October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of...

15
October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the schedule Integration and Installation

description

October 18, Muon Meeting B. Schmidt Comments: Sequence of chamber installation needs to be aligned to chamber production/dressing schedule. We should try to accelerate the installation of the chambers on the PZ-side, to finish before the sector test. Installation Schedule under Discussion

Transcript of October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of...

Page 1: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 1Muon Meeting B. Schmidt

Outline:

• Installation schedule under Discussion

• Status of Integration activities

• Possible modifications to the schedule

Integration and Installation

Page 2: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 2Muon Meeting B. Schmidt

Official Installation Schedule:Installation Schedule under Discussion

ID Task Name

163 Sructure behind muon/RB86164 Pre-modification to MET-CR165 Install MET-CR166 Pre- modification MET-PZ167 Install structure MET-PZ168 Electronics tower169 Design and ordering177 Electronics tower installation178 US-Side179 Assemble Muon tower US180 Install Muon Tower US181 Install panel support beams US182 Moving system M-tower US183 Nacelle system Muon US184 Install cable chain Muon US185 PZ-side186 Assemble Muon tower PZ187 Install Muon tower PZ188 Install panel support beams US189 Moving system M-tower US190 Nacelle system Muon US191 Install cable chain Muon US192 Support panel & services US193 Support panel & services PZ

Sep 26 Sep 30Oct 3 Oct 21

Sep 26 Sep 30Jan 9 Jan 27

Dec 1 Mar 10Dec 1 Sep 18

Oct 10 Oct 21Oct 24 Nov 4

Nov 24 Nov 30Dec 1 Dec 7

Dec 8 Dec 14Dec 15 Jan 11

Nov 28 Dec 9Jan 30 Feb 10

Feb 13 Feb 17Feb 20 Feb 24

Feb 27 Mar 3Mar 6 Mar 10

Jan 12 Apr 5Mar 13 Jun 2

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter

Page 3: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 3Muon Meeting B. Schmidt

Comments:• Sequence of chamber installation needs to be aligned to chamber production/dressing schedule.• We should try to accelerate the installation of the chambers on the PZ-side, to finish before the sector test.

Installation Schedule under DiscussionID Task Name

194 Muon system Installation 195 M5 US side196 M4 and M5 chamber, US side197 M3 and M4 chamber, US side198 M2 and M3 chamber, US side199 M2 chamber, US side200 M5 PZ side201 M4 and M5 chamber, PZ side202 M3 and M4 chamber, PZ side203 M3 and M2 chamber, PZ side204 M2 chamber, PZ side205 M1 chamber206 Commissioning of Muon elect.207 Chamber installation completed208 Commissioning209 Commissioning

Apr 6 Feb 23Apr 6 Apr 26

Apr 27 May 24May 25 Jun 21

Jun 22 Jul 19Jul 20 Aug 16

Aug 17 Sep 6Sep 7 Oct 11

Oct 12 Nov 15Nov 16 Dec 20

Dec 21 Feb 7Jan 8 Feb 23

Aug 17 Jan 24Feb 23 Feb 23Feb 23

Feb 5 Feb 23Feb 5 Feb 23

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter

Page 4: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 4Muon Meeting B. Schmidt

Constraints:Installation Schedule under Discussion

ID Task Name

399 Installation of Beam Pipe400 Section 1401 Section 2402 Section 3403 Section 4404 Bake out405 Commissioning406 Start Global Commissioning

May 4 Sep 15May 4 May 31

Jun 15 Jun 28Jun 29 Jul 12

Jul 13 Jul 26Aug 21 Sep 1

Sep 4 Sep 15Dec 4 Dec 4Dec 4

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter

ID Task Name

1 LHC machine2 LHC Cryo line installation 3 Sector Test

Jan 24 Dec 4

Nov 7 Dec 4

Oct Nov Dec Jan Feb4th Quarter 1st Quarter

Page 5: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 5Muon Meeting B. Schmidt

Manpower required:Resources

TimeTechn. Eng. Phys. Ind.Sup. (weeks) Techn. Eng. Phys. Ind.Sup. Sum

Support Structures General Sup.Struct. 2 0.25 2 4 8 0 1 8 17Walls + Ch.Sup. 3 1 0.25 8 24 8 2 0 34M1 (Gen,Walls,Ch.sup.,Cab.tray) 3 1 0.25 4 12 4 1 0 17

Sum 44 12 4 8 68

Services Gas Piping 0.4 2 10 0 0 4 20 24Cabling 0.4 2 16 0 0 6 32 38Cooling 0.4 2 5 0 0 2 10 12

Sum 0 0 12 62 74

Testing and Pre-assembly INFN 1 2 24 24 0 48 0 71PNPI 3 20 0 60 0 0 60CERN 1.5 9 0 0 13 0 13

Sum 24 60 61 0 145

Chamber Installation INFN 2 1 36 71 0 36 0 107PNPI 3 30 0 90 0 0 90CERN 0.5 1 13 7 0 13 0 20

78 90 49 0 217

Sum 146 162 127 70 504

LHCb Muon Manpower PlanNumber of people Manpower in Manweeks

Page 6: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 6Muon Meeting B. Schmidt

Platforms and staircases behind M5 (US-side):Integration and Installation

• Scaffolding for the cryo-line has been removed, despite the fact that the tests are not completed. . .-> Installation of the staircases and platforms started.

