ODOT Structure Project Management Seminar Structure Type Study. PDP Step 1 thru 6 (Major). Step 1 - Define study area and stakeholders involved Step 2- Data collection, base maps, RED FLAG SUMMARRY. Purpose and need statement Step 3 - Broad Conceptual Alternatives - PowerPoint PPT Presentation

Transcript of ODOT Structure Project Management Seminar Structure Type Study

Page 1: ODOT  Structure Project Management Seminar  Structure Type Study

ODOT Structure Project

ManagementSeminar

Structure Type Study

Page 2: ODOT  Structure Project Management Seminar  Structure Type Study

PDP Step 1 thru 6 (Major)• Step 1 - Define study area and stakeholders

involved• Step 2- Data collection, base maps, RED

FLAG SUMMARRY. Purpose and need statement

• Step 3 - Broad Conceptual Alternatives• Step 4 – Develop Strategic Plan and

Recommended Scope• Step 5 – Develop Conceptual Alternatives• Step 6 – Refinement of Feasible Alternatives.

FIRST VALUE ENGINEERING STUDY

Page 3: ODOT  Structure Project Management Seminar  Structure Type Study

Step 2 - Red Flag SummaryAppendix H in the PDP Manual1. Environmental Issues – Historical Bridge,

FEMA Flood Plain2. Geometric, Pavement Issues 3. Hydraulic Issues4. Geotechnical Issues – Slope failures,

scour, poor materials 5. STRUCTURE ISSUES6. MOT, Right of Way, Utility, Permit Issues7. Misc. Issues – Aesthetics, VE study

required

Page 4: ODOT  Structure Project Management Seminar  Structure Type Study

Structure Issues

• Existing Structure Condition• Deck Cores Required• Railing meet Current Standards• Hydraulic Capacity • Possible Channel Relocation• Temporary Shoring for Railroads• Any Substructure Movement

Page 5: ODOT  Structure Project Management Seminar  Structure Type Study

Additional Structure Issues

• “Landmark” structure • Navigable Waterway – United

States Coast Guard, determine navigation clearances. Movable or fixed spans.

Page 6: ODOT  Structure Project Management Seminar  Structure Type Study

Step 6 - 1st Value Engineering • For projects over 25 million• Multiple discipline teamWorkshop• Information Phase – Consultant provides • Brainstorming – Creative thinking• Evaluate alternatives • Constructability review• Present VE ideas to Owner/Designer• Office of Production - Facilitator

Page 7: ODOT  Structure Project Management Seminar  Structure Type Study

Project Development

Process (Major) Step 7

Develop Preferred Alternative

Page 8: ODOT  Structure Project Management Seminar  Structure Type Study
Page 9: ODOT  Structure Project Management Seminar  Structure Type Study

Structure Type StudyObjective

• Select the best Structure Alternative • The study must provide ODOT with all the

project constraints, background, facts and insights to support the preferred structure alternative selection.

• More upfront preliminary engineering and project team involvement to better assist the design decision making process.

• Documentation of the reasoning behind project related decisions

Page 10: ODOT  Structure Project Management Seminar  Structure Type Study

Structure Type StudyWhen Required

• Required in the Preferred Alternative Verification review submission for a Major Project (Step 7)

• Required in the Minor Project Preliminary Engineering Study review submission (Step 3)

• Not required for projects classified as Minimal

Page 11: ODOT  Structure Project Management Seminar  Structure Type Study

Project Development Process

Step 7: Develop Preferred Alternative

• Based on Agency and Public comments- Recommend preferred alternative– ODOT’s recommendation only.

• Submit Preferred Alternative Verification Study- (Design only report L&D 1403.5)

Page 12: ODOT  Structure Project Management Seminar  Structure Type Study

Preferred Verification Study • Design Topics

– Survey– Geometrics– Geotech– Pavements– Drainage– Structure Type

Study– Maintenance of

Traffic – (Cont.)

