Offset Project Report Form: Ember Resources Inc. …...Ember Resources Instrument Air Conversion at...
Transcript of Offset Project Report Form: Ember Resources Inc. …...Ember Resources Instrument Air Conversion at...
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 1 of 18
Offset Project Report Form:
Ember Resources Instrument Air Conversion at Strathmore Phase 1
Project Developer:
Ember Resources Inc.
Prepared by:
Ember Resources Inc.
Reporting Period:
August 1, 2016 to Dec 31, 2017
August 20, 2018
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 2 of 18
Greenhouse Gas Assertion
Project Developer:
Ember Resources Inc.
Steve Gell, P.Eng
The Devon Tower, 800 – 400 3rd Avenue SW
Calgary, Alberta, T2P 4H2
403-698-8983
http://emberresources.com/
Project Documents:
Offset Project Report Form: Ember Resources Instrument Air Conversion at Strathmore Phase 1
Offset Project Plan Form: Ember Resources Instrument Air Conversion at Strathmore Phase 1 (July
31, 2018)
Quantification Protocol for Instrument Gas to Instrument Air Conversion in Process Control
Systems” Version 1.0, October 2009
Project Identification:
Ember Resources Instrument Air Conversion at Strathmore Phase 1
Reporting Period: August 1, 2016 to December 31, 2017
The objective of the Ember Resources Instrument Air Conversion at Strathmore Phase 1 (“The
Project”) is to reduce greenhouse gas emissions from instrumentation by converting the existing
instrument gas system used for process control at the Strathmore 09-27-024-25W4 compressor
station over to instrument air.
Latitude: 51.076
Longitude : -113.403
LSD: 09-27-024-25 W4M (located near Strathmore, AB).
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 3 of 18
Emission Reduction or Sequestration Assertion:
Vintage Gas Type Quantity (tCO2e)
2016 CO2 1.11
2016 CH4 139.56
2016 N2O 0.02
2016 Other (CO2e) -0.54
Total 2016 CO2e 140.15
Total 2016 (Rounded) CO2e 140
2017 CO2 1.90
2017 CH4 214.83
2017 N2O 0.03
2017 Other (CO2e) -0.93
Total 2017 CO2e 215.83
Total 2017 (Rounded) CO2e 215
Total for Reporting
Period (Rounded)
CO2e 355
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 4 of 18
Project Developer Signature:
I am a duly authorized corporate officer of the project developer mentioned above and have
personally examined and am familiar with the information submitted in this greenhouse gas
assertion, the accompanying project report on which it is based. Based upon reasonable
investigation, including my inquiry of those individuals responsible for obtaining the information, I
hereby warrant that the submitted information is true, accurate and complete to the best of my
knowledge and belief, and that all matters affecting the validity of the emission reduction claim or
the protocol(s) upon which it is based have been fully disclosed. I understand that any false
statement made in the submitted information may result in de-registration of credits and may be
punishable as a criminal offence in accordance with provincial or federal statutes.
The project developer has executed this offset project report as of the ____day of____, 2018.
Signature: ________________________________________
Name: Steve Gell, P.Eng
Title: Vice President, Production
21 Aug
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 5 of 18
Table of Contents
Greenhouse Gas Assertion ..................................................................................................... 2 1.0 Contact Information .............................................................................................. 6 2.0 Project Scope and Site Description .......................................................................... 6
2.1 Project Implementation .......................................................................................... 7 2.2 Protocol ............................................................................................................. 10 2.3 Risks ................................................................................................................. 12
3.0 Project Quantification .......................................................................................... 13 3.1 Summary Table Non-Levied Emissions ................................................................... 13 3.2 Summary Table Levied Emissions and Biogenic CO2 ................................................. 14 3.3 Calculations ........................................................................................................ 14
4.0 References ......................................................................................................... 18
List of Tables
Table 1: Project Contact Information ...................................................................................... 6 Table 2: Project Information .................................................................................................. 6 Table 3: Assessment of Protocol Applicability Criteria .............................................................. 10 Table 4: Summary of Non-Levied Emissions .......................................................................... 13 Table 5: Data Sources Used in the Quantification of Baseline Emissions .................................... 15 Table 6: Data Sources Used in the Quantification of Project Emissions ...................................... 16
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 6 of 18
1.0 Contact Information
Table 1: Project Contact Information
Project Developer Contact Information Additional Contact Information
Ember Resources Inc. Ember Resources Inc.
