October 2012 Update
-
Upload
city-of-pearland -
Category
Documents
-
view
218 -
download
1
description
Transcript of October 2012 Update
![Page 1: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/1.jpg)
Project Update
October 8, 2012
![Page 2: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/2.jpg)
Roadway Projects
![Page 3: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/3.jpg)
• TxDOT reviewing Categorical Exclusion (CE) documents
• Wetland field work and report completed, request for jurisdictional determination sent to USACE
Pearland Parkway
![Page 4: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/4.jpg)
• Completed 100% review of plans and specifications and submitted to TXDOT August 1st
• Advertised for bids • Bid opening scheduled for Thursday, October 11th
ITS Project
![Page 5: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/5.jpg)
• Max Road – Negotiated scope and fee sent to TxDOT for review and
approval
• Fite Road – Staff is reviewing the scope and proposal
TIP Projects Update
![Page 6: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/6.jpg)
• Miller Ranch Road– Open
• O’Day Road – Open
• Old Alvin Road – Expected to open today
TxDOT Off-System Bridge Replacements
![Page 7: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/7.jpg)
TxDOT Off-System Bridge Replacements
![Page 8: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/8.jpg)
• Major lane shift was completed on September 20th
• Asphalt and base have been milled off the old road surface south of the bridge and 500 feet north of bridge
• Excavation and fill began along the east side of the project north of McHard/Brookside
Cullen Parkway – Phase II
![Page 9: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/9.jpg)
Phase I Streetlights– McDonald/Willits to Clear Creek
• Streetlights are operational
Dixie Farm Road
![Page 10: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/10.jpg)
![Page 11: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/11.jpg)
Phase II – Mary’s Creek Bypass to SH35• Punchlist work has been completed
Dixie Farm Road
![Page 12: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/12.jpg)
• Brick pavers have been installed around the railroad crossing arms
• One year maintenance continues in the median
Walnut Reconstruction
![Page 13: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/13.jpg)
• All outstanding issues have been resolved• The contractor has completed all the re-work with
the exception of injecting grout into the Town Ditch channel bottom which scheduled for Oct. 23rd
Orange Street
![Page 14: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/14.jpg)
• Advertised for bidders August 29th and September 5th
• Pre-bid meeting held September 6th
• Bid opening held September 13th
• Preparing for Council award on October 8th
Business Center Drive
![Page 15: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/15.jpg)
• Broadway/Main Street intersection– West bound lanes of FM518 have now been completed– Work on permanent traffic signals on this intersection is
scheduled to begin in the next week to 10 days• Bridge work continuing
– Center portions of the bridges at Town Ditch and Hickory Slough are now complete
• Drainage– Drainage laterals have been installed in the area between
FM518 and Orange
SH35 – BW8 to FM518
![Page 16: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/16.jpg)
![Page 17: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/17.jpg)
![Page 18: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/18.jpg)
• Received TxDOT comments on plan set and received information regarding required submittals for permitting
• Staff are coordinating with BNSF to perform all of the work at this crossing at one point in time
Quiet Zone Railroad Crossing
![Page 19: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/19.jpg)
Drainage Projects
![Page 20: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/20.jpg)
Diversion Ditch• Haddock Construction awarded slope paving through
BDD4 for section between CR 143 & Station 112+50• Hauling contract for segment between Bailey Rd (CR101)
and CR100 was awarded to David Wight Construction• BDD4 has begun clearing/grubbing operations on the
segment between Bailey Rd (CR101) and CR100
Cowart Creek Diversion
![Page 21: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/21.jpg)
Pump Station• Second vertical lift of wet well poured and sank to final
grade using caisson method. • Seal slab on bottom slab of wet well poured• Third and final lift of wet well poured• Pond pumping started todayRe-grading of Roadside Ditches• Consultant continued working to resolve utility conflicts
on Wayne Dr. and depth of cover issues on Holland. • City is assisting the engineer in obtaining utility
information from AT&T
Cowart Creek Diversion (cont’d)
![Page 22: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/22.jpg)
![Page 23: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/23.jpg)
![Page 24: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/24.jpg)
![Page 25: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/25.jpg)
![Page 26: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/26.jpg)
