 Months from
Tender condition prevails. P.O will
be processed as per company
norms
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Purchaser Order. Moreover,
Bidder requests OIL to confirm
Purchaser Order within 15 days
from issuing LOA as PO is must
for any procurement action from
the bidder. Purchaser to confirm
the understanding.
55
Electrical &
Instrumentation Tender
Quantity Variation Qurty#1: Bidder understands that
the price bid is in conjunction
with the SOR provided. There is
fixed quantities mentioned in
SOR. Bidder understands that the
add/delete will not be more than
5% of the quantity given in the
SOR. Purchaser to confirm the
understanding.
Query#2: We also understand that
being SOR based contract, any
addition with respect to tender
SOR will be paid as per unit rate.
In case the bidder is L1, the
detailed price break-up will be
submitted to purchaser for
approval (as given in Payment
terms clause). This break-up will
be base document for any addition
This is a lump sum contract.
Quantity mentioned in SOR is
tentative. Bidders have to estimate
required and quote accordingly.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
during detailed engineering.
Purchaser to confirm the
understanding.
56
Electrical &
Instrumentation Tender
Selection of Bidder Bidder understands that the
evaluation is combined for both
Nadua & Khagorijan i.e both
locations will be awarded to only
one bidder.
Bidder understanding is correct
57
Electrical &
Instrumentation Tender
Price Variation due to Commodity
Variation
If the Delivery Period agreed is
more than contractual period from
the effective date of the Contract,
necessary adjustments in the
Price for the changes in cost of
labour and material components
shall be made as per the Indian
Electrical and Electronics
Manufacturers' Association
(IEEMA) Index/ RBI Wholesale
Price Index. Purchaser to confirm
this provision.
This is a firm price Tender.
58
Electrical &
Instrumentation Tender
Clause – 54, Liquidated Damages :
Time is the essence of this Contract.
In the event, the MPC Contractor fails
to complete the works within the
stipulated completion period
Bidder requests OIL to review the
clause, bidder request following
amendment:
(a) The maximum cap of LD is
requested as 5% instead of 7.5%.
Many of the contemporary PSU Oil
LD: 0.5% of the total order price
as stipulated in order, per week for
such delay or part thereof as
mentioned in SOS/TOR, subject to
maximum of 7.5%. The Company
may without prejudice to any
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
mentioned elsewhere in the bidding
document, the Contractor shall be
liable to pay liquidated damages @
0.5% of the total Contract Value, per
week of delay or part thereof of delay
subject to maximum of 7.5% of the
Total Contract Value. Liquidated
Damages will be reckoned after expiry
of the completion period.
companies are accepting this
clause as max 5%.
(b) Bidder also requests Purchaser
to consider LD on the 'Undelivered
Portion' and not on the total
contract value due to the nature of
contract.
other method of recovery, deduct
the amount of such liquidated
damages from any amount due to
the Contractor.
Note: Normally, a Packaged Item is
considered as Unit and the supply and delivery should be in totality
as Unit and the LD on the delayed
period will be leviable considering the value of the Unit with GST.
However, in a situation, if a part of
the Unit could not be supplied with the packaged item, then the
value for purpose of LD will be the declared value of the part item
which is stated in the
Consignment Note or the value taken for Transit Insurance.
Both the Contractor & the Company agree that the above
percentages of liquidated damage
is genuine pre-estimates of loss /damage, which the Company
would have to suffer on account of
delay/breach on the part of the Contractor and the said amount
will be payable on demand without
there being any proof of the actual loss /or damage caused by such
delay/breach. Decision of the
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Company in the matter of
applicability liquidated damage
shall be final & binding on the Contractor.
59
Electrical &
Instrumentation Tender
Payment Terms :
(a) 10 % of Package Material Price
(SOR/P Item No. 1) against approval
of documents and drawings identified
in Contract at least in Code-2 and
against submission of Advance Bank
Guarantee (ABG) of equivalent
amount.
(b) 60% of Package Material Price
(SOR/P Item No. 1) against
submission of despatch documents
(along with copy of LR/GR and IRN)
together with full taxes, duties and
transportation charges.
(c) 15% of Package Material Price
(SOR/P Item No. 1) on successful
Erection/Installation and completion
of Commissioning.
(d) 15% of Package Material Price
(SOR/P Item No. 1) on successful
Qyery#1: Bidder requests
Purchaser to review the milestone
payment provided. Bidder
requests to keep the percentage as
(a) 10% (b) 75% (c) 10% (d) 5%.
Query#2: Bidder understands that
first milestone payment is against
deliverable (document submission)
and hence Advance BG shall not
be applicable. If ABG is must,
Purchaser to release this payment
along with LOI, on submission of
ABG by bidder. Purchaser to
confirm the understanding.
Query#3: Bidder understands that
payment under (b) & (c) are on
pro-rata basis. Purchaser to
confirm the understanding.
Tender Prevails
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
completion of PGTR of the project
works (by others) and on receipt of
Final/As built
Drawings/Documents/Data/Manual
in requisite number of
copies/sets/CDs as per VDR specified
in bidding documents (to be identified
during kick off meeting, if not
specified in bidding documents)
60
Electrical &
Instrumentation Tender
Payment Terms :
(viii) In case site is not available up to
Six (6) months (wherever site work is
applicable),after receipt of all supplies
at site, the payment against the same
shall be released on submission of
additional Bank Guarantee of
equivalent amount valid for One year
(1) or such extended period as may be
required.
Bidder has noted the captioned
provision for retention payment.
Bidder is requesting Purchaser to
put cap of 60 days for (c) & 90
days for (d) from supply being time
critical project of only 8 months.
Tender Prevails.
61
Electrical &
Instrumentation Tender
Payment Terms :
(i) 1ST Milestone payment shall be
released only after receipt of
Performance Bank Guarantee (PBG)
As per the payment terms,
Purchaser has asked for ABG in
case of pure advance along with
LOA. Since Bidder is already
providing security of 10%, the
Tender Prevails. Bidder to refer.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
PBG shall be submitted along with
first consignment of supply.
Purchaser to confirm.
62
Electrical &
Instrumentation Tender
Page no : 55, Bid Prices :
The SOR is given under NIT
document. Bidder has to fill only 2
columns. Also, some clauses in the
tender state that Bidder needs to
quote with taxes and duties whereas
some clauses state Bidder shall quote
prices exclusive of Taxes and Duties.
Bidder understands that Bidder
needs to quote prices inclusive of
packing and forwarding,
transportation & marine cum
transit insurance but exclusive of
GST. Bidder requests customer to
confirm the same.
Bidder understanding is correct.
63
Electrical &
Instrumentation Tender
Transit Insurance Bidder understands Transit
insurance is Bidders' scope.
Bidder requests OIL to confirm the
same.
Confirmed
64
Electrical &
Instrumentation Tender
Clause – 9.2, page – 20, Bid Security
:
Tender clause states "The bank
Guarantee issued by the Bank must
be routed through SFMS Platform as
per following details:"
Bidder understands that Bank
Guarantee in form of Bid Security
is acceptable apart from SFMS.
Bidder requests OIL to confirm the
same.
Bidder understanding is correct.
65
Electrical &
Instrumentation Tender
Clause – 8.3, page – 19, Price
Variation :
Bidder requests OIL to include
Price variation Clause on basis
constant fluctuation in prices of
Tender Prevails
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
Price quoted by the bidder, shall
remain firm & fixed until completion
of the contract and will not be subject
to any variation, except as otherwise
specifically provided in the Bidding
Documents
Raw Materials and unstable
variation in foreign currencies.
Bidder requests OIL to note that
these clauses are widely accepted
by the industry and purchasing
organizations.
66
Electrical &
Instrumentation Tender
Add/ Delete rate Add/ Delete rates for items shall
be mutually discussed and signed
off during kickoff.
Original Tender and Corrigendum
Condition Prevails.
67
Electrical &
Instrumentation Tender
Clause – 3, page – 54, Prefabricated
container
The Scope of supply involves package
engineering, procurement, fabrication,
assembly, wiring, factory testing,
supply and installation of electrical
systems required for OCS Nadua and
GGS East Khagorijan including
transportation and unloading of
complete package/skid to respective
site
Bidder understands all containers
shall be supplied in prefabricated
manner. Bidder requests OIL to
confirm
Confirmed
68
Electrical &
Instrumentation Tender
Clause – 11, page – 76, Fabrication :
The fabrication of panels/ containers
shall be carried out at MPC
Contractor’s fabrication yard.
We are OEMs of Switchgear
systems and the fabrication shall
be at our Authorized partners'
works.
Tender condition prevails.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
69
Electrical &
Instrumentation Tender
Clause – 10, page – 90, Change in
Scope :
ALTERATIONS IN DESIGNS, PLANS,
DRAWINGS, SPECIFICATIONS
ORDERS AND INSTRUCTIONS…
Bidder requests OIL to define
timeline to freeze the engineering
quantity. OIL shall send formal
confirmation within 2 months
from Kick off Meeting for any
change in BOM & the same shall
be reckoned for work completion
schedule.
Any upward change in the
quantity beyond the mentioned
time/after approval of document
shall be mutually discussed &
suitable provision of time and cost
for contractual completion shall be
done.
Also, variation cap on
Quantities.
Bidder requests OIL to confirm the
understanding.
This is a lump sum contract.
Quantity mentioned in SOR is
tentative. Bidders have to estimate
required and quote accordingly.
70
Electrical &
Instrumentation Tender
Clause – 12, page – 90, Third Party
Inspection
Consultant will arrange Third Party
Inspection wherever necessary.
Bidder understands that Third
Paty Inspections as required shall
be arranged by Consultant and all
charges for the same shall be
borne by the consultant.
Confirmed.
71
Electrical &
Instrumentation Tender
Clause – 16, page – 92, Liaising with
Third Parties :
Bidder requests OIL/ Consultant
to extend their help for any
liaising to be done with third party
Confirmed for other Agencies
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
COORDINATION WITH OTHER
AGENCIES:
agencies.
72
Electrical &
Instrumentation Tender
Clause – 21, page – 93, Termination
of Contract :
FAILURE BY THE CONTRACTOR TO
COMPLY WITH THE PROVISIONS OF
THE CONTRACT
In case performance of the vendor
is not successful, the corporation's
intent of cancelling the order shall
be notified with notice of atleast
30 days. Moreover, all the
payments of the material supplied
& material in 'Work in Progress'
shall be paid by the corporation.
Tender Prevails
73
Electrical Tender Electrical BEC Clause 1.2 :
1.2 The Bidder should have
experience of successfully supplied,
installed and commissioned at least
one number switchboard comprising
of PCC or PMCC or MCC panel
assembled inside a containerised
substation in the last five (05) years
reckoned from the bid closing date.
Bidder understands that team
'containerized substation' means
substation of modular/compact
design will be considered.
containerised substation refers to
prefabricated transportable
structural building which will
have modular/compact design
Electrical &
Instrumentation Tender
Site Layout Bidder requests OIL to provide
Site/plant Layout in AutoCAD
Format.
Will be provided to successful
bidder after award of contract
74
Electrical &
Instrumentation Tender
AC & Ventilation Bidder understands that AC &
Ventilation for the Container
needs to be provided under line
In SOR a separate line item is
provided for the Air conditioning
unit. Bidder shall verify the
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
item of prefabricated substation. quantity based on the heat load of
supplied equipments inside the
substation and estimate the
quantities accordingly. Any
addition in quantity and
Ventilation fans shall be part of
the line item of prefabricated
substation.
75
Electrical Tender Soil Resistivity Bidder requests OIL to provide Soil
Resistivity report to enable the
bidder to design Earthing System.
Soil resistivity report will be
shared to successful bidder after
award of contract.
76 General Bidder understands that all
statutory approvals shall be taken
by purchaser.
Bidder understanding is not correct. It shall be bidder scope of
work
77 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General Outgoing feeder details to be
provided for the UPS DBs.
90 nos. of Outgoing feeders shall be provided for AC UPS. For
telecom UPS it shall be 1o nos.
Battery charger shall be 20 nos.
78 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General For lighting and heat tracing
system, 3Ph 3W system is
proposed with a Delta/Delta transformer in SOR. But in SLD,
Dyn11 transformers are shown.
Kindly confirm whether it is 3Ph 3W system or 3Ph 4W system.
3 phase 3 wire system shall be
used
79 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General Utility DB & transformers quantity
is 1 as per the MODULAR PACKAGE CONTRACT (MPC–9)
tender document. But in SOR,
We require 2 nos. of Utility DB and transformer.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
there are 2 Utility DB &
transformers.
80 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General Heat tracing DB incoming is 100A
in SLD and 150A in SOR.
Heat tracing DB incoming shall be
150A.
81 ELECTRICAL SOR FOR NAUDA / EAST
KHAGORIJAN
General Emergency Lighting DB incoming
is 100A in SLD and 150A in SOR.
Emergency Lighting DB incoming
shall be150A.
82
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
General Hazardous Area Classification drawing for the plant is not
provided. So the following
assumptions are made. Kindly Confirm.
Please refer the attached
hazardous area classification
drawing
83
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
General
Only battery room is Zone 2
classified and the lighting fixtures and sockets for that room will be
Ex’d’ rated and classified as Zone-2, Gas group IIA/IIB, temperature
class T3. Quantity of fixtures and
sockets in Battery Room to be provided for the same.
Bidder shall follow SOR quantity.
This is a lump sum contract.
Quantity mentioned in SOR is tentative. Bidders have to estimate
required and quote accordingly.
84
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
General
LDBs in Plant areas will be Ex’d’
rated and classified as Zone-2, Gas group IIA/IIB, temperature
class T3.
Bidder understanding is correct.
85
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
General
In SOR, there are 2 packages, Modular Electrical Packages and
Non-Modular electrical packages.
The offer will be made based on the SOR provided for both the
packages for both the sites.(i.e.,
the quantities and No. of feeders
Bidder understanding is correct.