Steve Gell, P.Eng
Dana Sorensen
The Devon Tower, 800 – 400 3rd Avenue SW The Devon Tower, 800 – 400 3rd Avenue SW
Calgary, Alberta, T2P 4H2 Calgary, Alberta, T2P 4H2
403-698-8983 403-270-0803
http://emberresources.com/ http://emberresources.com/
[email protected] [email protected]
2.0 Project Scope and Site Description
Table 2: Project Information
Project title Ember Resources Instrument Air Conversion at Strathmore Phase 1
Project purpose and
objectives
The objective of the Ember Resources (“Ember”) Instrument Air
Conversion at Strathmore Phase 1 (“The Project”) was to reduce
greenhouse gas emissions from pneumatic instrumentation by
converting the existing instrument gas (natural gas) system used for
process control at Ember’s Strathmore 09-27-024-25W4 compressor
station over to instrument air.
Activity start date The project start date is January 1, 2010.
Offset start date The offset start date is January 1, 2010.
Offset crediting period The project crediting period is from January 1, 2010 to December 31,
2022, which includes the initial 8-year crediting period and a five year
crediting period extension granted by Alberta Climate Change Office.
Reporting period
covered by the project
August 1, 2016 to December 31, 2017
Actual emission
reductions/ capture/
sequestration
The total quantity of GHG emission reductions claimed as emission
offsets for the reporting period from August 1, 2016 to December 31,
2017 is 355 tonnes CO2e. The table below provides a summary of the
offsets claimed to date for the Project.
Vintage Year Offsets Created (tCO2e)
2010 2,161
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 7 of 18
2011 2,068
2012 2,787
2013 2,294
2014 3,238
2015 (January 1 to January 15th) 133
2015 (January 16 to Dec 31st) 2,728
2016 (January 1 to July 31st) 904
2016 (August 1 to Dec 31st) 140
2017 215
The total emission offsets generated to date for the Project are 16,668
tCO2e.
Unique site identifier Latitude: 51.076
Longitude : -113.403
LSD: 09-27-024-25 W4M (located near Strathmore, AB).
The project is not an aggregated project.
Is the project located
in Alberta?
Yes, the Project is located in Alberta, near the town of Strathmore.
Project boundary The Strathmore Phase 1 compressor station is located at 09-27-024-25
W4M, near the town of Strathmore, Alberta. The instrument air
conversion project is entirely located within the compressor station
lease site and consists of an air compressor package, auxiliary
equipment and piping to distribute compressed air to each unit
operation and process building at the site. The project boundary
includes all of the pneumatic devices that use compressed air (which
previously used pressurized natural gas for process control). The
Strathmore Phase 1 facility is connected to the Alberta electricity grid
and the air compressors use a small amount of electricity.
Ownership Ember Resources owns 100% of the Strathmore 09-27-024-25W4
facility and is the sole owner of the emission offsets from the
instrument gas to air conversion project. No other party could
reasonably claim entitlement to any other benefit associated with the
emission offsets.
2.1 Project Implementation
Since commissioning of the Strathmore Phase 1 Instrument Air Project in 2010, several
changes were made to the Project. The following section summarizes changes made since the
original Offset Project Plan was submitted as well as changes made during this reporting period
from August 1, 2016 to Dec 31, 2017.
i. Inclusion of Emissions from Fossil Fuel Extraction and Processing (B10)
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 8 of 18
The baseline emissions associated with the extraction and processing of fossil fuels under SSR
B10 had previously been excluded from quantification in prior offset claims (January 1, 2012 to
January 15, 2015) to simplify data management processes.
For consistency with the Instrument Air Protocol requirements, this emission source has now
been included in the quantification for subsequent offset claims beginning with the period
January 16, 2015 to July 31, 2016 and continuing in this reporting period from August 1, 2016
to Dec 31, 2017. The formulas used in the quantification of baseline emissions from fossil fuel
extraction and processing under SSR B10 are described in Section 3.3 of this offset project
report. The emission factors for fuel extraction and processing are taken from the Alberta
Environment and Parks Carbon Offset Emission Factors Handbook (Version 1, 2015).1
ii. Inclusion of Emissions from Electricity Use (SSR P6) (Previously Excluded)
The project emissions associated with the usage of electricity to operate the instrument air
compressors were added for all offset claims beginning January 1, 2012 to meet new
requirements from Alberta Environment and Parks. The electricity emission factor for grid
electricity usage from the Alberta Environment and Parks Carbon Offset Emission Factors
Handbook (Version 1, 2015)2 has been used for this reporting period. The addition of this
emission source to the quantification was both conservative and immaterial as the modification
resulted in <0.5% reduction in the quantity of offsets claimed during this reporting period.
