Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind...
Transcript of Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind...
Offshore Wind Capital Projects
An approach for Owners and Investors to deliver strong project performance
Deloitte’s Point of View
Offshore Wind Capital Projects©2019 Deloitte LLP 2Offshore Wind Capital Projects©2019 Deloitte LLP 2
The Market
Offshore Wind Capital Projects©2019 Deloitte LLP 3
Offshore wind has grown internationally, with most of the development occurring in Europe and the majority of future growth expected in Asia
Significant growth across Europe and Asia
Offshore wind cumulative capacity (global forecast) 2008-2022 (GW) segmented by continent
Source: International Renewable Energy Agency and Norwegian Energy Partners
1.4 2.1 2.9 3.55.0
6.78.0
11.012.6
16.4
19.9
23.4
26.9
30.4
33.92.9
4.5
6.2
7.9
9.6
11.3
1.42.1
3.13.8
5.3
7.2
8.5
11.7
14.4
19.3
24.7
30.1
35.6
41.0
46.4
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Europe Asia Rest of the world
Offshore Wind Capital Projects©2019 Deloitte LLP 4
Global annual expenditure for offshore wind will be approximately £33bn in 2022, with an expected £110bn spent between 2019 and 2022
Continuous investment increase
Offshore wind transaction value (global forecast) 2008-2019 (£bn) segmented by region
17.0
20.5
23.2
30.4
33.0
2018 2019 2020 2021 2022
Source: BVG associates, Statista
Offshore Wind Capital Projects©2019 Deloitte LLP 5Offshore Wind Capital Projects©2019 Deloitte LLP 5
The Challenge
Offshore Wind Capital Projects©2019 Deloitte LLP 6
Critical factors in developing / agreeing to invest in an offshore wind farm are revenue generation certainty, cost certainty and demonstration of deliverability competencies
Key challenges
Revenue generation certainty
• Wind speed assumptions
• Availability of wind turbines during Operations & Maintenance period
Cost certainty
• Risk of increase of high capital costs
− Projects at sea, increasingly offshore and potentially floating
− New technologies
− Specialised vessels
− Bespoke solutions (e.g. ports, foundations)
• Complex interfaces
• Often multiple supplier parties with implications for the owner
Demonstration of
deliverability competencies
for licencing / development
rights as well as for financing
01
02
03
Offshore Wind Capital Projects©2019 Deloitte LLP 7Offshore Wind Capital Projects©2019 Deloitte LLP 7
Deloitte’s Point Of View
Offshore Wind Capital Projects©2019 Deloitte LLP 8
We have identified 10 levers that drive project performance in offshore wind
Project Success Factors
5. Understand logistical complexities
3. Confirm critical supply chain early
1. Understand site and underlying risks
4. Build robust schedule
6. Setup appropriate project governance
7. Setup and maintain appropriate Project Controls`
8. Monitor progress through suitable reporting and proactive KPIs
9. Integrate the Operations & Maintenance Strategy across the project lifecycle
10. Develop a robust Decom./ Re-powering
strategy
2. Get procurement model right
Pre-Final Investment Decision
Project ConstructionOperations
& MaintenanceDecommission/
Re-power
Offshore Wind Capital Projects©2019 Deloitte LLP 9
Site characteristics based on accurate and dependable site information support a robust business case and reduce execution risks
Lever 1 – Understand site and underlying risks
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Context Business Case impact Execution Risk impact
Wind Speed Wind speed assumptions can vary depending on the location of the met mast and the height of the data collection point and the number of years that data have been collected for
Energy generation and hence revenue is proportionate to the wind speed. As such wind speed assumptions is the most significant parameter of the business case. If data is limited or inaccurate, there is high risk that the project’s revenue generation assumptions will be inaccurate.
Weather conditions, and most importantly wind tolerances for specific activities, determine the weather windows which allow construction to take place offshore (e.g. to lift a turbine it is necessary to have X hrsof certain wind conditions). Weather windows feed into the schedule assumptionsand as such have an impact across overall project duration, contract inter-dependencies and logistics.
Seabed Seabed considerations drive foundation and cablingspecification as well as installation activityrestrictions
Understanding ground conditions will allow appropriate specification for foundations and cabling to be defined, hence reducing the material and installation cost of over-design.