This is a lump sum contract.
Quantity mentioned in SOR is tentative. Bidders have to estimate
required and quote accordingly.
SL
No RFQ Section Ref. Clause
Existing Clause / Scope of
supply clarification. OIL / Consultant Response
including spare feeders will be
based on SOR only) Kindly
Confirm
86
ELECTRICAL SOR FOR
NAUDA / EAST
KHAGORIJAN
General
For all the 3 UPS (AC UPS, DC
UPS and telecom UPS), the UPS is
with integral DB. Kindly Confirm
Bidder understanding is correct.
87
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
General
As only S frame MCTs are
mentioned in SOR, we understand
that MCTs are installed on External wall only. Kindly
Confirm.
Confirmed.
88
ELECTRICAL SOR FOR
NAUDA / EAST KHAGORIJAN
General
As per the substation layout provided, for Normal LV
Switchgear room, Battery room &
CCR Room, 2 containers are combined together with a
detachable side wall. Kindly Confirm. Refer attached layout.
Bidder understanding is correct.
&&&&&&&&&&&&&&&&&&&&
Annexure - 1
Annexure - 2
Annexure - 3
Annexure - 4
CREATION OF SURFACE PRODUCTION FACILITIES (OCS & GGS) AT NADUA
& EAST KHAGORIJAN
Document Title : Specification for Lighting
Transformer
Kavin Document No. : 17039-ND-E-SP-9010
A 30 NOV 2018 ISSUED FOR REVIEW DS AD MSR/MSB
REV. DATE DESCRIPTION BY CHECKED APPROVED
PROJECT DOCUMENTS ARE CONTROLLED DOCUMENTS.
REVISIONS ARE DENOTED IN RIGHT HAND MARGIN
COMPANY:
OIL INDIA LIMITED
EPCM CONSULTANT:
KAVIN ENGINEERING AND SERVICES PRIVATE
LIMITED
Annexure-5
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 2 of 15
INDEX SHEET
PAGE NO. TITLE REV-A
1 COVER SHEET 30 NOV 2018
2 INDEX SHEET 30 NOV 2018
3 REVISION RECORD SHEET 30 NOV 2018
4 TABLE OF CONTENTS 30 NOV 2018
5-15 TECHNICAL SPECIFICATION FOR TRANSFORMER 30 NOV 2018
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 3 of 15
REVISION RECORD SHEET
REV. NO. PURPOSE LIST OF PAGES UPDATED / MODIFIED SECTIONS, IF ANY
A ISSUED FOR REVIEW FIRST ISSUE
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 4 of 15
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 5
2. OBJECTIVE .................................................................................................................... 5
3. DEFINITIONS AND ABBREVIATIONS ...................................................................... 6
3.1. DEFINITIONS .................................................................................................... 6
3.2. ABBREVIATIONS .............................................................................................. 6
4. CODES AND STANDARDS ......................................................................................... 7
5. GENERAL REQUIREMENTS ...................................................................................... 12
6. SITE CONDITION ....................................................................................................... 12
7. SCOPE .......................................................................................................................... 12
8. NOISE LEVEL .............................................................................................................. 13
9. INSPECTION, TESTING AND ACCEPTANCE .......................................................... 13
10. PACKING AND DESPATCH ...................................................................................... 14
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 5 of 15
1. INTRODUCTION
OIL INDIA LIMITED (OIL) a Government of India Enterprise, proposes to construct two
number of Surface Production facilities primarily for separation of Oil, Gas & Water and
processing of non-associated & associated gas in its producing field at Nadua and East
Khagorijan. The installation will be constructed on Modular design concept with emphasis on
skid mounted prefabricated facilities minimizing construction work at site to the extent possible
as per functional specifications of various process/utility packages. Instead of permanent civil
buildings, containerized offices/structures will be preferred.
The East Khagorijan (GGS) field is located near Dibrugarh town in Assam at a location
approximately 200m south (aerial distance) of LOC# at 27°32’N 95°09’E approx. elevation 121 M
MSL. The field is presently producing from 02 Nos. of wells through a QPS (Quick Production
Setup). Considering the potential of the field it is envisaged that Oil production is expected to
rise to a level of 1000 KLPD from 06 HP wells (02 wells + 04 future wells), 06 LP wells and 06
Non Associated Gas wells. Associated Gas is expected to be around 0.1 MMSCMD. The East
Khagorijan oil field also having the huge amount of non-associated gas potential and it is
expected to produce about 1 MMSCMD of non-associated natural gas from this area. It is also
expected that the field will produce about 800 KLPD of water along with the 1000 KLPD of
crude, so the plant design will be for handling 1800KLPD of total well fluid Oil India Limited
proposes to construct a Group Gathering Station at East Khagorijan to cater to the production in
that area.
Pipelines from Oil & Gas wells to the proposed plant and transfer lines for transporting Dry
Crude, treated Gas, treated water from the proposed plant to outside are not in the Project scope.
Procurement of LAND and construction of boundary wall in the land is not in the project scope
and will be done/ arranged by OIL separately.
KAVIN ENGINEERING AND SERVICES PRIVATE LIMITED is awarded a contract for
Engineering Procurement Construction Management to conceptualize / finalize the requirements
needed for the Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East
Khagorijan.
2. OBJECTIVE
This specification defines the minimum technical requirements for the design, materials, supply,
Installation, painting, testing, inspection and commissioning of LIGHTING TRANSFORMER system
in Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East Khagorijan.
VENDOR’s scope of supply shall include the furnishing of LIGHTING FIXTURE as complete and
functional unit, as described by the requisition.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 6 of 15
3. DEFINITIONS AND ABBREVIATIONS
3.1. DEFINITIONS
Company / Owner - Oil India Limited (OIL)
EPCM - Kavin Engineering and Services Private Limited
MPC - Bidder / EPC Contractor who supplies equipment / system / sub-
system in modules
Supplier / Vendor - Manufacturer / Seller / Sub-Vendor
The words ‚may‛, ‚should‛ and ‚shall‛ have specific meanings as follows:
‚May‛ is used where alternatives are equally acceptable.
‚Should‛ is used where a provision is preferred.
‚Shall‛ is used where a provision is mandatory.
3.2. ABBREVIATIONS
AC Alternating Current
ACB Air Circuit Breaker
API American Petroleum Institute
ASTM American Society for Testing of Material
BIS Bureau of Indian Standards
BS British Standard Institute
CBCT Core Balance Current Transformer
CEAR Central Electricity Authority Regulations, 2010
CMRI Central Mining Research Institute
CT Current Transformer
DC Direct Current
DGMS Director General of Mines and Safety
DOL Direct On-Line Starter
ELCB Earth Leakage Circuit Breaker
ELR Earth Leakage Relay
EPCM Engineering, Procurement, Construction Management
ESD Emergency Shut Down
FAT Factory Acceptance Test
HFFR Halogen Free Flame Retardant
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 7 of 15
HRC High Rupturing Capacity
HVAC Heating Ventilation Air Conditioning
IEC International Electro Technical Council
IEEE Institution of Electrical and Electronics Engineers
IP Ingress Protection
IRP Interposing Relay Panel
ITP Inspection and Test Plan
LV Low Voltage
MCB Miniature Circuit Breaker
MCC Motor Control Centre
MCCB Moulded Case Circuit Breaker
NEC National Electric Code (USA)
NFPA National Fire Protection Association
OISD Oil Industry Safety Directorate (Elect. Std.)
OMR Oil Mines Regulations, 2014
UPS Uninterrupted Power Supply
4. CODES AND STANDARDS
i. The equipment shall comply with the requirements of the latest revision of the following standards
issued by BIS unless otherwise specified.
CODES STANDARDS
IS 5 Colors for ready mixed paints and enamels
IS -772 (Part-1) (2nd rev.) AC electricity meters-general requirements
IS -1248 (1st rev.) Direct acting electrical indicating instruments
IS : 1271 Classification of lnsulating Materials.
IS-1646 Code of practice for the fire safety of buildings – Electrical
Installations
IS-1897 Copper strip for electrical purposes
IS-2189 Code of practice for selection: installation and maintenance
of automatic fire detection and alarm system
IS-2705 Current transformers
IS 2854 Method for determining the proof and the comparative
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 8 of 15
tracking indices of solid insulating materials.
IS-3034 Code of practice for the fire safety of industrial buildings –
Electrical generator and distribution stations
IS-3043 Code of practice for Earthing
IS-3156 Voltage transformers
IS-3231 Electrical relays for power systems protection.
IS-3618 Phosphate treatment of iron & steel for protection against
corrosion
IS-3646 Code of practice for Interior Illumination
IS-3716 Application guide for Insulation Coordination
IS-4051 Code of practice for the installation and maintenance of
electrical equipment in mines
IS-4171 Copper rods and bars for general engineering purpose
IS-5216 Guide for safety procedures and practices in electrical
work
IS-5571 Guide for selection of electrical equipment for hazardous
area
IS-5572 Classification of Hazardous Area (other than mines)
having flammable gases and vapours for electrical
installation
IS 5780 Electrical apparatus for explosive gas atmospheres
IS 5831 PVC insulation and sheath of electric cables
IS-6005 Code of practice of phosphating of iron &Steel
IS 6381 Electrical Apparatus For Explosive Gas Atmospheres -
Increased Safety 'E'
IS-6665 Code of practice for industrial Lighting
IS 7098-Part-1 Crosslinked polyethylene insulated PVC sheathed cables:
Part 1 for working voltage upto and including 1100 V
IS-7689 Guide for control of undesirable static electricity
IS 7693 Electrical Apparatus for Explosive Gas Atmospheres - Oil-
immersion "o"
IS 7724 Electrical Apparatus for Explosive Gas Atmospheres -
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 9 of 15
Powder Filling "q"
IS-7752 Guide for improvement of power factor- consumer
installations
IS-8478 Application guide for on load tap changers
IS-8623 Factory built assemblies of switchgear & control gear for
voltages up to and including 1000V AC and 1200V DC;
particular requirements for bus-bar trunking systems.
IS-9676 Reference ambient temperature for electrical equipment
IS-10028 Code of practice for selection, installation and maintenance
for transformer
IS-10118 Code of practice for selection, installation and maintenance
for switchgear and control gear
IS 10810 Methods of test for cables
IS-11353 Guide for uniform system marking & identification of
conductors and apparatus terminals.
IS : 11171 Dry type power transformers
IS-12360 Voltage bands for electrical installations including
preferred voltages and frequencies
IS-13234 Guide for short circuit calculations in the three phase AC
system
IS- 13235 Calculation of the effects of Short- Circuit Currents
IS-13408-1 Code of practices for the selection, installation and
maintenance of electrical apparatus for use in potentially
explosive atmospheres
IS-13947 (Part 4 – Part 5) LV switchgear and control gear
IS-15142 Guide to the use of electrical apparatus for potentially
explosive atmospheres in the presence of combustible
dusts
IS-16102 Self Ballasted LED Lamps for General Lighting Services
IS-16103 DC or AC Supplied Electronic Controlgear for LED
Modules – Performance Requirement
IS-16104 LED Modules for General Lighting
IS / IEC 60529 Degree of protection provided by enclosures (IP Code)
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 10 of 15
IS/IEC- 60947 Low voltage switchgear and controlgear : All parts
IS/IEC 60079-0 Electrical Apparatus for explosive gas atmospheres –
General requirements
IS/IEC 60079-1 Equipment protection flameproof enclosures ‚d‛
IEC 60079-5 Equipment Protection by Powder filling ‚q‛
IEC 60079-6 Equipment Protection by Oil immersion ‚o‛
IEC 60079-7 Equipment Protection by Increased Safety Type ‚e‛
IEC 60079-11 Equipment Protection by Intrinsic safety ‚I‛
IEC 60079-12 With air according to their maximum experimental safe
gaps and minimum igniting currents
IS/IEC 60079-15 Electrical apparatus for explosive gas atmosphere –
construction, test and making of type of protection ‚n‟
electrical apparatus
IEC 60228 Specification for conductor of insulated cables
IEC 60287 Electric cables - Calculation of the current rating (Current
rating equations (100% load factor) and calculation of
losses)
IEC 60502-1 Power cables with extruded insulation and their
accessories for rated voltages from 1kV (Um=1.2kV) up to
30kV (Um=36kV)
IEC 60885 Electrical test methods for electric cables
OISD-STD-110 Recommended Practices on Static Electricity
OISD-STD-113 Classification of Area for Electrical Installations at
Hydrocarbon processing and handling Facilities
OISD-GDN-115 Guidelines on Fire Fighting Equipment and Appliances in
Petroleum Industry
OISD-STD-116 Fire Protection Facilities for Petroleum Refineries and
Oil/Gas Processing Plants
OISD-STD-117 Fire protection Facilities for Petroleum Depots, Terminals,
Pipeline Installations and Lube Oil Installations
OISD-STD-118 Layouts for Oil and Gas installations
OISD-STD-137 Inspection of Electrical Equipment
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 11 of 15
OISD-RP-146 Preservation of Idle Electrical Equipment
OISD-RP-147 Inspection and Safe Practices during electrical installation
OISD-RP-148 Inspection & Safe Practices during overhauling Electrical
Equipment
OISD-RP-149 Design Aspects for Safety in Electrical System
OISD-STD-163 Process Control Room Safety
OISD STD-173 Fire Protection System for Electrical Installations
OISD-STD-180 Lightning Protection (OISD - GDN – 180)
OISD-STD-189 Standard on Fire Fighting Equipment for Drilling Rigs,
Work Over Rigs and production Installations.
ii. In case of imported equipment standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
iii. The equipment shall also conform to the provisions of Indian Electricity rules and other statutory
regulations currently in force in the country.
iv. In case Indian standards are not available for any equipment, standards issued by IEC / BS / VDE /
IEEE / NEMA or equivalent agency shall be applicable.
v. In case of any contradiction between various referred standards specifications and statutory
regulations the following order of priority shall govern:
Statutory regulations
Design Basis
Equipment specification
Codes and standards
vi. STATUTORY REQUIREMENTS & APPROVALS
The designed electrical system shall confirm to latest version of statutory and government
regulations. As a minimum need to meet and fulfil the requirement of following statutory
Acts/regulations, necessary for obtaining all statutory approvals/ certificates, as required from
concerned authorities:
Indian Electricity Act.