The GHG emissions associated with electricity usage under SSR P6 were estimated based
electrical equipment ratings in kilowatts, loading percentage, facility operating hours and the
Alberta Grid Usage Emission Factor, as shown in Section 3.3 of this offset project report.
iii. Update of the Global Warming Potential for Methane
Consistent with the most recent guidance from Alberta Environment and Parks and published
factors contained in the Carbon Offset Emission Factors Handbook (Version 1, 2015),3 the
Global Warming Potential of Methane was updated from 21 to 25 for all reporting periods
beginning January 1, 2014.
iv. Exclusion of Baseline Emissions of Vented CO2 (SSR B7)
The baseline emissions from venting CO2 contained in the instrument gas were excluded from
the calculation of emissions under SSR B7 as these emissions are negligible. In 2016, a
laboratory gas analysis of the fuel gas at the Strathmore Phase 1 site confirmed that the vented
gas contained only 0.12% CO2 by volume versus an average of 97.59% methane. The baseline
emissions from the venting of CO2 contained in the natural gas at Strathmore Phase 1 were
estimated to be less than 0.1 tonne of CO2 during this reporting period. Therefore this emission
source is immaterial. The exclusion of these emissions is also consistent with guidance in the
Instrument Air Protocol, found on page 28 in section 2.5 under the quantification of emissions
for SSR B7.
v. Air Usage from Equipment at the Fueling Station Adjacent to the Strathmore Phase 1
Plant
The Offset Project Plan makes reference to a compressed natural gas (CNG) fueling station that
previously operated adjacent to the Strathmore Phase 1 facility and used a very small amount
of compressed air that was supplied from the Project facilities. In 2014 the adjacent CNG
fueling station was completely decommissioned and the compressed air supply lines were
1 https://open.alberta.ca/publications/2368-9528
2 Ibid.
3 Ibid.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 9 of 18
removed from service. Therefore, the Project no longer supplies compressed air to this CNG
facility and the baseline emissions under SSR B7 are no longer impacted.
vi. Use of Daily Instrument Air Volumes from SCADA
Beginning January 16, 2015, the data management system for this offset Project was simplified
in order to pull data directly from SCADAvantage (“SCADA”) to avoid using a separate data
historian service called “PI” since this software was no longer available. The PI data historian
had been used to quantify GHG emissions since 2012 to trend and average data from the
instrument air flow meter and to perform standardized calculations.
The quantification of baseline emissions under SSR B7 is now done manually using daily
average instrument air volumes (e3m3/day) that are downloaded directly from SCADA instead
of the hourly average volumes obtained from the PI data historian. The underlying data still
comes from the same flow meter and is still polled at the same frequency as before using the
same SCADA system.
vii. Incorporation of Discount Factor for Leak Detection
For the offset claim for August 1, 2016 to December 31, 2017, the discount factor for leak
detection was set to 0% since a comprehensive leak detection assessment was completed in
December 2016 (e.g. it had been less than one year since all facilities had undergone a
complete leak survey and inspection).
viii. Change of Ownership
Since January 16, 2015 the Strathmore Phase 1 facility has been owned and operated by Ember
Resources. For the reporting period from January 16, 2015 to July 31, 2016, Encana acted as
the aggregator of emission offsets for this Project and several other instrument conversion
projects for administrative purposes. For the reporting period from August 1, 2016 to December
31, 2017 Encana Corporation had no ownership interest in the facility and did not participate in
the emission offset project. As such, the Project name has been changed to reflect the fact that
the Strathmore Phase 1 facility is 100% owned and operated by Ember Resources.
ix. Operational Changes Impacting Emission Offsets from the Project
The air usage at the Strathmore Phase 1 facility and the resulting GHG emission reductions
generated from the Project have decreased significantly since April 2016, when the majority of
the facility was shut-in. Only the inlet separator and one electric booster compressor are
currently operational as the sales gas compressor, dehydration unit and other equipment
continue to be shut-in since the boosted gas has been re-routed to another facility for final
processing and sales.
