MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, PH.D., ODOT DIRECTOR | GERY NOIROT, P.E., DISTRICT DEPUTY DIRECTOR
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SERVING ASHTABULA, MAHONING, PORTAGE, STARK, SUMMIT AND TRUMBULL COUNTIES
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
OVERVIEW 2
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
OVERVIEW 3
2019 Construction Program
Total Costs: $584.7 million - Construction Costs: $514.6 million
Thank you for your interest in Ohio Department of Transportation - District 4’s 2019 Construction Program. This publication is intended to
provide a general overview of projects that currently are under construction and those scheduled to be awarded or begin construction in 2019
The 2019 Construction Program is divided into six sections, one representing each county in District 4. Award dates, expected
completion dates, project descriptions, project locations, cost and maintenance of traffic are listed. Total costs include preliminary
engineering, right-of-way and construction. County maps have also been included for your reference.
Please keep this book on hand throughout the upcoming construction season. Information regarding construction projects is continually
changing; therefore, if you have any questions or require additional information, please do not hesitate to contact us or visit the District 4 website at
www.transportation.ohio.gov/dist4 for updates. District 4 utilizes Facebook and Twitter! Please like us on our Ohio Department of Transportation
Akron / Canton District 4 page and follow us on Twitter at ODOT_Akron.
District 4 Public Information Office 330-786-2208 Printed: April 2019
Front cover photo: Newly constructed roundabout on SR 164 and SR 626 in Beaver Township.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
OVERVIEW 4
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
ASHTABULA COUNTY 5
Ash
tab
ula
Co
un
ty
Co
nstr
uctio
n C
osts
: A
ctiv
e: $
16
.9 m
illion
U
pco
min
g: $
4.2
millio
n
To
tal: $
21
.1 m
illion
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
ASHTABULA COUNTY 6
Ashtabula County Active Projects
State Route 11 Wayne, Colebrook, New Lyme, Cherry Valley, Lenox & Dorset Townships
PID: 96733 PROJECT: 18-346
CONSTRUCTION COST: $2.2 million TOTAL COST: $2.2 million
START DATE: July 2018 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Painting of the following bridges over SR 11: US 6,
US 322, Cream Ridge Rd., Dodgeville, Rd., Sodam Rd., Mill Rd., Windsor Rd.,
Sentinel Rd., Footville-Richmond Rd. and Allen Comp Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 11.
US Route 20 City of Conneaut
PID: 94077 PROJECT: 18-598
CONSTRUCTION COST: $900,000 TOTAL COST: $1 million
START DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of US 20 from just east of SR 7 to the
Pennsylvania state line. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on US 20.
US Route 20 City of Ashtabula; Ashtabula Township
PID: 94073 PROJECT: 18-8003
CONSTRUCTION COST: $4.4 million TOTAL COST: $5 million
START DATE: May 2018 COMPLETION DATE: June 2019
PROJECT DESCRIPTION: Total pavement replacement of US 20 between
Seymour Dr. to just west of Park Ave. and the resurfacing of US 20 from the
eastern Ashtabula Corporation limit to Donahoe Dr. Project also includes minor
bridge repairs. Work completed in 2018 included the pavement replacement along
US 20. Work to be completed in 2019 includes the resurfacing of US 20 from the
eastern Ashtabula Corporation limit to Donahue Dr.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on US 20.
US Route 20 & State Route 84 City of Ashtabula; Saybrook, Ashtabula & Kingsville Townships
PID: 100815 PROJECT: 18-556
CONSTRUCTION COST: $1.9 million TOTAL COST: $1.9 million
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Resurfacing of US 20 between Brown Rd. and N.
Bend Rd. and on SR 84 between the eastern Ashtabula Corporation limit to SR
193. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 84. A minimum of one lane of traffic will be
maintained in each direction on US 20.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
ASHTABULA COUNTY 7
Ashtabula County Active Projects Continued
US Route 20 & State Routes 84 & 531 City of Geneva; Village of Geneva on the Lake; Harpersfield Township
PID: 96550 PROJECT: 19-075
CONSTRUCTION COST: $1.9 million TOTAL COST: $1.9 million
START DATE: April 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of US 20 from SR 534 to just east of
Ansel St., SR 84 between Chestnut St. and Walnut St., and SR 531 from just east
of SR 534 to just west of Myers Rd. Project also includes minor bridge repairs and
the replacement of the SR 84 bridge between Walter Main Rd. and LeFevre Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes. SR 84 will be closed for 21 days. A detour
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
State Routes 45 & 307 Orwell, Jefferson & Lenox Townships
PID: 100935 PROJECT: 18-599
CONSTRUCTION COST: $900,000 TOTAL COST: $900,000
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Microsurfacing of SR 45 between the Trumbull
County line to the southern Orwell Corporation limit. and on SR 307 between the
southern Jefferson Corporation limit to Union Rd. Project also includes
microsurfacing of various routes in Trumbull County.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
Interstate 90; State Routes 11 & 45 Various Locations
PID: 101797 PROJECT: 18-468
CONSTRUCTION COST: $2.3 million TOTAL COST: $2.4 million
START DATE: April 2019 COMPLETION DATE: Dec. 2019
PROJECT DESCRIPTION: Painting of 12 bridges including: Van Pelt Rd.,
Plymouth Ridge Rd., Wright Rd., and Middle Rd. over I-90, SR 11 over I-90, Nel
Retcher Rd., S. Denmark Rd., Griggs Rd., Morgan Meaney Rd., Seven Hills Rd.
and Plymouth Ridge Rd. over SR 11, SR 11 over SR 167 and SR 45 over Rock
Creek.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction. SR 45 will be closed for 14 days. A detour will be
posted. Access to all residences and businesses will be maintained at all times
throughout construction.
State Routes 193 & 534 Wayne, Williamsfield, Windsor, Hartsgrove & Trumbull Townships
PID: 100793 PROJECT: 18-483
CONSTRUCTION COST: $1.3 million TOTAL COST: $1.3 million
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Chip sealing of SR 193 from the Trumbull County
line to US 322 and on SR 534 from the Trumbull County line to just north of
Footville-Richmond Rd. Project also includes chip sealing on various routes in
Trumbull County.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
ASHTABULA COUNTY 8
Ashtabula County Active Projects Continued
US Route 322 Wayne & Williamsfield Townships
PID: 94108 PROJECT: 19-039
CONSTRUCTION COST: $1.1 million TOTAL COST: $1.1 million
START DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of US 322 between SR 193 and SR 7.
Project includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on US 322.
