Office of the University CIOIT Capital Projects Executive Summary -- Implementation Projects
Financial Data as of April 30, 2015
GL # Project Name
Planned
Actual
Planned
Actual Phase
Current
Budget
Cost to
Date
% of
Current
Estimate
to
Complete
Estimate
at
Complete
Start Date End Date
Total Number of Projects = 16 $109,120K $51,042K $56,999K $108,041K79.7%
520844-0004 Modernization of Financial Reporting 7/1/12
10/1/12
6/30/15 Implement$5,333K $4,249K 79.7% $1,084K $5,333K
520850-0011 Alumni Community Evolution (ACE) -
Implementation
7/1/14
7/1/14
6/30/16 Implement$3,723K $1,986K 53.3% $1,728K $3,714K
520894-0002 Student Information Systems 5/7/13
5/7/13
12/28/18 Implement$54,000K $29,295K 54.3% $24,705K $54,000K
520898-0006 Integrated Space Information System (ISIS) 7/1/11
7/1/11
2/1/15 Close$815K $709K 87.0% $6K $716K
520898-0012 EPACS (Enterprise Physical Access Control
Systems)
7/1/13
7/1/13
6/30/18 Implement$1,380K $812K 58.9% $218K $1,030K
5200813-0003GMAS 2.0 Implementation 2/2/15
2/2/15
6/30/16 Implement$2,838K $436K 15.4% $2,402K $2,838K
520802-0012 PeopleSoft Perfomance Management
System
9/1/12
9/1/12
6/30/15 Implement$2,834K $2,332K 82.3% $143K $2,475K
520823-0004 Cross Registration Phase 2 1/1/13
2/5/13
6/30/15 Implement$260K $201K 77.3% $59K $260K
520823-0005 Faculty Promotions Reappointment (Aries)
Implementation
5/13/14
5/13/14
9/29/15 Implement$599K $270K 45.1% $329K $599K
520824-0002 ADAMS Project 3/7/14
3/7/14
6/29/15 Implement$275K $218K 79.3% $11K $229K
520860-0002 Teaching and Learning Technologies 1/6/14
1/6/14
10/21/16 Implement$6,315K $1,622K 25.7% $4,693K $6,315K
520880-0008 Integrated IAM 7/1/13
7/1/13
12/30/16 Implement$12,524K $6,103K 48.7% $6,421K $12,524K
520883-0003 VoIP Implementation Project 9/29/14
9/22/14
8/19/16 Plan$11,216K $453K 4.0% $10,763K $11,216K
520886-0001 CIO Initiative - Collaboration 7/1/14 4/30/16 Implement$1,121K $957K 85.4% $163K $1,121K
520898-0010 ID Card Part II - Visitor Management
Implementation
8/15/13
8/15/13
6/30/15 Plan$1,454K $850K 58.5% $603K $1,454K
5/14/15 Troubled At Risk On Track Closed Complete On Hold Pending Closed Incomplete Page 1 of 2
Modernization of Financial Reporting
Project Status Report
Sponsor: State/Health
Period End
4/30/15
Project Manager: Raj Mariadoss
Delivery Organization: Administrative Technology Services
Replace CREW FIN and GM reports in OBI. Develop programmatic OBI governance
structure and prioritization framework to assess unmet needs collected during the
planning phase.
Business Value
Analytic needs for finance and research administration are not met by current tools
and technology; reliance on manual manipulation results in errors and inefficiency.
This project will migrate CREW Finance, Student and Grants Management reports to
the new Oracle Business Intelligence (OBIEE) platform. This project includes
stabilizing and performance tuning the existing OBIEE platform, developing a
reporting security strategy and deployment strategy for the 3,000+ CREW users
Describe the Solution
In spite of all the technical complexity and magnitude of the change management, the project team continues to chip through the CREW Financials reports incrementally. So
far 65 out of the 105 CREW Reports have been either delivered in OBIEE or identified as obsolete by the business users. The MFR project team is currently working on the
conversion of 13 Grants Report. The remaining 32 CREW reports belonging to Accounting, Budget and Detail Listing subject area will be address by MFR – Phase II Project.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
10/31/14Dashboard Delivery Process 6/1/14 6/1/14 2/27/15 2.0
10/31/14Higher Level Data Access 6/1/14 6/1/14 1/9/15 3.0
10/10/14Performance Test Setup 7/1/14 7/1/14 1/30/15 4.0
6/30/15Lower Level Data Access 7/1/14 7/1/14 5.0
11/25/14OBIEE Environment Setup 6/1/14 6/1/14 1/9/15 6.0
10/31/14Oracle EBS Database Replication 6/1/14 6/1/14 2/27/15 7.0
3/30/15NOETIX Workbench 6/1/14 6/1/14 3/3/15 8.0
3/30/15Tune Replicated EBS Database 8/1/14 8/1/14 4/30/15 9.0
6/30/15Mass Data Extract Strategy 10/1/14 10/1/14 10.0
7/18/14Student Financials Rollout 2/1/14 2/1/14 7/18/14 11.0
10/31/14CAPS Rollout 6/1/14 6/1/14 1/9/15 12.0
10/31/14CSMA Rollout 2/1/14 2/1/14 9/30/14 13.0
12/30/14Oracle Security Rollout 2/1/14 2/1/14 14.0
10/31/14Application Admin Rollout 2/1/14 2/1/14 9/30/14 15.0
5/18/15 GL# 520844-0004 Page 1 of 24
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
2/27/15Accounts Receivables Rollout 8/1/14 9/1/14 16.0
12/31/14Cash Management Rollout 8/1/14 9/1/14 2/27/15 17.0
2/27/15Accounts Payables Rollout 8/1/14 9/1/14 3/31/15 18.0
6/30/15Grants Management Rollout 9/1/14 1/5/15 19.0
6/30/15Finance – Group I Rollout 10/1/14 20.0
6/30/15Finance – Group II Rollout 10/1/14 21.0
6/30/15GL Detail Listing Rollout 10/1/14 22.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$1,918,539 $3,414,897 $1,918,539 $167,995$4,081,160 $4,249,155 $1,084,282 $5,333,437
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
Raj Mariadoss 6/30/153/10/15O 10031 Analysis of Sponsored CREW Reports and the design of
the underlying data structure need for BI reporting are in
progress. Progress is slow as the functional and
technical teams need business assistance in unraveling
the complex logic as well as get a better understanding
of various use cases. Project Team working with multiple
stakeholders to address outstanding requirements,
process and system related queries, which is
consuming development time.
