October 2010 Presentation

51
Project Update November 8 th , 2010

description

october_2010_presentation

Transcript of October 2010 Presentation

Page 1: October 2010 Presentation

Project Update

November 8th, 2010

Page 2: October 2010 Presentation

Roadway Projects

Page 3: October 2010 Presentation

• Approximately 90% of NB lanes poured• Pavement at all intersections completed• Signal installations at all intersections in

progress• Working on Retaining Wall north side of

Hickory Slough• Completed environmental Re-Evaluation

Cullen Parkway

Page 4: October 2010 Presentation

Cullen Parkway

Page 5: October 2010 Presentation

Construction phase II – Veterans Dr to Pearland Parkway

• Contractor completed partial work on minor drainage improvements at ponds

• Contractor conducted survey of paving grades for possible grinding of rough spots and submitted report to staff

• Continued working with CenterPoint with work order for streetlights

• John Lizer streetlights installed

Magnolia Road

Page 6: October 2010 Presentation

Construction Phase III – Morgan to Harkey and CR 89

• Enterprise Pipeline preparing billing information for submittal

• Placed concrete for left turn lane and installed traffic signal at Morgan/Southfork intersection

• Continued communication with the contractor regarding trench settlement locations

• Completed paving for Cullen southbound lanes• Cullen to be opened November 8th or 9th

Magnolia Road

Page 7: October 2010 Presentation
Page 8: October 2010 Presentation

Phase I - Beamer to FM518

• TxDOT refund check for $869,525.67 has been received

Dixie Farm Road

Page 9: October 2010 Presentation

Phase II – Mary’s Creek Bypass to SH35

• Continued excavation activities and lime stabilization in future southbound main lane area

• Paving SB lanes underway• Steel in place for most of the remaining

areas to be paved• All intersection paving completed

Dixie Farm Road

Page 10: October 2010 Presentation
Page 11: October 2010 Presentation

Detention – East Mary’s Creek• Granted Substantial Completion certificate

on September 27th

• Contractor completed punch list items and corrected fence and pond grades

• Working on project cleanup and closeout• Approx. $200K+ below contract amount• Approx. $1.5M under original budget

Dixie Farm Road

Page 12: October 2010 Presentation

• Jack and Bore final run began October 25th

and is expected to be complete in approximately 15 days

• Aluminum Box Culvert installation is complete; tie-ins and backfill are underway

• Mykawa Orange intersection will open after Thanksgiving.

Town Ditch Phase III

Page 13: October 2010 Presentation
Page 14: October 2010 Presentation

• TxDOT has verbally agreed to adjust their design to match the Orange Street design

• Engineer is met with Construction Manager on site to verify utility relocation

• Held Pre-bid conference on October 17th; eight contractors attended

• Bid opening scheduled for November 9th

Orange Street

Page 15: October 2010 Presentation

• One parcel remains but we have a ROE• Finalized utility relocations• Negotiating Construction Management

services• Provided plans and specs to the CM for

constructability review• Pre-bid held on November 3rd• Bid opening scheduled for November 18th

Walnut Reconstruction

Page 16: October 2010 Presentation

• 100% plans currently under review• Engineer began revising plans to incorporate

drainage changes• Held kickoff meeting for Noise Impact

Analysis contract and issued NTP• ROW acquisition underway – 55 of 65

parcels acquired

Bailey Road (Veterans to FM1128)

Page 17: October 2010 Presentation

• Final clean-up in progress• Roadway will open when signal/intersection at

Cullen is complete• Continued work with CenterPoint to install

streetlights along the new roadway

McHard Road (Country Place to Cullen)

Page 18: October 2010 Presentation

McHard Road (Country Place to Cullen)

Page 19: October 2010 Presentation

McHard Road (Soundwall Construction)

• Submittals for materials approved• Working on construction and material delivery

schedule• Continued utility coordination

Page 20: October 2010 Presentation

• Awaiting letter from TxDOT for balance of City’s cost of the utilities based on the AFA (est. $400,000)

• City and TxDOT projects underway• Working with TxDOT to address local business

concerns• Signals have been switched to split-phase timing• Submitted for USACE permit for low water crossing• Mitigation plans completed; waiting on permit and

TxDOT approval

SH35 – BW8 to FM518

Page 21: October 2010 Presentation

Drainage Projects

Page 22: October 2010 Presentation

Detention Pond• Pond A approximately 96% excavated• Hauling activities and fill placement at

second fill site continued• Began excavation of Pond B as well

Cowart Creek Diversion

Page 23: October 2010 Presentation
Page 24: October 2010 Presentation
Page 25: October 2010 Presentation

