October 22, 2003 H.J. Krebs 1
LST Mechanical Design Review
2004 IR-2 Installation Schedule
H.J. Krebs
October 22, 2003
October 22, 2003 H.J. Krebs 2
2004 Installation• Scope of work is located on top & bottom
sextants– Remove 18 layers of RPCs– Install 6 layers of 7/8” thick brass absorber in
layers 5,7,9,11,13 & 15 – 11.5 tons/sextant– Install LST detectors in layers
1,2,3,4,6,8,10,12,14,16,17 & 18– An investigation will be performed at
commencement of this down to determine if the layer 19 RPC can be retained at some functioning level
October 22, 2003 H.J. Krebs 3
2004 Installation• Schedules do not include any time for:
– Post and pre-run PEP survey work• In the past, this has been 2.5 to 3 work days
– PPS certification• In the past, this has been 4 days
– Tours and photography sessions• In 2002, we lost two days to this• If tours or photography sessions are important, they may
occur between midnight and 07:00
– LST commissioning• 15 work days for bottom sextant• 2 work days for top sextant
– Replacement of any LST detectors that have problems after installation
October 22, 2003 H.J. Krebs 4
2004 Installation• Flux return steel
– Side gap plates• Have removed many times• Very confident in schedule for these tasks
– Center gap plates• Have never removed before• Very confident in schedule for these tasks
– Corner plates• Have never removed before• Schedule times for these tasks are an educated guess• Test removal of two corner block bolts in summer 2003
– Somewhat easy to remove– Bolt threads appear to be in excellent condition
• An unbolting/bolting sequence needs to be developed– Assume torquing these bolts 3 times during reinstallation
– Helicoils• Have had trouble with these in the past• Assume a problem with 1% of helicoils
– Means replacing two helicoils in 2004– There is no time included in the schedule for helicoil replacement
» Probably a few hours per helicoil replacement
October 22, 2003 H.J. Krebs 5
2004 Installation• Steel position
– Shall be monitored to assure that the barrel assembly is stable
– Some early thoughts on this• Dial indicators at strategic locations• Survey targets added at strategic locations
– i.e., on mid corner blocks to see if structure is becoming egg shaped
• Take periodic measurements– At beginning for reference– After bolts are loosened on each corner plate– At the beginning of each day– At the beginning of second shift– At the end of each day– At end for final reference
October 22, 2003 H.J. Krebs 6
2004 Installation• RPC removal
– RPCs are “ripped” out• HV & gas line still connected on BWD end• Time may be lost cleaning the steel gaps of this debris
– Bottom RPCs must be ripped loose, then cut, then pulled, then cut, etc.
• Not enough space in Z to extract in one piece
– RPCs range in weight from approximately 150 pounds for layer 1 to 250 pounds for layer 18
– 3600 sq ft of RPCs will be removed– Cover FWD beamline and detector face for protection
October 22, 2003 H.J. Krebs 7
2004 Installation• Where do items go during the installation process?
– Flux return steel to IR-12– Flux return bolts
• There are approximately 232 bolts 1-1/2”-6UNC x 14” lg.• Need to keep track of these• Need to protect threads
– Platforms and walkways along service road to Building 611– Main shield wall blocks along the Loop Road– RPCs thrown out in the IR-2 parking lot
• Where do items come from during the installation process?– Steel handling fixtures from IR-12– Elevator platforms from IR-12– Brass absorber plates from IR-12– LST detectors from SLD Collider Hall– Electronics and gas system from SLD Collider Hall
October 22, 2003 H.J. Krebs 8
2004 Installation• Schedules are based on:
– Mechanical installation assumes two 8-hour shifts per day, six days per week (3rd,6th and last week one 10-hour shift) – very taxing
– LST installation assumes one 10-hour shift per day, six days per week
• Mechanical installation team will provide support to LST team during this period and will also work one 10-hour shift per day, six days per week
– Wireway installation, cabling and gas hookup will be performed on owl shift
– Installation schedules denote IFR/LST work only• Work by other systems must be performed during owl shift
October 22, 2003 H.J. Krebs 9
Hall Crew Actual Work Time (Two 8-hour Shifts)Days Actual Work Time
0.05 39 minutes
0.1 1 hour 18 minutes
0.15 1 hour 57 minutes
0.2 2 hours 36 minutes
0.25 3 hours 15 minutes
0.3 3 hours 54 minutes
0.35 4 hours 33 minutes
0.4 5 hours 12 minutes
0.45 5 hours 51 minutes
0.5 6 hours 30 minutes
0.55 7 hours 9 minutes
0.6 7 hours 48 minutes
0.65 8 hours 27 minutes
0.7 9 hours 6 minutes
0.75 9 hours 45 minutes
0.8 10 hours 24 minutes
0.85 11 hours 3 minutes
0.9 11 hours 42 minutes
0.95 12 hours 21 minutes
1 13 hours
October 22, 2003 H.J. Krebs 10
Hall Crew Actual Work Time (One 10-hour Shift)Days Actual Work Time
0.05 23 minutes
0.1 47 minutes
0.15 1 hour 10 minutes
0.2 1 hour 33 minutes
0.25 1 hour 56 minutes
0.3 2 hours 20 minutes
0.35 2 hours 43 minutes
0.4 3 hours 6 minutes
0.45 3 hours 29 minutes
0.5 3 hours 53 minutes
0.55 4 hours 16 minutes
0.6 4 hours 39 minutes
0.65 5 hours 2 minutes
0.7 5 hours 26 minutes
0.75 5 hours 49 minutes
