Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind...

23
Offshore Wind Capital Projects An approach for Owners and Investors to deliver strong project performance Deloitte’s Point of View

Transcript of Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind...

Page 1: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects

An approach for Owners and Investors to deliver strong project performance

Deloitte’s Point of View

Page 2: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 2Offshore Wind Capital Projects©2019 Deloitte LLP 2

The Market

Page 3: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 3

Offshore wind has grown internationally, with most of the development occurring in Europe and the majority of future growth expected in Asia

Significant growth across Europe and Asia

Offshore wind cumulative capacity (global forecast) 2008-2022 (GW) segmented by continent

Source: International Renewable Energy Agency and Norwegian Energy Partners

1.4 2.1 2.9 3.55.0

6.78.0

11.012.6

16.4

19.9

23.4

26.9

30.4

33.92.9

4.5

6.2

7.9

9.6

11.3

1.42.1

3.13.8

5.3

7.2

8.5

11.7

14.4

19.3

24.7

30.1

35.6

41.0

46.4

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Europe Asia Rest of the world

Page 4: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 4

Global annual expenditure for offshore wind will be approximately £33bn in 2022, with an expected £110bn spent between 2019 and 2022

Continuous investment increase

Offshore wind transaction value (global forecast) 2008-2019 (£bn) segmented by region

17.0

20.5

23.2

30.4

33.0

2018 2019 2020 2021 2022

Source: BVG associates, Statista

Page 5: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 5Offshore Wind Capital Projects©2019 Deloitte LLP 5

The Challenge

Page 6: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 6

Critical factors in developing / agreeing to invest in an offshore wind farm are revenue generation certainty, cost certainty and demonstration of deliverability competencies

Key challenges

Revenue generation certainty

• Wind speed assumptions

• Availability of wind turbines during Operations & Maintenance period

Cost certainty

• Risk of increase of high capital costs

− Projects at sea, increasingly offshore and potentially floating

− New technologies

− Specialised vessels

− Bespoke solutions (e.g. ports, foundations)

• Complex interfaces

• Often multiple supplier parties with implications for the owner

Demonstration of

deliverability competencies

for licencing / development

rights as well as for financing

01

02

03

Page 7: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 7Offshore Wind Capital Projects©2019 Deloitte LLP 7

Deloitte’s Point Of View

Page 8: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 8

We have identified 10 levers that drive project performance in offshore wind

Project Success Factors

5. Understand logistical complexities

3. Confirm critical supply chain early

1. Understand site and underlying risks

4. Build robust schedule

6. Setup appropriate project governance

7. Setup and maintain appropriate Project Controls`

8. Monitor progress through suitable reporting and proactive KPIs

9. Integrate the Operations & Maintenance Strategy across the project lifecycle

10. Develop a robust Decom./ Re-powering

strategy

2. Get procurement model right

Pre-Final Investment Decision

Project ConstructionOperations

& MaintenanceDecommission/

Re-power

Page 9: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 9

Site characteristics based on accurate and dependable site information support a robust business case and reduce execution risks

Lever 1 – Understand site and underlying risks

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Context Business Case impact Execution Risk impact

Wind Speed Wind speed assumptions can vary depending on the location of the met mast and the height of the data collection point and the number of years that data have been collected for

Energy generation and hence revenue is proportionate to the wind speed. As such wind speed assumptions is the most significant parameter of the business case. If data is limited or inaccurate, there is high risk that the project’s revenue generation assumptions will be inaccurate.

Weather conditions, and most importantly wind tolerances for specific activities, determine the weather windows which allow construction to take place offshore (e.g. to lift a turbine it is necessary to have X hrsof certain wind conditions). Weather windows feed into the schedule assumptionsand as such have an impact across overall project duration, contract inter-dependencies and logistics.

Seabed Seabed considerations drive foundation and cablingspecification as well as installation activityrestrictions

Understanding ground conditions will allow appropriate specification for foundations and cabling to be defined, hence reducing the material and installation cost of over-design.

Un-identified objects on seabed have hindered projects which were mid-construction, having a significant schedule delay and cost impact. Understanding these issues early means these can be incorporated in the integrated schedule of activities from the project start.