Ashtabula County Upcoming Projects
State Routes 7 & 531 City of Conneaut
PID: 98379
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $600,000
AWARD DATE: July 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 7 from US 20 to SR 531 and on SR
531 from Parrish Rd. to SR 7. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes.
State Route 45 & US Route 322 Village of Orwell; Austinburg and Windsor Townships
PID: 104661 PROJECT: 19-4011
CONSTRUCTION COST: $900,000 TOTAL COST: $1 million
START DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Replacement of the bridge on US 322 just east of SR
534 and on US 322 just east of SR 45 and minor bridge repairs to the SR 45 bridge
just south of Lampson Rd.
MAINTENANCE OF TRAFFIC: US 322 will close at each bridge for 14 days.
SR 45 will close for five days. These closures will NOT occur at the same time.
All detours will be posted. Access to all residences and businesses will be
maintained at all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
ASHTABULA COUNTY 9
Ashtabula County Upcoming Projects Continued
State Route 46 & 307 Lenox, Harpersfield & Andover Townships
PID: 106705
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $1.1 million
AWARD DATE: April 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Replacement of three culverts on SR 307 between
Van Pelt Rd. and LeFevre Rd., the replacement of a culvert on SR 46 just south of
Footville-Richmond Rd. and the replacement of a culvert in Pymatuning Lake
State park.
MAINTENANCE OF TRAFFIC: SR 46 will be closed for seven days. SR 307
will be closed for 21 days. Pymatuning Lake State Park driveway will be
closed for 14 days. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
State Route 86 Windsor Township
PID: 94083
ESTIMATED CONSTRUCTION COST: $900,000
ESTIMATED TOTAL COST: $900,000
AWARD DATE: July 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of SR 86 from the Geauga County line to
SR 534.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 86.
Interstate 90 Geneva Township
PID: 103026
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $600,000
AWARD DATE: July 2019 COMPLETION DATE: August 2020
PROJECT DESCRIPTION: Installation of tower lighting at the I-90 and State
Route 534 interchange.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-90.
State Route 531 Ashtabula Township
PID: 82819
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $600,000
AWARD DATE: July 2019 COMPLETION DATE: October 2019
PROJECT DESCRIPTION: Slide repair on SR 531 at Whitman’s Creek.
MAINTENANCE OF TRAFFIC: SR 531 will be closed for 45 days. A detour will
be posted. Access to all residences and businesses will be maintained at all times
throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
MAHONING COUNTY 10
Mahoning County Construction Costs:
Active: $22.3 million Upcoming: $19.3 million
Total: $41.6 million
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
MAHONING COUNTY 11
Mahoning County Active Projects
State Route 46 Austintown Township
PID: 103720 PROJECT: 19-220
CONSTRUCTION COST: $700,000 TOTAL COST: $1.2 million
START DATE: May 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Intersection improvements at SR 46 and Mahoning
Ave., including adding an eastbound right turn lane on Mahoning Ave., and adding
northbound through lane on SR 46. Project also includes curb and signal upgrades
and reduction of speed limit on Mahoning Ave. west of SR 46.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction throughout construction.
Interstate 76 & 80 Jackson and Milton Townships
PID: 104985 PROJECT: 19-135
CONSTRUCTION COST: $300,000 TOTAL COST: $300,000
START DATE: May 2019 COMPLETION DATE: Dec. 2019
PROJECT DESCRIPTION: Replacement of signs along I-76 between SR 534 and
I-80 and on I-80 between I-76/Ohio Turnpike to Lipkey Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-76 and I-80 during non-peak travel times.
Interstate 680 & State Route 164 Beaver Township
PID: 80192 PROJECT: 17-587
CONSTRUCTION COST: $11.6 million TOTAL COST: $14.7 million
START DATE: March 2018 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Construct new interchange at I-680 and SR 164.
Project also includes addition of a southbound lane on SR 164 between I-680 and
SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626
southbound junction, conversion of the SR 626 north junction to a single lane
roundabout and the widening and replacement of the SR 164 bridge over I-76/Ohio
Turnpike. Work completed in 2018 included the widening of SR 164 northbound,
completion of the roundabout and earthwork and drainage at the new interchange.
Work to be completed in 2019 includes the completion of the widening of the SR
164 bridge over the Ohio Turnpike, the widening of SR 164 southbound,
completion of the roundabout islands, lighting and landscaping and completion of
the pavement of the new ramps at SR 164 and I-680.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-680. A minimum of one lane of traffic will be
maintained by flaggers on SR 164 except for a 3-day period where the road
will be detoured. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
MAHONING COUNTY 12
Mahoning County Active Projects Continued
Interstate 680 City of Youngstown
PID: 96637 PROJECT: 18-203
CONSTRUCTION COST: $9.7 million TOTAL COST: $10.8 million
START DATE: June 2018 COMPLETION DATE: July 2021
PROJECT DESCRIPTION: Repairs to 12 bridges along I-680 between SR 711 to
just south of US 224. Project includes replacement of bridge deck on I-680 bridge
over Cherry Hill Rd., just west of Belle Vista Ave., the removal of the I-680 bridge
over an embankment and miscellaneous repairs to ten other bridges. Project also
includes installation of cable median rail between North Meridian Rd. and Belle
Vista Ave. Work completed in 2018 included the removal of the Renner Brewery
bridge, bridge repairs on the I-680 bridges over Price Rd. and Mahoning Ave. and
the replacement of approach slabs and pavement on I-680 over Oak Hill. Work to
be completed in 2019 includes the reconstruction of the I-680 bridge over Cherry
Hill and the I-680 bridge over the railroad.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained in each
direction of I-680 via a contraflow traffic pattern. The Bella Vista entrance ramp
I-680 northbound will be closed for 45 days. The ramp from SR 711
southbound to I-680 southbound will be closed for nine months. The ramp
from I-680 southbound to South Ave. will be closed for 14 days. All detours
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
MAHONING COUNTY 13
Mahoning County Upcoming Projects
State Route 45 & Interstate 76 Green, Goshen, Ellsworth & Jackson Townships
PID: 94140
ESTIMATED CONSTRUCTION COST: $4.7 million
ESTIMATED TOTAL COST: $4.8 million
AWARD DATE: October 2019 COMPLETION DATE: Sept. 2020
PROJECT DESCRIPTION: Resurfacing of SR 45 from the Columbiana County
line to Mahoning Ave. Project also includes minor bridge repairs. Project also
includes the addition of cable median rail on portions of I-76 and I-80.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 45.
State Route 46 Weathersfield Township
PID: 102103
ESTIMATED CONSTRUCTION COST: $2.5 million
ESTIMATED TOTAL COST: $3.5 million
AWARD DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Re-striping SR 46 between Lou Ida Blvd. and Webb
Rd. for two lanes of traffic. Installation of a northbound thru lane on SR 46
between Webb Rd. and County line Rd. Installation of a southbound left turn lane
at County Line Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 46.