Un-identified objects on seabed have hindered projects which were mid-construction, having a significant schedule delay and cost impact. Understanding these issues early means these can be incorporated in the integrated schedule of activities from the project start.
Grid connection
Grid connectionand capacity availability is necessary to ensure energy generated can be fed to the system
Understanding thelocation and timing that the wind farm is expected to connect to the grid is vital to estimate the underlying cost to reach such connection point (e.g. Cabling) but also to evaluate the risk of delay, should a third party be required to conduct work impacting the project grid connection (e.g. Grid capacity upgrade).
Execution phase interfaces need to be considered and incorporated on the project schedule and risk assessments to ensure that the technical interfaces are properly considered and timely addressed.
Offshore Wind Capital Projects©2019 Deloitte LLP 10
There are multiple procurement models and various factors to be considered before deciding on the optimal one
Lever 2 – Get procurement model right
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
EPC Model
Developer Entity
EPC Contractor
Multi-contract model 1
Developer Entity
Design
Turbine Supply &
Install
Foundation Supply &
Install
Cable Supply & Install
Multi-contract model 2
Developer Entity
Design
Turbine Supply
Foundation Supply
Cable Supply
Turbine Install
Foundation Install
Cable Install
More common
Increasing Developer Construction Risk
Reducing Developer Project Oversight
• Internal capabilities • Willingness to take on construction interface risk vs. improved project oversight
• Wind Farm componentsrequirements vs. installation vessel specification
• Lead time of key components and spare parts strategy
• Track record of suppliers /sub-contractors
• Guarantees provided by suppliers / sub-contractors
• Maintenance requirements and alignment with O&M strategy
• Decommissioning / Re-powering considerations
CONSIDERATIONS
Offshore Wind Capital Projects©2019 Deloitte LLP 11
Identifying and confirming the critical supply chain partners can significantly de-risk the project and provide improved cost certainty
Lever 3 – Confirm critical supply chain early
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Current
Market
Lever for
success
Competent and experienced supply chain partners/ suppliers provide increased cost certainty andreduced risk profile
However, the number of such supply chain partners/ suppliers is finite (and/or it can depend on local requirements) and the offshore wind market is growing, leading to pressures in securing such contracts
Irrespective of the procurement model chosen, it is hence important that critical supply chain partners/suppliers are:
1. Identified both strategically(e.g. vessel owners) and locally (e.g. understand local government requirements and pressures to be overcome)
2. Confirmed and secured as early as possible
3. Consulted and their input is fed into the project schedule to improve its robustness
Supply
Chain
Importance
Offshore Wind Capital Projects©2019 Deloitte LLP 12
Project schedule is dependent on progress during good weather windows and on key scope interfaces, making float consideration critical to the project success
Lever 4 – Build robust schedule
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Year 1 Year 2 Year 3
Winter Spring Summer Autumn Winter Spring Summer Autumn Winter Spring Summer Autumn
Foundations installation
Cabling installation
Turbine installation
Periods of high productivity means that a relatively small delay
can have significant knock on impact on the
project
Multiple interfaces likely to be managed by the Developer, making
considerations across project float very critical
Periods of high productivitySupplier A Supplier B Supplier CInstallation
Offshore Wind Capital Projects©2019 Deloitte LLP 13
A number of logistical challenges between the manufacturing sites, construction port and installation area need to be overcome
Lever 5 – Understand logistical complexities
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Suppliers’
Manufacturing
Site(s)
Port/
Construction Site
Wind Farm/
Installation Area
Transport Installation Vessel
Balance to be achieved
• Schedule requirements vs.