• Structure Type Study– Hydraulic study and scour– Structure Types– Clearances

• Maintenance of Traffic:– Permitted Lane Closures

Exceptions Committee

Step 7

Page 13: ODOT  Structure Project Management Seminar  Structure Type Study

Ohio Depar t ment of Tr anspor t at ion

Preferred Verification Study • Design Topics (cont.)

– Traffic Control– Other– Right of Way– Environmental– Sheets– Cost Estimates– Reviews

• Environmental– FEMA Zones– Stream/Wetland Mitigation– Waterway permits

(Determination or Draft Permit)

– Permissible waste and borrow areas

– Environmental Commitments

Step 7

Page 14: ODOT  Structure Project Management Seminar  Structure Type Study

Preferred Verification Study • Design Topics (cont.)

– Traffic Control– Other– Right of Way– Environmental– Sheets– Cost Estimates– Reviews

• Cost Estimates– ROW Acquisition– Utility Reimbursement– Construction

Step 7

Page 15: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1

B. Preliminary Structure Site Plan Section 201.2.2(preferred bridge alternative)

C. Hydraulic Report Section 201.2.3

D. Narrative of Bridge Alternatives Section 201.2.4

E. Cost Analysis Section 201.2.5

F. Foundation Recommendation Section 201.2.6

G. Preliminary Maintenance of Traffic Plan Section 201.2.7

Page 16: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION ADDITIONAL RELATED

ITEMS • Retaining Wall Justification L&D Section

1404.2

• Noise Wall Justification ODOT Policy #21-001

• Pedestrian Overpass Justification L&D Section 1404.4

• Special Design Submission to OSE if there are non-standard designs, special railing, fracture critical elements, etc.

• Aesthetics

• Constructibility

Page 17: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Minimum Requirements for Submission B. Based on the complexity of the project some

work in Step 8 may be pertinent to perform in Step 7

C. Example – A project in an highly urban, high traffic setting may require more in-depth development of the Maintenance of Traffic to ensure it’s feasibility and cost

Page 18: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1

• Main characters are the existing and proposed profiles, ground line, water elevations and outline of structure

• Profile is an abbreviated version, items not required footing, bedrock, top of slope elevations, etc.

• Horizontal and Vertical Clearances need to be shown

Page 19: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1

B. Preliminary Structure Site Plan Section 201.2.2

• Site Plan with Plan and Profile view required for preferred alternative only

• Plan view of existing and proposed, contours, utilities, hydraulic & traffic data, proposed and existing structure blocks.

• Window dressing not required for example guardrail stationing, treatment of slopes, etc. (BDM 202.2.1)

Page 20: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1B. Preliminary Structure Site Plan Section 201.2.2

C. Hydraulic Report Section 201.2.3

• All hydraulic analysis done at this stage, including scour for all the alternatives

• SS 832 – potential placement of temporary construction access fills

Page 21: ODOT  Structure Project Management Seminar  Structure Type Study
Page 22: ODOT  Structure Project Management Seminar  Structure Type Study
Page 23: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1B. Preliminary Structure Site Plan Section 201.2.2C. Hydraulic Report Section 201.2.3

D. Narrative of Bridge Alternatives Section 201.2.4

Provide In-depth Insight- List Factors

• Geometry, alignment (curved/skew), grades (min. for deck drainage) horizontal and vertical clearances, clear/sight distance, superelevation requirements, etc.

• Future maintenance concerns• Right of Way impacts• Disruption to traveling public, user cost

Page 24: ODOT  Structure Project Management Seminar  Structure Type Study

Provide In-depth Insight- (continued)

• Construction access to site – transportation of members (weight or length restrictions)

• Any SI-9 “build bridges faster” opportunities• Utilities• Misc. scour, stability of slopes, debris/ice flows in river• Project aesthetics, project corridor• Rehabilitation projects – Fatigue evaluation, color

photographs, summary of field investigation

Page 25: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1B. Preliminary Structure Site Plan Section 201.2.2C. Hydraulic Report Section 201.2.3D. Narrative of Bridge Alternatives Section 201.2.4E. Cost Analysis Section 201.2.5• Cost analysis for all alternatives• Major cost rule 80/20, C-1 estimate • Initial and maintenance cost converted to present cost• Contingency items use between 15 to 20%

– Based on % design completed• For rehabilitation projects cost over-runs should be

expected• Required estimating software “Estimator 2.2” for all

ODOT budget estimating. Office of Estimating has a training course.