0.8 6 hours 12 minutes
0.85 6 hours 36 minutes
0.9 6 hours 59 minutes
0.95 7 hours 22 minutes
1 7 hours 45 hours
October 22, 2003 H.J. Krebs 11
2004 Installation Schedule
ID Task Name Duration Start Finish Predecessors
209 SUMMER DOWN 2004 57.75 days 7/1/04 9/8/04210 Begin Summer Down 0 days 7/1/04 7/1/04
211 OPEN DETECTOR (Two 8-hour Shifts) 2 days 7/1/04 7/2/04212 Open IR-2 Curtain Wall 0.1 days 7/1/04 7/1/04 210
213 Open FWD End Door - East 0.1 days 7/1/04 7/1/04 212
214 Install EQ Brace - FWD Lwr East 0.15 days 7/1/04 7/1/04 213
215 Insert Manlift 1 - FWD East 0.05 days 7/1/04 7/1/04 214
216 Install EQ Brace - FWD Upr East 0.1 days 7/1/04 7/1/04 215
217 Open Fwd End Door - West 0.1 days 7/1/04 7/1/04 216
218 Install EQ Brace - FWD Lwr West 0.15 days 7/1/04 7/1/04 217
219 Install EQ Brace - FWD Upr West 0.1 days 7/1/04 7/1/04 218
220 Remove DIRC Cyl, Lead and BWD End plug 0.25 days 7/1/04 7/2/04 219
221 Transport DIRC Cyl, Lead and BWD End Plug to IR-12 0.1 days 7/2/04 7/2/04 220
222 Open BWD End Door - West 0.1 days 7/2/04 7/2/04 221
223 Install EQ Brace - BWD Lwr West 0.15 days 7/2/04 7/2/04 222
224 Insert Manlift 2 - BWD West 0.05 days 7/2/04 7/2/04 223
225 Install EQ Brace - BWD Upr West 0.1 days 7/2/04 7/2/04 224
226 Open BWD End Door - East 0.1 days 7/2/04 7/2/04 225
227 Install EQ Brace - BWD Lwr East 0.15 days 7/2/04 7/2/04 226
228 Insert Manlift 3 - BWD East 0.05 days 7/2/04 7/2/04 227
229 Install EQ Brace - BWD Upr East 0.1 days 7/2/04 7/2/04 228
230 Detector Open and EQ Braced 0 days 7/2/04 7/2/04 229
7/1
BBR,HC,Crane
BBR,HC,FE
BBR,HC,Crane,FE
BBR,HC,Crane,FE
BBR,HC,Crane,FE
BBR,HC,FW
BBR,HC,Crane,FW
BBR,HC,Crane,FW
BBR,HC,Crane,BC
BBR,HC,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
7/2
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 12
Open FWD and BWD End Doors
October 22, 2003 H.J. Krebs 13
Install EQ Braces & Remove IFR Cooling Loops
Earthquaqe blocks are installed with shims.
Earthquaqe blocks
October 22, 2003 H.J. Krebs 14
2004 Installation ScheduleID Task Name Duration Start Finish Predecessors
231 PREP TO REMOVE STEEL (Two 8-Hour Shifts) 6.4 days 7/1/04 7/9/04232 IFR WORK (Owl Shift) 3.2 days 7/1/04 7/6/04233 Shut Off & Drain IFR Barrel Cooling System 0.25 days 7/1/04 7/1/04 210
234 Remove IFR HV Boxes - Upr FWD East & Upr FWD West 0.5 days 7/1/04 7/2/04 219
235 Remove Barrel FECs - FWD Top & Bottom 0.25 days 7/3/04 7/3/04 257
236 Disconnect Gas, HV & Remove Lines/Cables/Wireways - FWD Top & Bottom 0.25 days 7/3/04 7/3/04 235
237 Remove Barrel FECs - BWD Top & Bottom 0.25 days 7/3/04 7/3/04 236
238 Disconnect Gas, HV & Remove Lines/Cables/Wireways - BWD Top & Bottom 0.25 days 7/3/04 7/6/04 237
239 RELEASE SOLENOID SUPPORTS (Day Shift) 1.2 days 7/3/04 7/6/04240 Unbolt Solenoid External Axial Support Rods - Upr FWD East & Upr FWD West 0.25 days 7/3/04 7/3/04 230
241 Remove Solenoid Radial Support Arm - FWD Upr East 0.1 days 7/3/04 7/3/04 240
242 Remove Solenoid Radial Support Arm - FWD Upr West 0.1 days 7/3/04 7/3/04 241
243 Release Solenoid External Radial Wedge Support - FWD Upr East 0.05 days 7/3/04 7/3/04 242
244 Release Solenoid External Radial Wedge Support - FWD Upr West 0.05 days 7/3/04 7/3/04 243
245 Release Solenoid External Radial Wedge Support - BWD Upr East 0.05 days 7/3/04 7/3/04 244
246 Release Solenoid External Radial Wedge Support - BWD Upr West 0.05 days 7/3/04 7/3/04 245
247 Unbolt Solenoid External Axial Support Rods - Lwr East & Lwr West 0.25 days 7/3/04 7/3/04 246
248 Remove Solenoid Radial Support Arm - FWD Lwr East 0.1 days 7/3/04 7/3/04 247
249 Remove Solenoid Radial Support Arm - FWD Lwr West 0.1 days 7/6/04 7/6/04 248
250 Transport Solenoid Radial Support Arms to IR-12 0.1 days 7/6/04 7/6/04 249
251 Solenoid Supports Released 0 days 7/6/04 7/6/04 250
252 REMOVE SHIELDING (Day Shift) 3 days 7/6/04 7/9/04253 Disassemble Shield Wall Blocks 2 days 7/6/04 7/8/04 251
254 Remove FWD IFR Background Shield Wall 1 day 7/8/04 7/9/04 253
255 MISCELLANEOUS PREP WORK (Swing Shift) 4.4 days 7/3/04 7/9/04256 Remove FWD Upr & Lwr Ctr Cooling Loops & Hoses 0.1 days 7/3/04 7/3/04 230
257 Remove BWD Upr & Lwr Ctr Cooling Loops & Hoses 0.1 days 7/3/04 7/3/04 256
258 Drill & Tap FWD Door Tracks 0.5 days 7/3/04 7/3/04 257
259 Modify FWD PEP Pier Platforms 0.5 days 7/3/04 7/6/04 258
260 Remove FWD GAP Filler Plates - Transport to IR-12 0.5 days 7/6/04 7/6/04 259
261 Cover FWD Barrel Face & FWD Beamline 0.5 days 7/6/04 7/7/04 260
262 Install Steel Position Dial Indicators & Survey Targets 0.25 days 7/7/04 7/7/04 261
263 Remove Lower West Electronics House Walkway - Take to Shop 0.1 days 7/9/04 7/9/04 254,262
264 Install Upper Electronics House to East Detector Stairway 0.1 days 7/9/04 7/9/04 263
BBR,IFR
BBR,IFR,FC
BBR,IFR,FC
BBR,IFR,FC
BBR,IFR,BC
BBR,IFR,BC
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,CRYO,Crane,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,CRYO,Crane,FW
7/6
BBR,HC,RIG,Crane
BBR,HC,Crane,FC
BBR,HC,FC
BBR,HC,Crane,FE,FW
BBR,HC
BBR,HC
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 15
Install Beam Line Protection, Remove Solenoid Support Arms
Beam pipe protection can interfere with the man lift.