x. Change in Fuel Gas Composition
In August 2017, the Strathmore Phase 1 facility began receiving a richer gas supply from a
third party so the gas composition analysis was updated to reflect that operational change. In
past reporting periods the annual percent methane value from the gas analysis was used for
the entire calendar year, but for this reporting period the new gas analysis from October 13,
2017 was used only from August 1, 2017 to December 31, 2017 to more accurately reflect the
time period that the facility was handling the richer gas supply. The Nov 7, 2016 fuel gas
analysis was used for the period from August 1, 2016 to July 31, 2017 to more accurately
reflect the fuel gas composition at the facility.
Calculation procedures, data collection procedures and record keeping practices have not been
modified since the last offset project report. No changes were made to the emission factors
used for the project.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 10 of 18
No changes have been made to the Project for regulatory reasons and the Project continues to
be additional (surplus to regulations).
2.2 Protocol
The relevant quantification protocol being applied to this Project is the “Quantification Protocol
for Instrument Gas to Instrument Air Conversion in Process Control Systems” Version 1.0,
October 2009 (Herein referred to as the “Instrument Air Protocol”).
The quantification protocol is applicable to the Project because the Project replaces pressurized
natural gas (fuel gas) with compressed air to power pneumatic instruments in process control
systems. The instrument air conversion project achieves GHG emission reductions by utilizing
compressed air instead of compressed natural gas for control of pneumatic equipment, avoiding
methane emissions. Prior to the instrument air conversions, the process control equipment at
the Strathmore Phase 1 compressor station was driven by fuel gas (“instrument gas”).
The table below outlines how the Strathmore Phase 1 Instrument Air Conversion Project meets
the applicability requirements in the Instrument Air Protocol.
Table 3: Assessment of Protocol Applicability Criteria
Criteria Proponent Justification
1. Pneumatic instruments are designed to operate
using a pressurized gas (i.e. 20 or 35 psig for
commercially available devices), regardless of the
gas type. As a result, the instrument air system
must be designed to provide this same level of
pressure that the instrument gas system would
have provided to ensure functional equivalency;
The installation of an instrument air system
does not require any changes to be made to
the operating pressures of individual
instruments. The same pressure signal is
delivered to the instruments regardless of
whether the supply medium is natural gas or
compressed air. The pressure of the supply
medium is regulated down to specific
pressures as required by the instrument
specifications, not the type of pressure
delivery medium. Most instruments operate
at 20 or 30-35 pounds per square inch,
gauge (psig).
2. The Project is a conversion from instrument gas
to instrument air and does not include facilities
originally constructed to use instrument air or
replacements due to end-of-life;
The Project was implemented as a retrofit to
an existing facility that previously relied on
instrument gas (natural gas) to operate
pneumatic instrumentation systems.
3. To facilitate verification and allow for changes in
the facility, the proponent will develop an inventory
of devices to be maintained annually. Any changes
to the inventory, i.e. devices removed, will impact
net offsets claimed. The list will also help in
determining what fraction of the natural gas used
by pneumatic devices was vented and what fraction
was flared (if applicable);
An inventory of pneumatic devices has been
developed for the Project and will be updated
annually. Instrument gas was not flared in
the baseline as all vent lines were directed to
atmosphere for operational and safety
reasons (e.g. to avoid putting backpressure
on the controllers).
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 11 of 18
4. The key concept in this applicability criterion is
for the project proponent to inspect and repair
leaks prior to actual metering to reduce and
mitigate risks associated with overestimation of
emissions. Prior to the implementation of the
instrument air system and metering, the project
proponent must demonstrate that the instrument
air system’s piping network has been inspected for
leaks as pursuant to section 8.7 in Directive 60.
The project proponent must develop and implement
a program to detect and repair leaks meeting or
exceeding the CAPP Best Management Practice
(BMP) for Fugitive Emissions Management;
A leak inspection and repair program was
carried out prior to commissioning of the
instrument air conversion. Post
commissioning, leak inspections have been
performed periodically using ultrasonic leak
detection equipment. During periods when
leak detection has not been performed, the
discount factor has been used, in accordance
with the quantification methods in the
Instrument Air Protocol.