Central Electrical Authority Regulations 2010.
The Petroleum Rules.
Petroleum and Explosives Safety Organisation.
Central Pollution Control Board Norms.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 12 of 15
Any other applicable Rules / Regulation of central/ state/ local statutory body.
5. GENERAL REQUIREMENTS
5.1. All electrical equipment and accessories / material shall be suitable for installation and operation
for onshore application.
5.2. Supplier shall ensure availability of spare parts and maintenance support services for the
offered equipment at least for 20 years from the date of supply.
5.3. Supplier shall give a notice of at least one-year to the end user of equipment and EPCM
CONSULTANT contractor before phasing out the product/spares to enable the end user for
placement of order for spares and services.
The electrical system shall be designed to provide:
Safety to personnel and equipment both during operation & maintenance..
Reliability of service
Minimal Fire Risk
Ease of maintenance and convenience of operation
Automatic protection of electrical equipment through automatic relaying system
Electrical supply to equipment and machinery within the design operating limits.
Adequate provision for future extension and modification
Suitability or applicable environmental factors.
6. SITE CONDITION
All electrical equipment and accessories/ materials are to be suitable for installation and operation
under dusty, humid, corrosive and hostile environment with special degree of hazards. Refer to
‚17039-ND-P-GD-1002, Site Conditions and available utilities‛ for details.
7. SCOPE
7.1 CONSTRUCTION
a) The transformer shall be dry type, ANAN cooled suitable for indoor installations. Transformer shall
be housed in freestanding enclosures of welded sheet steel frames with expanded metal screens of
suitable size or louvers backed by wire-mesh. Transformer and the enclosure shall be suitably
reinforced to prevent distortion during handling. Base channels shall be provided with skids and
pulling eyes to facilitate handling. Tag plate shall be provided.
b) The transformer shall be double wound core type with cold rolled grain oriented silicon steel
insulated laminations and clamped to minimise vibrations and noise. Core fastening bolts shall be
insulated to reduce losses and to avoid hot spots. All parts of the magnetic circuit shall be effectively
connected to earth system.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 13 of 15
c) The winding shall be of copper and shall be designed for full load current and to withstand the
thermal and electromagnetic stresses arising due to the through fault current. The current carrying
winding joints shall be electrically brazed.
d) 415V/240V AC, 50Hz, 3 phase, 3 wire, Delta/Delta, 4% impedance, Off Load Tap changer (OCTC)
with ±5% in steps of 2.5%, The windings shall be provided with class B for lighting transformers upto
100kVA and class H insulation for rating more than 100kVA.
e) Different parts of transformers shall be connected by copper flexible for earth continuity purpose.
f) All the fasteners and bolts shall be hot dip galvanised as per IS: 802 or zinc passivated.
g) All surfaces to be painted shall be thoroughly cleaned, descaled, made free from rust and shall be
epoxy painted.
7.2 TERMINALS
a) Windings shall be brought out and terminated in cable boxes.
b) Cable boxes shall be supplied with cable lugs and glands. For power /control cables double
compression cable glands and crimped type tinned copper cable lugs shall be supplied. Gland plate
shall be removable type. For single core cables, gland plate shall be of non- magnetic material.
7.3 ACCESSORIES
Tappings and control gears shall be provided on the Primary side. Tap changer shall be off- circuit
type. Under conditions of external short circuit, the tap changing equipment shall be capable of
carrying the same current as the winding. Unless specified otherwise, tap changer regulation range
shall be +/-5% with each step of 2.5%. Tap changing mechanism shall be easily accessible and it shall
be possible to change the taps without opening the main transformer enclosure.
8. NOISE LEVEL
Audible noise level for lighting transformers shall be as below:
KVA Average sound level decibel (At 30cm from transformer)
0-50 50
51-150 55
151·500 65
9. INSPECTION, TESTING AND ACCEPTANCE
Owner’s representative shall be given free access in the works from time to time for stage wise
inspection and progress reporting. Four weeks advance notice shall be given to witness the final
routine test as per IS-11171. These tests shall be performed on the complete assembly at
manufacturer‘s works. Test certificates duly signed by owner’s representative shall be issued as a part
of final document.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 14 of 15
10. PACKING AND DESPATCH
The equipment shall be properly packed for the selected mode of transportation i.e. by ship /rail or
trailer. The equipment shall be wrapped in polythene sheets before being placed in crates/cases to
prevent damage to finish. Crates /cases shall have skid bottom for handling. Special notations such as
`Fragile', `This side up', `Center of gravity’, `Weight’, Owners particulars, PO nos. etc., shall be clearly
marked on the package together with other details as per purchase order. The equipment may be
stored outdoors for long periods before installation. The packing shall be suitable for outdoor storage
in areas with heavy rains/high ambient temperature unless otherwise agreed.
Note:
1. Lighting Transformer shall be constructed complying to Seismic Zone 5 as per IEC 60068-2-47,59.
2. Type Test Certificate, not more than 5 years old, conducted on similar type of equipment shall be
submitted along with the offer.
DATA SHEET OF
LIGHTING TRANSFORMER (DRY TYPE)
1.0 SITE CONDITIONS
1. 1 Maximum ambient temperature : 41°C
1.2 Minimum ambient temperature : 2°C
1.3 Design ambient temperature : 45°C
1.4 Relative humidity : 98% Max.
1.5 Altitude : Less than 1000 m above MSL
1.6 Environment : Highly corrosive and dusty as applicable
1.7 Location : Dibrugarh town in Assam, India
2.0 OPERATING CONDITIONS
2.1 Primary voltage : 415V
2.2 Fault level : 50 KA (1 sec.)
2.3 Earthing system
Primary : Unearthed
Secondary : Solidly Earthed
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -ND-E-SP-9010
Rev : A
Page : 15 of 15
3.0 GENERAL DATA
3. 1 Service : Lighting transformer
3. 2 Duty : Continuous
3.3 Type of cooling : Air Natural cooled (AN)
3.4 Installation : Indoor
3.5 Painting : Epoxy
3.6 Colour : Shade 631 as per IS-5
4.0 ELECTRICAL DATA
4.1 No. of windings : Two
4.2 Phase : Three phase
4.3 Frequency : 50 Hz +/- 3%
4.4 Insulation class:
Distribution transformer : Not applicable
Lighting/ Isolation transformer : F (upto 100KVA) /H (above 100KVA)
4.5 Winding insulation : Uniform
5.0 SPECIFIC REQUIREMENTS Normal/Emergency Lighting
5.1 Transformer Tag no. : TBC
5.2 Rated KVA : * kVA
5,3 Voltage ratio : 415V / 240V
5.4 % Impedance : As per IS
5.5 Terminal details
Terminal location
Primary : *
Secondary : *
5.6 Primary : Cable box
Cable size/Type : */CU, XLPE, armoured
Secondary : Cable box
Cable size/Type : */CU, XLPE, armoured
NOTE : ` *’ Data to be furnished by Vendor / Contractor.
CREATION OF SURFACE PRODUCTION FACILITIES (OCS & GGS) AT NADUA
& EAST KHAGORIJAN
Document Title : Specification for Lighting
Transformer
Kavin Document No. : 17039-EK-E-SP-9010
A 30 NOV 2018 ISSUED FOR REVIEW DS AD MSR/MSB
REV. DATE DESCRIPTION BY CHECKED APPROVED
PROJECT DOCUMENTS ARE CONTROLLED DOCUMENTS.
REVISIONS ARE DENOTED IN RIGHT HAND MARGIN
COMPANY:
OIL INDIA LIMITED
EPCM CONSULTANT:
KAVIN ENGINEERING AND SERVICES PRIVATE
LIMITED
Annexure - 6
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 2 of 15
INDEX SHEET
PAGE NO. TITLE REV-A
1 COVER SHEET 30 NOV 2018
2 INDEX SHEET 30 NOV 2018
3 REVISION RECORD SHEET 30 NOV 2018
4 TABLE OF CONTENTS 30 NOV 2018
5-15 TECHNICAL SPECIFICATION FOR TRANSFORMER 30 NOV 2018
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 3 of 15
REVISION RECORD SHEET
REV. NO. PURPOSE LIST OF PAGES UPDATED / MODIFIED SECTIONS, IF ANY
A ISSUED FOR REVIEW FIRST ISSUE
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 4 of 15
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 5
2. OBJECTIVE .................................................................................................................... 5
3. DEFINITIONS AND ABBREVIATIONS ...................................................................... 6
3.1. DEFINITIONS .................................................................................................... 6
3.2. ABBREVIATIONS .............................................................................................. 6
4. CODES AND STANDARDS ......................................................................................... 7
5. GENERAL REQUIREMENTS ...................................................................................... 12
6. SITE CONDITION ....................................................................................................... 12
7. SCOPE .......................................................................................................................... 12
8. NOISE LEVEL .............................................................................................................. 13
9. INSPECTION, TESTING AND ACCEPTANCE .......................................................... 13
10. PACKING AND DESPATCH ...................................................................................... 14
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 5 of 15
1. INTRODUCTION
OIL INDIA LIMITED (OIL) a Government of India Enterprise, proposes to construct two
number of Surface Production facilities primarily for separation of Oil, Gas & Water and
processing of non-associated & associated gas in its producing field at Nadua and East
Khagorijan. The installation will be constructed on Modular design concept with emphasis on
skid mounted prefabricated facilities minimizing construction work at site to the extent possible
as per functional specifications of various process/utility packages. Instead of permanent civil
buildings, containerized offices/structures will be preferred.
The East Khagorijan (GGS) field is located near Dibrugarh town in Assam at a location
approximately 200m south (aerial distance) of LOC# at 27°32’N 95°09’E approx. elevation 121 M
MSL. The field is presently producing from 02 Nos. of wells through a QPS (Quick Production
Setup). Considering the potential of the field it is envisaged that Oil production is expected to
rise to a level of 1000 KLPD from 06 HP wells (02 wells + 04 future wells), 06 LP wells and 06
Non Associated Gas wells. Associated Gas is expected to be around 0.1 MMSCMD. The East
Khagorijan oil field also having the huge amount of non-associated gas potential and it is
expected to produce about 1 MMSCMD of non-associated natural gas from this area. It is also
expected that the field will produce about 800 KLPD of water along with the 1000 KLPD of
crude, so the plant design will be for handling 1800KLPD of total well fluid Oil India Limited
proposes to construct a Group Gathering Station at East Khagorijan to cater to the production in
that area.
Pipelines from Oil & Gas wells to the proposed plant and transfer lines for transporting Dry
Crude, treated Gas, treated water from the proposed plant to outside are not in the Project scope.
Procurement of LAND and construction of boundary wall in the land is not in the project scope
and will be done/ arranged by OIL separately.
KAVIN ENGINEERING AND SERVICES PRIVATE LIMITED is awarded a contract for
Engineering Procurement Construction Management to conceptualize / finalize the requirements
needed for the Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East
Khagorijan.
2. OBJECTIVE
This specification defines the minimum technical requirements for the design, materials, supply,
Installation, painting, testing, inspection and commissioning of LIGHTING TRANSFORMER system
in Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East Khagorijan.
VENDOR’s scope of supply shall include the furnishing of LIGHTING FIXTURE as complete and
functional unit, as described by the requisition.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 6 of 15
3. DEFINITIONS AND ABBREVIATIONS
3.1. DEFINITIONS
Company / Owner - Oil India Limited (OIL)
EPCM - Kavin Engineering and Services Private Limited
MPC - Bidder / EPC Contractor who supplies equipment / system / sub-
system in modules
Supplier / Vendor - Manufacturer / Seller / Sub-Vendor
The words ‚may‛, ‚should‛ and ‚shall‛ have specific meanings as follows:
‚May‛ is used where alternatives are equally acceptable.
‚Should‛ is used where a provision is preferred.
‚Shall‛ is used where a provision is mandatory.
3.2. ABBREVIATIONS
AC Alternating Current
ACB Air Circuit Breaker
API American Petroleum Institute
ASTM American Society for Testing of Material
BIS Bureau of Indian Standards
BS British Standard Institute
CBCT Core Balance Current Transformer
CEAR Central Electricity Authority Regulations, 2010
CMRI Central Mining Research Institute
CT Current Transformer
DC Direct Current
DGMS Director General of Mines and Safety
DOL Direct On-Line Starter
ELCB Earth Leakage Circuit Breaker
ELR Earth Leakage Relay
EPCM Engineering, Procurement, Construction Management
ESD Emergency Shut Down
FAT Factory Acceptance Test
HFFR Halogen Free Flame Retardant
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 7 of 15
HRC High Rupturing Capacity
HVAC Heating Ventilation Air Conditioning
IEC International Electro Technical Council
IEEE Institution of Electrical and Electronics Engineers
IP Ingress Protection
IRP Interposing Relay Panel
ITP Inspection and Test Plan
LV Low Voltage
MCB Miniature Circuit Breaker
MCC Motor Control Centre
MCCB Moulded Case Circuit Breaker
NEC National Electric Code (USA)
NFPA National Fire Protection Association
OISD Oil Industry Safety Directorate (Elect. Std.)
OMR Oil Mines Regulations, 2014
UPS Uninterrupted Power Supply
4. CODES AND STANDARDS
i. The equipment shall comply with the requirements of the latest revision of the following standards
issued by BIS unless otherwise specified.
CODES STANDARDS
IS 5 Colors for ready mixed paints and enamels
IS -772 (Part-1) (2nd rev.) AC electricity meters-general requirements
IS -1248 (1st rev.) Direct acting electrical indicating instruments
IS : 1271 Classification of lnsulating Materials.
