OEE - invuldocument
Transcript of OEE - invuldocument
-
7/30/2019 OEE - invuldocument
1/1
Date of Study: _________ CD132 2001 MY LRR OE
Supplier : _____________
OEE Analysis- (Uses data that can be gathered from a sample production run)Please perform this analysis for all key processes.
(Note: White cells must be filled in, Shaded cells are calculated fields)
Constraint Process: Example data
Operating pattern and machine data: Process 1 Proces
A. Shifts/day 1
B. Hours/shift 9
C. Minutes/shift =B x 60 540
D. Planned downtime: lunch,breaks (minutes/shift) Note: If tag relief is used, enter 0 40
E. Total planned production time/shift (minutes) =C - D 500
F. Total planned production time/day (minutes) =A x E 500G. Days/week 5
H. Total planned production time/week (minutes) =F x G 2500
Sample production run data: Process 1 Proces
I. Total minutes run 440
J. Total breakdown time + time for minor setups and adjustments (minutes) 10
K. Total number of parts made (good + bad) 60
L. Total good parts (first time through only- do not include parts that were re-processed or reworked) 59
M. Total bad parts =K - L 1
N. Actual cycle time (sec/part) =((I - J)*60) / K 430
Other data: Process 1 Proces
O. Planned cycle time-the one used for capacity planning (seconds/part) 135
P. Projected time per changeover (minutes) 0
Q. Projected changeovers per shift 0R. Projected downtime: changeover time/shift (minutes) =P x Q 0
S. Projected downtime: (breakdown time+time for minor setups and adjustments)/shift (minutes) This should agree with field J 10
T. Total projected unplanned downtime/day (minutes) = (R + S) x A 10
OEE calculation Process 1 Proces
U. Equipment Availability: =(F-T)/F 98.000%
V. Performance Efficiency =O / N 31.395%
W. Quality Rate: =L / K 98.333%
X. OEE: =U x V x W 30.255%
Capacity analysis Process 1 Proces
Y. Planned uptime (hours/day) = F/60 8.333333333
Z. Planned uptime (days/week) = G 5
AA. Planned rate of production (parts/minute) = 60/O 0.444444444
AB. Theoritical production capacity per day = Y x 60 x AA 222.2222222AC. Theoritical production capacity per week = AB x Z 1111.111111
AD. Weekly Demand 300
AE. Weekly Parts Available for Shipment = AC x X 336.1627907
AF. Daily Demand (DPV) = AD/Z 60
AG. Daily Parts Available for Shipment = AB x X 67.23255814
AH. Percent above/below DPV = (AG-AF)/AF 12.05%
Percent above/below DPV for bottleneck operation (Minimum value of AH) 12.05%
What are the process assumptions for yield, OEE, and first-run capability?
Page 10