• ODOT “Summary of Contracts Awarded”• www.dot.state.oh.us/CONTRACT/estimating/

CustSupport/services.htm

Page 26: ODOT  Structure Project Management Seminar  Structure Type Study

Life Cycle Analysis• FHWA Executive Order – “…consider the

use of life cycle cost…”• Initial cost (replacement cost)• Cost accrued by traveling public due to

delays/detours (rehabilitation v. replacement)

• Maintenance costs of various structure types– from year 1 to year 39 (0% @ year 1 to

2% @ year 39 of replacement cost, repeat at year 41after major rehabilitation) Uniform Gradient

• Future major rehabilitation – coatings (sealers, painting), deck replacement– At year 40 new deck

Page 27: ODOT  Structure Project Management Seminar  Structure Type Study

Span Optimization Chart

• To be used for 4 or more spans

Page 28: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1B. Preliminary Structure Site Plan Section 201.2.2

(preferred bridge alternative)C. Hydraulic Report Section 201.2.3D. Narrative of Bridge Alternatives Section 201.2.4E. Cost Analysis Section 201.2.5

F. Foundation Recommendation Section 201.2.6

Page 29: ODOT  Structure Project Management Seminar  Structure Type Study

201.2 STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS

A. Profile for each bridge alternative Section 201.2.1B. Preliminary Structure Site Plan Section 201.2.2

(preferred bridge alternative)C. Hydraulic Report Section 201.2.3D. Narrative of Bridge Alternatives Section 201.2.4E. Cost Analysis Section 201.2.5F. Foundation Recommendation Section 201.2.6

G. Preliminary Maintenance of Traffic Plan Section 201.2.7• Transverse sections showing all stages of removal and

construction• Define temporary lane widths, lateral clearances to barriers, type

of temporary barriers, cut lines, any modifications to existing structure require, closure pour locations

• Temporary shoring considerations• Consider effects of differences in profile grade and alignment

Page 30: ODOT  Structure Project Management Seminar  Structure Type Study
Page 31: ODOT  Structure Project Management Seminar  Structure Type Study
Page 32: ODOT  Structure Project Management Seminar  Structure Type Study

Example List of Contentsfor Structure Type Study

• Listing of Alternatives• Project description and overview• Roadway alignments/geometry• Maintenance of traffic• Maintenance and inspection access• Design criteria – road type, traffic, typical

roadway, loading, etc.• Narrative of Bridge Alternatives• Cost comparison and life cycle considerations• Conclusion and recommendation• Preferred site plan, transverse section and

misc. details• Alternative profiles• Appendix – cost estimate and quantity

breakdown, foundation recommendation

Page 33: ODOT  Structure Project Management Seminar  Structure Type Study

EXAMPLE

Page 34: ODOT  Structure Project Management Seminar  Structure Type Study
Page 35: ODOT  Structure Project Management Seminar  Structure Type Study
Page 36: ODOT  Structure Project Management Seminar  Structure Type Study
Page 37: ODOT  Structure Project Management Seminar  Structure Type Study
Page 38: ODOT  Structure Project Management Seminar  Structure Type Study
Page 39: ODOT  Structure Project Management Seminar  Structure Type Study
Page 40: ODOT  Structure Project Management Seminar  Structure Type Study
Page 41: ODOT  Structure Project Management Seminar  Structure Type Study
Page 42: ODOT  Structure Project Management Seminar  Structure Type Study
Page 43: ODOT  Structure Project Management Seminar  Structure Type Study