US Route 62 & State Route 630 Green, Boardman & Canfield Townships
PID: 98714
ESTIMATED CONSTRUCTION COST: $3.2 million
ESTIMATED TOTAL COST: $3.3 million
AWARD DATE: June 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Resurfacing of US 62 from the Columbiana County
line to SR 446 and on SR 630 between SR 170 to the Pennsylvania State line.
Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on US 62 and SR 630 at all times.
State Routes 170 & 616 Poland Township; City of Struthers
PID: 98423
ESTIMATED CONSTRUCTION COST: $1.8 million
ESTIMATED TOTAL COST: $1.9 million
AWARD DATE: July 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 170 from the Northern Poland
Corporation limit to Midlothian Blvd. and on SR 616 from US 224 to SR 289 and
from Highland Ave. to Upland Ave. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
MAHONING COUNTY 14
Mahoning County Upcoming Projects Continued
US Route 224 Ellsworth Township
PID: 106706
ESTIMATED CONSTRUCTION COST: $200,000
ESTIMATED TOTAL COST: $400,000
AWARD DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Replacement of a culvert on US 224 just west of
Bailey Rd.
MAINTENANCE OF TRAFFIC: US 224 will be closed for five days. A detour
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
US Route 224 Boardman & Canfield Townships
PID: 94132
ESTIMATED CONSTRUCTION COST: $6.9 million
ESTIMATED TOTAL COST: $7.1 million
AWARD DATE: Sept. 2019 COMPLETION DATE: Nov. 2020
PROJECT DESCRIPTION: Resurfacing of US 224 between SR 11 and I-680.
Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction of US 224 during non-peak traffic times.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
PORTAGE COUNTY 15
Po
rta
ge C
ou
nty
C
on
str
uctio
n C
osts
A
ctiv
e: $
11
.4 m
illion
U
pco
min
g: $
3.9
millio
n
To
tal: $
15
.3 m
illion
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
PORTAGE COUNTY 16
Portage County Active Projects
State Route 14 Edinburg Township
PID: 101977 PROJECT: 18-366
CONSTRUCTION COST: $1.2 million TOTAL COST: $1.6 million
START DATE: July 2018 COMPLETION DATE: June 2019
PROJECT DESCRIPTION: Intersection improvements at SR 14 and Tallmadge
Rd. Project includes addition of left turn lanes, curb and radius improvements on
the northwest and southeast corners of the intersection and a signal replacement.
Work completed in 2018 included the widening of the northern side of SR 14.
Work to be completed in 2019 includes the widening of the southern side of SR 14
and the placement of the final layer of asphalt.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 14.
State Routes 14, 43 & 303 City of Streetsboro
PID: 99879 PROJECT: 18-616
CONSTRUCTION COST: $3.7 million TOTAL COST: $4.9 million
START DATE: May 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Upgrade signals along various intersection on SR 14,
SR 43 and SR 303 in the City of Streetsboro to improve connectability. Project
also includes the addition of a right turn lane on SR 14 westbound at SR 43 and a
southbound turn lane on Market Square at SR 14.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 14, SR 43 and SR 303.
State Routes 44, 82, 88, 282 & 303 City of Ravenna; Villages of Windham & Mantua; Ravenna & Windham
Townships
PID: 103282 PROJECT: 19-224
CONSTRUCTION COST: $3.7 million TOTAL COST: $4.2 million
START DATE: April 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of SR 44 between Mill St. and SR 82, SR
82 from just east of SR 44 to Vaughn Rd., SR 88 from E. Main St. to east of
Cooley Rd., SR 282 from SR 305 to the Geauga County line and on SR 303
between the western Windham Village limit to the Trumbull County line. Project
includes minor bridge repairs and the replacement of the SR 88 bridge just north of
Peck Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes. SR 88 will be closed for 60 days. A detour
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
Interstate 480 & State Route 14 City of Streetsboro; Twinsburg Township
PID: 87283 PROJECT: 18-073
CONSTRUCTION COST: $2.8 million TOTAL COST: $2.9 million
START DATE: April 2018 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Resurfacing of I-480 between the Summit County line
to SR 14 and on SR 14 just south of I-480. Project also includes minor bridge
repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-480 and SR 14.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
PORTAGE COUNTY 17
Portage County Upcoming Projects
State Routes 5 & 44 Rootstown & Ravenna Townships
PID: 100957
ESTIMATED CONSTRUCTION COST: $1.8 million
ESTIMATED TOTAL COST: $1.8 million
AWARD DATE: Oct. 2019 COMPLETION DATE: Oct. 2020
PROJECT DESCRIPTION: Resurfacing of SR 5 from I-76 to SR 59 and on SR 44
from SR 14 to the SR 14 entrance ramp and from Enterprise Parkway to Lake
Rockwell Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 5 and SR 44.
State Route 43 City of Streetsboro
PID: 98378
ESTIMATED CONSTRUCTION COST: $500,000
ESTIMATED TOTAL COST: $500,000
AWARD DATE: Sept. 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 43 from Frost Rd. to the northern
Streetsboro Corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 5 and SR 43.
State Route 44 Rootstown Township
PID: 102204
ESTIMATED CONSTRUCTION COST: $400,000
ESTIMATED TOTAL COST: $1.3 million
AWARD DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Improvements at the SR 44 and Tallmadge Rd.
intersection. Project includes addition of a southbound right turn lane, restriping to
add more vehicle storage, a signal replacement and access management.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 44 and Tallmadge Rd.
Interstate 76 Palmyra Township
PID: 103201
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $900,000
AWARD DATE: June 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Slide repair on I-76 westbound just east of
McClintocksburg Rd.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained on I-76 westbound during peak travel times.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
PORTAGE COUNTY 18
Portage County Upcoming Projects Continued
State Route 700 Freedom Township
PID: 101572
ESTIMATED CONSTRUCTION COST: $500,000
ESTIMATED TOTAL COST: $700,000
AWARD DATE: May 2019 COMPLETION DATE: Dec. 2019
PROJECT DESCRIPTION: Culvert replacement on SR 700 just north of I-
80/Ohio Turnpike. Project also includes culvert replacements in Summit County.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 700.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 19
Stark County Construction Costs:
Active: $38.5 million Upcoming: $73.3 million
Total: $111.8 million
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 20
Stark County Active Projects
State Routes 44, 153 & 173 City of Louisville; Nimishillen, Marlboro, Lexington & Washington
Townships
PID: 98392 PROJECT: 18-432
CONSTRUCTION COST: $2.9 million TOTAL COST: $3 million
START DATE: September 2018 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Resurfacing of SR 44 from just north of US 62 to just
north of St. Peter’s Church Rd., SR 153 from SR 44 to just east of Brookfield St.
and on SR 173 from SR 44 to US 62. Project also includes miscellaneous bridge
repairs. Work completed in 2018 included the resurfacing of SR 44 and SR 153.