Grid connection

Grid connectionand capacity availability is necessary to ensure energy generated can be fed to the system

Understanding thelocation and timing that the wind farm is expected to connect to the grid is vital to estimate the underlying cost to reach such connection point (e.g. Cabling) but also to evaluate the risk of delay, should a third party be required to conduct work impacting the project grid connection (e.g. Grid capacity upgrade).

Execution phase interfaces need to be considered and incorporated on the project schedule and risk assessments to ensure that the technical interfaces are properly considered and timely addressed.

Page 10: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 10

There are multiple procurement models and various factors to be considered before deciding on the optimal one

Lever 2 – Get procurement model right

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

EPC Model

Developer Entity

EPC Contractor

Multi-contract model 1

Developer Entity

Design

Turbine Supply &

Install

Foundation Supply &

Install

Cable Supply & Install

Multi-contract model 2

Developer Entity

Design

Turbine Supply

Foundation Supply

Cable Supply

Turbine Install

Foundation Install

Cable Install

More common

Increasing Developer Construction Risk

Reducing Developer Project Oversight

• Internal capabilities • Willingness to take on construction interface risk vs. improved project oversight

• Wind Farm componentsrequirements vs. installation vessel specification

• Lead time of key components and spare parts strategy

• Track record of suppliers /sub-contractors

• Guarantees provided by suppliers / sub-contractors

• Maintenance requirements and alignment with O&M strategy

• Decommissioning / Re-powering considerations

CONSIDERATIONS

Page 11: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 11

Identifying and confirming the critical supply chain partners can significantly de-risk the project and provide improved cost certainty

Lever 3 – Confirm critical supply chain early

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Current

Market

Lever for

success

Competent and experienced supply chain partners/ suppliers provide increased cost certainty andreduced risk profile

However, the number of such supply chain partners/ suppliers is finite (and/or it can depend on local requirements) and the offshore wind market is growing, leading to pressures in securing such contracts

Irrespective of the procurement model chosen, it is hence important that critical supply chain partners/suppliers are:

1. Identified both strategically(e.g. vessel owners) and locally (e.g. understand local government requirements and pressures to be overcome)

2. Confirmed and secured as early as possible

3. Consulted and their input is fed into the project schedule to improve its robustness

Supply

Chain

Importance

Page 12: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 12

Project schedule is dependent on progress during good weather windows and on key scope interfaces, making float consideration critical to the project success

Lever 4 – Build robust schedule

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Year 1 Year 2 Year 3

Winter Spring Summer Autumn Winter Spring Summer Autumn Winter Spring Summer Autumn

Foundations installation

Cabling installation

Turbine installation

Periods of high productivity means that a relatively small delay

can have significant knock on impact on the

project

Multiple interfaces likely to be managed by the Developer, making

considerations across project float very critical

Periods of high productivitySupplier A Supplier B Supplier CInstallation

Page 13: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 13

A number of logistical challenges between the manufacturing sites, construction port and installation area need to be overcome

Lever 5 – Understand logistical complexities

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Suppliers’

Manufacturing

Site(s)

Port/

Construction Site

Wind Farm/

Installation Area

Transport Installation Vessel

Balance to be achieved

• Schedule requirements vs.

Manufacturing vs. Port Site

capacities

• Port installation buffer

requirements

• Weather constraints between

Manufacturing and Port and

Port and Wind Farm

• Tidal constraints

Option 1 – Development of

individual foundation elements

aligned to individual turbine

locations

+ Material cost savings

- Logistical challenges

Option 2 – Development of

standard foundation elements

which can be used at any turbine

location

+ Reduced logistical challenges

- Material cost savings

Logistics dilemma to be

resolved:

Page 14: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 14

A governance structure that provides sufficient flexibility but also maintains control at the right level will allow for an efficient and effective management of the project

Lever 6 – Setup appropriate project governance

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

• Investor requirements• Roles and

Responsibilities• Escalation Routes

• Client requirements • Reporting lines• Meetings cadence and

Terms of Reference

• Organisation structure (e.g. matrix)