IS-1646 Code of practice for the fire safety of buildings – Electrical
Installations
IS-1897 Copper strip for electrical purposes
IS-2189 Code of practice for selection: installation and maintenance
of automatic fire detection and alarm system
IS-2705 Current transformers
IS 2854 Method for determining the proof and the comparative
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 8 of 15
tracking indices of solid insulating materials.
IS-3034 Code of practice for the fire safety of industrial buildings –
Electrical generator and distribution stations
IS-3043 Code of practice for Earthing
IS-3156 Voltage transformers
IS-3231 Electrical relays for power systems protection.
IS-3618 Phosphate treatment of iron & steel for protection against
corrosion
IS-3646 Code of practice for Interior Illumination
IS-3716 Application guide for Insulation Coordination
IS-4051 Code of practice for the installation and maintenance of
electrical equipment in mines
IS-4171 Copper rods and bars for general engineering purpose
IS-5216 Guide for safety procedures and practices in electrical
work
IS-5571 Guide for selection of electrical equipment for hazardous
area
IS-5572 Classification of Hazardous Area (other than mines)
having flammable gases and vapours for electrical
installation
IS 5780 Electrical apparatus for explosive gas atmospheres
IS 5831 PVC insulation and sheath of electric cables
IS-6005 Code of practice of phosphating of iron &Steel
IS 6381 Electrical Apparatus For Explosive Gas Atmospheres -
Increased Safety 'E'
IS-6665 Code of practice for industrial Lighting
IS 7098-Part-1 Crosslinked polyethylene insulated PVC sheathed cables:
Part 1 for working voltage upto and including 1100 V
IS-7689 Guide for control of undesirable static electricity
IS 7693 Electrical Apparatus for Explosive Gas Atmospheres - Oil-
immersion "o"
IS 7724 Electrical Apparatus for Explosive Gas Atmospheres -
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 9 of 15
Powder Filling "q"
IS-7752 Guide for improvement of power factor- consumer
installations
IS-8478 Application guide for on load tap changers
IS-8623 Factory built assemblies of switchgear & control gear for
voltages up to and including 1000V AC and 1200V DC;
particular requirements for bus-bar trunking systems.
IS-9676 Reference ambient temperature for electrical equipment
IS-10028 Code of practice for selection, installation and maintenance
for transformer
IS-10118 Code of practice for selection, installation and maintenance
for switchgear and control gear
IS 10810 Methods of test for cables
IS-11353 Guide for uniform system marking & identification of
conductors and apparatus terminals.
IS : 11171 Dry type power transformers
IS-12360 Voltage bands for electrical installations including
preferred voltages and frequencies
IS-13234 Guide for short circuit calculations in the three phase AC
system
IS- 13235 Calculation of the effects of Short- Circuit Currents
IS-13408-1 Code of practices for the selection, installation and
maintenance of electrical apparatus for use in potentially
explosive atmospheres
IS-13947 (Part 4 – Part 5) LV switchgear and control gear
IS-15142 Guide to the use of electrical apparatus for potentially
explosive atmospheres in the presence of combustible
dusts
IS-16102 Self Ballasted LED Lamps for General Lighting Services
IS-16103 DC or AC Supplied Electronic Controlgear for LED
Modules – Performance Requirement
IS-16104 LED Modules for General Lighting
IS / IEC 60529 Degree of protection provided by enclosures (IP Code)
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 10 of 15
IS/IEC- 60947 Low voltage switchgear and controlgear : All parts
IS/IEC 60079-0 Electrical Apparatus for explosive gas atmospheres –
General requirements
IS/IEC 60079-1 Equipment protection flameproof enclosures ‚d‛
IEC 60079-5 Equipment Protection by Powder filling ‚q‛
IEC 60079-6 Equipment Protection by Oil immersion ‚o‛
IEC 60079-7 Equipment Protection by Increased Safety Type ‚e‛
IEC 60079-11 Equipment Protection by Intrinsic safety ‚I‛
IEC 60079-12 With air according to their maximum experimental safe
gaps and minimum igniting currents
IS/IEC 60079-15 Electrical apparatus for explosive gas atmosphere –
construction, test and making of type of protection ‚n‟
electrical apparatus
IEC 60228 Specification for conductor of insulated cables
IEC 60287 Electric cables - Calculation of the current rating (Current
rating equations (100% load factor) and calculation of
losses)
IEC 60502-1 Power cables with extruded insulation and their
accessories for rated voltages from 1kV (Um=1.2kV) up to
30kV (Um=36kV)
IEC 60885 Electrical test methods for electric cables
OISD-STD-110 Recommended Practices on Static Electricity
OISD-STD-113 Classification of Area for Electrical Installations at
Hydrocarbon processing and handling Facilities
OISD-GDN-115 Guidelines on Fire Fighting Equipment and Appliances in
Petroleum Industry
OISD-STD-116 Fire Protection Facilities for Petroleum Refineries and
Oil/Gas Processing Plants
OISD-STD-117 Fire protection Facilities for Petroleum Depots, Terminals,
Pipeline Installations and Lube Oil Installations
OISD-STD-118 Layouts for Oil and Gas installations
OISD-STD-137 Inspection of Electrical Equipment
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 11 of 15
OISD-RP-146 Preservation of Idle Electrical Equipment
OISD-RP-147 Inspection and Safe Practices during electrical installation
OISD-RP-148 Inspection & Safe Practices during overhauling Electrical
Equipment
OISD-RP-149 Design Aspects for Safety in Electrical System
OISD-STD-163 Process Control Room Safety
OISD STD-173 Fire Protection System for Electrical Installations
OISD-STD-180 Lightning Protection (OISD - GDN – 180)
OISD-STD-189 Standard on Fire Fighting Equipment for Drilling Rigs,
Work Over Rigs and production Installations.
ii. In case of imported equipment standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
iii. The equipment shall also conform to the provisions of Indian Electricity rules and other statutory
regulations currently in force in the country.
iv. In case Indian standards are not available for any equipment, standards issued by IEC / BS / VDE /
IEEE / NEMA or equivalent agency shall be applicable.
v. In case of any contradiction between various referred standards specifications and statutory
regulations the following order of priority shall govern:
Statutory regulations
Design Basis
Equipment specification
Codes and standards
vi. STATUTORY REQUIREMENTS & APPROVALS
The designed electrical system shall confirm to latest version of statutory and government
regulations. As a minimum need to meet and fulfil the requirement of following statutory
Acts/regulations, necessary for obtaining all statutory approvals/ certificates, as required from
concerned authorities:
Indian Electricity Act.
Central Electrical Authority Regulations 2010.
The Petroleum Rules.
Petroleum and Explosives Safety Organisation.
Central Pollution Control Board Norms.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 12 of 15
Any other applicable Rules / Regulation of central/ state/ local statutory body.
5. GENERAL REQUIREMENTS
5.1. All electrical equipment and accessories / material shall be suitable for installation and operation
for onshore application.
5.2. Supplier shall ensure availability of spare parts and maintenance support services for the
offered equipment at least for 20 years from the date of supply.
5.3. Supplier shall give a notice of at least one-year to the end user of equipment and EPCM
CONSULTANT contractor before phasing out the product/spares to enable the end user for
placement of order for spares and services.
The electrical system shall be designed to provide:
Safety to personnel and equipment both during operation & maintenance..
Reliability of service
Minimal Fire Risk
Ease of maintenance and convenience of operation
Automatic protection of electrical equipment through automatic relaying system
Electrical supply to equipment and machinery within the design operating limits.
Adequate provision for future extension and modification
Suitability or applicable environmental factors.
6. SITE CONDITION
All electrical equipment and accessories/ materials are to be suitable for installation and operation
under dusty, humid, corrosive and hostile environment with special degree of hazards. Refer to
‚17039-EK-P-GD-1002, Site Conditions and available utilities‛ for details.
7. SCOPE
7.1 CONSTRUCTION
a) The transformer shall be dry type, ANAN cooled suitable for indoor installations. Transformer shall
be housed in freestanding enclosures of welded sheet steel frames with expanded metal screens of
suitable size or louvers backed by wire-mesh. Transformer and the enclosure shall be suitably
reinforced to prevent distortion during handling. Base channels shall be provided with skids and
pulling eyes to facilitate handling. Tag plate shall be provided.
b) The transformer shall be double wound core type with cold rolled grain oriented silicon steel
insulated laminations and clamped to minimise vibrations and noise. Core fastening bolts shall be
insulated to reduce losses and to avoid hot spots. All parts of the magnetic circuit shall be effectively
connected to earth system.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 13 of 15
c) The winding shall be of copper and shall be designed for full load current and to withstand the
thermal and electromagnetic stresses arising due to the through fault current. The current carrying
winding joints shall be electrically brazed.
d) 415V/240V AC, 50Hz, 3 phase, 3 wire, Delta/Delta, 4% impedance, Off Load Tap changer (OCTC)
with ±5% in steps of 2.5%, The windings shall be provided with class B for lighting transformers upto
100kVA and class H insulation for rating more than 100kVA.
e) Different parts of transformers shall be connected by copper flexible for earth continuity purpose.
f) All the fasteners and bolts shall be hot dip galvanised as per IS: 802 or zinc passivated.
g) All surfaces to be painted shall be thoroughly cleaned, descaled, made free from rust and shall be
epoxy painted.
7.2 TERMINALS
a) Windings shall be brought out and terminated in cable boxes.
b) Cable boxes shall be supplied with cable lugs and glands. For power /control cables double
compression cable glands and crimped type tinned copper cable lugs shall be supplied. Gland plate
shall be removable type. For single core cables, gland plate shall be of non- magnetic material.
7.3 ACCESSORIES
Tappings and control gears shall be provided on the Primary side. Tap changer shall be off- circuit
type. Under conditions of external short circuit, the tap changing equipment shall be capable of
carrying the same current as the winding. Unless specified otherwise, tap changer regulation range
shall be +/-5% with each step of 2.5%. Tap changing mechanism shall be easily accessible and it shall
be possible to change the taps without opening the main transformer enclosure.
8. NOISE LEVEL
Audible noise level for lighting transformers shall be as below:
KVA Average sound level decibel (At 30cm from transformer)
0-50 50
51-150 55
151·500 65
9. INSPECTION, TESTING AND ACCEPTANCE
Owner’s representative shall be given free access in the works from time to time for stage wise
inspection and progress reporting. Four weeks advance notice shall be given to witness the final
routine test as per IS-11171. These tests shall be performed on the complete assembly at
manufacturer‘s works. Test certificates duly signed by owner’s representative shall be issued as a part
of final document.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 14 of 15
10. PACKING AND DESPATCH
The equipment shall be properly packed for the selected mode of transportation i.e. by ship /rail or
trailer. The equipment shall be wrapped in polythene sheets before being placed in crates/cases to
prevent damage to finish. Crates /cases shall have skid bottom for handling. Special notations such as
`Fragile', `This side up', `Center of gravity’, `Weight’, Owners particulars, PO nos. etc., shall be clearly
marked on the package together with other details as per purchase order. The equipment may be
stored outdoors for long periods before installation. The packing shall be suitable for outdoor storage
in areas with heavy rains/high ambient temperature unless otherwise agreed.
Note:
1. Lighting Transformer shall be constructed complying to Seismic Zone 5 as per IEC 60068-2-47,59.
2. Type Test Certificate, not more than 5 years old, conducted on similar type of equipment shall be
submitted along with the offer.
DATA SHEET OF
LIGHTING TRANSFORMER (DRY TYPE)
1.0 SITE CONDITIONS
1. 1 Maximum ambient temperature : 41°C
1.2 Minimum ambient temperature : 2°C
1.3 Design ambient temperature : 45°C
1.4 Relative humidity : 98% Max.
1.5 Altitude : Less than 1000 m above MSL
1.6 Environment : Highly corrosive and dusty as applicable
1.7 Location : Dibrugarh town in Assam, India
2.0 OPERATING CONDITIONS
2.1 Primary voltage : 415V
2.2 Fault level : 50 KA (1 sec.)
2.3 Earthing system
Primary : Unearthed
Secondary : Solidly Earthed
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Transformer
Doc No : 17039 -EK-E-SP-9010
Rev : A
Page : 15 of 15
3.0 GENERAL DATA
3. 1 Service : Lighting transformer
3. 2 Duty : Continuous
3.3 Type of cooling : Air Natural cooled (AN)
3.4 Installation : Indoor
3.5 Painting : Epoxy
3.6 Colour : Shade 631 as per IS-5
4.0 ELECTRICAL DATA
4.1 No. of windings : Two
4.2 Phase : Three phase
4.3 Frequency : 50 Hz +/- 3%
4.4 Insulation class:
Distribution transformer : Not applicable
Lighting/ Isolation transformer : F (upto 100KVA) /H (above 100KVA)
4.5 Winding insulation : Uniform
5.0 SPECIFIC REQUIREMENTS Normal/Emergency Lighting
5.1 Transformer Tag no. : TBC
5.2 Rated KVA : * kVA
5,3 Voltage ratio : 415V / 240V
5.4 % Impedance : As per IS
5.5 Terminal details
Terminal location
Primary : *
Secondary : *
5.6 Primary : Cable box
Cable size/Type : */CU, XLPE, armoured
Secondary : Cable box
Cable size/Type : */CU, XLPE, armoured
NOTE : ` *’ Data to be furnished by Vendor / Contractor.
CREATION OF SURFACE PRODUCTION FACILITIES (OCS & GGS) AT NADUA & EAST
KHAGORIJAN
Document Title : Specification for Lighting
Fixtures and Distribution Board
Kavin Document No. : 17039-ND-E-SP-9009
A 30 NOV 2018 ISSUED FOR REVIEW DS AD MSR/MSB
REV. DATE DESCRIPTION BY
CHECKE
D
APPROVE
D
PROJECT DOCUMENTS ARE CONTROLLED DOCUMENTS.