5. This protocol has been designed for specific use
in natural gas processing plants. However, other
facilities in the oil and gas industry use instrument
gas to provide pressure to pneumatic devices. This
protocol may be applied to projects where existing
gas provides pressure to instrumentation or
Chemical Injection Pumps (CIP), or other types of
equipment.
The instrument air conversion project was
constructed and commissioned at the
Strathmore Phase 1 facility, which is a
natural gas processing and compression
facility.
6 a. The date of equipment installation, operating
parameter changes or process reconfiguration are
initiated or have effect on the project on or after
January 1, 2002 as indicated by facility records;
The Project was constructed in late 2009 and
was commissioned on January 1, 2010.
6 b. The project may generate emission reduction
offsets for a period of 8 years unless an extension is
granted by the Alberta Climate Change Office, as
indicated by facility and offset records.
The Project will claim offsets for a period of 8
years beginning January 1, 2010 and ending
Dec 31, 2017. A crediting period extension
has been requested.
6 c. Ownership of offsets must be established as
indicated by facility records.
Ember is the sole owner of offsets from the
Project through its 100% working interest in
the Strathmore Phase 1 facility.
No flexibility mechanisms have been used in the quantification of GHG emission reductions for
this Project.
No deviations were made to the Quantification Protocol and no other protocols were used in the
quantification. The Quantification Protocol for Instrument Gas to Instrument Air Conversion in
Process Control Systems is not currently “flagged”, but the protocol was replaced by the
Quantification Protocol for Greenhouse Gas Emission Reductions from Pneumatic Devices in
January 2017. Therefore the Project will cease using the Instrument Air Protocol after the end
of its initial 8-year crediting period, which ends Dec 31, 2017. This offset project report covers
activities from August 1, 2016 to Dec 31, 2017 and therefore still uses the Instrument Air
Protocol.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 12 of 18
2.3 Risks
There are a number of risks that could impact the performance of the Strathmore Phase 1
Instrument Air Conversion Project and a non-exhaustive list of risks has been provided below.
None of these risks are expected to materially impact the Project.
Technical risks
o Data risks – a loss of data caused by a communications system failure or meter
failure could cause the Project to rely on contingent data collection mechanisms.
Given the significant operational history of the Project this risk can be managed
by experienced personnel and the use of conservative estimates based on past
performance, if required.
o Metering failure – the instrument air meter is calibrated annually and is a
common type of meter that Ember technicians and contractors are very familiar
with maintaining for other measurement purposes.
o A power outage, air compressor failure or related equipment failure could lead to
facility blowdowns (venting), downtime or other issues. This is mitigated by using
a lead-lag air compressor configuration, selection of robust equipment and
regular maintenance.
o Instrumentation system leaks resulting in increased air usage. This is mitigated
through periodic air leak inspections or the use of the discount factor provided in
the protocol.
Permanence risks
o There is no risk of a reversal of emissions as GHG emission reductions from this
Project are permanent in nature as they are achieved by a dedicated capital
investment into the installation of an instrument air system at an existing natural
gas processing and compression facility to eliminate the venting of natural gas
from pneumatic instrumentation systems.
o Commodity price/market risks could result in facility shut-ins due to low natural
gas prices or declining production and result in gas production being moved to a
facility that does not have an instrument air system. This risk is mitigated by the
fact that Ember operates a number of other instrument air and vent gas capture
projects at nearby facilities which also reduce or eliminate methane emissions
from pneumatic equipment.
Regulatory risks
o There are currently no regulatory requirements that are expected to impact the
Project. Since the voluntary instrument air conversion eliminated all methane
emissions from pneumatic devices at the facility since 2010, the Project is not
expected to be impacted by future methane regulations.
o Project level additionality, in terms of common practice, is assessed at the
protocol development stage. The Instrument Air Protocol was approved in 2009
and as of year-end 2017, no other companies appear to be operating instrument
air offset projects in Alberta. All of these factors support the fact that instrument
gas to air conversion retrofits are not common practice.
o Regulatory additionality is also continuously monitored. At this time, there are no
regulations requiring the retrofit or conversion of existing natural gas compressor
stations from instrument gas to instrument air.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 13 of 18
Other Risks
o There are not expected to be any scenarios that could result in double counting of
emission offsets since the Strathmore Phase 1 facility is 100% owned by Ember.
o There are no adverse impacts expected from the Project.
o The Project will not generate any other types of environmental attributes.
o There are no other emission offset projects at the site and the Project is not an
aggregated offset project.
