OEE - invuldocument

download OEE - invuldocument

of 1

Transcript of OEE - invuldocument

  • 7/30/2019 OEE - invuldocument

    1/1

    Date of Study: _________ CD132 2001 MY LRR OE

    Supplier : _____________

    OEE Analysis- (Uses data that can be gathered from a sample production run)Please perform this analysis for all key processes.

    (Note: White cells must be filled in, Shaded cells are calculated fields)

    Constraint Process: Example data

    Operating pattern and machine data: Process 1 Proces

    A. Shifts/day 1

    B. Hours/shift 9

    C. Minutes/shift =B x 60 540

    D. Planned downtime: lunch,breaks (minutes/shift) Note: If tag relief is used, enter 0 40

    E. Total planned production time/shift (minutes) =C - D 500

    F. Total planned production time/day (minutes) =A x E 500G. Days/week 5

    H. Total planned production time/week (minutes) =F x G 2500

    Sample production run data: Process 1 Proces

    I. Total minutes run 440

    J. Total breakdown time + time for minor setups and adjustments (minutes) 10

    K. Total number of parts made (good + bad) 60

    L. Total good parts (first time through only- do not include parts that were re-processed or reworked) 59

    M. Total bad parts =K - L 1

    N. Actual cycle time (sec/part) =((I - J)*60) / K 430

    Other data: Process 1 Proces

    O. Planned cycle time-the one used for capacity planning (seconds/part) 135

    P. Projected time per changeover (minutes) 0

    Q. Projected changeovers per shift 0R. Projected downtime: changeover time/shift (minutes) =P x Q 0

    S. Projected downtime: (breakdown time+time for minor setups and adjustments)/shift (minutes) This should agree with field J 10

    T. Total projected unplanned downtime/day (minutes) = (R + S) x A 10

    OEE calculation Process 1 Proces

    U. Equipment Availability: =(F-T)/F 98.000%

    V. Performance Efficiency =O / N 31.395%

    W. Quality Rate: =L / K 98.333%

    X. OEE: =U x V x W 30.255%

    Capacity analysis Process 1 Proces

    Y. Planned uptime (hours/day) = F/60 8.333333333

    Z. Planned uptime (days/week) = G 5

    AA. Planned rate of production (parts/minute) = 60/O 0.444444444

    AB. Theoritical production capacity per day = Y x 60 x AA 222.2222222AC. Theoritical production capacity per week = AB x Z 1111.111111

    AD. Weekly Demand 300

    AE. Weekly Parts Available for Shipment = AC x X 336.1627907

    AF. Daily Demand (DPV) = AD/Z 60

    AG. Daily Parts Available for Shipment = AB x X 67.23255814

    AH. Percent above/below DPV = (AG-AF)/AF 12.05%

    Percent above/below DPV for bottleneck operation (Minimum value of AH) 12.05%

    What are the process assumptions for yield, OEE, and first-run capability?

    Page 10