REVISIONS ARE DENOTED IN RIGHT HAND MARGIN
COMPANY:
OIL INDIA LIMITED
EPCM CONSULTANT:
KAVIN ENGINEERING AND SERVICES PRIVATE
LIMITED
Annexure - 7
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 2 of 18
INDEX SHEET
PAGE NO. TITLE REV-A
1 COVER SHEET 30 NOV 2018
2 INDEX SHEET 30 NOV 2018
3 REVISION RECORD SHEET 30 NOV 2018
4 TABLE OF CONTENTS 30 NOV 2018
5-18
TECHNICAL SPECIFICATION FOR
LIGHTING FIXTURES AND
DISTRIBUTION BOARD
30 NOV 2018
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 3 of 18
REVISION RECORD SHEET
REV. NO. PURPOSE LIST OF PAGES UPDATED / MODIFIED SECTIONS, IF ANY
A ISSUED FOR REVIEW FIRST ISSUE
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 4 of 18
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 5
2. OBJECTIVE .................................................................................................................... 5
3. DEFINITIONS AND ABBREVIATIONS ...................................................................... 6
3.1. DEFINITIONS .................................................................................................... 6
3.2. ABBREVIATIONS .............................................................................................. 6
4. CODES AND STANDARDS ......................................................................................... 7
5. GENERAL REQUIREMENTS ...................................................................................... 12
6. SITE CONDITION ....................................................................................................... 12
7. SCOPE .......................................................................................................................... 12
8. LIGHTING FIXTURES (LUMINAIRES) ...................................................................... 17
9. TESTING AND INSPECTION .................................................................................... 18
10. PACKING AND TRANSPORT ................................................................................... 18
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 5 of 18
1. INTRODUCTION
OIL INDIA LIMITED (OIL) a Government of India Enterprise, proposes to construct two number of
Surface Production facilities primarily for separation of Oil, Gas & Water and processing of non-
associated & associated gas in its producing field at Nadua and East Khagorijan. The installation will
be constructed on Modular design concept with emphasis on skid mounted prefabricated facilities
minimizing construction work at site to the extent possible as per functional specifications of various
process/utility packages. Instead of permanent civil buildings, containerized offices/structures will be
preferred.
The East Khagorijan (GGS) field is located near Dibrugarh town in Assam at a location approximately
200m south (aerial distance) of LOC# at 27°32’N 95°09’E approx. elevation 121 M MSL. The field is
presently producing from 02 Nos. of wells through a QPS (Quick Production Setup). Considering the
potential of the field it is envisaged that Oil production is expected to rise to a level of 1000 KLPD
from 06 HP wells (02 wells + 04 future wells), 06 LP wells and 06 Non Associated Gas wells.
Associated Gas is expected to be around 0.1 MMSCMD. The East Khagorijan oil field also having the
huge amount of non-associated gas potential and it is expected to produce about 1 MMSCMD of non-
associated natural gas from this area. It is also expected that the field will produce about 800 KLPD of
water along with the 1000 KLPD of crude, so the plant design will be for handling 1800KLPD of total
well fluid Oil India Limited proposes to construct a Group Gathering Station at East Khagorijan to
cater to the production in that area.
Pipelines from Oil & Gas wells to the proposed plant and transfer lines for transporting Dry Crude,
treated Gas, treated water from the proposed plant to outside are not in the Project scope.
Procurement of LAND and construction of boundary wall in the land is not in the project scope and
will be done/ arranged by OIL separately.
KAVIN ENGINEERING AND SERVICES PRIVATE LIMITED is awarded a contract for Engineering
Procurement Construction Management to conceptualize / finalize the requirements needed for the
Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East Khagorijan.
2. OBJECTIVE
This specification defines the minimum technical requirements for the design, materials, supply,
Installation, painting, testing, inspection and commissioning of LIGHTING FIXTURE AND
LIGHTING FIXTURE DISTRIBUTION BOARD system in Oil Collection Station (OCS) at Nadua and
Group Gathering Station (GGS) at East Khagorijan. VENDOR’s scope of supply shall include the
furnishing of LIGHTING FIXTURE as complete and functional unit, as described by the requisition.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 6 of 18
3. DEFINITIONS AND ABBREVIATIONS
3.1. DEFINITIONS
Company / Owner - Oil India Limited (OIL)
EPCM - Kavin Engineering and Services Private Limited
MPC - Bidder / EPC Contractor who supplies equipment / system / sub-
system in modules
Supplier / Vendor - Manufacturer / Seller / Sub-Vendor
The words “may”, “should” and “shall” have specific meanings as follows:
“May” is used where alternatives are equally acceptable.
“Should” is used where a provision is preferred.
“Shall” is used where a provision is mandatory.
3.2. ABBREVIATIONS
AC Alternating Current
ACB Air Circuit Breaker
API American Petroleum Institute
ASTM American Society for Testing of Material
BIS Bureau of Indian Standards
BS British Standard Institute
CBCT Core Balance Current Transformer
CEAR Central Electricity Authority Regulations, 2010
CMRI Central Mining Research Institute
CT Current Transformer
DC Direct Current
DGMS Director General of Mines and Safety
DOL Direct On-Line Starter
ELCB Earth Leakage Circuit Breaker
ELR Earth Leakage Relay
EPCM Engineering, Procurement, Construction Management
ESD Emergency Shut Down
FAT Factory Acceptance Test
HFFR Halogen Free Flame Retardant
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 7 of 18
HRC High Rupturing Capacity
HVAC Heating Ventilation Air Conditioning
IEC International Electro Technical Council
IEEE Institution of Electrical and Electronics Engineers
IP Ingress Protection
IRP Interposing Relay Panel
ITP Inspection and Test Plan
LV Low Voltage
MCB Miniature Circuit Breaker
MCC Motor Control Centre
MCCB Moulded Case Circuit Breaker
NEC National Electric Code (USA)
NFPA National Fire Protection Association
OISD Oil Industry Safety Directorate (Elect. Std.)
OMR Oil Mines Regulations, 2014
UPS Uninterrupted Power Supply
4. CODES AND STANDARDS
i. The equipment shall comply with the requirements of the latest revision of the following standards
issued by BIS unless otherwise specified.
CODES STANDARDS
IS 5 Colors for ready mixed paints and enamels
IS -772 (Part-1) (2nd rev.) AC electricity meters-general requirements
IS -1248 (1st rev.) Direct acting electrical indicating instruments
IS-1646 Code of practice for the fire safety of buildings – Electrical
Installations
IS-1897 Copper strip for electrical purposes
IS-2189 Code of practice for selection: installation and maintenance
of automatic fire detection and alarm system
IS-2705 Current transformers
IS 2854 Method for determining the proof and the comparative
tracking indices of solid insulating materials.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 8 of 18
IS-3034 Code of practice for the fire safety of industrial buildings –
Electrical generator and distribution stations
IS-3043 Code of practice for Earthing
IS-3156 Voltage transformers
IS-3231 Electrical relays for power systems protection.
IS-3618 Phosphate treatment of iron & steel for protection against
corrosion
IS-3646 Code of practice for Interior Illumination
IS-3716 Application guide for Insulation Coordination
IS-4051 Code of practice for the installation and maintenance of
electrical equipment in mines
IS-4171 Copper rods and bars for general engineering purpose
IS-5216 Guide for safety procedures and practices in electrical
work
IS-5571 Guide for selection of electrical equipment for hazardous
area
IS-5572 Classification of Hazardous Area (other than mines)
having flammable gases and vapours for electrical
installation
IS 5780 Electrical apparatus for explosive gas atmospheres
IS 5831 PVC insulation and sheath of electric cables
IS-6005 Code of practice of phosphating of iron &Steel
IS 6381 Electrical Apparatus For Explosive Gas Atmospheres -
Increased Safety 'E'
IS-6665 Code of practice for industrial Lighting
IS 7098-Part-1 Crosslinked polyethylene insulated PVC sheathed cables:
Part 1 for working voltage upto and including 1100 V
IS-7689 Guide for control of undesirable static electricity
IS 7693 Electrical Apparatus for Explosive Gas Atmospheres - Oil-
immersion "o"
IS 7724 Electrical Apparatus for Explosive Gas Atmospheres -
Powder Filling "q"
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 9 of 18
IS-7752 Guide for improvement of power factor- consumer
installations
IS-8478 Application guide for on load tap changers
IS-8623 Factory built assemblies of switchgear & control gear for
voltages up to and including 1000V AC and 1200V DC;
particular requirements for bus-bar trunking systems.
IS-9676 Reference ambient temperature for electrical equipment
IS-10028 Code of practice for selection, installation and maintenance
for transformer
IS-10118 Code of practice for selection, installation and maintenance
for switchgear and control gear
IS 10810 Methods of test for cables
IS-11353 Guide for uniform system marking & identification of
conductors and apparatus terminals.
IS-12360 Voltage bands for electrical installations including
preferred voltages and frequencies
IS-13234 Guide for short circuit calculations in the three phase AC
system
IS- 13235 Calculation of the effects of Short- Circuit Currents
IS-13408-1 Code of practices for the selection, installation and
maintenance of electrical apparatus for use in potentially
explosive atmospheres
IS-13947 (Part 4 – Part 5) LV switchgear and control gear
IS-15142 Guide to the use of electrical apparatus for potentially
explosive atmospheres in the presence of combustible
dusts
IS-16102 Self Ballasted LED Lamps for General Lighting Services
IS-16103 DC or AC Supplied Electronic Controlgear for LED
Modules – Performance Requirement
IS-16104 LED Modules for General Lighting
IS / IEC 60529 Degree of protection provided by enclosures (IP Code)
IS/IEC- 60947 Low voltage switchgear and controlgear : All parts
IS/IEC 60079-0 Electrical Apparatus for explosive gas atmospheres –
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 10 of 18
General requirements
IS/IEC 60079-1 Equipment protection flameproof enclosures “d”
IEC 60079-5 Equipment Protection by Powder filling “q”
IEC 60079-6 Equipment Protection by Oil immersion “o”
IEC 60079-7 Equipment Protection by Increased Safety Type “e”
IEC 60079-11 Equipment Protection by Intrinsic safety “I”
IEC 60079-12 With air according to their maximum experimental safe
gaps and minimum igniting currents
IS/IEC 60079-15 Electrical apparatus for explosive gas atmosphere –
construction, test and making of type of protection “n‟
electrical apparatus
IEC 60228 Specification for conductor of insulated cables
IEC 60287 Electric cables - Calculation of the current rating (Current
rating equations (100% load factor) and calculation of
losses)
IEC 60502-1 Power cables with extruded insulation and their
accessories for rated voltages from 1kV (Um=1.2kV) up to
30kV (Um=36kV)
IEC 60885 Electrical test methods for electric cables
OISD-STD-110 Recommended Practices on Static Electricity
OISD-STD-113 Classification of Area for Electrical Installations at
Hydrocarbon processing and handling Facilities
OISD-GDN-115 Guidelines on Fire Fighting Equipment and Appliances in
Petroleum Industry
OISD-STD-116 Fire Protection Facilities for Petroleum Refineries and
Oil/Gas Processing Plants
OISD-STD-117 Fire protection Facilities for Petroleum Depots, Terminals,
Pipeline Installations and Lube Oil Installations
OISD-STD-118 Layouts for Oil and Gas installations
OISD-STD-137 Inspection of Electrical Equipment
OISD-RP-146 Preservation of Idle Electrical Equipment
OISD-RP-147 Inspection and Safe Practices during electrical installation
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 11 of 18
OISD-RP-148 Inspection & Safe Practices during overhauling Electrical
Equipment
OISD-RP-149 Design Aspects for Safety in Electrical System
OISD-STD-163 Process Control Room Safety
OISD STD-173 Fire Protection System for Electrical Installations
OISD-STD-180 Lightning Protection (OISD - GDN – 180)
OISD-STD-189 Standard on Fire Fighting Equipment for Drilling Rigs,
Work Over Rigs and production Installations.
ii. In case of imported equipment standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
iii. The equipment shall also conform to the provisions of Indian Electricity rules and other statutory
regulations currently in force in the country.
iv. In case Indian standards are not available for any equipment, standards issued by IEC / BS / VDE /
IEEE / NEMA or equivalent agency shall be applicable.
v. In case of any contradiction between various referred standards specifications and statutory
regulations the following order of priority shall govern:
Statutory regulations
Design Basis
Equipment specification
Codes and standards
vi. STATUTORY REQUIREMENTS & APPROVALS
The designed electrical system shall confirm to latest version of statutory and government
regulations. As a minimum need to meet and fulfil the requirement of following statutory
Acts/regulations, necessary for obtaining all statutory approvals/ certificates, as required from
concerned authorities:
Indian Electricity Act.
Central Electrical Authority Regulations 2010.
The Petroleum Rules.
Petroleum and Explosives Safety Organisation.
Central Pollution Control Board Norms.
Any other applicable Rules / Regulation of central/ state/ local statutory body.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 12 of 18
5. GENERAL REQUIREMENTS
5.1. All electrical equipment and accessories / material shall be suitable for installation and operation
for onshore application.
5.2. Supplier shall ensure availability of spare parts and maintenance support services for the
offered equipment at least for 20 years from the date of supply.
5.3. Supplier shall give a notice of at least one-year to the end user of equipment and EPCM
CONSULTANT contractor before phasing out the product/spares to enable the end user for
placement of order for spares and services.
The electrical system shall be designed to provide:
Safety to personnel and equipment both during operation & maintenance..
Reliability of service
Minimal Fire Risk
Ease of maintenance and convenience of operation
Automatic protection of electrical equipment through automatic relaying system
Electrical supply to equipment and machinery within the design operating limits.
Adequate provision for future extension and modification
Suitability or applicable environmental factors.
6. SITE CONDITION
All electrical equipment and accessories/ materials are to be suitable for installation and operation
under dusty, humid, corrosive and hostile environment with special degree of hazards. Refer to
“17039-ND-P-GD-1002, Site Conditions and available utilities” for details.