October 22, 2003 H.J. Krebs 16
2004 Installation Schedule
ID Task Name Duration Start Finish Predecessors
265 REMOVE STEEL (Two 8-hour Shifts) 2.45 days 7/9/04 7/12/04266 Remove Upr FWD Center Gap Plate - Transport to IR-12 0.15 days 7/9/04 7/9/04 264
267 Remove Corner Plate F1 - Transport to IR-12 0.4 days 7/9/04 7/9/04 266
268 Record Steel Movement 0.05 days 7/9/04 7/9/04 267
269 Remove Corner Plate F6 - Transport to IR-12 0.4 days 7/9/04 7/10/04 267
270 Record Steel Movement 0.05 days 7/10/04 7/10/04 269
271 Remove Flux Bar - FWD Top - Transport to IR-12 0.2 days 7/10/04 7/10/04 269
272 Remove Lwr FWD Center Gap Plate - Transport to IR-12 0.2 days 7/10/04 7/10/04 271
273 Remove Corner Plate F3 - Transport to IR-12 0.4 days 7/10/04 7/12/04 272
274 Record Steel Movement 0.05 days 7/12/04 7/12/04 273
275 Remove Corner Plate F4 - Transport to IR-12 0.4 days 7/12/04 7/12/04 273
276 Record Steel Movement 0.05 days 7/12/04 7/12/04 275
277 Remove Flux Bar - FWD Bottom - Transport to IR-12 0.25 days 7/12/04 7/12/04 276
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC
BBR,HC,Crane,FW
BBR,HC
BBR,HC,Crane,FC
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC
BBR,HC,Crane,FW
BBR,HC
BBR,HC,Crane,FC
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 17
Remove Gap Plates, Upper Corner Blocks & Upper Flux Bar
October 22, 2003 H.J. Krebs 18
Remove Lower Corner Blocks & Lower Flux BarInstall Elevator Platform, Begin Brass Absorber and LST Installation
October 22, 2003 H.J. Krebs 19
2004 Installation ScheduleID Task Name Duration Start Finish Predecessors
278 BOTTOM SEXTANT DETECTOR REPLACEMENT 19.45 days 7/12/04 8/4/04279 (Two 8-hour Shifts) 0 days 7/12/04 7/12/04 277
280 Transport Lower Vertical Positioner Components to IR-2 0.1 days 7/12/04 7/12/04 277
281 Install Lower General Fixture Vertical Positioner 0.25 days 7/12/04 7/13/04 280
282 Transport RPC Removal Hardware to IR-2 0.1 days 7/13/04 7/13/04 281
283 Remove 18 Layers of RPCs & Dispose (2hr 53min/layer)(Pull & Cut) 4 days 7/13/04 7/17/04 282
284 Deliver LST Modules to IR-2 0.15 days 7/17/04 7/17/04 283
285 Install 12 Layers of LSTs (7hr 30min/layer) (One 10-hour Shift) 9 days 7/17/04 7/28/04 284
286 Transport Bottom Brass Absorber Plates to IR-2 (84 Plates) 0.1 days 7/28/04 7/28/04 285
287 Install 6 Layers of Brass Absorber - Bottom (51min/plate) 5.5 days 7/28/04 8/4/04 286
288 Bottom Sextant LSTs & Brass Absorber Installed 0 days 8/4/04 8/4/04 287
289 Remove Lower General Fixture Vertical Positioner - Transport to IR-12 0.25 days 8/4/04 8/4/04 288
290 SCHEDULE STATUS - DO WE PROCEED? 0 days 8/4/04 8/4/04 289291 TOP SEXTANT DETECTOR REPLACEMENT 15.7 days 8/4/04 8/21/04292 (Two 8-hour Shifts) 0 days 8/4/04 8/4/04 290
293 Transport Upper Vertical Positioner Components to IR-2 0.1 days 8/4/04 8/4/04 290
294 Install Upper General Fixture Vertical Positioner 0.25 days 8/4/04 8/4/04 293
295 Remove 18 Layers of RPCs & Dispose - Top (1hr 48min/lyr) 2.5 days 8/4/04 8/7/04 294
296 Transport RPC removal Hardware to IR-12 0.1 days 8/7/04 8/7/04 295
297 Deliver LST Modules to IR-2 0.15 days 8/7/04 8/7/04 296
298 Install 12 Layers of LSTs (6hr 40 min/lyr) (One 10-hour Shift) 8 days 8/7/04 8/17/04 297
299 Transport Top Brass Absorber Plates to IR-2 (84 Plates) 0.1 days 8/17/04 8/17/04 298
300 Install 6 Layers of Brass Absorber - Top (42min/plate) 4.5 days 8/17/04 8/21/04 299
301 Top Sextant LSTs & Brass Absorber Installed 0 days 8/21/04 8/21/04 300
7/12
BBR,HC,Crane,FC
BBR,HC,Crane,FC,BE,BW
BBR,HC,LST,Crane,FC,BE,BW
BBR,HC,Crane,FC,BE,BW
8/4
BBR,HC,Crane,FC
8/4
8/4
BBR,HC,Crane,FC
BBR,HC,Crane,FC,BE,BW
BBR,HC,LST,Crane,FC,BE,BW
BBR,HC,Crane,FC,BE,BW
8/21
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 20
2004 Installation
October 22, 2003 H.J. Krebs 21
2004 Installation Schedule
ID Task Name Duration Start Finish Predecessors
302 LST CABLING, HV & GAS (Owl Shift) 26.95 days 7/28/04 8/28/04303 Install Wireways and Connect Signal Cabling - Bottom FWD 2 days 7/28/04 7/30/04 285
304 Install HV Cabling - Bottom FWD 1 day 7/30/04 7/31/04 303