• Delegated Levels of Authority

• Technology to be used

KEY CONSIDERATIONS

Steering Committee

Project Director

Project Management Engineering Procurement Commercial

Construction Project Controls Legal QHSE

Investor 1 Investor 2

Page 15: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 15

Appropriate and integrated project controls will allow project to be understood and tracked effectively and risks to be escalated timely

Lever 7 – Setup and maintain appropriate Project Controls

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Scope and Change Management

Development of scope

requirements

Review and evaluation of

changes

Approval of changes and re-

baseline

Baseline set up to measure progress

against

Initiation of changes to scope

Full integration across project control areas

and alignment with reporting requirements

Schedule Management

Cost Management Risk Management

Development of initial schedule

Milestones definition and

tracking

Continuous monitoring of

schedule

Schedule integration

Critical path identification

Development of initial budget

Costs reporting

Risk mitigation measures

incorporation

Development of cost estimate

Update of forecast

Development of risk provision and

management reserve

Quantitative Risk Analysis

Schedule Risk Analysis

Monitoring of risk exposure vs.

provision & mgt. reserve

Qualitative Risk Review

Page 16: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 16

Aggregation of the right, forward-looking KPIs through system generated dashboards will improve efficiency and decision making and provide a single source of the truth

Lever 8 – Monitor progress through suitable reporting and proactive KPIs

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Identify forward-looking KPI’s

Monitor project performances

Create data-informed dashboard

Insight to actionIntervention on ongoing projects & sharper project selection

Cost Schedule Risk

Forw

ard

-lookin

g d

ecis

ion m

akin

gIn

sig

ht

cre

ation

Page 17: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 17

Early production of the Operations and Maintenance (O&M) strategy will allow Construction to account for it, increasing energy generation and reducing cost in the long term

Lever 9 – Integrate the Operations and Maintenance Strategy across project lifecycle

O&M interfaces across project lifecycle

Factors impacting

O&M:

• Number of turbines

• Turbine selection

• Foundation type

Factors impacting O&M:

• Port base

• Key equipment for O&M use

(e.g. turbine cranes)

• Material selection and their

design life

Factors impacting

O&M:

• Pro-active /

Re-active

• Vessel availability

• Weather

constraints

• Spare Parts

• Port base

• Vessel types depending on site and maintenance requirements

• Framework agreements with installation contractors for proactive maintenance

• Consideration of risk associated with installation contractors for proactive maintenance (e.g. other potential commitments impacting ability to serve maintenance agreement)

• Mitigation strategies for reactive maintenance and spare parts strategy

KEY DECISIONS

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Pre-Final Investment Decision

Project ConstructionOperations

& MaintenanceRe-power

Page 18: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 18

A D V A N T A G E S

As projects get towards the end of their design life, determining whether they should be extended, re-powered or decommissioned becomes a key question to be answered

Lever 10 – Develop a robust Decommissioning / Re-powering strategy

Extension

Re-Powering

Decommissioning

A D V A N T A G E S D I S A D V A N T A G E S

No need for major component change

Potential for replacement of wind farm with larger turbines or like for like replacement with a lower cost

Solid assumptions on revenue generation on basis of past performance

Clean end to project lifecycle

Not easy to determine length of extension achieved, reducing confidence onbusiness case

Requirements to un-install and re-install offshore wind turbines not yet tested in the industry

Environmental / Social constraints as per project delivery

Incurring of cost without additional revenue benefit

1. Site characteristics

2. Procurement Model

3. Critical Supply Chain

4. Schedule 5. Logistics 6. Governance7. Project Controls

8. Reporting 9. O&M Strategy 10. Re-powering

Page 19: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 19Offshore Wind Capital Projects©2019 Deloitte LLP - Private and Confidential 19

Why Deloitte

Page 20: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 20

Deloitte provides expert advice across the lifecycle of capital projects for project owners, investors, lenders and contractors

Why Deloitte

INVESTMENT CONFIDENCE – FINANCE , FUNDING AND PROCUREMENT

Providing the confidence that the value of the organization is maximized and the right decisions are made which are strategically aligned with organizational objectives to attract investment.