7. SCOPE
7.1 Lighting Distribution Board (LDB) And Lighting Panels
a) LDB and panels shall be of sheet steel enclosed and shall be fully dust and vermin proof,
providing a degree of protection of IP 52 for busbars, incoming and outgoing feeding
compartment and IP 42 for enclosure for transformer. Outdoor panels shall in addition be
completely weather-proof with a sloping canopy for protection against rain and providing a
degree of protection of IP 55. The sheet steel used shall be cold rolled and 2 mm thick.
b) All boards and panels shall be provided with hinged doors for access to equipment. Doors shall
be gasketted all round with neoprene gaskets. The lighting distribution boards shall be either
wall mounted/ stool mounted or floor mounted depending upon the dimension of DB and shall
be provided with MCCB for incomer and MCBs + ELCB for outgoing feeders. The hinged door of
incomer shall be interlocked so as to prevent opening of the door when the switch is ON and to
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 13 of 18
prevent closing of the switch with the door not fully closed. However, a device for bypassing the
door interlock shall be provided to enable the operation of the switch with the door open, when
necessary, for examination/maintenance. For wall mounting lighting panels when provided with
ELCBs and MCBs a hinged, latched front door shall be provided with key-locking facility and a
slotted Bakelite sheet inside. Only the ELCBs/MCBs operating knobs shall project out of the
bakelite sheet slots for safe operation and neat appearance.
c) Outdoor LDBs for street lighting/area lighting shall have ON/OFF operation through real time
based timer control in addition to manual control. In this case incomer to LDB shall have
suitably rated contactor in addition to MCCB and same shall be controlled by timer contacts. The
outgoing feeders of indoor LDB used for street lighting/area lighting shall have dedicated timer
controlled contactors in addition to MCB
d) All accessible live connection/metals shall be shrouded and it shall be possible to change
individual fuses, switches, MCCB / MCBs from the front of LDB without danger of contact with
live parts.
e) For floor mounting type LDB, adequately sized mounting channels shall be supplied and for
wall/column/structure mounting type panels suitable mounting straps shall be provided.
f) Adequate interior cabling space and suitable removable cable entry plates shall be provided for
top/bottom entry of cables through glands and or conduits. Necessary number of glands to suit
the specified cable sizes shall be provided. Cable glands shall be double compression screwed on
type and made of chrome plated brass.
g) Aluminium earth bus shall be provided throughout the panel length. Earthing terminal shall be
provided at either side of the panel to suit the OWNER’s earthing conductor.
h) All sheet steel parts shall undergo rust-proofing process which should include degreassing, de-
scaling and a recognised phosphating process. The steel works shall then be painted with two
coats of zinc chromate primer and two coats of final stove enamelled finish paint of colour. For
chemical/corrosive areas, epoxy paint shall be used.
7.1.1. BUSBARS
a) Busbars shall be of copper, unless otherwise specified.
b) Busbars shall be provided with minimum clearances in air.
c) Busbars shall be adequately sized for the continuous current rating such that the maximum
temperature of the busbars, busbar risers/droppers and contacts does not exceed 85˚ C under site
reference temperature. Busbar shall be covered with heat shrinkable coloured PVC sleeves.
d) The busbars, busbar connections and busbar supports shall have sufficient strength to withstand
thermal and electro-mechanical stresses of the fuse/ MCBs let through / cut-off current associated
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 14 of 18
with the specified short-circuit level of the system.
e) Busbar supports shall be made from suitable insulating material such as Hylam sheets, glass
reinforced moulded plastic materials, or cast resin. Separate supports shall be provided for each
phase of the busbars. If a common support is provided for all three phases, antitracking barriers
shall be incorporated.
7.1.2. BOARD MOUNTED COMPONENTS
a) MCCB/MCBs/ELCBs shall be hand operated, air break, quick make, quick break type conforming
to applicable standards.
b) The feeders shall be provided with MCB/MCCB for overload/short circuit protection. ELCBs of
suitable rating shall be provided for earth leakage protection.
c) Switch shall have provision for locking in both fully open and closed positions. MCBs/ELCBs
shall be provided with locking facility.
7.1.3. Indicating Instruments and Meters
a) Ammeters of appropriate rating, size and type along with CTs, wherever necessary, along with
ON/OFF indicating lamps shall be provided on the front door of the distribution panel.
a) Instruments shall be of minimum 96 mm square size, shall have provision for zero adjustment
outside the cover and black numerals on white dial.
b) Ammeter/voltmeter selector switches having 3 positions and off, with stay put contacts rated 10
A shall be provided when specified.
c) Potential fuses shall be provided at the tap off point from the busbars for the voltmeters.
7.1.4. Instrument Transformers
a) Current and voltage transformers shall be of the dry type, of metering accuracy class 1.0. Unless
otherwise specified, it shall be the responsibility of the VENDOR to ensure that the VA burden
of the instrument transformer is adequate for the meters connected to it.
b) Test links shall be provided in both secondary leads of the CTs to easily carry out current and
phase angle measurement tests. Facilities shall be provided for short circuiting and grounding
the CTs at the terminal blocks.
c) Voltage transformers shall be provided with suitably rated primary and secondary fuses.
7.1.5. Internal Wiring
a) LDB and panels shall be supplied completely wired, ready for the operation. Wiring shall be
carried out with 1100 V grade, PVC insulated, stranded copper conductors. Conductors of
adequate sizes shall be used to suit the rated circuit current.
b) Engraved identification ferrules, marked to correspond with the wiring diagram shall be fitted at
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 15 of 18
both ends of each wire.
c) All wiring shall be terminated on terminal blocks. Terminal blocks shall be one piece moulded,
650 V, of reputed make, preferably stud type for higher current ratings such that wires are
connected by cable lugs and complete with nuts and washers. Terminals shall be adequately
rated for the circuit current, the minimum rating shall be 20 A.
d) Terminals for circuits with voltage exceeding 125 V shall be shrouded.
e) Terminals shall be numbered and provided with identification strip for identification of the
circuit and additional 20% spares shall be provided.
7.1.6. Labels & Diagram Plate
a) All door mounted equipment as well as equipment mounted inside the boards/panels shall be
provided with individual labels with equipment designation/rating. Also the boards/panels shall
be provided on the front with a label engraved with the designation of the board/panel as
furnished by the OWNER.
b) Labels shall be made of non rusting metal, 3 ply lamicoid or engraved PVC.
c) Inside the door of lighting panels a circuit diagram/description shall be fixed for reference and
identification
7.1.7. RECEPTACLE UNITS
a) The indoor type receptacles units shall consist of socket outlet with associated switch, neon
indicating lamp and plug. The socket outlet and switch or MCB shall be flush mounted within a
stove enamelled/ galvanised 1.2 mm thick CRCA sheet steel enclosure with perspex/insulating
cover. The box may be recessed into or mounted on a wall as per requirements of project layouts.
b) The outdoor type receptacles shall be housed in a 2 mm thick CRCA sheet steel epoxy painted
enclosure with gasketed, hinged door having locking arrangement. The enclosure shall be with
rain canopy and removable gland plate entry from bottom. Composite receptacle with switch
modules housed in a box shall be with degree of protection IP 66.
c) The receptacle units shall be suitable for 240 V, 2 phase, 50Hz supply.
d) Convenient receptacles shall be associated with a switch/MCB of same current rating and the
receptacle shall become live only when the associated switch/MCB is in “ON” position.
e) The plugs shall be provided with cord grips to prevent strain and damage to conductors/wires at
connection and entry points.
f) The types and current ratings of receptacle units shall be as indicated in the Project layout
drawing/price schedule and they shall conform to the applicable standards.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 16 of 18
7.1.8. FLAMEPROOF EQUIPMENT
a) The enclosure of all flameproof equipment for use in hazardous areas where gases/vapours of
Group I, IIA, IIB are present, shall be of cast iron/cast aluminium, stove enamel finished.
Chemical corrosion resistant epoxy finish shall be provided.
b) If the enclosures are additionally required to be weather proof, neoprene gaskets shall be
provided to make the enclosure dust and weather proof providing a degree of protection of IP
55.
c) All ferrous parts, exposed to atmosphere shall be suitably plated / galvanised.
d) All internal wiring shall be connected to terminal blocks provided in terminal enclosure on
incoming side.
e) Flameproof cable gland entries shall be provided. The number of required cable entries for
junction/terminal boxes as required for branching, terminating of cables for lighting distribution
shall be provided. All unused cable entries shall be closed by flameproof plugs.
f) Flameproof receptacle unit (socket with associated switch/MCB and plug) shall have interlocking
feature such that plug cannot be inserted or taken out with switch/MCB in “ON” position.
g) Two external earthing terminals shall be provided on the enclosure to suit the OWNER’s
specified conductor. Additionally, one internal earthing terminal shall be provided in
junction/terminal boxes.
h) Adequate mounting lugs with necessary hardware shall be provided for mounting the equipment
on wall/structure.
i) These enclosures shall have inscription warning against opening the enclosure unless the circuit
is isolated. Equipment rating and ON/OFF positions of switches/MCBs shall also be designated.
j) The BIDDER shall indicate that the enclosures have been tested and certified by relevant statutory
authorities for use in hazardous areas.
7.1.9. LIGHTING WIRES
a) The wires for wiring in lighting system shall be 1100 V, 1 core, PVC insulated, unarmoured with
stranded copper conductors. The wires shall conform to the applicable standards.
b) The minimum area of conductors shall be 2.5 sq.mm for light fittings and 5A receptacles and 4
sq.mm for receptacles rated 15 A.
c) The wires shall be coded white for phase/positive of DC and black for neutral/ negative of DC.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 17 of 18
8. LIGHTING FIXTURES (LUMINAIRES)
8.1 TECHNICAL REQUIREMENTS
8.1.1. General
a) All the light fixtures and junction boxes along with accessories to be used in hazardous area shall be
certified by BASEEFA, UL, FM, CMRI, PESO or an Internationally Recognised Certification Agency
for the area and service in which they could be used.
b) All the light fixtures and junction boxes along with accessories shall have weatherproof enclosures
(IP-55/NEMA-4 or equivalent) and suitable for the hazard in which they are installed. The
temperature class shall be at least T3 as per IEC, unless otherwise specified.
c) The glass/ polycarbonate used shall be clear and toughened type suitable for use under conditions
involving exceptional risk of mechanical damage. The light fixtures shall have glass sealed into
retaining ring, which, in turn, shall be secured to the body.
d) The lighting fixtures shall be suitable for mounting on poles/ceilings/columns. Suitable fastening
devices such as Clamps/brackets etc required for installation, shall also be supplied.
e) All the lighting fixtures/junction boxes shall be provided with an internal earthing terminal.
f) Special tools, if required, shall also be provided.
g) All the fixture nameplates shall bear the stamp of certifying agency.
The LED fixtures shall be high efficiency, durable, rugged, with minimum lumen depreciation and
designed for ambient temperature of 41 deg C. The fixtures shall have been type tested in a NVLAP
(National Voluntary Laboratory Accreditation Program, USA) accredited laboratory
LM-79 (IESNA) for Total Luminous Flux
– Luminous Intensity Distribution
– Electrical Power Characteristics
– Luminous Efficacy (calculated)
– Color Characteristics
Minimum power factor of LED fixtures shall be 0.9. Light colour shall be white and CRI shall be
minimum 75.
8.2 Normal Light fixtures
These shall be suitable for operation on 240V, 2-Phase, 50 Hz, supply and shall be suitable for the
classified area in which they are installed. Fixture shall have double side entry suitable for armoured
copper cable complete with termination accessories. Spare plug shall be provided to block the
unused entry. The terminals shall be anti-loosening non sparking type and in adequate numbers to
terminate two cables.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -ND-E-SP-9009
Rev : A
Page : 18 of 18
8.3 D.C. Emergency Light fixtures
Fixtures shall be suitable for use in Zone 2 area. Fixtures shall have double side entry suitable for
copper cable complete with flame proof termination accessories. Spare explosion proof plug shall be
supplied to block unused entry. The terminal block shall be adequate to terminate two cables.
8.4 Cable Glands and lugs
a) Explosion proof, double compression type, nickel/chromium plated brass cable glands shall be
provided for all Zone 2 equipment.
b) Double compression type nickel/chromium plated brass cable glands shall be provided for all Div. -
2 or Zone 2 equipment.
c) The lugs provided shall be tinned copper crimping type.
9. TESTING AND INSPECTION
Testing and inspection of light fixtures and Junction boxes shall include but not necessarily be
limited to the following:
- A visual inspection shall be made to ensure that the finishing and workmanship are up to the
mark.
- Company reserves the right to witness the final testing and inspection. Prior intimation of at
least 20 days shall be given to enable the Company to depute its representative to witness the
test.
10. PACKING AND TRANSPORT
The lighting fixtures and junction boxes along with their accessories shall be shipped to site
packed in wooden crates. They shall be wrapped with polythene sheets, before being placed in the
crates to prevent damage to finish. Crates shall have skid bottom for handling.
CREATION OF SURFACE PRODUCTION FACILITIES (OCS & GGS) AT NADUA & EAST
KHAGORIJAN
Document Title : Specification for Lighting
Fixtures and Distribution Board
Kavin Document No. : 17039-EK-E-SP-9009
A 30 NOV 2018 ISSUED FOR REVIEW DS AD MSR/MSB
REV. DATE DESCRIPTION BY
CHECKE
D
APPROVE
D
PROJECT DOCUMENTS ARE CONTROLLED DOCUMENTS.