305 Install/Connect Gas Lines - Bottom FWD 1 day 7/31/04 8/2/04 304
306 Install Wireways and Connect Signal Cabling - Bottom BWD 2 days 8/2/04 8/4/04 305
307 Install/Connect HV Cabling - Bottom BWD 1 day 8/4/04 8/5/04 306
308 Install/Connect Gas Lines - Bottom BWD 1 day 8/5/04 8/6/04 307
309 Bottom LSTs Connected With Cabling, HV & Gas 0 days 8/6/04 8/6/04 308
310 Install Wireways and ConnectSignal Cabling - Top FWD 2 days 8/17/04 8/19/04 298
311 Install/Connect HV Cabling - Top FWD 1 day 8/19/04 8/20/04 310
312 Install/Connect Gas Lines - Top FWD 1 day 8/20/04 8/21/04 311
313 Install Wireways and Connect Signal Cabling - Top BWD 2 days 8/21/04 8/24/04 312
314 Install/Connect HV Cabling - Top BWD 1 day 8/24/04 8/25/04 313
315 Install/Connect Gas Lines - Top BWD 1 day 8/25/04 8/26/04 314
316 Top LSTs Connected With Cabling, HV & Gas 0 days 8/26/04 8/26/04 315
317 LST System Commissioning - Bottom 15 days 8/6/04 8/24/04 309
318 LST System Commissioning - Top 2 days 8/26/04 8/28/04 316
319 Remove Upper General Fixture Vertical Positioner - Transport to IR-12 0.5 days 8/26/04 8/26/04 316
BBR,LST,FC
BBR,LST,FC
BBR,LST,FC
BBR,LST,BE,BW
BBR,LST,BE,BW
BBR,LST,BE,BW
8/6
BBR,LST,FC
BBR,LST,FC
BBR,LST,FC
BBR,LST,BE,BW
BBR,LST,BE,BW
BBR,LST,BE,BW
8/26
BBR,LST
BBR,HC,Crane,FC
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 22
2004 Installation ScheduleID Task Name Duration Start Finish Predecessors
320 INSTALL STEEL (Two 8-hour Shifts) 4.2 days 8/26/04 9/1/04321 INSTALL LOWER STEEL 1.75 days 8/26/04 8/28/04322 Deliver FWD Bottom Flux Bar to IR-2 - Install 0.25 days 8/26/04 8/27/04 319
323 Deliver Corner Plate F3 to IR-2 - Install 0.5 days 8/27/04 8/27/04 322
324 Torque Corner Plate Bolts - F3 0.5 days 8/27/04 8/28/04 323
325 Deliver Corner Plate F4 to IR-2 - Install 0.5 days 8/27/04 8/28/04 323
326 Torque Corner Plate Bolts - F4 0.5 days 8/28/04 8/28/04 325
327 Deliver LWR Center Gap Plate to IR-2 - Install 0.15 days 8/28/04 8/28/04 325
328 Deliver Lwr FWD Gap Plates to IR-2 0.05 days 8/28/04 8/28/04 327
329 Install Lwr FWD Gap Filler Plates 0.25 days 8/28/04 8/28/04 328
330 INSTALL UPPER STEEL 1.7 days 8/28/04 8/31/04331 Deliver FWD Top Flux Bar to IR-2 - Install 0.2 days 8/28/04 8/28/04 329,319
332 Deliver Corner Plate F1 to IR-2 - Install 0.5 days 8/28/04 8/30/04 331
333 Torque Corner Plate Bolts - F1 0.5 days 8/30/04 8/30/04 332
334 Deliver Corner Plate F6 to IR-2 - Install 0.5 days 8/30/04 8/30/04 332
335 Torque Corner Plate Bolts - F6 0.5 days 8/30/04 8/31/04 334
336 Deliver UPR FWD Center Gap Plate to IR-2 - Install 0.15 days 8/30/04 8/30/04 334
337 Deliver Upr FWD Gap Plates to IR-2 0.05 days 8/30/04 8/30/04 336
338 Install Upr FWD Gap Filler Plates 0.25 days 8/31/04 8/31/04 337
339 Flux Return Steel Assembled 0 days 8/31/04 8/31/04 338
340 MISCELLANEOUS WORK 0.2 days 8/31/04 8/31/04341 Record Final Steel Movement 0.05 days 8/31/04 8/31/04 339
342 Remove Steel Position Dial Indicators 0.05 days 8/31/04 8/31/04 341
343 Remove FWD Detector Cover & FWD Beamline Cover 0.1 days 8/31/04 8/31/04 342
344 IFR WORK 0.65 days 8/31/04 9/1/04345 Install IFR Cooling Loops/Connect Hoses - FWD Bottom 0.1 days 8/31/04 8/31/04 343
346 Install IFR Cooling Loops/Connect Hoses - FWD Top 0.1 days 8/31/04 8/31/04 345
347 Install IFR Cooling Loops/Connect Hoses - BWD Top 0.1 days 8/31/04 8/31/04 346
348 Install IFR Cooling Loops/Connect Hoses - BWD Bottom 0.1 days 8/31/04 8/31/04 347
349 Fill and Start IFR Barrel Cooling System 0.25 days 8/31/04 9/1/04 348
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE,FW
8/31
BBR,HC
BBR,HC
BBR,HC
BBR,HC,FC
BBR,HC,FC
BBR,HC,BE,BW
BBR,HC,BE,BW
BBR,IFR
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 23
2004 Installation Schedule
ID Task Name Duration Start Finish Predecessors
350 PREP FOR DETECTOR CLOSE-UP (One 10-hour Shift) 4.15 days 8/31/04 9/4/04351 ADJUST SOLENOID SUPPORTS 1.2 days 8/31/04 9/1/04352 Deliver Solenoid Radial Support Arms to IR-2 0.1 days 8/31/04 8/31/04 339
353 Install Solenoid Radial Support Arm - FWD Lwr West 0.1 days 8/31/04 8/31/04 352,338