Manufacturing vs. Port Site
capacities
• Port installation buffer
requirements
• Weather constraints between
Manufacturing and Port and
Port and Wind Farm
• Tidal constraints
Option 1 – Development of
individual foundation elements
aligned to individual turbine
locations
+ Material cost savings
- Logistical challenges
Option 2 – Development of
standard foundation elements
which can be used at any turbine
location
+ Reduced logistical challenges
- Material cost savings
Logistics dilemma to be
resolved:
Offshore Wind Capital Projects©2019 Deloitte LLP 14
A governance structure that provides sufficient flexibility but also maintains control at the right level will allow for an efficient and effective management of the project
Lever 6 – Setup appropriate project governance
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
• Investor requirements• Roles and
Responsibilities• Escalation Routes
• Client requirements • Reporting lines• Meetings cadence and
Terms of Reference
• Organisation structure (e.g. matrix)
• Delegated Levels of Authority
• Technology to be used
KEY CONSIDERATIONS
Steering Committee
Project Director
Project Management Engineering Procurement Commercial
Construction Project Controls Legal QHSE
Investor 1 Investor 2
Offshore Wind Capital Projects©2019 Deloitte LLP 15
Appropriate and integrated project controls will allow project to be understood and tracked effectively and risks to be escalated timely
Lever 7 – Setup and maintain appropriate Project Controls
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Scope and Change Management
Development of scope
requirements
Review and evaluation of
changes
Approval of changes and re-
baseline
Baseline set up to measure progress
against
Initiation of changes to scope
Full integration across project control areas
and alignment with reporting requirements
Schedule Management
Cost Management Risk Management
Development of initial schedule
Milestones definition and
tracking
Continuous monitoring of
schedule
Schedule integration
Critical path identification
Development of initial budget
Costs reporting
Risk mitigation measures
incorporation
Development of cost estimate
Update of forecast
Development of risk provision and
management reserve
Quantitative Risk Analysis
Schedule Risk Analysis
Monitoring of risk exposure vs.
provision & mgt. reserve
Qualitative Risk Review
Offshore Wind Capital Projects©2019 Deloitte LLP 16
Aggregation of the right, forward-looking KPIs through system generated dashboards will improve efficiency and decision making and provide a single source of the truth
Lever 8 – Monitor progress through suitable reporting and proactive KPIs
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Identify forward-looking KPI’s
Monitor project performances
Create data-informed dashboard
Insight to actionIntervention on ongoing projects & sharper project selection
Cost Schedule Risk
Forw
ard
-lookin
g d
ecis
ion m
akin
gIn
sig
ht
cre
ation
Offshore Wind Capital Projects©2019 Deloitte LLP 17
Early production of the Operations and Maintenance (O&M) strategy will allow Construction to account for it, increasing energy generation and reducing cost in the long term
Lever 9 – Integrate the Operations and Maintenance Strategy across project lifecycle
O&M interfaces across project lifecycle
Factors impacting
O&M:
• Number of turbines
• Turbine selection
• Foundation type
Factors impacting O&M:
• Port base
• Key equipment for O&M use
(e.g. turbine cranes)
• Material selection and their
design life
Factors impacting
O&M:
• Pro-active /
Re-active
• Vessel availability
• Weather
constraints
• Spare Parts
• Port base
• Vessel types depending on site and maintenance requirements
• Framework agreements with installation contractors for proactive maintenance
• Consideration of risk associated with installation contractors for proactive maintenance (e.g. other potential commitments impacting ability to serve maintenance agreement)
• Mitigation strategies for reactive maintenance and spare parts strategy
KEY DECISIONS
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Pre-Final Investment Decision
Project ConstructionOperations
& MaintenanceRe-power
Offshore Wind Capital Projects©2019 Deloitte LLP 18
A D V A N T A G E S
As projects get towards the end of their design life, determining whether they should be extended, re-powered or decommissioned becomes a key question to be answered
Lever 10 – Develop a robust Decommissioning / Re-powering strategy
Extension
Re-Powering
Decommissioning
A D V A N T A G E S D I S A D V A N T A G E S
No need for major component change
Potential for replacement of wind farm with larger turbines or like for like replacement with a lower cost
Solid assumptions on revenue generation on basis of past performance
Clean end to project lifecycle
Not easy to determine length of extension achieved, reducing confidence onbusiness case
Requirements to un-install and re-install offshore wind turbines not yet tested in the industry
Environmental / Social constraints as per project delivery
Incurring of cost without additional revenue benefit
1. Site characteristics
2. Procurement Model
3. Critical Supply Chain
4. Schedule 5. Logistics 6. Governance7. Project Controls
8. Reporting 9. O&M Strategy 10. Re-powering
Offshore Wind Capital Projects©2019 Deloitte LLP 19Offshore Wind Capital Projects©2019 Deloitte LLP - Private and Confidential 19
Why Deloitte
Offshore Wind Capital Projects©2019 Deloitte LLP 20
Deloitte provides expert advice across the lifecycle of capital projects for project owners, investors, lenders and contractors
Why Deloitte
INVESTMENT CONFIDENCE – FINANCE , FUNDING AND PROCUREMENT
Providing the confidence that the value of the organization is maximized and the right decisions are made which are strategically aligned with organizational objectives to attract investment.