Raj Mariadoss 3/31/153/10/15C 10032 The rollout of the Sub-Ledger Dashboards(CM, AP and
AR) has been delayed by a month due to the technical
challenges associated with the stabilization of the
replicated database and the complexity of the solution.
Cash Management dashboards are in Production and
signed off by business owners. Accounts Receivables
and Payables dashboards will be migrated to OBIEE
before the end of March.
Accounts Receivables and Payables dashboards
were migrated to OBIEE in March.
5/18/15 GL# 520844-0004 Page 2 of 24
Alumni Community Evolution (ACE) - Implementation
Project Status Report
Sponsor: Siovhan O'ConnorState/Health
Period End
4/30/15
Project Manager: Julie Broad
Delivery Organization: Administrative Technology Services
Data accessibility – data mart that aggregates data from a variety of sources for
analysis and reporting; Business operations functions supported using best-in-class
platforms that increase our ability to execute outreach to alumni, donor, and
volunteers through multiple channels; Foundational architecture that allows for
experimentation with new functionality as new technologies emerge; Architecture that
allows integration options for schools not utilizing the full platform;
Business Value
Replace Harvard's alumni portal, currently hosted by vendor iModules / Harris
Connect, with an improved, best-in-class series of services. Implement alumni
community services on a supported platform that can grow and expand over time and
allow us to provide a more personalized experience.
Describe the Solution
The project continues to trend towards green. Sprints 20 and 21 will be key to achieving the green status again. Much of the work that was being delayed should be
completed in these sprints. We closely managing scope and resources in order to continue to regain ground on the development tasks.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
10/3/14Alumni Profile and Search enhancements post pilot phase 7/1/14 7/1/14 10/3/14 1.0
8/15/14Discussion Groups Requirements 7/1/14 7/1/14 8/15/14 2.0
10/3/14Discussion Groups Development 8/4/14 8/4/14 10/3/14 3.0
10/13/14Responsive/Mobile Design & Ehancements 8/4/14 8/4/14 10/13/14 4.0
8/29/14Online Giving Requirements/Design 7/1/14 7/1/14 8/29/14 5.0
4/24/15Online Giving Development - Admin Tools 9/8/14 1/5/15 6.0
1/23/15Email Marketing (ExactTarget) Planning & Configuration 8/4/14 8/4/14 8/4/14 7.0
3/13/15Email Forwarding Design & Development 10/27/14 10/27/14 3/13/15 8.0
3/27/15Administrative portal Design & Development 2/2/15 2/2/15 4/3/15 9.0
6/26/15Class Notes Migration to VanillaForums 5/1/15 10.0
5/22/15Events Registration Design & Configuration 1/5/15 1/5/15 11.0
5/22/15Alumni Authentication Design & Development 8/4/14 8/4/14 12.0
4/29/16Reporting Environment - Phase 1 6/8/15 13.0
5/22/15Class Pages Migration to AlumniMagnet 1/5/15 3/16/15 14.0
6/26/15Online Giving donation forms 1/12/15 1/12/15 15.0
5/18/15 GL# 520850-0011 Page 3 of 24
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
4/17/15Data Integration - Advance and Alumni.Harvard 2/2/15 2/2/15 4/24/15 16.0
4/17/15Data Integration - Advance and ExactTarget 3/2/15 3/2/15 17.0
6/26/15Data Integration - Online Giving 5/4/15 18.0
5/29/15Data Integration - Advance and Certain 4/1/15 2/16/15 19.0
5/29/15Profile Components - Phase 2 4/1/15 3/23/15 20.0
5/7/15Data Integration - Communication Preferences 4/13/15 22.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-9,454.59$3,723,018 $0 $3,723,018 $207,677$1,778,205 $1,985,882 $1,727,681 $3,713,563
5/18/15 GL# 520850-0011 Page 4 of 24
Student Information Systems
Project Status Report
Sponsor: Anne MarguliesState/Health
Period End
4/30/15
Project Manager: Catherine Rhodes
Delivery Organization: Student Information Systems (SIS)
Adopt a modern, secure, flexible, and intuitive student information technology platform
that provides an excellent user experience, supports unique requirements of the
Schools, and facilitates access to integrated student and course data.
Business Value
Provide a university-wide student information system.
Describe the Solution
The project is yellow.