REVISIONS ARE DENOTED IN RIGHT HAND MARGIN
COMPANY:
OIL INDIA LIMITED
EPCM CONSULTANT:
KAVIN ENGINEERING AND SERVICES PRIVATE
LIMITED
Annexure - 8
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 2 of 18
INDEX SHEET
PAGE NO. TITLE REV-A
1 COVER SHEET 30 NOV 2018
2 INDEX SHEET 30 NOV 2018
3 REVISION RECORD SHEET 30 NOV 2018
4 TABLE OF CONTENTS 30 NOV 2018
5-18
TECHNICAL SPECIFICATION FOR
LIGHTING FIXTURES AND
DISTRIBUTION BOARD
30 NOV 2018
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 3 of 18
REVISION RECORD SHEET
REV. NO. PURPOSE LIST OF PAGES UPDATED / MODIFIED SECTIONS, IF ANY
A ISSUED FOR REVIEW FIRST ISSUE
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 4 of 18
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 5
2. OBJECTIVE .................................................................................................................... 5
3. DEFINITIONS AND ABBREVIATIONS ...................................................................... 6
3.1. DEFINITIONS .................................................................................................... 6
3.2. ABBREVIATIONS .............................................................................................. 6
4. CODES AND STANDARDS ......................................................................................... 7
5. GENERAL REQUIREMENTS ...................................................................................... 12
6. SITE CONDITION ....................................................................................................... 12
7. SCOPE .......................................................................................................................... 12
8. LIGHTING FIXTURES (LUMINAIRES) ...................................................................... 17
9. TESTING AND INSPECTION .................................................................................... 18
10. PACKING AND TRANSPORT ................................................................................... 18
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 5 of 18
1. INTRODUCTION
OIL INDIA LIMITED (OIL) a Government of India Enterprise, proposes to construct two number of
Surface Production facilities primarily for separation of Oil, Gas & Water and processing of non-
associated & associated gas in its producing field at Nadua and East Khagorijan. The installation will
be constructed on Modular design concept with emphasis on skid mounted prefabricated facilities
minimizing construction work at site to the extent possible as per functional specifications of various
process/utility packages. Instead of permanent civil buildings, containerized offices/structures will be
preferred.
The East Khagorijan (GGS) field is located near Dibrugarh town in Assam at a location approximately
200m south (aerial distance) of LOC# at 27°32’N 95°09’E approx. elevation 121 M MSL. The field is
presently producing from 02 Nos. of wells through a QPS (Quick Production Setup). Considering the
potential of the field it is envisaged that Oil production is expected to rise to a level of 1000 KLPD
from 06 HP wells (02 wells + 04 future wells), 06 LP wells and 06 Non Associated Gas wells.
Associated Gas is expected to be around 0.1 MMSCMD. The East Khagorijan oil field also having the
huge amount of non-associated gas potential and it is expected to produce about 1 MMSCMD of non-
associated natural gas from this area. It is also expected that the field will produce about 800 KLPD of
water along with the 1000 KLPD of crude, so the plant design will be for handling 1800KLPD of total
well fluid Oil India Limited proposes to construct a Group Gathering Station at East Khagorijan to
cater to the production in that area.
Pipelines from Oil & Gas wells to the proposed plant and transfer lines for transporting Dry Crude,
treated Gas, treated water from the proposed plant to outside are not in the Project scope.
Procurement of LAND and construction of boundary wall in the land is not in the project scope and
will be done/ arranged by OIL separately.
KAVIN ENGINEERING AND SERVICES PRIVATE LIMITED is awarded a contract for Engineering
Procurement Construction Management to conceptualize / finalize the requirements needed for the
Oil Collection Station (OCS) at Nadua and Group Gathering Station (GGS) at East Khagorijan.
2. OBJECTIVE
This specification defines the minimum technical requirements for the design, materials, supply,
Installation, painting, testing, inspection and commissioning of LIGHTING FIXTURE AND
LIGHTING FIXTURE DISTRIBUTION BOARD system in Oil Collection Station (OCS) at Nadua and
Group Gathering Station (GGS) at East Khagorijan. VENDOR’s scope of supply shall include the
furnishing of LIGHTING FIXTURE as complete and functional unit, as described by the requisition.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 6 of 18
3. DEFINITIONS AND ABBREVIATIONS
3.1. DEFINITIONS
Company / Owner - Oil India Limited (OIL)
EPCM - Kavin Engineering and Services Private Limited
MPC - Bidder / EPC Contractor who supplies equipment / system / sub-
system in modules
Supplier / Vendor - Manufacturer / Seller / Sub-Vendor
The words “may”, “should” and “shall” have specific meanings as follows:
“May” is used where alternatives are equally acceptable.
“Should” is used where a provision is preferred.
“Shall” is used where a provision is mandatory.
3.2. ABBREVIATIONS
AC Alternating Current
ACB Air Circuit Breaker
API American Petroleum Institute
ASTM American Society for Testing of Material
BIS Bureau of Indian Standards
BS British Standard Institute
CBCT Core Balance Current Transformer
CEAR Central Electricity Authority Regulations, 2010
CMRI Central Mining Research Institute
CT Current Transformer
DC Direct Current
DGMS Director General of Mines and Safety
DOL Direct On-Line Starter
ELCB Earth Leakage Circuit Breaker
ELR Earth Leakage Relay
EPCM Engineering, Procurement, Construction Management
ESD Emergency Shut Down
FAT Factory Acceptance Test
HFFR Halogen Free Flame Retardant
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 7 of 18
HRC High Rupturing Capacity
HVAC Heating Ventilation Air Conditioning
IEC International Electro Technical Council
IEEE Institution of Electrical and Electronics Engineers
IP Ingress Protection
IRP Interposing Relay Panel
ITP Inspection and Test Plan
LV Low Voltage
MCB Miniature Circuit Breaker
MCC Motor Control Centre
MCCB Moulded Case Circuit Breaker
NEC National Electric Code (USA)
NFPA National Fire Protection Association
OISD Oil Industry Safety Directorate (Elect. Std.)
OMR Oil Mines Regulations, 2014
UPS Uninterrupted Power Supply
4. CODES AND STANDARDS
i. The equipment shall comply with the requirements of the latest revision of the following standards
issued by BIS unless otherwise specified.
CODES STANDARDS
IS 5 Colors for ready mixed paints and enamels
IS -772 (Part-1) (2nd rev.) AC electricity meters-general requirements
IS -1248 (1st rev.) Direct acting electrical indicating instruments
IS-1646 Code of practice for the fire safety of buildings – Electrical
Installations
IS-1897 Copper strip for electrical purposes
IS-2189 Code of practice for selection: installation and maintenance
of automatic fire detection and alarm system
IS-2705 Current transformers
IS 2854 Method for determining the proof and the comparative
tracking indices of solid insulating materials.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 8 of 18
IS-3034 Code of practice for the fire safety of industrial buildings –
Electrical generator and distribution stations
IS-3043 Code of practice for Earthing
IS-3156 Voltage transformers
IS-3231 Electrical relays for power systems protection.
IS-3618 Phosphate treatment of iron & steel for protection against
corrosion
IS-3646 Code of practice for Interior Illumination
IS-3716 Application guide for Insulation Coordination
IS-4051 Code of practice for the installation and maintenance of
electrical equipment in mines
IS-4171 Copper rods and bars for general engineering purpose
IS-5216 Guide for safety procedures and practices in electrical
work
IS-5571 Guide for selection of electrical equipment for hazardous
area
IS-5572 Classification of Hazardous Area (other than mines)
having flammable gases and vapours for electrical
installation
IS 5780 Electrical apparatus for explosive gas atmospheres
IS 5831 PVC insulation and sheath of electric cables
IS-6005 Code of practice of phosphating of iron &Steel
IS 6381 Electrical Apparatus For Explosive Gas Atmospheres -
Increased Safety 'E'
IS-6665 Code of practice for industrial Lighting
IS 7098-Part-1 Crosslinked polyethylene insulated PVC sheathed cables:
Part 1 for working voltage upto and including 1100 V
IS-7689 Guide for control of undesirable static electricity
IS 7693 Electrical Apparatus for Explosive Gas Atmospheres - Oil-
immersion "o"
IS 7724 Electrical Apparatus for Explosive Gas Atmospheres -
Powder Filling "q"
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 9 of 18
IS-7752 Guide for improvement of power factor- consumer
installations
IS-8478 Application guide for on load tap changers
IS-8623 Factory built assemblies of switchgear & control gear for
voltages up to and including 1000V AC and 1200V DC;
particular requirements for bus-bar trunking systems.
IS-9676 Reference ambient temperature for electrical equipment
IS-10028 Code of practice for selection, installation and maintenance
for transformer
IS-10118 Code of practice for selection, installation and maintenance
for switchgear and control gear
IS 10810 Methods of test for cables
IS-11353 Guide for uniform system marking & identification of
conductors and apparatus terminals.
IS-12360 Voltage bands for electrical installations including
preferred voltages and frequencies
IS-13234 Guide for short circuit calculations in the three phase AC
system
IS- 13235 Calculation of the effects of Short- Circuit Currents
IS-13408-1 Code of practices for the selection, installation and
maintenance of electrical apparatus for use in potentially
explosive atmospheres
IS-13947 (Part 4 – Part 5) LV switchgear and control gear
IS-15142 Guide to the use of electrical apparatus for potentially
explosive atmospheres in the presence of combustible
dusts
IS-16102 Self Ballasted LED Lamps for General Lighting Services
IS-16103 DC or AC Supplied Electronic Controlgear for LED
Modules – Performance Requirement
IS-16104 LED Modules for General Lighting
IS / IEC 60529 Degree of protection provided by enclosures (IP Code)
IS/IEC- 60947 Low voltage switchgear and controlgear : All parts
IS/IEC 60079-0 Electrical Apparatus for explosive gas atmospheres –
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 10 of 18
General requirements
IS/IEC 60079-1 Equipment protection flameproof enclosures “d”
IEC 60079-5 Equipment Protection by Powder filling “q”
IEC 60079-6 Equipment Protection by Oil immersion “o”
IEC 60079-7 Equipment Protection by Increased Safety Type “e”
IEC 60079-11 Equipment Protection by Intrinsic safety “I”
IEC 60079-12 With air according to their maximum experimental safe
gaps and minimum igniting currents
IS/IEC 60079-15 Electrical apparatus for explosive gas atmosphere –
construction, test and making of type of protection “n‟
electrical apparatus
IEC 60228 Specification for conductor of insulated cables
IEC 60287 Electric cables - Calculation of the current rating (Current
rating equations (100% load factor) and calculation of
losses)
IEC 60502-1 Power cables with extruded insulation and their
accessories for rated voltages from 1kV (Um=1.2kV) up to
30kV (Um=36kV)
IEC 60885 Electrical test methods for electric cables
OISD-STD-110 Recommended Practices on Static Electricity
OISD-STD-113 Classification of Area for Electrical Installations at
Hydrocarbon processing and handling Facilities
OISD-GDN-115 Guidelines on Fire Fighting Equipment and Appliances in
Petroleum Industry
OISD-STD-116 Fire Protection Facilities for Petroleum Refineries and
Oil/Gas Processing Plants
OISD-STD-117 Fire protection Facilities for Petroleum Depots, Terminals,
Pipeline Installations and Lube Oil Installations
OISD-STD-118 Layouts for Oil and Gas installations
OISD-STD-137 Inspection of Electrical Equipment
OISD-RP-146 Preservation of Idle Electrical Equipment
OISD-RP-147 Inspection and Safe Practices during electrical installation
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 11 of 18
OISD-RP-148 Inspection & Safe Practices during overhauling Electrical
Equipment
OISD-RP-149 Design Aspects for Safety in Electrical System
OISD-STD-163 Process Control Room Safety
OISD STD-173 Fire Protection System for Electrical Installations
OISD-STD-180 Lightning Protection (OISD - GDN – 180)
OISD-STD-189 Standard on Fire Fighting Equipment for Drilling Rigs,
Work Over Rigs and production Installations.
ii. In case of imported equipment standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
iii. The equipment shall also conform to the provisions of Indian Electricity rules and other statutory
regulations currently in force in the country.
iv. In case Indian standards are not available for any equipment, standards issued by IEC / BS / VDE /
IEEE / NEMA or equivalent agency shall be applicable.
v. In case of any contradiction between various referred standards specifications and statutory
regulations the following order of priority shall govern:
Statutory regulations
Design Basis
Equipment specification
Codes and standards
vi. STATUTORY REQUIREMENTS & APPROVALS
The designed electrical system shall confirm to latest version of statutory and government
regulations. As a minimum need to meet and fulfil the requirement of following statutory
Acts/regulations, necessary for obtaining all statutory approvals/ certificates, as required from
concerned authorities:
Indian Electricity Act.
Central Electrical Authority Regulations 2010.
The Petroleum Rules.
Petroleum and Explosives Safety Organisation.
Central Pollution Control Board Norms.
Any other applicable Rules / Regulation of central/ state/ local statutory body.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 12 of 18
5. GENERAL REQUIREMENTS
5.1. All electrical equipment and accessories / material shall be suitable for installation and operation
for onshore application.
5.2. Supplier shall ensure availability of spare parts and maintenance support services for the
offered equipment at least for 20 years from the date of supply.
5.3. Supplier shall give a notice of at least one-year to the end user of equipment and EPCM
CONSULTANT contractor before phasing out the product/spares to enable the end user for
placement of order for spares and services.
The electrical system shall be designed to provide:
Safety to personnel and equipment both during operation & maintenance..
Reliability of service
Minimal Fire Risk
Ease of maintenance and convenience of operation
Automatic protection of electrical equipment through automatic relaying system
Electrical supply to equipment and machinery within the design operating limits.
Adequate provision for future extension and modification
Suitability or applicable environmental factors.
6. SITE CONDITION
All electrical equipment and accessories/ materials are to be suitable for installation and operation
under dusty, humid, corrosive and hostile environment with special degree of hazards. Refer to
“17039-EK-P-GD-1002, Site Conditions and available utilities” for details.