COST & SCHEDULE CONFIDENCE
Providing the confidence that project’s cost and schedule during the design, engineering and construction are effectively planned, managed and controlled.
DIGITAL TRANSFORMATION
Enabling capital project organisations to adopt the latest technology innovations and develop their capability to use deep data insights and analytics for better control, efficient delivery and operations of capital projects.
DEL IVERY CONFIDENCE – GOVERNANCE, PEOPLE AND ORGANIZATION
Building an efficient and scalable organisation, robust systems and controls to improve the confidence in delivery of capital projects and operation of the asset being created.
ASSET MANAGEMENT & OPTIMISATION
Maximising asset availability, life and value for customers, shareholders and asset users.
Pre-Final Investment Decision
Project ConstructionOperations
& MaintenanceDecommission/
Re-power
Offshore Wind Capital Projects©2019 Deloitte LLP 21
Deloitte is a leading global strategic consultancy, with extensive energy and resources and construction experience
Why Deloitte
Combined Capabilities of Deloitte
We bring a unique combination of skills and assets:
E&R AND CONSTRUCTION INSIGHT
STRATEGIC LOGIC
ANALYTICS & VISUALIZATION
• Business expertise
• Proofs and empirical reasoning
• Case studies
• Designated Analytics & Information management
• Solid track record
• Market research
• Proprietary sources
• Industry
• Practitioners & Capabilities
Offshore Wind Capital Projects©2019 Deloitte LLP 22
Deloitte’s main points of contact
Why Deloitte
R O B S C O P E S
PartnerFinancial Advisory Capital ProjectsUnited Kingdom
+44 20 7007 8629
+44 7803 853955
M A R C O ’ C O N N O R
PartnerInfrastructure and Capital ProjectsUnited Kingdom
+44 20 7303 5324
+44 79766 608156
A L E X T S A R O U C H I S
Assistant DirectorFinancial Advisory Capital ProjectsUnited Kingdom
+44 20 7007 4562
+44 7775 017220
Important notice
The information contained in this document has been compiled by Deloitte LLP and includes material which may have been obtained from information provided by various sources and discussions with management but has not been verified or audited. This document also contains material proprietary to Deloitte LLP. No reliance may be placed for any purposes whatsoever on the contents of this document or on its completeness. No representation or warranty, express or implied, is given and no responsibility or liability is or will be accepted by or on behalf of Deloitte LLP or by any of its partners, members, employees, agents or any other person as to the accuracy, completeness or correctness of the information contained in this document or any other oral information made available and any such liability is expressly disclaimed.
Other than as stated below, this document and its contents are confidential and prepared solely for your information, and may not be reproduced, redistributed or passed on, directly or indirectly, to any other person in whole or in part. Therefore you should not refer to or use our name or this document for any other purpose, disclose them or refer to them in any prospectus or other document, or make them available or communicate them to any other party. If this document contains details of an arrangement that could result in a tax or National Insurance saving, no such conditions of confidentiality apply to details of that arrangement (for example, for the purpose of discussion with tax authorities). In any event, no party is entitled to rely on our documentation for any purpose whatsoever and thus we accept no liability to any other party who is shown or gains access to this document.
This document is not an offer and is not intended to be contractually binding.
In this document references to Deloitte are references to Deloitte LLP. Deloitte LLP is the United Kingdom member firm of Deloitte Touche Tohmatsu Limited (“DTTL”), a UK private company limited by guarantee, whose member firms are legally separate and independent entities. Please see www.deloitte.co.uk/about for a detailed description of the legal structure of DTTL and its member firms.
© 2019 Deloitte LLP. All rights reserved.
Deloitte LLP is a limited liability partnership registered in England and Wales with registered number OC303675 and its registered office at 2 New Street Square, London EC4A 3BZ, United Kingdom.