The annual quantity of GHG emission reductions from this Project may vary from year to year
depending on facility downtime, commodity prices and other factors.
3.0 Project Quantification
3.1 Summary Table Non-Levied Emissions
The table below provides a summary of the net GHG emission reductions from the Project for the
reporting period. All emission sources quantified for this Project are considered “Non-Levied”
emissions since none of the quantified emission sources are subject to the Alberta Carbon Levy.
Note that the totals may not add up due to rounding.
Table 4: Summary of Non-Levied Emissions
Vintage Gas Type Baseline
Emissions
(tCO2e)
Project
Emissions
(tCO2e)
Total Reduction
or Sequestration
(tCO2e)
2016 CO2 1.11 n/a 1.11
2016 CH4 139.56 n/a 139.56
2016 N2O 0.02 n/a 0.02
2016 Other (CO2e) n/a 0.54 -0.54
Total 2016 CO2e 140.69 0.54 140.15
Total 2016 (Rounded) CO2e n/a n/a 140
2017 CO2 1.90 n/a 1.90
2017 CH4 214.83 n/a 214.83
2017 N2O 0.03 n/a 0.03
2017 Other (CO2e) n/a 0.93 -0.93
Total 2017 CO2e 216.75 0.93 215.83
Total 2017 (Rounded) CO2e n/a n/a 215
Total for Reporting
Period (Rounded)
CO2e n/a n/a 355
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 14 of 18
3.2 Summary Table Levied Emissions and Biogenic CO2
N/A. The Project does not include any “Levied” emission sources and does not include any biogenic
sources of CO2, so this section is not applicable and the summary table of Levied Emissions and
Biogenic CO2 has been deleted.
3.3 Calculations
The quantification of reductions of relevant sources of greenhouse gases has been completed
according to the methods outlined in Section 2.5 of the “Quantification Protocol for
Instrument Gas to Instrument Air Conversion in Process Control Systems”.
As outlined below, three sources and sinks of emissions were excluded from the quantification
since they are not applicable to the Project, and the equations in the following section reflect these
changes.
B8 Flared/ Combusted Fuel Gas - Not applicable. Excluded as the Strathmore Phase 1
facility did not previously flare instrument gas. Instrument gas was vented directly outside
each building for safety and operational reasons.
P9 Fuel Extraction/ Processing - Not applicable. Excluded as fossil fuels are not used to
operate any of the equipment added to operate the instrument air system.
P7 Air Management System - Not applicable. Excluded as all incremental electricity usage
in the project condition is already captured under P6 Air compression. The air management
system (air receiver) does not consist of any equipment that uses fossil fuels or electricity.
The following three equations serve as the basis for calculating GHG emission reductions from the
comparison of the baseline and the project:
Emission Reduction = Emissions Baseline – Emissions Project
Emissions Baseline = Emissions Vented Fuel Gas + Emissions Fuel Extraction/Processing
Emissions Project = Emissions Air Compression
Where:
Emissions Baseline = sum of the emissions under the baseline condition.
Emissions Vented Fuel Gas = emissions under SS B7 Vented Fuel Gas.
Emissions Fuel Extraction/Processing = emissions under SS B10 Fuel Extraction/Processing.
Emissions Project = sum of the emissions under the project condition.
Emissions Air Compression = emissions under SS P6 Air Compression.
Calculation of Baseline Emissions (SS B7 & B10)
The following two formulas are used to calculate baseline emissions under SS B7 and SS B10,
respectively.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 15 of 18
i. Emissions Vented Fuel Gas (SS B7) =
444sInstrument Control **%**days/year 365*DR)-(1* Air Compressed CHCH GWPCHGEF
ii. Emissions Fuel Extraction/Processing (SS B10) =
tionFuelExtractionFuelExtracFuel EFGEFEFVol **days/year 365* Air Compressed* sInstrument Control
The following table provides a summary of the key data sources used in the calculation of baseline
emissions for the Strathmore Phase 1 Instrument Air Project.
Table 5: Data Sources Used in the Quantification of Baseline Emissions
Baseline Emissions under SS B7
Parameter Description Units Source
Compressed Air
Used for
Pneumatic
Instruments /
Compressed Air
Control Instruments
Volume of compressed air used
for pneumatic instruments.
e3m3/
day
Continuous direct
measurement of air flow
rate in units of e3m3/ day
and averaging of
measurements on a daily
basis.