Overall Evaluation
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-0.28$54,000,000 $0 $54,000,000 $1,522,520$27,772,779 $29,295,299 $24,704,701 $54,000,000
5/18/15 GL# 520894-0002 Page 5 of 24
EPACS (Enterprise Physical Access Control Systems)
Project Status Report
Sponsor: Robert IulianoState/Health
Period End
4/30/15
Project Manager: John Avery
Delivery Organization: Harvard University Police
The EPACS project addresses the expressed needs of schools and units for
specialized physical security systems management and support, mitigates risks
identified by RMAS in the 2008 university-wide physical security systems risk
assessment, and supports Harvard's goal of maintaining a safe and secure campus.
Business Value
The EPACS project team will partner with HUIT, RMAS, University schools, and units
to create a robust and secure, centrally managed, physical security platform and
accompanying controls to safeguard people and assets for the Harvard community.
EPACS Phase One will be considered complete when 9 schools and units have
migrated to the enterprise system.
Describe the Solution
Two tasks remain from Phase 1. The Alarm project is on hold until finalization of the relocation study. The second task is part of the enterprise engineering effort which is in
progress. The architecture is being reviewed and discussed with the HUIT engineering groups.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
10/1/13H_S_A Migration 7/1/13 7/1/13 10/1/13 1.0
9/27/13CNS Migration (FAS Department) 7/1/13 7/1/13 9/27/13 2.0
11/27/13HUP Migration 9/1/13 9/1/13 11/27/13 3.0
1/30/14GSD Migration 10/1/13 10/1/13 1/15/14 4.0
1/30/14HKS Migration 10/1/13 10/1/13 1/23/14 5.0
3/31/14Arnold Arboretum NEW CANDIDATE 2/5/14 2/5/14 3/26/14 6.0
5/30/14Divinity Migration REVISED due date 3/1/14 3/1/14 5/21/14 7.0
10/8/14FAS Athletics 9/30/14 7/22/14 10/8/14 8.0
4/25/14HUHS Migration-REVISED due date 10/1/13 10/1/13 4/22/14 9.0
3/31/15Alarms dispatch 7/1/13 11.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-349,706.32$1,379,979 $0 $1,379,979 $4,979$807,172 $812,152 $218,121 $1,030,272
5/18/15 GL# 520898-0012 Page 6 of 24
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
1/2/159/1/13O 10548 Need to put helpdesk/EPACS support solution in to
place by next fiscal year. Risk-lack of permanent
helpdesk solution may result in reputational damage
9/1/149/1/13O 10550 PACS feed is impacting some clients. Project and team
resources have been stretched very thin, pushing
response time for PACS feed testing back. Risk-lack of
change management processes and effective
communication may cause reputational harm and may
discourage schools and units from adopting to the
central server.
11/14/147/28/14O 10614 George Fox has resigned. Maureen Kelly will assume
George's role in EPACS but George's experience will be
missed and the labor force again has been reduced
which will slow the process and hinder the ability to
meet the milestones.
5/18/15 GL# 520898-0012 Page 7 of 24
GMAS 2.0 Implementation
Project Status Report
Sponsor: Catherine BreenState/Health
Period End
4/30/15
Project Manager: Phil Murgatroyd
Delivery Organization: Administrative Technology Services
The GMAS 2.0 project seeks to upgrade the core technology backbone of Harvard's
Grants Management Application Suite (GMAS), which is nearly 10 years old, with
modern, extensible architecture and address long-standing user requests for usability
enhancements and functionality.
Business Value
Building upon the findings of the user research and technical proofs of concept
completed in the Planning Phase, update the Grants Management Application Suite
(GMAS) in both technical and user-facing ways to enable the FSS and HUIT teams to
improve the accessibility, usability, and maintainability of the system.
Describe the Solution
The project is in good health with page development starting last month, the team is currently learning a lot about the process as this in unknown territory. In parallel the
business steering committee, functional GMAS team and UX vendor has identified the areas of GMAS to focus their design efforts on.
Resources: The leadership team has identified a suitable full time Scrum Master and they're scheduled to start June 1st. The project risk associated to resources will be
downgraded to observe as this was the final critical resource needed to make this project a success.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
3/20/15Page Conversion - Foundational Work 2/2/15 2/2/15 3/27/15 1.0
6/30/16Page Conversion - Build and Test 3/16/15 3/16/15 2.0
6/26/15Business Priority Design Concept Development 3/9/15 3/23/15 3.0
4/17/15Release 38 4/17/15 4/17/15 4/17/15 4.0
7/31/15Release 39 7/31/15 5.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$2,838,000 $0 $2,838,000 $166,365$269,474 $435,839 $2,402,160 $2,838,000
5/18/15 GL# 5200813-0003 Page 8 of 24
PeopleSoft Perfomance Management System
Project Status Report
Sponsor: Marilyn HausammannState/Health
Period End
4/30/15
Project Manager: Isabelle Modiano
Delivery Organization: Administrative Technology Services
This project will lay the foundation for an integrated Talent Mangement solution, incl.
career and succession planning. Benefits: automate the current process, eliminate
flow of paper forms, easy access to data, track employees' competencies, identify
top performers, increase Harvard's engagement scores, facilitate internal mobility,
and contribute to the "One Harvard" vision.
Business Value
Provide a University-wide on-line performance management system.