• 30% plans being reviewed by City staff
Westchester Sidewalk and Drainage
![Page 27: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/27.jpg)
• Staff is reviewing 90% PER• Geotech field work completed• Reviewing options for implementing a regional
plan
Cullen Regional Detention
![Page 28: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/28.jpg)
Facility Projects
![Page 29: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/29.jpg)
• 60% plan review competed• 90% plans due the end of this week• Reviewing construction estimate
Westside Library
![Page 30: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/30.jpg)
Parks
![Page 31: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/31.jpg)
• Council approved Construction and Construction Materials Testing contracts
• Staff executed (deductive) Change Order No. 1• Conducted the Pre-Construction meeting for
Detention Pond and issued Notice to Proceed• Staff reviewing 60% plans for the sports complex
Hickory Slough Detention at Max Road & Max Road Sports Complex, Phase I
![Page 32: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/32.jpg)
• Reviewed plan revisions with consultant• Parks Department received notification of possible
grant funds becoming available
Dolores Fenwick Nature Center Phase II
![Page 33: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/33.jpg)
• Southgate concrete trail completed• 70% decomposed granite trail completed
South Gate & Cypress Village Parks
![Page 34: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/34.jpg)
![Page 35: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/35.jpg)
![Page 36: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/36.jpg)
• Contract negotiations completed• On Council Agenda for review & approval
Shadow Creek Ranch Park
![Page 37: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/37.jpg)
Utility Projects
![Page 38: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/38.jpg)
City of Houston Interconnect
Alice Street Water Plant• Start-up of the Turbine System was completed on
September 19th
• Producing 20KW of power at current average flows of 2.8MGD
![Page 39: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/39.jpg)
• Continuing with excavating disk filter area and 8-inch drain area
• Continue breaking/removing concrete pavement for scum pump stations
Longwood WWTP Rehabilitation
![Page 40: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/40.jpg)
![Page 41: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/41.jpg)
• Bar screen and transpactor installed, tested and accepted
• Progress meeting held September 20th
• Contractor on schedule with equipment submittals and major equipment buy out
Barry Rose WWTP Rehabilitation
![Page 42: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/42.jpg)
![Page 43: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/43.jpg)
• Hosted Open House Meeting at Jamison Middle School on September 12th
• Tree evaluation report completed on selected segments
• Determined Mary’s Creek crossing will not require a USACE permit
• Approved alternative to Woody Road alignment behind Jamison Middle School
• 15 of 16 parcels acquired or closing
Hatfield Basin Trunk Sewer
![Page 44: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/44.jpg)
• Contractor has completed the wet well structure. Influent manhole has been set and the influent line has been partially installed. Electrical rough-in has been completed and riser pipes have been installed
Twin Creek Regional Lift Station
![Page 45: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/45.jpg)
![Page 46: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/46.jpg)
Far Northwest Wastewater Treatment Plant Improvements
• Staff reviewed 60% plans and provided comments• Engineer to review requested revisions
![Page 47: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/47.jpg)
Old Alvin 20” Waterline
• Continued working with the Acquisition Manager to acquire ROE and/or easements
• 10 of 13 parcels acquired or closing• Received 100% plans and specifications along
with responses to the 90% review
![Page 48: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/48.jpg)
BellaVita Waterline Interconnect
• Harris County approved the permit• Advertised for bidders on August 29th &
September 5th
• Mandatory pre-bid held September 6th • Bid opening held September 13th
![Page 49: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/49.jpg)
SH35 South Water Line
• Substantial completion punchlist completed• Final walk through September 13th
![Page 50: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/50.jpg)
• Survey work completed and waiting for proposed alignment
• Freese and Nichols determining if geotechnical testing can work around areas we do not have a ROE
• Engineer reviewing hydraulic analysis again to determine if roadway can be lower than proposed 3 ft. elevation previously reported
McHard Road 16” Water Line & Roadway PER
![Page 51: October 2012 Update](https://reader030.fdocuments.us/reader030/viewer/2022032612/568c33931a28ab02358d37d3/html5/thumbnails/51.jpg)
Project Update
Questions/Comments
October 8, 2012