Work to be completed in 2019 includes the resurfacing of SR 173 and minor
bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 44, SR 153 and SR 173 during construction.
Interstate 77 & US Route 62 City of Canton; Plain Township
PID: 84654 PROJECT: 19-065
CONSTRUCTION COST: $5.2 million TOTAL COST: $5.3 million
START DATE: April 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of US 62 between Harrison Ave. to just
west of Middlebranch Ave. Project also includes minor bridge repairs and noise
wall installation at I-77 exit ramp to SR 687.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction during peak travel times on US 62. Various ramp
closures ranging from one night to seven days. All detours will be posted.
Access to all residences and businesses will be maintained at all times throughout
construction.
US Route 62 City of Canton; Plain Township
PID: 96346 PROJECT: 18-271
CONSTRUCTION COST: $5.5 million TOTAL COST: $7.9 million
AWARD DATE: April 2018 COMPLETION DATE: August 2020
PROJECT DESCRIPTION: Re-alignment and reconfiguration of the US 62 and
Middlebranch, Harrisburg and 30th St. intersections. Project includes construction
of a roundabout at Harrisburg and 30th St. intersection and minor widening on US
62. Work completed in 2018 included drainage improvements. Work to be
completed in 2019 includes the construction of the roundabout at Harrisburg Ave.
and 30th St. and drainage improvements along Middlebranch Ave.
MAINTENANCE OF TRAFFIC: US 62 will have various lane restrictions.
Middlebranch will be closed for 7 days. 30th St. will be closed for 270 days.
Harrisburg will be closed for 15 days. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
US Route 62 City of Alliance; Lexington & Washington Townships
PID: 94127 PROJECT: 19-129
CONSTRUCTION COST: $900,000 TOTAL COST: $900,000
START DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of US 62 from SR 173 to Freshley Ave.
and from Federal Ave. to McKinley Ave. Project also includes sidewalk and
bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on US 62.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 21
Stark County Active Projects Continued
Interstate 77 Jackson Township
PID: 93102 PROJECT: 19-026
CONSTRUCTION COST: $4.8 million TOTAL COST: $4.8 million
START DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of I-77 from just south of Shuffel St. to
the Summit County line. Project also includes minor bridge repairs and resurfacing
of I-77 in southern Summit County.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-77 during peak
traffic times. Various nightly ramp closures. All detours will be posted. Access
to all residences and businesses will be maintained at all times throughout
construction.
Interstate 77 City of Canton; Plain Township
PID: 100290 PROJECT: 18-111
CONSTRUCTION COST: $3.6 million TOTAL COST: $5 million
START DATE: April 2018 COMPLETION DATE: May 2019
PROJECT DESCRIPTION: Widening and resurfacing of northbound and
southbound ramps at I-77 and SR 687/Fulton Rd./US 62 interchange. Project also
includes median wall construction and various other work to ramps at interchange,
the construction of a cul de sac on Blake Ave. NW and resurfacing of SR 687
between Blake Ave. and the I-77 entrance ramp. Work complete in 2018 included
all widening and ramp work. Work to be completed in 2019 includes placement of
the final course of asphalt and final striping.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction at all times on SR 687/Fulton Ave. Night time ramp
closures will occur. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
Interstate 77 & State Route 800 Jackson, Lexington & Nimishillen Townships
PID: 106201 PROJECT: 18-596
CONSTRUCTION COST: $900,000 TOTAL COST: $1 million
START DATE: May 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Lighting system upgrade at the I-77 and SR 800
interchange.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-77 during non-peak travel times.
Interstate 77; State Routes 21 & 619 City of Canton; Villages of Navarre & Wilmot; Bethlehem, Jackson,
Lexington, Marlboro, Plain & Sugar Creek townships
PID: 100939 PROJECT: 19-066
CONSTRUCTION COST: $3.9 million TOTAL COST: $3.9 million
START DATE: May 2019 COMPLETION DATE: August. 2019
PROJECT DESCRIPTION: Microsurfacing of I-77 from US 62 to just south of
Shuffel St., SR 21 from the Tuscarawas County line to Canal St., and on SR 619
from just west of Byers Ave. to Atwater Ave.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on all routes. The
ramp from Everhard Rd. to I-77 southbound will be closed for three nights. A
detour will be posted. Access to all residences and businesses will be maintained at
all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 22
Stark County Active Projects Continued
Interstate 77 & US Route 30 City of Canton; Bethlehem, Canton & Pike Townships
PID: 104986 PROJECT: 19-170
CONSTRUCTION COST: $200,000 TOTAL COST: $200,000
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Replacement of signs on I-77 between the Tuscarawas
County line to US 30 and on US 30 between Belden Ave. and Trump Ave.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction during peak travel times on I-77 and US 30.
State Route 172 City of Massillon & Tuscarawas Township
PID: 107452 PROJECT: 19-025
CONSTRUCTION COST: $700,000 TOTAL COST: $800,000
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Replacement of the SR 172 bridge just east of
Deermont Ave.
MAINTENANCE OF TRAFFIC: SR 172 will be closed for 30 days. Access to all
residences and businesses will be maintained at all times throughout construction.
State Route 619 Lake Township
PID: 93172 PROJECT: 17-043
CONSTRUCTION COST: $10 million TOTAL COST: $13.2 million
START DATE: May 2017 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Widening of SR 619 between Kaufman St. and Milan
Ave. and the addition of turn lanes. Project also includes roundabouts at the SR
619 and King Church Ave. intersection and Kaufman Ave. and SR 619
intersection. Project also includes drainage repairs and new signals. Work
completed in 2018 included the completion of the widening between Misty Ave. to
Market Ave. and the completion of the roundabouts at the SR 619/Kaufman Ave.
and SR 619/King Church Ave. intersections. Work to be complete in 2019 includes
the widening of SR 619 between Market Ave. and Milan Ave.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 619. Market Ave. north of SR 619 will be
closed for 14 days. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 23
Stark County Upcoming Projects
State Route 21 Lawrence Township
PID: 103721
ESTIMATED CONSTRUCTION COST: $2.2 million
ESTIMATED TOTAL COST: $2.4 million
AWARD DATE: June 2019 COMPLETION DATE: June. 2020
PROJECT DESCRIPTION: Installation of a restricted crossing U-turn intersection
to remove the median opening at the SR 21 and Butterbridge Rd. intersection.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 21. Butterbridge Rd. will be closed for 120
days. A detour will be posted. Access to all residences and businesses will be
maintained at all times throughout construction.