Describe the Solution
All schools have started the FY15 annual review phase for about 11,000 employees. We are working closely with the schools who are going through this phase for the first
time. So far, no major issues have been reported. We continue to make small fixes and enhancements to improve the process. The project is scheduled to end in 2 months.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
3/15/14Design 1/1/13 1/1/13 3/15/14 2.0
3/15/14Training Development - Wave 1 1/1/13 1/1/13 3/15/14 3.0
10/15/13Psoft Release 36 - Development and Testing 4/1/13 4/1/13 10/15/13 4.0
2/28/14Change Management - University Wide 5/27/13 5/27/13 2/28/14 5.0
10/25/13Data Collection Wave 1 5/31/13 5/31/13 10/25/13 6.0
5/18/15Training Development - Wave 2 6/1/13 6/1/13 7.0
5/18/15Wave 2: HDS, HLS, HGSE, GSD, HMS, CADM#2, RIAS, SEAS 6/1/13 6/1/13 8.0
9/16/13HDW Release 36 - Development and Testing 6/7/13 6/7/13 9/16/13 9.0
3/28/14Change Management - FAS, CADM1 (wave 1a) 6/14/13 6/14/13 2/28/14 10.0
2/28/14Change Management - HKS, HBS, HSPH (wave 1b) 6/17/13 6/17/13 2/28/14 11.0
9/19/13Prepare Go-Live Tasks 7/15/13 7/15/13 9/9/13 12.0
12/9/13HDW Release 37 - Development and Testing 7/26/13 7/26/13 12/9/13 13.0
12/23/13Psoft Release 37 - Development and Testing 9/2/13 9/1/13 12/23/13 14.0
5/30/14Psoft Release 38 - Development and Testing 11/1/13 11/1/13 5/31/14 15.0
7/15/14Change Management - HDS, HLS, HGSE, GSD, HMS, CADM#2, RIAS, SEAS 12/1/13 12/1/13 7/15/14 16.0
5/18/15 GL# 520802-0012 Page 9 of 24
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
3/31/15Phase 2 Forms (Exit Interviews, FY15 and FY6 forms) 12/1/13 12/1/13 3/26/15 17.0
5/29/15Cascading Goals 12/1/13 12/1/13 3/26/15 18.0
9/30/14HDW Release 39 - Development and Testing 5/1/14 5/1/14 9/30/14 19.0
9/30/14Psoft Release 39 - Development and Testing 5/1/14 5/1/14 9/30/14 20.0
5/29/15Performance Management Reporting 5/1/14 3/24/14 21.0
6/30/15Phase 2 - Performance cycle for FY15 7/1/14 7/1/14 22.0
12/10/14Psoft Release 40 - Development and Testing 9/1/14 9/1/14 12/10/14 23.0
12/10/14HDW Release 40 - Development and Testing 9/1/14 9/1/14 12/10/14 24.0
5/29/15Training Development - Wave 3 9/1/14 9/1/14 25.0
5/29/15Psoft Release 41 - Development and Testing 11/1/14 11/1/14 26.0
5/29/15HDW Release 41 - Development and Testing 11/1/14 11/1/14 27.0
6/30/15Stabilization 5/31/15 28.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-359,543.41$2,834,416 $0 $2,834,416 $64,804$2,267,052 $2,331,855 $143,017 $2,474,872
5/18/15 GL# 520802-0012 Page 10 of 24
Cross Registration Phase 2
Project Status Report
Sponsor: Judith SingerState/Health
Period End
4/30/15
Project Manager: Georgina Prager
Delivery Organization: Administrative Technology Services
Increase in total number of Harvard and non Harvard students cross-registering for
Harvard courses. Decrease in total cross registration application development,
maintenance, and infrastructure expenses.
Business Value
Enhance the University Cross-Registration application to include all schools and
enhancement requests as identified by surveying faculty, registrars, students, and
advisers.
Describe the Solution
Migration to the cloud has been delayed to FY16 due to DevOps team schedule adjustments. An ITCRB change request will be submitted to accommodate this change.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
6/17/14Cross Reg. Summer 2014 Release - Go Live 6/17/14 6/17/14 6/17/14 1.0
9/5/14Cross Reg. Fall Startup Patch 9/5/14 9/5/14 9/5/14 2.0
11/17/14Cross Reg. Fall Startup Patch 7/29/14 7/29/14 11/17/14 3.0
9/18/13August 2013 Release 1/1/13 2/5/13 8/15/13 4.0
6/23/14FY2015 Product Roadmap approved 6/23/14 6/23/14 6/23/14 5.0
1/9/14January 2014 Release 12/16/13 12/16/13 1/9/14 6.0
8/6/14Cross Reg. Summer 2014 Release Service Pack 7/7/14 7/7/14 8/6/14 7.0
6/29/15Move Course Catalog application to HUIT production servers 6/29/15 9.0
6/30/15Migrate Cross Registration application to the cloud 6/30/15 10.0
6/30/15Migrate University Course Catalog application to the cloud 6/30/15 11.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$260,010 $0 $260,010 $0$200,918 $200,918 $59,092 $260,010
5/18/15 GL# 520823-0004 Page 11 of 24
Faculty Promotions Reappointment (Aries) Implementation
Project Status Report
Sponsor: Judith SingerState/Health
Period End
4/30/15
Project Manager: Barbara Ciccolini
Delivery Organization: ATS - OPPP - Faculty Promotions
-Compliance with federal EEO/AA requirements
-Increase the efficiency of faculty and staff time through enhanced data access,
quality, accuracy, and portability.