Discount Rate /
DR
Discount rate for leak detection
and repair (if not completed). %
DR = 0 if leak inspection
occurred within < 1 year.
Otherwise DR assumed to
be 2.5% per year from the
date that the system was
last inspected.
Gas Equivalency
Factor / GEF
Conversion factor to convert from
volume of air to an equivalent
volume of natural gas that would
have been vented in the baseline.
-
Gas Equivalency Factor of
1.2977 used as per
Appendix A (page 39) of the
Instrument Air Protocol.
% CH4
Percent methane (by volume)
contained in the fuel gas
(instrument gas) at each facility.
%
volume
Direct measurement of
composition of fuel gas at
the Strathmore Phase 1
facility, completed annually
by a third party laboratory.
Density of
Methane /
0.6797 kg/m3 at 15°C and 1
atmosphere.4 t/e3m3
At 15º C and 101.3kPa, the
standard reference
conditions used by the
natural gas industry.
Global Warming
Potential of
Reference value of 25 as per the
Alberta Environment and Parks
t CO2e/
t CH4 Alberta Environment and
Parks Carbon Offset
4 http://encyclopedia.airliquide.com/Encyclopedia.asp?GasID=41
4CH
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 16 of 18
Methane /
Carbon Offset Emission Factors
Handbook.
Emission Factors Handbook
(version 1, March 2015).
FuelVol
Calculated value. The baseline
volume of fuel gas used (vented
from pneumatic equipment) is
calculated based on the
measured air volume times the
gas equivalency factor. This
calculated value is then used to
determine the indirect upstream
emissions associated with fuel
extraction and processing under
SS B10.
e3m3
natural
gas/
day
Calculated value.
tionFuelExtracEF
Reference emission factors for
CO2, CH4 and N2O. Emission
factors for fuel extraction and
processing are from the Alberta
Environment and Parks Carbon
Offset Emission Factors
Handbook.
tCO2/
e3m3;
tCH4/
e3m3;
tN2O/
e3m3;
Alberta Environment and
Parks Carbon Offset
Emission Factors Handbook
(version 1, March 2015),
Table 4.
Note that the emissions of vented CO2 contained in the fuel gas have not been included in the
calculation for emissions under SS B7 as these emissions are negligible (the instrument gas at the
Strathmore Phase 1 site contains approximately 0.1% CO2 by volume) and the exclusion of <0.1
tonne of vented CO2 emissions is immaterial and conservative. Refer to page 28 in the Instrument
Air Protocol for further explanation.
Calculation of Project Emissions
The following formula is used to calculate project emissions under SS P6.
iii. Emissions Air Compression (SS P6) =
yElectricitGridRatingEquipment EFHoursOperatingLoadkW _**%*001.0*
The following table provides a summary of the key data sources used in the calculation of project
emissions for the Strathmore Phase 1 Instrument Air Project.
Table 6: Data Sources Used in the Quantification of Project Emissions
Project Emissions Under P6 Air Compression
Parameter Description Units Source
4CHGWP
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 17 of 18
Equipment
Rating / kW
Equipment Rating
kW rating of air
compressor electric
motors are used to
estimate electricity
usage for the
instrument air project.
kW
Air compressor motor size
(kW) obtained from
equipment specifications.
% Load Percentage loading of
air compressor. %
The percent loading is
estimated based on the
annual average volume of
air used during the year
divided by the maximum
dry air capacity of the air
compressor.
Operating
Hours
Air compressor
operating hours. hours
Assumed 24/7 operating
time per day for
conservativeness.
Alberta Grid
Electricity
Emission
Factor / EF Grid
Electricity
Reference value of
0.64 t CO2e /MWh for
increased on-site use
of grid electricity as per
the Alberta
Environment and Parks
Carbon Offset Emission
Factors Handbook.
tCO2e/
MWh
Alberta Environment and
Parks Carbon Offset
Emission Factors
Handbook (version 1,
March 2015), Table 2.
Ember Resources Instrument Air Conversion at Strathmore Phase 1
August 2018
Page 18 of 18
4.0 References
Alberta Government. Quantification Protocol for Instrument Gas to Instrument Air Conversion in
Process Control Systems. Version 1, October 2009.
Alberta Government. Carbon Offset Emission Factors Handbook. Version 1. April 2015.