US Route 30 Village of Minerva
PID: 103718
ESTIMATED CONSTRUCTION COST: $1.1 million
ESTIMATED TOTAL COST: $1.8 million
AWARD DATE: October 2019 COMPLETION DATE: August 2020
PROJECT DESCRIPTION: Improvements at US 30 and Grant Blvd. including
increasing radius and horizontal curve.
MAINTENANCE OF TRAFFIC: US 30 at Grant Blvd. will be closed for 60
days. A detour will be posted. Access to all residences and businesses will be
maintained at all times throughout construction.
State Route 43 Canton, Osnaburg & Sandy Townships
PID: 98386
ESTIMATED CONSTRUCTION COST: $2.7 million
ESTIMATED TOTAL COST: $2.8 million
AWARD DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of SR 43 from the Carroll County line to
just north of Sandy Ave. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of lane of traffic will be maintained
by flaggers on SR 43.
State Routes 43, 172 & 619 City of Canton; Lake Township
PID: 98383
ESTIMATED CONSTRUCTION COST: $2.1 million
ESTIMATED TOTAL COST: $2.1 million
AWARD DATE: October 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 43 between 3rd St. and Market St.
and between SR 619 and the Portage County line, SR 172 from SR 43 to 3rd St. and
on SR 619 between the Summit County line and Kaufman Ave. Project also
includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 43, SR 172 and SR 619.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
STARK COUNTY 24
Stark County Upcoming Projects Continued
Interstate 77 & US Route 30 City of Canton
PID: 90973
ESTIMATED CONSTRUCTION COST: $60.2 million
ESTIMATED TOTAL COST: $66.3 million
AWARD DATE: June 2019 COMPLETION DATE: July 2023
PROJECT DESCRIPTION: Resurfacing on I-77 between SR 800 and US
30. Pavement replacement on I-77 at the US 30 interchange. Project also includes
the rehabilitation of the I-77 bridge over Market St., 15th St., and Cleveland Ave.,
the replacement of the I-77 bridge over the West Branch of the Nimishillin
Creek, and the replacement of the US 30 bridge over the West Branch of the
Nimishillin Creek. Project also includes minor bridge repairs on I-77 at US 30
within the project limits.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of I-77 southbound
will be maintained at all times via a contraflow traffic pattern, A minimum of one
lane of I-77 northbound will be maintained via a contraflow traffic pattern on I-77
and a second northbound lane will be maintained utilizing the US 30 and Cherry
Avenue Interchange as a by-pass. Ramp closures will vary in length from one
weekend to two construction seasons. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
US Route 250; State Routes 93 & 212 Villages of Brewster, Beach City & Wilmot; Bethlehem &Sugar Creek
Township
PID: 96671
ESTIMATED CONSTRUCTION COST: $3.5 million
ESTIMATED TOTAL COST: $3.6 million
AWARD DATE: May 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Resurfacing of US 250 from the Wayne County line to
the Tuscarawas County line, SR 212 from US 250 to the Tuscarawas County line
and on SR 93 between the Tuscarawas County line to Lawndell Rd. and between
Navarre Rd. and Harmon Ave. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on US 250, SR 93 & SR 212.
State Route 800 Canton Township
PID: 102673
ESTIMATED CONSTRUCTION COST: $1.5 million
ESTIMATED TOTAL COST: $1.5 million
AWARD DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Widening of SR 800 between 34th St. and the
Southgate Shopping Plaza to create a two way left turn lane and new sidewalks.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 800. Various 14-day side street closures. All
detours will be posted. Access to all residences and businesses will be maintained
at all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 25
Su
mm
it Co
un
ty
Co
nstr
uctio
n C
osts
: A
ctiv
e: $
258.1
millio
n
Up
co
min
g: $
43.2
millio
n
To
tal: $
30
1.3
millio
n
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 26
Summit County Active Projects
Various Routes
PID: 101376 PROJECT: 18-602
CONSTRUCTION COST: $1 million TOTAL COST: $1 million
START DATE: April 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Minor bridge repairs to various structures in Summit
County
MAINTENANCE OF TRAFFIC: Various ramp closures including: Portage
Trail to SR 8 southbound (1 night), SR 8 northbound ramp to Portage Trail (1
night), SR 8 southbound to Broad St. (2 nights), I-76 eastbound to Innovation
Way (4 nights) and I-76 eastbound to Brittain Rd. (4 nights). All detours will
be posted. Access to all businesses will be maintained at all times throughout
construction.
Cleveland Massillon Rd. City of Norton
PID: 97638 PROJECT: 18-591
CONSTRUCTION COST: $8 million TOTAL COST: $10.7 million
START DATE: April 2019 COMPLETION DATE: August 2020
PROJECT DESCRIPTION: Widening of Cleveland Massillon Rd. between
Pleasant Drive and Weber St.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on Cleveland Massillon Rd. Cleveland Massillon
Rd. will close for 14 days just north of Shannon Ave. at the railroad tracks.
Various side street closures. All detours will be posted. Access to all businesses
will be maintained at all times throughout construction.
Howe Ave. City of Cuyahoga Falls
PID: 93819 PROJECT: 19-067
CONSTRUCTION COST: $5.9 million TOTAL COST: $6.5 million
START DATE: April 2019 COMPLETION DATE: Sept. 2020
PROJECT DESCRIPTION: Pavement replacement on Howe Ave. between SR 8
and Bucholzer Blvd. Project also includes drainage, curbs, sidewalks, lighting and
new signage.
MAINTENANCE OF TRAFFIC: Ramps at SR 8 and Howe Ave. between SR 8
and Home Avenue will be closed for 35 days. The eastbound direction of Howe
Ave closed through November 2019. Plaza drive entrances may be closed for up to
7 days. All detours will be posted. Access to all businesses will be maintained at all
times throughout construction.