-Enable effective business continuity planning and protection from the risk of data
loss inherent to paper-based, non-standardized storage procedures.
Business Value
Financial risk in losing federal grant funding for being out of compliance.
Lack of data retention/business continuity
Describe the Solution
Project is moving forward, with vendor making high priority functional changes and Pilot schools advising on testing and go live timeline availability. An ITCRB change request
will be submitted after stakeholder review of proposed schedule and budget changes.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
8/29/14Security and Architecture Reviews 5/13/14 5/13/14 8/29/14 2.0
9/12/14Faculty Affairs office configuration and training 7/8/14 7/8/14 9/12/14 3.0
10/15/14Pilot promotion cases start (all 3 schools) 9/8/14 9/8/14 10/15/14 4.0
3/31/15Vendor response and delivery plan 2/3/15 2/3/15 3/31/15 5.0
3/26/15Pilot Completion and Review 2/27/15 2/2/15 2/27/15 7.0
5/8/15Revise Project Plan 3/23/15 3/23/15 8.0
2/27/15Pilot complete 2/27/15 2/27/15 2/27/15 9.0
8/31/15Vendor final delivery complete 8/31/15 8/31/15 8/31/15 10.0
8/31/15User Training complete 8/31/15 11.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$599,000 $0 $599,000 $40,015$230,184 $270,199 $328,801 $599,000
5/18/15 GL# 520823-0005 Page 12 of 24
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
Georgina Prager 4/30/152/3/15O 10018 The pilot feedback confirmed that the existing product
does not meet the needs of Harvard users.
Vendor responded to the issues and has committed
to delivering high priority requested changes by
August. The project team is reviewing impact to the
project schedule.
Georgina Prager 4/30/152/3/15C 10019 Pilot schools have requested a follow up pilot after
requested functionality is delivered.
The leadership team determined that a second pilot
was not necessary, however the project plan will be
revised to include additional demonstrations and user
testing prior to roll out.
5/18/15 GL# 520823-0005 Page 13 of 24
ADAMS Project
Project Status Report
Sponsor: Kristen BoltState/Health
Period End
4/30/15
Project Manager: Georgina Prager
Delivery Organization: ATS - OPPP - Research Contracts Management
Expand the current ADAMS implementation from HMS to all researchers at Harvard.
ADAMS is a tool to track and manage workflow for the Harvard Research Data
Security Policy and Data Use Agreement contracts. The implementation will enable
faster approvals for research and greater accountability for research data security.
Business Value
Project is to achieve three things:
1. Enhance the system to accommodate the additional requirements of pilot users
as well as defined enhancements from the business owner.
2. Implement the system on HUIT infrastructure, supported by HUIT staff at both the
system and application level. To include training and documentation.
3. Take the system through a pilot to production where GSE, FAS Economics
Describe the Solution
Project will remain active through June to develop training video and ensure that new user issues are resolved quickly.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
2/27/15FAS Economics Go Live 2/23/15 2/23/15 2/27/15 1.0
3/7/14Development of enhancements complete 3/7/14 3/7/14 3/7/14 2.0
4/18/14Soft-launch with pilot users (GSE, HBS, FAS Econ, HMS) 3/10/14 3/10/14 4/18/14 3.0
1/30/15HMS Migration and Upgrade 11/25/14 11/25/14 1/30/15 4.0
2/6/15GSE Go Live 11/12/14 2/2/15 2/6/15 5.0
6/26/15Training materials complete 5/4/15 7.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-45,661.60$275,000 $0 $275,000 $1,794$216,340 $218,134 $11,205 $229,338
5/18/15 GL# 520824-0002 Page 14 of 24
Teaching and Learning Technologies
Project Status Report
Sponsor: Anne MarguliesState/Health
Period End
4/30/15
Program Manager: Kristin Sullivan
Delivery Organization: Teaching and Learning Technologies
To provide a continually evolving set of faculty-friendly, student-focused technologies
that support teaching and learning across all Harvard schools, facilitate pedagogical
innovation, and contribute to educational research
Business Value
Plan, design, and implement a modular, integrated set of powerful, extensible and
flexible tools and services to support the full range of teaching and learning activities
across Harvard.
Describe the Solution
Program is proceeding as planned. Staffing nearly complete. A/B pilot is complete with constructive feedback. Canvas migration spring 2015 evaluation work underway with
Schools. Successfully stood up instance of open edX in order to test ability to bring edX content into Canvas course via LTI (known as "LTI provider project"). Planning
underway for iSite decommissioning and for year 2 of the developer community.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
4/30/15Hire Program Staff 5/19/14 5/19/14 3.0
6/29/15Define data format and semantics for research data 4/1/14 4/1/14 4.0
5/28/15Determine UX strategy 7/28/14 7/28/14 6.0
4/30/15Define data storage repository for research data 11/3/14 11/3/14 10.0
8/28/15Coordinate summer and fall 2015 migration planning 2/2/15 2/2/15 12.0
11/9/15Complete LTI provider project to bring edX content into Canvas course 4/1/14 4/1/15 13.0
6/30/16Stand up and run instance of Open edX in support of LTI provider project 4/1/15 4/1/15 14.0
10/21/16Complete spring 2015 Canvas migration evaluation 4/15/15 4/15/15 15.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$6,314,579 $0 $6,314,579 $218,518$1,403,105 $1,621,624 $4,692,955 $6,314,579
5/18/15 GL# 520860-0002 Page 15 of 24
Integrated IAM
Project Status Report
Sponsor: Anne MarguliesState/Health
Period End
4/30/15
Project Manager: Ann Lurie
Delivery Organization: University Identity Access Management
The program is building a federated identity management solution that will simplify the
process of identification and authorization throughout Harvard. This project is layered
on top of the various identity and access management solutions used by the various
schools, and also includes the goal of being able to inter-operate with IAM systems in
the non-Harvard world.