Page 7: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 7Muon Meeting B. Schmidt

Platforms and staircases behind M5 (PZ- side):Integration and Installation

• Design ready • Price Enquiry being launched• Installation could earliest start December 1, 2005

Page 8: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 8Muon Meeting B. Schmidt

General Support Structures:Integration and Installation

Delivery of preassembled components this week.

Work on traction system not finished.

Nacelles need ‘certificate of conformity’ to be approved by the safety commission.

Page 9: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 9Muon Meeting B. Schmidt

Proposed schedule:1. Refurbishing of zone behind M5 US-side: 10.10 – 24.10

PZ-side: 10.12 – 13.1.062. Mounting general support structure US-side 24.10 – 14.11 PZ-side: 16.1.06 – 31.1.063. Installation chamber structure (LNF) US-side: 12.1.06 – 10.2.

PZ-side: 13.2.06 – 10.3.064. Integration of nacelles and guiding system1.12 - 22.12

-> Only possible if the open safety issues don’t cause a delay (visit to company scheduled for Friday). 5. On detector cabling, gas piping M4/M5: 30.1.06 – 10.3.06

-> Cables for M2/M3 come only in Feb’06, installation only in April ’06-> Conflict with chamber installation, starting at the same time, due to nacelles, needed for both tasks.-> We have to consider buying a 3rd nacelle !

Installation of Services

Page 10: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 10Muon Meeting B. Schmidt

Conclusions

• The installation of the M2-M5 infrastructure is on the critical path.

• With the open questions (e.g. on the nacelles and the cable quality) it is difficult to take the decisions required to bring the project back on schedule.

Page 11: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 11Muon Meeting B. Schmidt

Cabling:Good news: - Best bidder for cable well within our budget - Positive experience of CMS, but not on big samples Bad news: - Prototypes have to be done.

Plan (agreed with Adalberto and CERN purchase office): - Order ~10% of LVDS and ~15% of ECS cables (for M4/M5 cryo side)-> Allows to avoid delay in chamber installation (which will start with M5 cryo side). -> In case of unexpected problems with prototype, financial losses are limited, while schedule problems are then unavoidable.Similar situation for HV-cables (same company).Situation with LV-cables to be clarified further.

Integration and Installation

Page 12: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 12Muon Meeting B. Schmidt

On detector Gas Piping:• Progress in LNF (Emiliano, Massimo)

on design of distribution box.

• Gas pipes of PEEK type turned outto be MUCH too expensive(~15 × more expensive than copper)

->Optimized design now being finalized (meet next week)->Validation tests can hopefully been done within the next 3-4

weeks

Integration and Installation

Page 13: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 13Muon Meeting B. Schmidt

Impedance (Δp) adaptation requirement: • Ensure an equal pressure drop of about 1mbar for

each individual chamber. • Old scheme:

• New scheme:

Gas Distribution Scheme

flow (l/h) pipe diam. (mm) pipe length (m) Reynolds Num velocity (m/s) Delta p (mbar)0.75 3 2 9.05 0.029 0.0350.75 0.762 0.25 36.3 0.46 1.0871.5 2 2 27.7 0.133 0.1821.5 0.5 0.02 110.4 2.1 0.928

Manifolds Distr.box Chambers3mm PEEK pipe

Capillary8mm copper pipe x16

Manifolds Distr.box Chambers4/2mm copper pipe

Capillary8mm copper pipe

x8

Page 14: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 14Muon Meeting B. Schmidt

Cooling:• Reminder about power consumption:

• Reminder of cooling strategy:

• The chambers in regions R1 and R2 have up to 24 FE-boards/chamber and hence quite a large power consumption on a small area

->We foresee to have a sort of air cooling, where air of about 17oC is blown into or around the chambers in R1 and R2 in stations M1-M3

Integration and Installation

Power Consumption (Watt) M1 M2 M3 M4 M5 SumAll FE-boards (1.8W/board) 3629 2981 2981 2074 2074 13738

FE-boards R1 and R2 (air cooled) 1555 907 907 518 518 4406IM-boards (5W/board) 0 240 240 140 140 760ODE-boards (20W/board) 960 640 640 360 360 2960SB-boards (5W/board) 240 120 120 120 120 720Sum 4829 3981 3981 2694 2694 18178

Page 15: October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

October 18, 2005 15Muon Meeting B. Schmidt

Cooling for FE-boards:• In order to avoid hot spots close to the beam pipe, air blowers are

foreseen for both sides, providing an airflow of about 400m3/h (this would be enough to remove about 2.5kW of dissipated power by air.

• Distribution principle:

Temperature reduction due to cooling:ΔT2,3 ~ 7.5oC

Hoses have 30mm diameter

• Something similar is planned for M1• Cost estimate: ~30kCHF• Schedule: Blowers for M2-M3 ready for installation in January 2006

Integration and Installation