354 Install Solenoid Radial Support Arm - Fwd Lwr East 0.1 days 8/31/04 8/31/04 353
355 Connect and Tension Solenoid External Axial Support Rods - Lwr FWD West & Lwr Fwd East 0.25 days 8/31/04 8/31/04 354
356 Adjust Solenoid External Radial Support Wedge - Upr Fwd West 0.05 days 8/31/04 8/31/04 355
357 Adjust Solenoid External Radial Support Wedge - Upr FWD East 0.05 days 8/31/04 8/31/04 356
358 Adjust Solenoid External Radial Support Wedge - Upr Bwd East 0.05 days 8/31/04 8/31/04 357
359 Adjust Solenoid External Radial Support Wedge - Upr Bwd West 0.05 days 9/1/04 9/1/04 358
360 Install Solenoid Radial Support Arm - Upr FWD West 0.1 days 9/1/04 9/1/04 359
361 Install Solenoid Radial Support Arm - Upr FWD East 0.1 days 9/1/04 9/1/04 360
362 Connect and Tension Solenoid External Axial Support Rods - Upr Fwd West & Upr Fwd East 0.25 days 9/1/04 9/1/04 361
363 Solenoid Supports Adjusted 0 days 9/1/04 9/1/04 362
364 INSTALL SHIELDING 3.2 days 9/1/04 9/4/04365 Install FWD IFR Background Shield Wall 1 day 9/1/04 9/2/04 361
366 Install Shielding in Shield Wall Cable Tray Opening 1 day 9/1/04 9/2/04 361
367 Remove Upper Electronics House to East Detector Stairway 0.1 days 9/2/04 9/2/04 365
368 Replace Lower West Electronics House Walkway 0.1 days 9/2/04 9/2/04 367
369 Assemble Shield Wall 2 days 9/2/04 9/4/04 368
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,Crane,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,CRYO,FE,FW
9/1
BBR,HC,Crane,FC
BBR,HC,Crane
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 24
2004 Installation Schedule
ID Task Name Duration Start Finish Predecessors
370 CLOSE DETECTOR (One 10-hour Shift) 2.3 days 9/4/04 9/8/04371 Deliver BWD End Plug, Lead Horseshoe and DIRC Cylinder to IR-2 0.2 days 9/4/04 9/4/04 369,363,339
372 Install BWD End Plug, Lead Horseshoe and DIRC Cylinder 0.25 days 9/4/04 9/4/04 371
373 Remove EQ Brace - Upr FWD East 0.15 days 9/4/04 9/7/04 372
374 Remove EQ Brace - Upr Fwd West 0.15 days 9/7/04 9/7/04 373
375 Remove EQ Brace - Lwr Fwd East 0.1 days 9/7/04 9/7/04 374
376 Close FWD East End Door 0.15 days 9/7/04 9/7/04 375,345
377 Remove Manlift 1 - Fwd West 0.05 days 9/7/04 9/7/04 376
378 Remove EQ Brace - Lwr FWD West 0.1 days 9/7/04 9/7/04 377
379 Close FWD West End Door 0.15 days 9/7/04 9/7/04 378
380 Remove EQ Brace - Upr BWD West 0.15 days 9/7/04 9/7/04 379,348
381 Remove Manlift 2 - BWD West 0.05 days 9/7/04 9/7/04 380
382 Remove EQ Brace - Lwr BWD West 0.1 days 9/7/04 9/8/04 381
383 Remove EQ Brace - Upr BWD East 0.15 days 9/8/04 9/8/04 382
384 Remove Manlift 3 - BWD East 0.05 days 9/8/04 9/8/04 383
385 Remove EQ Brace - Lwr BWD East 0.1 days 9/8/04 9/8/04 384
386 Close BWD West End Door 0.15 days 9/8/04 9/8/04 385
387 Close BWD East End Door 0.15 days 9/8/04 9/8/04 386
388 Close Curtain Wall 0.1 days 9/8/04 9/8/04 387
389 Detector Closed 0 days 9/8/04 9/8/04 388
BBR,HC,Crane,BC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FE
BBR,HC,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FW
BBR,HC,FW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,BW
BBR,HC,BE
BBR,HC,Crane
9/8
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 25
2004 Critical Path
ID Task Name Duration Start Finish Predecessors
1 SUMMER DOWN 2004 57.75 days 7/1/04 9/8/042 Begin Summer Down 0 days 7/1/04 7/1/04
3 OPEN DETECTOR (Two 8-hour Shifts) 2 days 7/1/04 7/2/044 Open IR-2 Curtain Wall 0.1 days 7/1/04 7/1/04 2
5 Open FWD End Door - East 0.1 days 7/1/04 7/1/04 4
6 Install EQ Brace - FWD Lwr East 0.15 days 7/1/04 7/1/04 5
7 Insert Manlift 1 - FWD East 0.05 days 7/1/04 7/1/04 6
8 Install EQ Brace - FWD Upr East 0.1 days 7/1/04 7/1/04 7
9 Open Fwd End Door - West 0.1 days 7/1/04 7/1/04 8
10 Install EQ Brace - FWD Lwr West 0.15 days 7/1/04 7/1/04 9
11 Install EQ Brace - FWD Upr West 0.1 days 7/1/04 7/1/04 10
12 Remove DIRC Cyl, Lead and BWD End plug 0.25 days 7/1/04 7/2/04 11
13 Transport DIRC Cyl, Lead and BWD End Plug to IR-12 0.1 days 7/2/04 7/2/04 12
14 Open BWD End Door - West 0.1 days 7/2/04 7/2/04 13
15 Install EQ Brace - BWD Lwr West 0.15 days 7/2/04 7/2/04 14