Business Value
The program is building a federated identity management solution that will simplify the
process of identification and authorization throughout Harvard. This project is layered
on top of the various identity and access management solutions used by the various
schools, and also includes the goal of being able to inter-operate with IAM systems in
the non-Harvard world.
Describe the Solution
Accomplishments this month include implementation of consolidated database schemas for IAM databases - reducing support and testing overhead and enabling faster cloud
migrations - as well as the deployment of a SailPoint IIQ release enabling Alumni provisioning. Program Increment 3 (scheduled through June 3) is underway, and handoff of
final deliverables from Isobar (for user-facing design patterns) was completed and implemented with HarvardKey. Cloud migrations of IIQ and PIN/CAS are underway, and
team opted to realize immediate cost savings by also migrating a number of Dev and QA environments for additional IAM applications to the cloud. The corresponding
on-premise hardware has been decommissioned.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
5/30/14SailPoint Readiness Release 5/30/14 1/1/14 5/30/14 2.0
6/30/14Sailpoint Foundation Release 1/1/14 1/1/14 6/30/14 3.0
8/31/15SailPoint Expansion (0365) 8/31/15 4.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$5,825,180 $6,698,640 $5,825,180 $343,790$5,758,741 $6,102,532 $6,421,288 $12,523,820
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
11/14/14O 10556 The recent events at the University of Maryland highlight
the need to assess Harvard's risk. IAM data stores have
two databases with SSN numbers including historical
data.
5/18/15 GL# 520880-0008 Page 16 of 24
VoIP Implementation Project
Project Status Report
Sponsor: Susan WalshState/Health
Period End
4/30/15
Project Manager: Bud Minahan
Delivery Organization: Communications Technologies Services and Projects
The Harvard Phone Program will provide a simplified communications services set;
Deliver features and applications for voice, conferencing, instant messaging and
presence; Unify the feature set for anytime, anywhere accessibility; Drive, through
parallel initiatives, ubiquitous access to cellular and WiFi services and Empower
users through availability self-service capabilities and resources.
Business Value
This project will migrate approximately 24,000 legacy centrex stations to Next
Generation Voice-over-the-IP (VoIP) communication lines University-wide. All schools
and departments will participate in this implementation which is expected to take
from four to five years to complete. The VoIP service will be sourced from Verizon's
in-the-cloud Unified Communications and Collaboration as a Service (UCCaaS)
platform. Current plans call for two early adopter migrations during summer 2015;
Describe the Solution
Overall, this Program is on track per the established project plan with only minor deviations required to date. Critical development items are due in May and June from
Verizon, among them Infrastructure, UCCaaS platform, AD/LDAP, Incident Management and Early Adopter porting.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
12/22/14Harvard Phone Program Initiation Phase 9/29/14 9/29/14 12/22/14 1.0
11/28/14Finalize Harvard Phone Contract development with Verizon 10/1/14 10/1/14 12/22/14 2.0
3/2/15Establish the project team/kick-off the Harvard Phone Program Implementation 10/8/14 10/8/14 3/23/15 3.0
2/16/15Provide Vz all required Low Level System Design Parameters 10/22/14 10/22/14 2/17/15 4.0
3/31/15Activate the Project Resource Plan 10/1/14 10/15/14 3/20/15 5.0
5/1/15Create HPh Service Bundles 10/13/14 10/13/14 5/1/15 6.0
11/18/14Finalize the Scope of Work 10/14/14 9/22/14 11/18/14 7.0
4/30/15 Create the HUN HPh VLAN Structure 10/15/14 10/15/14 4/30/15 8.0
6/5/15Create the HPh Operations Support Plan 10/16/14 10/16/14 9.0
6/1/15Develop a HPh Technical Supp Plan 11/5/14 10/29/14 10.0
5/14/15Create UCCaaS MPLS Environment 1/5/15 1/5/15 11.0
7/3/15Develop SNOW VoIP Inc Management & ebonding 2/23/15 2/23/15 12.0
6/12/15Develop a work scope and initate the ctx inventory scrub; on-board a scrub
contractor
3/16/15 3/16/15 5/1/15 13.0
6/12/15Work through the Migration Check List for 1230 SFR 4/1/15 3/18/15 14.0
5/18/15 GL# 520883-0003 Page 17 of 24
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
9/30/15Pre porting centrex number range 'breakouts' 4/15/15 4/15/15 15.0
7/10/15Develop a detailed test plan & perform UCCaaS UAT 5/22/15 3/16/15 16.0
7/22/15Migrate Early Adopter Scope at 1230 SFR to HPh 6/15/15 3/16/15 17.0
7/31/15Migrate HUIT Early Adopters at 60 Oxford St. 5/4/15 3/16/15 18.0
10/30/15Migrate 114 Mt. Auburn Greenfield HPh Users 9/29/14 3/6/15 19.0
12/18/15Potential migration of FAS Early Adopters due to Merlin Key system Issues 8/3/15 20.0
6/30/16Continue CADM Migrations post 114 Mount Auburn Greenfield installs 12/7/15 21.0
8/19/16Initate FAS migrations (TENTATIVE) 1/4/16 22.0
12/15/15Verizon develop Service Now Service Request process 9/29/14 23.0
6/30/15Cisco Unified Communications Domain Manager (CUCDM) development 4/10/15 4/10/15 24.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.36$11,216,390 $0 $11,216,390 $123,374$329,627 $453,001 $10,763,389 $11,216,390
5/18/15 GL# 520883-0003 Page 18 of 24
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
Susan DeLellis 5/4/153/9/15O 10024 The Program team recommends use of University
AD/LDAP for credentialing and directory use. Susan is
working with Cisco and Verizon to vet this proposal and
identify any issues with Lync and Jabber existing in
same desktop workspace.