COST & SCHEDULE CONFIDENCE

Providing the confidence that project’s cost and schedule during the design, engineering and construction are effectively planned, managed and controlled.

DIGITAL TRANSFORMATION

Enabling capital project organisations to adopt the latest technology innovations and develop their capability to use deep data insights and analytics for better control, efficient delivery and operations of capital projects.

DEL IVERY CONFIDENCE – GOVERNANCE, PEOPLE AND ORGANIZATION

Building an efficient and scalable organisation, robust systems and controls to improve the confidence in delivery of capital projects and operation of the asset being created.

ASSET MANAGEMENT & OPTIMISATION

Maximising asset availability, life and value for customers, shareholders and asset users.

Pre-Final Investment Decision

Project ConstructionOperations

& MaintenanceDecommission/

Re-power

Page 21: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 21

Deloitte is a leading global strategic consultancy, with extensive energy and resources and construction experience

Why Deloitte

Combined Capabilities of Deloitte

We bring a unique combination of skills and assets:

E&R AND CONSTRUCTION INSIGHT

STRATEGIC LOGIC

ANALYTICS & VISUALIZATION

• Business expertise

• Proofs and empirical reasoning

• Case studies

• Designated Analytics & Information management

• Solid track record

• Market research

• Proprietary sources

• Industry

• Practitioners & Capabilities

Page 22: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Offshore Wind Capital Projects©2019 Deloitte LLP 22

Deloitte’s main points of contact

Why Deloitte

R O B S C O P E S

PartnerFinancial Advisory Capital ProjectsUnited Kingdom

+44 20 7007 8629

+44 7803 853955

[email protected]

M A R C O ’ C O N N O R

PartnerInfrastructure and Capital ProjectsUnited Kingdom

+44 20 7303 5324

+44 79766 608156

[email protected]

A L E X T S A R O U C H I S

Assistant DirectorFinancial Advisory Capital ProjectsUnited Kingdom

+44 20 7007 4562

+44 7775 017220

[email protected]

Page 23: Offshore Wind Capital Projects - Deloitte US · 2020-05-09 · ©2019 Deloitte LLP Offshore Wind Capital Projects 8 We have identified 10 levers that drive project performance in

Important notice

The information contained in this document has been compiled by Deloitte LLP and includes material which may have been obtained from information provided by various sources and discussions with management but has not been verified or audited. This document also contains material proprietary to Deloitte LLP. No reliance may be placed for any purposes whatsoever on the contents of this document or on its completeness. No representation or warranty, express or implied, is given and no responsibility or liability is or will be accepted by or on behalf of Deloitte LLP or by any of its partners, members, employees, agents or any other person as to the accuracy, completeness or correctness of the information contained in this document or any other oral information made available and any such liability is expressly disclaimed.

Other than as stated below, this document and its contents are confidential and prepared solely for your information, and may not be reproduced, redistributed or passed on, directly or indirectly, to any other person in whole or in part. Therefore you should not refer to or use our name or this document for any other purpose, disclose them or refer to them in any prospectus or other document, or make them available or communicate them to any other party. If this document contains details of an arrangement that could result in a tax or National Insurance saving, no such conditions of confidentiality apply to details of that arrangement (for example, for the purpose of discussion with tax authorities). In any event, no party is entitled to rely on our documentation for any purpose whatsoever and thus we accept no liability to any other party who is shown or gains access to this document.

This document is not an offer and is not intended to be contractually binding.

In this document references to Deloitte are references to Deloitte LLP. Deloitte LLP is the United Kingdom member firm of Deloitte Touche Tohmatsu Limited (“DTTL”), a UK private company limited by guarantee, whose member firms are legally separate and independent entities. Please see www.deloitte.co.uk/about for a detailed description of the legal structure of DTTL and its member firms.

© 2019 Deloitte LLP. All rights reserved.

Deloitte LLP is a limited liability partnership registered in England and Wales with registered number OC303675 and its registered office at 2 New Street Square, London EC4A 3BZ, United Kingdom.