State Route 8 Cities of Stow and Hudson; Villages of Boston Heights and Silver Lake
PID: 76721 PROJECT: 18-382
CONSTRUCTION COST: $58.6 million TOTAL COST: $63.6 million
START DATE: September 2018 COMPLETION DATE: July 2022
PROJECT DESCRIPTION: Pavement replacement on SR 8 between Graham Rd.
to just north of SR 303, including drainage, signing and lighting. Project includes
the re-decking of the SR 8 bridges over Hudson Drive and Mud Brook and
miscellaneous repairs to nine other bridges.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction on SR 8 during peak hours. Various ramp closures
at Graham Rd., Steels Corners Rd., Seasons Rd. and SR 303 will occur. All
detours will be posted. Access to all businesses will be maintained at all times
throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 27
Summit County Active Projects Continued
State Route 59 City of Akron
PID: 91071 PROJECT: 18-500
CONSTRUCTION COST: $900,000 TOTAL COST: $900,000
START DATE: Spring 2019 COMPLETION DATE: June 2019
PROJECT DESCRIPTION: Repairs to SR 59 bridge over I-76. Project includes
expansion joint repairs, bridge deck patching and sealing and painting.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction of SR 59.
Interstate 76/Main/Broadway City of Akron
PID: 77269 PROJECT: 16-219
CONSTRUCTION COST: $84.2 million TOTAL COST: $97.6 million
START DATE: August 2016 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Reconstruction of the Main/Broadway Interchange
along I-76. Project will remove the interchanges at Wolf Ledges Pkwy. and Grant
St. and reconstruct access points and realign Main/Broadway at I-76. Work
completed in 2018 included the completion of new Main St., the reconstruction of
I-76 eastbound and the construction of the new ramp from I-76 westbound to
Broadway St. Work to be completed in 2019 includes the reconstruction of the I-76
westbound pavement and bridges and the reconstruction of the Broadway
Ave./Thornton St. intersection.
MAINTENANCE OF TRAFFIC: The ramp from SR 8 south to I-77
northbound is closed through fall 2019. The I-76 westbound entrance ramp
from Main St. is closed through fall 2019. Broadway Ave./Thornton St.
intersection and ramp from I-76 westbound to Broadway Ave. will close for 14
days. All detours will be posted. Access to all businesses will be maintained at all
times throughout construction.
Interstate 76 (Design Build) Cities of Norton & Barberton
PID: 93501 PROJECT: 16-3003
CONSTRUCTION COST: $80.4 million TOTAL COST: $87.6 million
START DATE: August 2016 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Widening of I-76 to three lanes in each direction
between SR 21 and Central Ave. Project also includes pavement replacement on I-
76 between the Medina County line and SR 21 and the re-decking of two bridges
on I-76 over SR 261 in Medina County. Work completed in 2018 included the
complete reconstruction of eastbound I-76 from State St. to the Medina County
line, including the eastbound bridge over SR 261 in Medina County and widening
of the Cleveland-Massillon Rd. bridge over I-76. Work to be completed in 2019
includes the competition of the Cleveland Massillon Rd. bridge over I-76 and the
final placement of asphalt along I-76.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained in each
direction of I-76 during peak travel times. One lane of traffic will be maintained in
each direction of I-76 during non-peak travel times.
Interstate 77 City of Green
PID: 93102 PROJECT: 19-026
CONSTRUCTION COST: $4.8 million TOTAL COST: $4.9 million
START DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of I-77 the Stark County line to SR 241.
Project includes minor bridge repairs and the resurfacing of I-77 in northern Stark
County.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-77 during peak
traffic times. Various nightly ramp closures. All detours will be posted. Access
to all residences and businesses will be maintained at all times throughout
construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 28
Summit County Active Projects Continued
State Route 91; US Route 224 & Canton Rd. Village of Lakemore; Springfield Township
PID: 89113 PROJECT: 19-130
CONSTRUCTION COST: $8.3 million TOTAL COST: $12.2 million
START DATE: May 2019 COMPLETION DATE: Oct. 2020
PROJECT DESCRIPTION: Intersection improvements at US 224, SR 91 and
Canton Rd. Project includes widening of Canton Rd. to create a dual northbound
left turn lane at US 224, widening of US 224 eastbound to create a dedicated right
turn lane, widening portions of SR 91 and Canton Rd. to create two way left turn
lanes, construction of dedicated U-turns on Canton Rd. at Springfield Lake Dr. and
on SR 91 at Linwood Rd. Project also includes access management improvements.
MAINTENANCE OF TRAFFIC: A single lane in each direction will be
maintained on SR 91, Canton Road, and US 224. Left turns will be restricted at
the SR 91, Canton Road, US 224 intersection for the construction through the
intersection. Left turning vehicles will use the newly constructed median U-
turns both north and south of US 224 to complete the left turn
movements. There will be various side street closures. All detours will be
posted. Access to all businesses will be maintained at all times throughout
construction.
State Route 93 City of Akron
PID: 107337 PROJECT: 18-370
CONSTRUCTION COST: $1.9 million TOTAL COST: $2 million
START DATE: July 2018 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Bridge repairs to the SR 93 bridge just north of SR
764/Wilbeth Rd. Project includes expansion joint repairs, substructure repairs and
bridge painting. Work completed in 2018 included bridge substructure repairs,
bridge deck repairs and approach asphalt replacement. Work to be completed in
2019 includes bridge painting, concrete sealing and drainage repairs.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained in each
direction on SR 93. The ramp from SR 93 northbound to Maryland Ave. will
be closed for 14 days. A detour will be posted. Access to all businesses will be
maintained at all times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 29
Summit County Active Projects Continued
State Route 91 City of Twinsburg
PID: 92032 PROJECT: 18-8012
CONSTRUCTION COST: $4.1 million TOTAL COST: $4.4 million
START DATE: September 2018 COMPLETION DATE: October 2019
PROJECT DESCRIPTION: Widening of SR 91 between Glenwood Drive and the
Cuyahoga County line. Project also includes new curbs, drainage, sidewalks,
driveway approaches, lighting and a roundabout at the intersection of SR 91 and
Meadowood Dr. Work completed in 2018 included installation of new storm
sewers on Ethan’s Dr. and widening of a portion of the east side of SR 91. Work to
be completed in 2019 includes the completion of the drainage improvements,
widening and partial roundabout construction at Meadowood / Ethan’s on the west
side of SR 91 and the completion of the widening and roundabout on east side of
SR 91.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction of SR 91. Various side street closures at Ethan
Drive and Meadowood Blvd. will range from 15 to 45 days. All detours will be
posted. Access to all businesses will be maintained at all times throughout
construction.
Summit County Upcoming Projects
State Routes 18, 241 & 261 City of Akron
PID: 98475
ESTIMATED CONSTRUCTION COST: $2.4 million
ESTIMATED TOTAL COST: $2.4 million
AWARD DATE: Sept. 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 18 from I-76 to SR 91, SR 241
from SR 764/Triplett Blvd. to Spencer St. and from Goodyear Headquarters to SR
18/E. Market St. and on SR 261 from Romig Rd. to McTaggart Dr. and Edgewood
St. to Cedar St.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 18, 241 and 261.