05/08/14 A solution has been found by Cisco to the
supposed UCCaaS restriction of using only a single
domain. Verizon owes a development timeline and
test plan. This item will remain open until this solution
can be verified.
Bud Minahan 8/1/153/9/15O 10027 Use of NAT on HUN AP's and some landline networks
will not allow Cisco Jabber softphone and mobile client
calls to complete. Use of Cisco Expressway would
provide the required IP addressing and routing to
UCCaaS to complete these calls. All on and off campus
Jabber calls would utilize the expressway cluster in the
Vz cloud.
5/15/15 Verizon has announced that Expressway will
not be available until 08/01/15. Vz will provide costs
and a design the week of May 18th. Of concern is the
number of domains supported per Expressway
cluster. A new Harvard Phone subteam will address
Harvard's Expressway and Jabber development
issues.
Bud Minahan 3/20/153/20/15O 10038 Harvard specified that UCCaaS would be turned-up on
latest version of Cisco's HCS software (now 10.5). Vz
cannot provide a date when this will occur. Most
build-out activities including Expressway hinge on the
availability of the platform.
05/08/15 Verizon has stated that UCCaaS platform
v10.5 will be available on 05/20/15. This item will
remain open until this date is verified.
6/1/153/20/15O 10040 Harvard is concerned as CUCDM is the user portal to
add, move and change VoIP lines in the system. It is the
expected contingency in the event SNOW Service
request is not available. Also, it is the basis of any
Schools elf-service activities.
05/15/15 Vz reports that 17 of Harvard's requested 22
CUCDM port 'capabilities' will be available by
06/30/15. Joint Harvard, Verizon and Cisco
requirements development meetings will kick-off the
week of May 18th.
Bud Minahan 6/30/155/8/15O 10050 End user line porting from the centrex to the UCCaaS
requires that all centrex lines be in a 'single station'
state. Currently a majority of the centrex lines reside
within 'common block ranges' on the centrex. These
ranges must be 'broken out'. Some functionality is lost
while this work is in progress (i.e., 5 digit dialing). Of
concern is the loss of dialing on emergency services
auto dialers. The Team is working with Vz engineers to
determine what remediation is available to avoid any
issues on these critical services lines.
05/08/15 Team has developed an Access DB script to
determine which of 853 centrex range blocks have
Early Adopter numbers embedded. These ranges will
be compared to the 2000+ known emergency lines on
campus to determine the ranges needing special
handling. Team has queried schools for any critical
lines that may not be identified as such in the UC
Telecom records.
Karen Erasmi 3/16/1510/16/14C 10639 VoIP services are not recommended to run on CAT3
station wiring. Although much of the University is CAT5
or higher, there is legacy CAT3 wiring in-place in some
areas; the project team is working to determine the
extent of this use and to test the service quality
experience when CAT3 is used for the VoIP service. Use
of CAT3 will be validated by testing in the HUTTL Lab at
1230 SFR using a range of Cisco VoIP end point
devices, CAT3 wiring and jacks.
03/30/15 Testing has shown good voice quality on low
end VoIP deices; daisy chaining will not be
recommended; Team will place CAT3
recommendations in upcoming Network
Requirements Guidelines release,
5/18/15 GL# 520883-0003 Page 19 of 24
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
Bud Minahan 6/30/1510/17/14O 10640 Harvard is concerned that critical ebonded SNOW
processes will not be in-place as contracted on
06/30/15. Verizon has indicated that it may take up to
one year to develop an automated VoIP service ordering
process from Harvard's ServiceNow system into the
UCCaaS platform.
05/08/15; Verizon will receive API from Cisco on
09/18/15; development of a plug-in will complete on
11/18/15; ebonding service request development will
complete by 12/11/15; UAT completes 12/1/15.
Harvard has escalated lack of time for Service Now
development.
5/18/15 GL# 520883-0003 Page 20 of 24
CIO Initiative - Collaboration
Project Status Report
Sponsor: Benoit GaucherinState/Health
Period End
4/30/15
Project Manager: Tim Vaverchak
Delivery Organization: Strategy and Planning
* To simplify and facilitate University collaboration by creating a universal Harvard
directory within email and calendaring tools significantly improving the efficiency of
scheduling meetings easing coordination efforts across the University thus
decreasing cost and increasing agility
* To position toolsets to allow files to be shared between and outside of Harvard
consistently, efficiently and securely
Business Value
To support the diverse communication and collaboration needs within the Harvard
community as well as external participants in a seamless, consistent and effective
way.