Diversion Ditch• East – West corridor acquisition complete• Conoco Phillips issued NTP• Began diversion ditch south of the pond• JKC and ESPA submitted design plans for

N/S ditches; meeting scheduled with Brazoria County to discuss criteria

Cowart Creek Diversion

Page 26: October 2010 Presentation

• Contractor completing punch list items• Harris completed work at the Bailey pond to

fill in washed out area under pilot channel at outfall to Cowart’s Creek, low spots were also filled in

• BDD4 submitted invoice for final payment

Bailey & Veterans Regional Detention

Page 27: October 2010 Presentation

Facility Projects

Page 28: October 2010 Presentation

Old PD Renovations

• Off-site storage relocation to the old jail area complete

• Remainder of renovation on hold

Page 29: October 2010 Presentation

• Held Pre-Bid meeting on Oct. 21st

• Plans in for permitting• Submitted plan package for LEED Certification• Bids opened November 2nd

• Approximately 30% below estimates• Apparent low bid approx. $3.2M

Hillhouse Road Service Center

Page 30: October 2010 Presentation

• TDLR inspection conducted and report submitted, with minor corrections

• Working to complete final change order

Recreation and Natatorium Center

Page 31: October 2010 Presentation

• Facility Access Control and Security system is in testing mode

• Completed HVAC system changes in the mode of operation capabilities

• Waiting on parts to replace air control damper in Jail air handler

• Completed electrical and HVAC system and equipment audit on facility with Program Manager

• Working towards building commissioning

Public Safety Building

Page 32: October 2010 Presentation

• Steel erection and interior framing are complete • The brick is approximately 50% complete• Alerting system for the facility will be bid

separately from the construction contract• Dewatering and Sanitary sewer tie-in and bore

dewatering will be completed early in November

Fire Station #5

Page 33: October 2010 Presentation
Page 34: October 2010 Presentation

• FDC received bids• $997,000• Building permit issued• Contractor started site preparation• Requested submittals from architect

Fire Station #6

Page 35: October 2010 Presentation

• Renovations to office areas complete, punchlist items being corrected

• New furniture items installed• Warranty items sent to contractors attention

Animal Control Expansion

Page 36: October 2010 Presentation

Parks

Page 37: October 2010 Presentation

• Awaiting plan of action from Parks Department

Trail Connectivity

Page 38: October 2010 Presentation

• Council approved design contract with Jacobs• Kick off meeting scheduled for early November

Sports Complex at Max Road

Page 39: October 2010 Presentation

Utility Projects

Page 40: October 2010 Presentation

30” Waterline Interconnect

• Installation of waterline under Beltway 8 complete• 3,752 feet of waterline has been installed• Casing for waterline has been installed under U of H

driveway• Began installation of casing at Kinder Morgan

Pipeline crossing, and installation of waterline at CenterPoint crossing

• CoH 72” line scheduled for completion in March 2011

City of Houston Interconnect

Page 41: October 2010 Presentation
Page 42: October 2010 Presentation

City of Houston Interconnect

Alice Street Water Plant

• Select fill for the Ground Storage Tank has been completed

• Temporary road for Ground Storage Tank construction has been completed

• Majority of underground electrical duct banks have been installed

• Began installation of vertical turbine cans at pump building

Page 43: October 2010 Presentation
Page 44: October 2010 Presentation

• Contractor has worked on the east and west slopes of the basin

• Contractor has finished grading the back wash basin area

• Change Order processed to address slope failure on the west bank

Surface Water Reservoir

Page 45: October 2010 Presentation

Knapp Road LS & SH35 Utilities

Page 46: October 2010 Presentation

• PEDC Funded• 100% plans completed. • Easement donations pursued by PEDC• Project on hold; awaiting direction from PEDC

Hooper Road Utilities

Page 47: October 2010 Presentation

• PER submitted for approval• Negotiating design contract with Malcom Pirnie;

submit for Council approval in November

Longwood WWTP Rehabilitation

Page 48: October 2010 Presentation

• Staff met with BBI to discuss comments on the draft Preliminary Engineering Report

• Revising PER to address City comments

Barry Rose WWTP Rehabilitation

Page 49: October 2010 Presentation

• Held substantial walk through inspections of Knapp Road lift station and Blockbuster grinder pump station

• Punch list items noted• All facilities have been placed in operation• Project completed approximately $200K under

contract amount

Knapp Road LS & SH35 Utilities

Page 50: October 2010 Presentation
Page 51: October 2010 Presentation

Project Update

Questions/Comments

November 8th, 2010