State Routes 18 & 261 City of Akron
PID: 96562
ESTIMATED CONSTRUCTION COST: $1 million
ESTIMATED TOTAL COST: $1 million
AWARD DATE: April 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of SR 18 from Hawkins Ave. to Portage
Path and on SR 261 from Market St. to Perkins St. and from Olive St. to SR
261/Tallmadge Ave. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 18 and 261.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 30
Summit County Upcoming Projects Continued
Interstate 77 & State Routes 21 & 176 Village of Richfield
PID: 81632
ESTIMATED CONSTRUCTION COST: $5.2 million
ESTIMATED TOTAL COST: $5.3 million
AWARD DATE: October 2019 COMPLETION DATE: Nov. 2020
PROJECT DESCRIPTION: Resurfacing of I-77 from the Everett Rd. to just south
of I-80/Ohio Turnpike, SR 21 just north of I-77 and SR 176 at the I-77 interchange.
Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction on I-77 during peak travel times. A minimum of one
lane of traffic will be maintained in each direction on SR 21 and SR 176. The
ramps from I-77 northbound to Wheatley Rd. and from SR 21 southbound to
I-77 southbound will each be closed for three days. All detours will be posted.
Access to all businesses will be maintained at all times throughout construction.
Interstate 77 Cities of Fairlawn & Twinsburg
PID: 101572
ESTIMATED CONSTRUCTION COST: $500,000
ESTIMATED TOTAL COST: $700,000
AWARD DATE: May 2019 COMPLETION DATE: Dec. 2019
PROJECT DESCRIPTION: Culvert replacement on the ramp from I-77 south to
SR 18 east. Project also includes a culvert replacement on SR 700 in Portage
County.
MAINTENANCE OF TRAFFIC: The ramp from I-77 south to SR 18 east will
be closed for five days. SR 91 will be closed for two weekends. All detours will
be posted. Access to all businesses will be maintained at all times throughout
construction.
Interstate 76 Cities of Akron & Barberton
PID: 96670
ESTIMATED CONSTRUCTION COST: $27.8 million
ESTIMATED TOTAL COST: $36.3 million
AWARD DATE: May 2019 COMPLETION DATE: July 2022
PROJECT DESCRIPTION: Widening of I-76 between Central Ave. and the
Kenmore Leg. Project also includes the reconstruction and reconfiguration of the
East Ave./Wooster Rd./State St. interchange. Project includes the removal of the
bridge over Central Ave. and replacement of I-76 bridge over Wooster Rd. Project
also includes resurfacing on SR 619 from I-76 to E. Hiram St. and from Harding
Ave. to E. Park Ave. and other minor bridge repairs on I-76/Kenmore Leg.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction during peak travel times. Ramp from I-76 eastbound
to Wooster Rd. and from Wooster Road to I-76 eastbound will be
permanently closed, but not until the new on eastbound on ramp from State
Street is open. I-76 westbound ramp to Wooster Rd. will be closed for 260
days. I-76/Kenmore Leg will be closed for 45 days in each direction. All
detours will be posted. Access to all businesses will be maintained at all times
throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
SUMMIT COUNTY 31
Summit County Upcoming Projects Continued
State Route 162 Copley Township
PID: 103171
ESTIMATED CONSTRUCTION COST: $1.3 million
ESTIMATED TOTAL COST: $1.7 million
AWARD DATE: May 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Improvements to the intersection of SR 162 and
Cleveland Massillon Rd. Project includes installation of an eastbound left turn lane
on SR 162 and a southbound right turn lane on Copley Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 162 and Cleveland Massillon Rd. SR 162
westbound will be closed for 14 days. A detour will be posted. Access to all
businesses will be maintained at all times throughout construction.
US Route 224 Springfield Township
PID: 98486
ESTIMATED CONSTRUCTION COST: $1.8 million
ESTIMATED TOTAL COST: $1.8 million
AWARD DATE: December 2019 COMPLETION DATE: July 2020
PROJECT DESCRIPTION: Resurfacing of US 224 from Kelly Ave. to the eastern
Akron Corporation limit and from SR 91 to just west of Neal Rd. Project also
includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on US 224.
Interstate 480 City of Twinsburg
PID: 84657
ESTIMATED CONSTRUCTION COST: $3.2 million
ESTIMATED TOTAL COST: $3.5 million
AWARD DATE: October 2019 COMPLETION DATE: August 2020
PROJECT DESCRIPTION: Installation of noise walls along I-480 westbound
between SR 82 and Chamberlain Rd.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-480.
The ramp from SR 82 to I-480 westbound will be closed for 45 days. A detour
will be posted. Access to all businesses will be maintained at all times throughout
construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
TRUMBULL COUNTY 32
Tru
mb
ull C
ou
nty
C
on
str
uctio
n C
osts
: A
ctiv
e: $
14
.1 m
illion
U
pco
min
g: $
9.4
millio
n
To
tal: $
23
.5 m
illion
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
TRUMBULL COUNTY 33
Trumbull County Active Projects
East Market Street City of Warren; Howland Township
PID: 104740 PROJECT: 19-131
CONSTRUCTION COST: $700,000 TOTAL COST: $800,000
START DATE: May 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Reconfiguring the SR 82 exit ramp and E. Market St.
intersection to allow left turns off the SR 82 eastbound exit to E. Market St. Project
will also reconfigure eastbound Market St. to consist of a left turn lane and a right
signalized by-pass lane. Also includes re-alignment of westbound Warren Sharon
Rd. and the installation of two traffic signals.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on E. Market St. at all
times during construction. Warren Sharon Rd. at E. Market St. will be closed
for 30 days. All detours will be posted. Access to all residences and businesses
will be maintained at all times throughout construction.
State Routes 5, 87 & 88 Bristol, Farmington, Vernon, Johnston, Kinsman & Mesopotamia
Townships
PID: 100954 PROJECT: 19-132
CONSTRUCTION COST: $1.8 million TOTAL COST: $1.8 million
START DATE: May 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of SR 5 from SR 88 to SR 7, SR 87 from
the Geauga County line to just west of SR 534 and on SR 88 from just east of SR
534 to SR 45. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes.
State Routes 7 & 305 Hartford, Vernon & Kinsman Townships
PID: 94118 PROJECT: 19-027
CONSTRUCTION COST: $1.9 million TOTAL COST: $2 million
START DATE: April 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Resurfacing of SR 7 from Bradley Brownlee Rd. to
SR 5 and on SR 305 from SR 7 to the Pennsylvania State line. Project also includes
minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes. SR 7 just north of SR 88 will be closed for 3
days. Access to all residences and businesses will be maintained at all times
throughout construction.