Describe the Solution
Overall, green but work needs to be done to better structure the program going forward to ensure strategy and execution are aligned. Work now needs to be done to release
FY'16 funds to continue momentum.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
11/14/14Provisioning Infrastructure to support HMS in place 7/1/14 7/1/14 11/14/14 1.0
10/30/14Exchange environment established to allow HMS migrations 9/1/14 9/1/14 2/10/15 2.0
6/30/15HMS O365 Pilot / Early Adopters complete 11/3/14 2/13/15 3.0
4/30/16HMS Migrations 7/1/15 4.0
5/29/15SEAS Phase 1 Migrations (IceMail) 1/26/15 1/26/15 5.0
1/30/15Central Admin Mailbox Migrations 9/1/14 9/1/14 1/30/15 6.0
3/30/15HSPH Mailbox Migrations 2/2/15 2/23/15 3/31/15 7.0
3/30/16FAS Mailbox Migrations 6/1/15 8.0
4/30/15GSE Migrations 4/1/15 9.0
5/29/15SEAS Migration to O365 5/1/15 10.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$1,120,575 $0 $1,120,575 $57,987$899,419 $957,406 $163,169 $1,120,575
5/18/15 GL# 520886-0001 Page 21 of 24
Open/
Closed Issue # Owner
Date
Opened
Date
Due Next StepsIssue Description
Deneyse
Maestas
3/4/15C 10009 Potential issue with resource collisions across all school
migration efforts, currently being investigated further -
Resource plan developed Includes Migration
Engineering, Support Services, School Impact
Initial draft reviewed 2/25. Next version should include
more formal definition of gaps and resolution plans.
Jonah Pollard 3/4/15C 10010 Need to hire an additional $90/hour contractor to backfill
for Bobby
REPs approved
Tim Vaverchak 3/4/15O 10011 Group meetings bi-weekly to develop and execute plan
to provision HMS users to O365 via FIM (pre-requisite for
Mailbox Migrations). Promoting all "Happy Path users
first and then flipping a switch to make HMS user
promotion the default behavior
Promotion of users ongoing. Target for all Happy Path
users promoted to O365 - 3/6
Deneyse
Maestas
3/4/15O 10012 As more migration efforts are now underway a more full
definition of Collaboration Program objectives in relation
to Project activities is required. Effort begins with
Program Plan definition
Collaboration program will be discussed after the
resource plan is completed.
5/18/15 GL# 520886-0001 Page 22 of 24
ID Card Part II - Visitor Management Implementation
Project Status Report
Sponsor: John NolanState/Health
Period End
4/30/15
Project Manager: Ian Crowley
Delivery Organization: Harvard University Police
The visitor management system will improve security on campus; provide centralized
process; provide reporting and analysis.
Business Value
The implementation of a Harvard Cambridge Visitor Management system will help
managing visitors' authorized physical access on campus.
Describe the Solution
Project on track for recommendation at the end of 1st week of May. Planning for test and implementation for the walk-in and pre-registration process
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
3/31/15Scope 9/1/14 9/1/14 3.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
0.00$1,453,521 $0 $1,453,521 $30,575$819,782 $850,356 $603,164 $1,453,521
5/18/15 GL# 520898-0010 Page 23 of 24
EPACS Consolidation - Phase 2
Project Status Report
Sponsor: State/Health
Period End
4/30/15
Project Manager: John Avery
Delivery Organization: Harvard University Police
Business Value
Consolidating access control systems to centralized access control.
Describe the Solution
The migrations of GSE, the Learning Incubator and Phase 1 of HRE continued. Both GSE and the Learning incubator the work has been completed and the systems are now
on EPACS. GSE will add another building(50 Church St.) by end of FY15. HRE has been broken into 4 groups, the first group of buildings is targeted for completion the end
of May. The second group will commence in early June. The enterprise architecture effort has ramped up and several meetings with the HUIT engineering groups has been
productive. The EPACS VLAN is stretched between 60 Oxford and 1 Summer St. providing the foundation for a more robust architecture.
Overall Evaluation
Task/Milestone Description
State/
Health
Planned
Start Date
Actual
Start DatePlanned
End Date
Actual
End Date
12/10/14Migrate Radcliffe to the EPACS server, provide training and support. 7/1/14 10/6/14 12/12/14 1.0
2/25/15Migrate SEAS to the EPACS 9000 server 7/1/14 1/5/15 3/10/15 2.0
4/3/15Activate new panels at GSE to the EPACS server 3/6/15 3/9/15 3.0
5/15/15Migrate HRE to EPACS group 1 3/24/15 3/26/15 4.0
4/10/15Harvard Global Health Institute & Learning Incubator migration to EPACS 7/1/14 3/2/15 5.0
Original
Budget
Changed
Budget
Current
Budget
Spend Since
Last Report
Spend to Date
Last Report Cost to Date
Estimate to
Complete
Estimate at
Complete
$ Diff
Current to
-215,227.85$4,433,000 $0 $4,433,000 $73,135$475,299 $548,434 $3,669,338 $4,217,772
5/18/15 GL# 520898-0013 Page 24 of 24
GL # Project Name
Planned
Actual
Planned
Actual Phase
Current
Budget
Cost to
Date
% of
Current
Estimate
to
Complete
Estimate
at
Complete
Start Date End Date
520898-0013 EPACS Consolidation - Phase 2 7/1/14
10/6/14
5/15/15 Discover$4,433K $548K 12.4% $3,669K $4,218K
5/14/15 Troubled At Risk On Track Closed Complete On Hold Pending Closed Incomplete Page 2 of 2