16 Insert Manlift 2 - BWD West 0.05 days 7/2/04 7/2/04 15
17 Install EQ Brace - BWD Upr West 0.1 days 7/2/04 7/2/04 16
18 Open BWD End Door - East 0.1 days 7/2/04 7/2/04 17
19 Install EQ Brace - BWD Lwr East 0.15 days 7/2/04 7/2/04 18
20 Insert Manlift 3 - BWD East 0.05 days 7/2/04 7/2/04 19
21 Install EQ Brace - BWD Upr East 0.1 days 7/2/04 7/2/04 20
22 Detector Open and EQ Braced 0 days 7/2/04 7/2/04 21
7/1
BBR,HC,Crane
BBR,HC,FE
BBR,HC,Crane,FE
BBR,HC,Crane,FE
BBR,HC,Crane,FE
BBR,HC,FW
BBR,HC,Crane,FW
BBR,HC,Crane,FW
BBR,HC,Crane,BC
BBR,HC,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
7/2
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 26
2004 Critical PathID Task Name Duration Start Finish Predecessors
23 PREP TO REMOVE STEEL (Two 8-Hour Shifts) 6.4 days 7/1/04 7/9/0431 RELEASE SOLENOID SUPPORTS (Day Shift) 1.2 days 7/3/04 7/6/0432 Unbolt Solenoid External Axial Support Rods - Upr FWD East & Upr FWD West 0.25 days 7/3/04 7/3/04 22
33 Remove Solenoid Radial Support Arm - FWD Upr East 0.1 days 7/3/04 7/3/04 32
34 Remove Solenoid Radial Support Arm - FWD Upr West 0.1 days 7/3/04 7/3/04 33
35 Release Solenoid External Radial Wedge Support - FWD Upr East 0.05 days 7/3/04 7/3/04 34
36 Release Solenoid External Radial Wedge Support - FWD Upr West 0.05 days 7/3/04 7/3/04 35
37 Release Solenoid External Radial Wedge Support - BWD Upr East 0.05 days 7/3/04 7/3/04 36
38 Release Solenoid External Radial Wedge Support - BWD Upr West 0.05 days 7/3/04 7/3/04 37
39 Unbolt Solenoid External Axial Support Rods - Lwr East & Lwr West 0.25 days 7/3/04 7/3/04 38
40 Remove Solenoid Radial Support Arm - FWD Lwr East 0.1 days 7/3/04 7/3/04 39
41 Remove Solenoid Radial Support Arm - FWD Lwr West 0.1 days 7/6/04 7/6/04 40
42 Transport Solenoid Radial Support Arms to IR-12 0.1 days 7/6/04 7/6/04 41
43 Solenoid Supports Released 0 days 7/6/04 7/6/04 42
44 REMOVE SHIELDING (Day Shift) 3 days 7/6/04 7/9/0445 Disassemble Shield Wall Blocks 2 days 7/6/04 7/8/04 43
46 Remove FWD IFR Background Shield Wall 1 day 7/8/04 7/9/04 45
47 MISCELLANEOUS PREP WORK (Swing Shift) 4.4 days 7/3/04 7/9/0455 Remove Lower West Electronics House Walkway - Take to Shop 0.1 days 7/9/04 7/9/04 46,54
56 Install Upper Electronics House to East Detector Stairway 0.1 days 7/9/04 7/9/04 55
57 REMOVE STEEL (Two 8-hour Shifts) 2.45 days 7/9/04 7/12/0458 Remove Upr FWD Center Gap Plate - Transport to IR-12 0.15 days 7/9/04 7/9/04 56
59 Remove Corner Plate F1 - Transport to IR-12 0.4 days 7/9/04 7/9/04 58
61 Remove Corner Plate F6 - Transport to IR-12 0.4 days 7/9/04 7/10/04 59
63 Remove Flux Bar - FWD Top - Transport to IR-12 0.2 days 7/10/04 7/10/04 61
64 Remove Lwr FWD Center Gap Plate - Transport to IR-12 0.2 days 7/10/04 7/10/04 63
65 Remove Corner Plate F3 - Transport to IR-12 0.4 days 7/10/04 7/12/04 64
67 Remove Corner Plate F4 - Transport to IR-12 0.4 days 7/12/04 7/12/04 65
68 Record Steel Movement 0.05 days 7/12/04 7/12/04 67
69 Remove Flux Bar - FWD Bottom - Transport to IR-12 0.25 days 7/12/04 7/12/04 68
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,CRYO,Crane,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,CRYO,Crane,FW
7/6
BBR,HC,RIG,Crane
BBR,HC,Crane,FC
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC
BBR,HC,Crane,FC
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 27
2004 Critical PathID Task Name Duration Start Finish Predecessors
70 BOTTOM SEXTANT DETECTOR REPLACEMENT 19.45 days 7/12/04 8/4/0472 Transport Lower Vertical Positioner Components to IR-2 0.1 days 7/12/04 7/12/04 69
73 Install Lower General Fixture Vertical Positioner 0.25 days 7/12/04 7/13/04 72
74 Transport RPC Removal Hardware to IR-2 0.1 days 7/13/04 7/13/04 73
75 Remove 18 Layers of RPCs & Dispose (2hr 53min/layer)(Pull & Cut) 4 days 7/13/04 7/17/04 74
76 Deliver LST Modules to IR-2 0.15 days 7/17/04 7/17/04 75
77 Install 12 Layers of LSTs (7hr 30min/layer) (One 10-hour Shift) 9 days 7/17/04 7/28/04 76
78 Transport Bottom Brass Absorber Plates to IR-2 (84 Plates) 0.1 days 7/28/04 7/28/04 77
79 Install 6 Layers of Brass Absorber - Bottom (51min/plate) 5.5 days 7/28/04 8/4/04 78