State Route 11 Fowler & Johnston Townships
PID: 87292 PROJECT: 19-225
CONSTRUCTION COST: $2.6 million TOTAL COST: $2.6 million
AWARD DATE: April 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Resurfacing of SR 11 from King Graves Rd. to just
south of SR 5. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 11.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
TRUMBULL COUNTY 34
Trumbull County Active Projects Continued
State Routes 45 & 88 Village of West Farmington; Farmington & Bloomfield Townships
PID: 100935 PROJECT: 18-592
CONSTRUCTION COST: $900,000 TOTAL COST: $900,000
START DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Microsurfacing of SR 45 from Peck Leach Rd. to SR
87 and on SR 88 between the Geauga County line to just east of SR 534. Project
also includes microsurfacing of various routes in Ashtabula County.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
State Route 45 City of Warren; Champion & Warrant Townships
PID: 100817 PROJECT: 18-592
CONSTRUCTION COST: $400,000 TOTAL COST: $400,000
START DATE: May 2019 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Microsurfacing of SR 45 from the northern Warren
Corporation limit to SR 5 and from Champion Ave. to SR 305.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 45.
US Route 62 Liberty & Hubbard Townships
PID: 87291 PROJECT: 19-103
CONSTRUCTION COST: $300,000 TOTAL COST: $300,000
START DATE: April 2019 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Placement on thin concrete overlay on US 62 from the
Mahoning County line to the southern Hubbard Corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes. US 62.
Interstate 80 Liberty & Hubbard Townships
PID: 100959 PROJECT: 18-548
CONSTRUCTION COST: $1.5 million TOTAL COST: $1.5 million
START DATE: April 2019 COMPLETION DATE: July 2019
PROJECT DESCRIPTION: Resurfacing of I-80 from just east of SR 193 to just
west of US 62/SR 7.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained in each direction of I-80 during peak travel times. A minimum of one
lane of traffic will be maintained in each direction of I-80 during non-peak travel
times.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
TRUMBULL COUNTY 35
Trumbull County Active Projects Continued
State Routes 88 & Chestnut Ridge Rd. Johnston, Vernon and Gustavus Townships
PID: 100793 PROJECT: 18-483
CONSTRUCTION COST: $1.3 million TOTAL COST: $1.3 million
START DATE: May 2019 COMPLETION DATE: August 2019
PROJECT DESCRIPTION: Chip sealing of SR 88 from SR 5 to just west of SR 7
and on Chestnut Ridge Rd. from SR 7 to US 62. Project includes chip sealing of
various routes in Ashtabula County.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
State Route 304 Cities of Girard & Hubbard; Liberty & Hubbard Townships
PID: 94116 PROJECT: 19-104
CONSTRUCTION COST: $1.4 million TOTAL COST: $1.4 million
START DATE: April 2019 COMPLETION DATE: Oct. 2019
PROJECT DESCRIPTION: Resurfacing of SR 304 from just west of SR 11 to just
west of US 62. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 304.
State Route 534 Village of Newton Falls; Newton Township
PID: 93485 PROJECT: 18-566
CONSTRUCTION COST: $1.3 million TOTAL COST: $1.5 million
START DATE: April 2019 COMPLETION DATE: October 2019
PROJECT DESCRIPTION: Bridge deck replacement on the SR 534 bridge over
the Mahoning River between River Rd. and Milton Blvd. Project also includes
resurfacing of SR 534 from just south of the SR 534 bridge over the Mahoning
River to the northern Newton Falls Corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 534. SR 534 will be closed for 75 days. A detour
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
ODOT DISTRICT 4 2019 CONSTRUCTION PROGRAM
TRUMBULL COUNTY 36
Trumbull County Upcoming Projects
Bedford Road Brookfield Township
PID: 84727
ESTIMATED CONSTRUCTION COST: $2.2 million
ESTIMATED TOTAL COST: $2.8 million
AWARD DATE: May 2019 COMPLETION DATE: Oct. 2020
PROJECT DESCRIPTION: Widening of Bedford Rd. between US 62 and Stewart
Sharon Rd. Project also includes new drainage and signing.
MAINTENANCE OF TRAFFIC: Eastbound direction of Bedford Rd. will be
closed for a period of 180 days. A detour will be posted. Access to all residences
and businesses will be maintained at all times throughout construction.
State Routes 45, 169, 303 & 304 Cities of Warren & Hubbard; Champion, Bazetta, Braceville & Hubbard
Townships
PID: 98509
ESTIMATED CONSTRUCTION COST: $2.3 million
ESTIMATED TOTAL COST: $2.3 million
AWARD DATE: July 2019 COMPLETION DATE: June 2020
PROJECT DESCRIPTION: Resurfacing of SR 45 from SR 5/82 to Champion
Ave., SR 169 from Rhodes Rd. to US 422, SR 303 from the Portage County line to
SR 534 and on SR 304 from SR 7 to the Pennsylvania state line. Project also
includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on all routes.
State Route 46 Champion Township
PID: 106708
ESTIMATED CONSTRUCTION COST: $100,000
ESTIMATED TOTAL COST: $300,000
AWARD DATE: May 2019 COMPLETION DATE: Nov. 2019
PROJECT DESCRIPTION: Replacement of culvert on SR 46 just south of SR
305.
MAINTENANCE OF TRAFFIC: SR 46 will be closed for 21 days. A detour will
be posted. Access to all residences and businesses will be maintained at all times
throughout construction.
State Route 305 City of Cortland; Southington, Champion, Bazetta, Fowler & Hartford
Townships
PID: 96568
ESTIMATED CONSTRUCTION COST: $4.8 million
ESTIMATED TOTAL COST: $5 million
AWARD DATE: May 2019 COMPLETION DATE: Sept. 2019
PROJECT DESCRIPTION: Resurfacing of SR 305 from SR 534 to SR 7. Project
includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 305.
To provide easy conveyance of people
and goods from place to place, we will:
Take care of what we have;
Make our system work better;
Improve safety;
Enhance capacity
A long-term, reliable, professional and
highly productive organization
O U R M I S S I O N
O U R V I S I O N
For more information, contact the ODOT District 4 Public Information Office at (330) 786-2208.
Like us on Facebook: www.facebook.com/ODOTD4
Follow us on Twitter: www.twitter.com/ODOT_Akron
Statewide Traffic Information: www.Ohgo.com
For general information, call (330) 786-2230 or visit District 4’s Web site at: www.transportation.ohio.gov/dist4