Oil and Gas Production and Exploration, Part II · 1 1 Oil and Gas Production and Exploration, Part...
Transcript of Oil and Gas Production and Exploration, Part II · 1 1 Oil and Gas Production and Exploration, Part...
1
1
Oil and Gas Production and Exploration, Part II
American Translators Association52th Annual ConferenceBoston, October 26, 2011
Presenter: Steven Marzuola
2
Progression
2
3
Water depths
Shallow
Up to 1000 / 1500 ft deep
Christmas tree on platform (“dry tree”)
Deepwater
Christmas tree on bottom(subsea, “wet tree”)
4
Offshore “building blocks”
3
5
Shallowest water
Lake Maracaibo, Venezuela
Louisiana
6
Jackup drilling rigsMobile, flexibleUsually up to 400 ft water depth
Can handle surface trees on permanent platform, OR subsea trees
4
7
Conventional platform
Depths up to 1000 feet
Wells drilled directionally
Surface-type wellheads
Drilling equipment often permanent
Source: California Department of Conservation - www.conservation.ca.gov
8
Semi SubmersibleMore stable in rough weatherSlow transit speed
DrillshipFaster deploymentLess stableIncreased Capacities
Liquids, bulk material, personnel
Deepwater drilling rigs
5
9
Marine Riser
10
System used to keep a positive pulling force on the marine riser independent of the movements of the rig.If there was no tensioner system in place every time that the rig moved downward, the riser would buckle
Riser tensioner system
6
11
Subsea BOP stack
12
Anchor handling vesselsMoored (anchors)
Reduced operating cost (fuel)No “Drive-Off” (loss of control)No “Drift-Off”
7
13
Dynamic Positioning (DP)
Thrusters Any water depthFaster to mobilize/demobilize, avoid bad weatherNo anchors to handle, drag on bottomExpensive to operate (fuel)
Not shown: “Built-in” type
14
Unmanned submarineControlled from rig with tether
Multiple functionsVideo
Operate wellheads or BOP Stack
Classed by horsepower, number of actuators
Remotely Operated Vehicles (ROVs)
8
15
TLP - Tension Leg PlatformSemisubmersible, moored to seafloor Production through subsea manifoldsMore stable in rough weatherReduced transit speed Onboard drilling and production facilities
Production facilities
16
SPARSLarge submerged cylinder, moored to seafloorStable PlatformSurface BOP Stacks / treesWeather has less impact on operationsUsually Reduced Capacities
Liquids Bulk MaterialPersonnel
Production facilities (cont.)
9
17
Pipelay vessels
S-Lay
Shallower water
J-Lay
Deeper water
18
Subsea pipeline - complications
Concrete coating:
Reel-lay
10
19
Up to $550,000 per day
Total operating costsUp to $1,000,000 per day =
$41,600 per hour$694 per minute$11.57 per second
Rig costs
20
Subsalt
11
21
Particular problems with salt
Salt “blurs” seismic imagesRequired advances in seismic technologyDrilling problems
Plastic salt movementAbnormal pressuresLost circulationShale problems
22
• Installed in 1996
• Water depth 303 meters
• Overall height 472 meters
• Weighs 656,000 tons.
• Produces gas from 40 wells
• Towed 200 km to the Norwegian Sea. Tallest structure ever moved by man.
Norske Shell “Troll A”
12
23
FPSO - Floating Production Storage, Offtake
24
ChevronTexaco “Genesis”
13
25
Independence Trail Hub
Located 200 miles SE of New Orleans. Anchored in 7920 ft of waterCost $385 million. Service life of 20 yearsReceives flow from subsea wells up to 30 miles away, connected via 176 miles of flowlinesPeak production 850 million cubic feet of gas per daySent to shore via 24” pipeline (cost $280 million)Current price of $4.30 / MCF, provides cash flow of $3.5 million per day
26
Chevron “Typhoon”
• Installed May 2001
• Capsized during Hurricane Rita, drifted 70 miles away –September 2004
14
27
Project lifecycleConsequence of size, expense, complexity
PhasesConceptualPre-FEEDFEED (Front End Engineering Design)Detailed EngineeringConstruction, Installation, Commissioning
28
Factors that influence projects
Long lead times – 1-2 years for major equipment, longer for vessels and platformsPlans change due toMarket pricesInterest ratesOther opportunities, access via pipelines built for nearby fieldsMergers
15
29
Peak Oil, or Hubbert’s Peak
M. King Hubbert - Shell geophysicist Theory: production tends to follow bell-shaped curve. Can be predicted in advance.Production increases early due to discoveries and new infrastructure. Later declines due to depletion.
30
Peak Oil, or Hubbert’s Peak (cont)
In 1956, Hubbert predicted peak of USA production late 1960s - early 1970s.Controversial, but proven right by 1976. Actual peak was in 1970.Is it applicable to world production?Rapidly growing demand in China, IndiaNew technologies, increased depletion ratesWhat is the effect of higher real prices?
16
31
Historical oil production
32
Steven Marzuola
281-381-9337www.techlanguage.com
Houston Interpreters and Translators Association
© 2011 Steven Marzuola
American Translators Association