80 Bottom Sextant LSTs & Brass Absorber Installed 0 days 8/4/04 8/4/04 79
81 Remove Lower General Fixture Vertical Positioner - Transport to IR-12 0.25 days 8/4/04 8/4/04 80
82 SCHEDULE STATUS - DO WE PROCEED? 0 days 8/4/04 8/4/04 8183 TOP SEXTANT DETECTOR REPLACEMENT 15.7 days 8/4/04 8/21/0485 Transport Upper Vertical Positioner Components to IR-2 0.1 days 8/4/04 8/4/04 82
86 Install Upper General Fixture Vertical Positioner 0.25 days 8/4/04 8/4/04 85
87 Remove 18 Layers of RPCs & Dispose - Top (1hr 48min/lyr) 2.5 days 8/4/04 8/7/04 86
88 Transport RPC removal Hardware to IR-12 0.1 days 8/7/04 8/7/04 87
89 Deliver LST Modules to IR-2 0.15 days 8/7/04 8/7/04 88
90 Install 12 Layers of LSTs (6hr 40 min/lyr) (One 10-hour Shift) 8 days 8/7/04 8/17/04 89
94 LST CABLING, HV & GAS (Owl Shift) 25.45 days 7/28/04 8/26/04102 Install Wireways and ConnectSignal Cabling - Top FWD 2 days 8/17/04 8/19/04 90
103 Install/Connect HV Cabling - Top FWD 1 day 8/19/04 8/20/04 102
104 Install/Connect Gas Lines - Top FWD 1 day 8/20/04 8/21/04 103
105 Install Wireways and Connect Signal Cabling - Top BWD 2 days 8/21/04 8/24/04 104
106 Install/Connect HV Cabling - Top BWD 1 day 8/24/04 8/25/04 105
107 Install/Connect Gas Lines - Top BWD 1 day 8/25/04 8/26/04 106
108 Top LSTs Connected With Cabling, HV & Gas 0 days 8/26/04 8/26/04 107
110 LST System Commissioning - Top 0 days 8/26/04 8/26/04 108
111 Remove Upper General Fixture Vertical Positioner - Transport to IR-12 0.5 days 8/26/04 8/26/04 110,109
BBR,HC,Crane,FC
BBR,HC,Crane,FC,BE,BW
BBR,HC,LST,Crane,FC,BE,BW
BBR,HC,Crane,FC,BE,BW
8/4
BBR,HC,Crane,FC
8/4
BBR,HC,Crane,FC
BBR,HC,Crane,FC,BE,BW
BBR,HC,LST,Crane,FC,BE,BW
BBR,LST,FC
BBR,LST,FC
BBR,LST,FC
BBR,LST,BE,BW
BBR,LST,BE,BW
BBR,LST,BE,BW
8/26
8/26
BBR,HC,Crane,FC
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 28
2004 Critical PathID Task Name Duration Start Finish Predecessors
112 INSTALL STEEL (Two 8-hour Shifts) 4.2 days 8/26/04 9/1/04113 INSTALL LOWER STEEL 1.75 days 8/26/04 8/28/04114 Deliver FWD Bottom Flux Bar to IR-2 - Install 0.25 days 8/26/04 8/27/04 111
115 Deliver Corner Plate F3 to IR-2 - Install 0.5 days 8/27/04 8/27/04 114
117 Deliver Corner Plate F4 to IR-2 - Install 0.5 days 8/27/04 8/28/04 115
119 Deliver LWR Center Gap Plate to IR-2 - Install 0.15 days 8/28/04 8/28/04 117
120 Deliver Lwr FWD Gap Plates to IR-2 0.05 days 8/28/04 8/28/04 119
121 Install Lwr FWD Gap Filler Plates 0.25 days 8/28/04 8/28/04 120
122 INSTALL UPPER STEEL 1.7 days 8/28/04 8/31/04123 Deliver FWD Top Flux Bar to IR-2 - Install 0.2 days 8/28/04 8/28/04 121,111
124 Deliver Corner Plate F1 to IR-2 - Install 0.5 days 8/28/04 8/30/04 123
126 Deliver Corner Plate F6 to IR-2 - Install 0.5 days 8/30/04 8/30/04 124
128 Deliver UPR FWD Center Gap Plate to IR-2 - Install 0.15 days 8/30/04 8/30/04 126
129 Deliver Upr FWD Gap Plates to IR-2 0.05 days 8/30/04 8/30/04 128
130 Install Upr FWD Gap Filler Plates 0.25 days 8/31/04 8/31/04 129
131 Flux Return Steel Assembled 0 days 8/31/04 8/31/04 130
142 PREP FOR DETECTOR CLOSE-UP (One 10-hour Shift) 4.15 days 8/31/04 9/4/04143 ADJUST SOLENOID SUPPORTS 1.2 days 8/31/04 9/1/04144 Deliver Solenoid Radial Support Arms to IR-2 0.1 days 8/31/04 8/31/04 131
145 Install Solenoid Radial Support Arm - FWD Lwr West 0.1 days 8/31/04 8/31/04 144,130
146 Install Solenoid Radial Support Arm - Fwd Lwr East 0.1 days 8/31/04 8/31/04 145
147 Connect and Tension Solenoid External Axial Support Rods - Lwr FWD West & Lwr Fwd East 0.25 days 8/31/04 8/31/04 146
148 Adjust Solenoid External Radial Support Wedge - Upr Fwd West 0.05 days 8/31/04 8/31/04 147
149 Adjust Solenoid External Radial Support Wedge - Upr FWD East 0.05 days 8/31/04 8/31/04 148
150 Adjust Solenoid External Radial Support Wedge - Upr Bwd East 0.05 days 8/31/04 8/31/04 149
151 Adjust Solenoid External Radial Support Wedge - Upr Bwd West 0.05 days 8/31/04 8/31/04 150
152 Install Solenoid Radial Support Arm - Upr FWD West 0.1 days 9/1/04 9/1/04 151
153 Install Solenoid Radial Support Arm - Upr FWD East 0.1 days 9/1/04 9/1/04 152