7. SCOPE
7.1 Lighting Distribution Board (LDB) And Lighting Panels
a) LDB and panels shall be of sheet steel enclosed and shall be fully dust and vermin proof,
providing a degree of protection of IP 52 for busbars, incoming and outgoing feeding
compartment and IP 42 for enclosure for transformer. Outdoor panels shall in addition be
completely weather-proof with a sloping canopy for protection against rain and providing a
degree of protection of IP 55. The sheet steel used shall be cold rolled and 2 mm thick.
b) All boards and panels shall be provided with hinged doors for access to equipment. Doors shall
be gasketted all round with neoprene gaskets. The lighting distribution boards shall be either
wall mounted/ stool mounted or floor mounted depending upon the dimension of DB and shall
be provided with MCCB for incomer and MCBs + ELCB for outgoing feeders. The hinged door of
incomer shall be interlocked so as to prevent opening of the door when the switch is ON and to
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 13 of 18
prevent closing of the switch with the door not fully closed. However, a device for bypassing the
door interlock shall be provided to enable the operation of the switch with the door open, when
necessary, for examination/maintenance. For wall mounting lighting panels when provided with
ELCBs and MCBs a hinged, latched front door shall be provided with key-locking facility and a
slotted Bakelite sheet inside. Only the ELCBs/MCBs operating knobs shall project out of the
bakelite sheet slots for safe operation and neat appearance.
c) Outdoor LDBs for street lighting/area lighting shall have ON/OFF operation through real time
based timer control in addition to manual control. In this case incomer to LDB shall have
suitably rated contactor in addition to MCCB and same shall be controlled by timer contacts. The
outgoing feeders of indoor LDB used for street lighting/area lighting shall have dedicated timer
controlled contactors in addition to MCB
d) All accessible live connection/metals shall be shrouded and it shall be possible to change
individual fuses, switches, MCCB / MCBs from the front of LDB without danger of contact with
live parts.
e) For floor mounting type LDB, adequately sized mounting channels shall be supplied and for
wall/column/structure mounting type panels suitable mounting straps shall be provided.
f) Adequate interior cabling space and suitable removable cable entry plates shall be provided for
top/bottom entry of cables through glands and or conduits. Necessary number of glands to suit
the specified cable sizes shall be provided. Cable glands shall be double compression screwed on
type and made of chrome plated brass.
g) Aluminium earth bus shall be provided throughout the panel length. Earthing terminal shall be
provided at either side of the panel to suit the OWNER’s earthing conductor.
h) All sheet steel parts shall undergo rust-proofing process which should include degreassing, de-
scaling and a recognised phosphating process. The steel works shall then be painted with two
coats of zinc chromate primer and two coats of final stove enamelled finish paint of colour. For
chemical/corrosive areas, epoxy paint shall be used.
7.1.1. BUSBARS
a) Busbars shall be of copper, unless otherwise specified.
b) Busbars shall be provided with minimum clearances in air.
c) Busbars shall be adequately sized for the continuous current rating such that the maximum
temperature of the busbars, busbar risers/droppers and contacts does not exceed 85˚ C under site
reference temperature. Busbar shall be covered with heat shrinkable coloured PVC sleeves.
d) The busbars, busbar connections and busbar supports shall have sufficient strength to withstand
thermal and electro-mechanical stresses of the fuse/ MCBs let through / cut-off current associated
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 14 of 18
with the specified short-circuit level of the system.
e) Busbar supports shall be made from suitable insulating material such as Hylam sheets, glass
reinforced moulded plastic materials, or cast resin. Separate supports shall be provided for each
phase of the busbars. If a common support is provided for all three phases, antitracking barriers
shall be incorporated.
7.1.2. BOARD MOUNTED COMPONENTS
a) MCCB/MCBs/ELCBs shall be hand operated, air break, quick make, quick break type conforming
to applicable standards.
b) The feeders shall be provided with MCB/MCCB for overload/short circuit protection. ELCBs of
suitable rating shall be provided for earth leakage protection.
c) Switch shall have provision for locking in both fully open and closed positions. MCBs/ELCBs
shall be provided with locking facility.
7.1.3. Indicating Instruments and Meters
a) Ammeters of appropriate rating, size and type along with CTs, wherever necessary, along with
ON/OFF indicating lamps shall be provided on the front door of the distribution panel.
a) Instruments shall be of minimum 96 mm square size, shall have provision for zero adjustment
outside the cover and black numerals on white dial.
b) Ammeter/voltmeter selector switches having 3 positions and off, with stay put contacts rated 10
A shall be provided when specified.
c) Potential fuses shall be provided at the tap off point from the busbars for the voltmeters.
7.1.4. Instrument Transformers
a) Current and voltage transformers shall be of the dry type, of metering accuracy class 1.0. Unless
otherwise specified, it shall be the responsibility of the VENDOR to ensure that the VA burden
of the instrument transformer is adequate for the meters connected to it.
b) Test links shall be provided in both secondary leads of the CTs to easily carry out current and
phase angle measurement tests. Facilities shall be provided for short circuiting and grounding
the CTs at the terminal blocks.
c) Voltage transformers shall be provided with suitably rated primary and secondary fuses.
7.1.5. Internal Wiring
a) LDB and panels shall be supplied completely wired, ready for the operation. Wiring shall be
carried out with 1100 V grade, PVC insulated, stranded copper conductors. Conductors of
adequate sizes shall be used to suit the rated circuit current.
b) Engraved identification ferrules, marked to correspond with the wiring diagram shall be fitted at
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 15 of 18
both ends of each wire.
c) All wiring shall be terminated on terminal blocks. Terminal blocks shall be one piece moulded,
650 V, of reputed make, preferably stud type for higher current ratings such that wires are
connected by cable lugs and complete with nuts and washers. Terminals shall be adequately
rated for the circuit current, the minimum rating shall be 20 A.
d) Terminals for circuits with voltage exceeding 125 V shall be shrouded.
e) Terminals shall be numbered and provided with identification strip for identification of the
circuit and additional 20% spares shall be provided.
7.1.6. Labels & Diagram Plate
a) All door mounted equipment as well as equipment mounted inside the boards/panels shall be
provided with individual labels with equipment designation/rating. Also the boards/panels shall
be provided on the front with a label engraved with the designation of the board/panel as
furnished by the OWNER.
b) Labels shall be made of non rusting metal, 3 ply lamicoid or engraved PVC.
c) Inside the door of lighting panels a circuit diagram/description shall be fixed for reference and
identification
7.1.7. RECEPTACLE UNITS
a) The indoor type receptacles units shall consist of socket outlet with associated switch, neon
indicating lamp and plug. The socket outlet and switch or MCB shall be flush mounted within a
stove enamelled/ galvanised 1.2 mm thick CRCA sheet steel enclosure with perspex/insulating
cover. The box may be recessed into or mounted on a wall as per requirements of project layouts.
b) The outdoor type receptacles shall be housed in a 2 mm thick CRCA sheet steel epoxy painted
enclosure with gasketed, hinged door having locking arrangement. The enclosure shall be with
rain canopy and removable gland plate entry from bottom. Composite receptacle with switch
modules housed in a box shall be with degree of protection IP 66.
c) The receptacle units shall be suitable for 240 V, 2 phase, 50Hz supply.
d) Convenient receptacles shall be associated with a switch/MCB of same current rating and the
receptacle shall become live only when the associated switch/MCB is in “ON” position.
e) The plugs shall be provided with cord grips to prevent strain and damage to conductors/wires at
connection and entry points.
f) The types and current ratings of receptacle units shall be as indicated in the Project layout
drawing/price schedule and they shall conform to the applicable standards.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 16 of 18
7.1.8. FLAMEPROOF EQUIPMENT
a) The enclosure of all flameproof equipment for use in hazardous areas where gases/vapours of
Group I, IIA, IIB are present, shall be of cast iron/cast aluminium, stove enamel finished.
Chemical corrosion resistant epoxy finish shall be provided.
b) If the enclosures are additionally required to be weather proof, neoprene gaskets shall be
provided to make the enclosure dust and weather proof providing a degree of protection of IP
55.
c) All ferrous parts, exposed to atmosphere shall be suitably plated / galvanised.
d) All internal wiring shall be connected to terminal blocks provided in terminal enclosure on
incoming side.
e) Flameproof cable gland entries shall be provided. The number of required cable entries for
junction/terminal boxes as required for branching, terminating of cables for lighting distribution
shall be provided. All unused cable entries shall be closed by flameproof plugs.
f) Flameproof receptacle unit (socket with associated switch/MCB and plug) shall have interlocking
feature such that plug cannot be inserted or taken out with switch/MCB in “ON” position.
g) Two external earthing terminals shall be provided on the enclosure to suit the OWNER’s
specified conductor. Additionally, one internal earthing terminal shall be provided in
junction/terminal boxes.
h) Adequate mounting lugs with necessary hardware shall be provided for mounting the equipment
on wall/structure.
i) These enclosures shall have inscription warning against opening the enclosure unless the circuit
is isolated. Equipment rating and ON/OFF positions of switches/MCBs shall also be designated.
j) The BIDDER shall indicate that the enclosures have been tested and certified by relevant statutory
authorities for use in hazardous areas.
7.1.9. LIGHTING WIRES
a) The wires for wiring in lighting system shall be 1100 V, 1 core, PVC insulated, unarmoured with
stranded copper conductors. The wires shall conform to the applicable standards.
b) The minimum area of conductors shall be 2.5 sq.mm for light fittings and 5A receptacles and 4
sq.mm for receptacles rated 15 A.
c) The wires shall be coded white for phase/positive of DC and black for neutral/ negative of DC.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 17 of 18
8. LIGHTING FIXTURES (LUMINAIRES)
8.1 TECHNICAL REQUIREMENTS
8.1.1. General
a) All the light fixtures and junction boxes along with accessories to be used in hazardous area shall be
certified by BASEEFA, UL, FM, CMRI, PESO or an Internationally Recognised Certification Agency
for the area and service in which they could be used.
b) All the light fixtures and junction boxes along with accessories shall have weatherproof enclosures
(IP-55/NEMA-4 or equivalent) and suitable for the hazard in which they are installed. The
temperature class shall be at least T3 as per IEC, unless otherwise specified.
c) The glass/ polycarbonate used shall be clear and toughened type suitable for use under conditions
involving exceptional risk of mechanical damage. The light fixtures shall have glass sealed into
retaining ring, which, in turn, shall be secured to the body.
d) The lighting fixtures shall be suitable for mounting on poles/ceilings/columns. Suitable fastening
devices such as Clamps/brackets etc required for installation, shall also be supplied.
e) All the lighting fixtures/junction boxes shall be provided with an internal earthing terminal.
f) Special tools, if required, shall also be provided.
g) All the fixture nameplates shall bear the stamp of certifying agency.
The LED fixtures shall be high efficiency, durable, rugged, with minimum lumen depreciation and
designed for ambient temperature of 41 deg C. The fixtures shall have been type tested in a NVLAP
(National Voluntary Laboratory Accreditation Program, USA) accredited laboratory
LM-79 (IESNA) for Total Luminous Flux
– Luminous Intensity Distribution
– Electrical Power Characteristics
– Luminous Efficacy (calculated)
– Color Characteristics
Minimum power factor of LED fixtures shall be 0.9. Light colour shall be white and CRI shall be
minimum 75.
8.2 Normal Light fixtures
These shall be suitable for operation on 240V, 2-Phase, 50 Hz, supply and shall be suitable for the
classified area in which they are installed. Fixture shall have double side entry suitable for armoured
copper cable complete with termination accessories. Spare plug shall be provided to block the
unused entry. The terminals shall be anti-loosening non sparking type and in adequate numbers to
terminate two cables.
CREATION OF SURFACE PRODUCTION FACILITIES
(OCS & GGS) AT NADUA & EAST KHAGORIJAN
Specification for Lighting Fixtures and
Distribution Board
Doc No : 17039 -EK-E-SP-9009
Rev : A
Page : 18 of 18
8.3 D.C. Emergency Light fixtures
Fixtures shall be suitable for use in Zone 2 area. Fixtures shall have double side entry suitable for
copper cable complete with flame proof termination accessories. Spare explosion proof plug shall be
supplied to block unused entry. The terminal block shall be adequate to terminate two cables.
8.4 Cable Glands and lugs
a) Explosion proof, double compression type, nickel/chromium plated brass cable glands shall be
provided for all Zone 2 equipment.
b) Double compression type nickel/chromium plated brass cable glands shall be provided for all Div. -
2 or Zone 2 equipment.
c) The lugs provided shall be tinned copper crimping type.
9. TESTING AND INSPECTION
Testing and inspection of light fixtures and Junction boxes shall include but not necessarily be
limited to the following:
- A visual inspection shall be made to ensure that the finishing and workmanship are up to the
mark.
- Company reserves the right to witness the final testing and inspection. Prior intimation of at
least 20 days shall be given to enable the Company to depute its representative to witness the
test.
10. PACKING AND TRANSPORT
The lighting fixtures and junction boxes along with their accessories shall be shipped to site
packed in wooden crates. They shall be wrapped with polythene sheets, before being placed in the
crates to prevent damage to finish. Crates shall have skid bottom for handling.
SCHEDULE OF RATES/PRICES (SOR/P) FOR ELECTRICAL PACKAGE
Note:
1. Price quoted 1, 2, 3 and 4 above is exclusive of GST, which is extra as applicable
2. The total price(1+2+3+4) in this Schedule of Rates/Prices (SOR/P) shall be considered for evaluation of the price bid.
DESCRIPTION PRICE (INR)
1. Nadua Electrical Package "Annexure-II A" Price covering Engineering, Supply, Installation, Testing and
Commissioning including, packing/forwarding on Ex Work’s basis.
2. East Khagorijan Electrical Package "Annexure-II B" Price covering Engineering, Supply, Installation, Testing and Commissioning including, packing/forwarding on Ex Work’s basis.
3. Nadua Electrical Package Freight & Insurance Charges for delivery & Unloading at site Price
4. East Electrical Package Freight & Insurance Charges for delivery & Unloading at site Price
TOTAL (1+2+3+4)
GRAND TOTAL PRICE
Annexure - 9