156 INSTALL SHIELDING 3.2 days 9/1/04 9/4/04157 Install FWD IFR Background Shield Wall 1 day 9/1/04 9/2/04 153
159 Remove Upper Electronics House to East Detector Stairway 0.1 days 9/2/04 9/2/04 157
160 Replace Lower West Electronics House Walkway 0.1 days 9/2/04 9/2/04 159
161 Assemble Shield Wall 2 days 9/2/04 9/4/04 160
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FC
BBR,HC,Crane,FE,FW
8/31
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,FE,FW
BBR,HC,CRYO,FW
BBR,HC,CRYO,FE
BBR,HC,CRYO,Crane,FW
BBR,HC,CRYO,Crane,FE
BBR,HC,Crane,FC
BBR,HC,Crane
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 29
2004 Critical Path
ID Task Name Duration Start Finish Predecessors
162 CLOSE DETECTOR (One 10-hour Shift) 2.3 days 9/4/04 9/8/04163 Deliver BWD End Plug, Lead Horseshoe and DIRC Cylinder to IR-2 0.2 days 9/4/04 9/4/04 161,155,131
164 Install BWD End Plug, Lead Horseshoe and DIRC Cylinder 0.25 days 9/4/04 9/4/04 163
165 Remove EQ Brace - Upr FWD East 0.15 days 9/4/04 9/4/04 164
166 Remove EQ Brace - Upr Fwd West 0.15 days 9/7/04 9/7/04 165
167 Remove EQ Brace - Lwr Fwd East 0.1 days 9/7/04 9/7/04 166
168 Close FWD East End Door 0.15 days 9/7/04 9/7/04 167,137
169 Remove Manlift 1 - Fwd West 0.05 days 9/7/04 9/7/04 168
170 Remove EQ Brace - Lwr FWD West 0.1 days 9/7/04 9/7/04 169
171 Close FWD West End Door 0.15 days 9/7/04 9/7/04 170
172 Remove EQ Brace - Upr BWD West 0.15 days 9/7/04 9/7/04 171,140
173 Remove Manlift 2 - BWD West 0.05 days 9/7/04 9/7/04 172
174 Remove EQ Brace - Lwr BWD West 0.1 days 9/7/04 9/7/04 173
175 Remove EQ Brace - Upr BWD East 0.15 days 9/8/04 9/8/04 174
176 Remove Manlift 3 - BWD East 0.05 days 9/8/04 9/8/04 175
177 Remove EQ Brace - Lwr BWD East 0.1 days 9/8/04 9/8/04 176
178 Close BWD West End Door 0.15 days 9/8/04 9/8/04 177
179 Close BWD East End Door 0.15 days 9/8/04 9/8/04 178
180 Close Curtain Wall 0.1 days 9/8/04 9/8/04 179
181 Detector Closed 0 days 9/8/04 9/8/04 180
BBR,HC,Crane,BC
BBR,HC,Crane,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FE
BBR,HC,FE
BBR,HC,Crane,FW
BBR,HC,Crane,FW
BBR,HC,FW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BW
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,Crane,BE
BBR,HC,BW
BBR,HC,BE
BBR,HC,Crane
9/8
H2 H1 H2 H1 H2 H12003 2004 2005 2006
October 22, 2003 H.J. Krebs 30
Conclusions and Comments• 10 weeks of scheduled work time is needed to replace RPCs with 6
layers of brass absorber and 12 layers of LST detectors in both the top and bottom sextants if NOTHING goes wrong– Additional 4 days of PPS certification almost a certainty– Some time lost for tours and/or photography is a probability– No time allotted to replace LSTs that are not functioning properly after
installation – overly optimistic– 17 days allotted for commissioning of lower sextant LSTs but only 2
days are allotted for commissioning of upper sextant LSTs– Many tasks have NEVER been performed previously – could be a long
learning curve– Will lose 1:1 on schedule time for any of the above
• There may be some schedule optimization possible – but not much. From the critical path it is determined that the schedule is:– Driven by crane usage – 1 crane– Driven by LST installation – 1 installation team– Most everyone is working in the same place – FWD end of barrel
October 22, 2003 H.J. Krebs 31
Conclusions and Comments• Our mechanical installation team is aging
– Have some young replacements but not as experienced• A mechanical breakdown of the crane would have an
adverse schedule effect• An agreement must be worked out to deal with the
VESDA system during this installation period– Have experienced significant schedule delays in the past by us
setting off the fire alarms• A two month down would result in a reduced scope of
work– Only one sextant could have the brass absorber/LST
replacement, or– Remove RPCs and replace with brass in both sextants but NO
LST installation (just an opinion), or– Some other option
• Our goal is to be ready as early as possible to take advantage of any potential schedule advancement.