October 16, 2013 Feed In Tariff (FIT) and Renewables Procurement in Ontario Dirk van de Waal –...
-
Upload
lamont-godwin -
Category
Documents
-
view
215 -
download
1
Transcript of October 16, 2013 Feed In Tariff (FIT) and Renewables Procurement in Ontario Dirk van de Waal –...
October 16, 2013
Feed In Tariff (FIT) and Renewables Procurement in Ontario
Dirk van de Waal – Business Analyst, Renewables Procurement
Ontario Power Authority
2
Long-Term Power System Planning
Procuring New
Supply
Enabling Conservation
Across the Province
Key Activities
Ensure reliable, cost-effective, sustainable electricity supply for Ontario.
A cleaner electricity system
• Phasing out coal by the end of 2014– 75 percent reduction in electricity sector’s carbon footprint
• Replacing coal with clean, renewable energy resources– FIT Program is helping to bring on more renewable
generation
3
System Capacity
Wind
Gas
Nuclear
Hydro
Nuclear
Gas
Coal
Hydro
Nuclear
Hydro
Wind
Bioenergy
Solar PV
Natural Gas
Coal
Efficiency/DR 2009
Nuclear
Hydro
Wind
Bioenergy
Solar PV
Natural Gas
Coal Efficiency/DR
2013 (est.)
4
Feed-in Tariff (FIT) Program
• Launched in 2009
• First comprehensive FIT program in North America
• Open to various renewable energy supply technologies – Solar Photovoltaic (PV) – Wind power– Waterpower – Bioenergy technologies (biogas, biomass,
landfill gas)
• Different prices for different technologies and project sizes
• Long-term contracts (e.g. 20 years)
FIT Program Impact
• Has encouraged billions of dollars of investment• More than 30 companies have already invested in Ontario –
manufacturers/generators/related services• Created thousands of direct and indirect clean energy jobs
5
Procurement to date
6
2004 2005 2007 2008 2009 2010 2011 2012 20130
500
1,000
1,500
2,000
2,500
3,000
3,500
314
779
424 391 447
2,320
3,237
245
Total
Bio-energy
Solar PV
Co
ntr
ac
t C
ap
ac
ity
(M
W)
(Est)
~170
Non-Hydro Renewables – Executed Contract Capacity
FIT Launched
MicroFIT Program
7* Data as of Oct 1, 2013
Q4 2009
Q1 2010
Q2 Q3 Q4 Q1 2011
Q2 Q3 Q4 Q1 2012
Q2 Q3 Q4 Q1 2013
Q2 Q30
10,000
20,000
30,000
40,000
50,000
60,000
70,000
0
20
40
60
80
100
120
140
160microFIT Applications and Contracted Capacity
Accumulated Capacity
Accumulated Applications
Applications (MW)
FIT 3 and Beyond
• June 12, 2013 Minister’s direction further clarifies policy goals• Support long-term sustainability of FIT program by setting annual
procurement targets for next 4 years:– 150 MW/yr for Small FIT– 50 MW/yr for microFIT
• Replace Large FIT program with new competitive procurement process– Work with municipalities and Aboriginal communities to identify
appropriate locations and siting requirements• Strengthen participation of municipalities and public sector entities
in Small FIT– Schools, colleges, universities, hospitals, long-term care homes,
public transit services and Metrolinx• Measures to bring program into compliance with May 24, 2013 WTO
rulings8
Fall 2013 Procurement Targets
• FIT 3 application window to open on November 4, 2013 targeting 123.5 MW– Encourage participation by municipalities and public sector
entities (revised points system, CCSAs, price adders)– Rules and application process have been improved
• 15 MW pilot program for rooftop solar projects on unconstructed buildings to run concurrently
• 30 MW Fall 2013 microFIT procurement target
9
Unconstructed Rooftop Solar Pilot Program
• Pilot stream for applicants with unconstructed buildings• Small FIT rooftop solar projects
– 10 kW – 500 kW
• Up to 15 MW in 2013• Considerable industry stakeholdering• Goal is to synchronize successful pilot framework into
regular FIT program in 2014
10
August 26, 2013 Price Schedule
11
Renewable Fuel Project Size Tranche* August 26, 2013Price (¢/kWh)
April 5, 2012Price (¢/kWh) % Change
Solar (PV)(Rooftop)
≤ 10 kW 39.6 54.9 -27.9%
> 10 ≤ 100 kW 34.5 54.8 -37.0%
> 100 kW 32.9 53.9 -39.0%
Solar (PV)(Non-Rooftop)
≤ 10 kW 29.1 44.5 -34.6%
> 10 kW 28.8 38.8 -25.8%
On-Shore Wind All sizes 11.5 11.5 0%
Waterpower All sizes 14.8 13.1 13.0%
Renewable Biomass All sizes 15.6 13.8 13.0%
On-Farm Biogas ≤ 100 kW 26.5 19.5 35.9%
> 100 kW ≤ 250 kW 21.0 18.5 13.5%
Biogas All sizes 16.4 16.0 2.5%
Landfill gas All sizes 7.7 11.1 -31%
* The FIT 3 program is available to projects generally ≤ 500 kW
2013 Procurement Schedule
• This is an anticipated schedule and is subject to change
12
2014 Procurement Schedule
• This is an anticipated schedule and is subject to change
13
FIT Application and Contracting Process
14*Timelines are targets
Application Review
*60 DAYS
Connection Screen
*60 DAYS
Contract Execution, Approvals, NTP, COD
Large Renewable Projects
• Engage stakeholders and provide interim report– Through August 2013, OPA facilitated various engagement
activities for municipalities, Aboriginal communities, industry associations, general public and other stakeholders.
• OPA submitted interim recommendations report to Minister of Energy on August 30, 2013
• Interim recommendations report publicly available15
• No more procurement under Large FIT program (generally > 500 kW)
• Large FIT program to be replaced by competitive procurement process
Hydroelectric Standard Offer Program (HESOP)
• Municipal Stream– Eligible municipal waterpower projects– New-build– 10 MW for projects 500 kW – 5MW– 50 MW for projects > 5 MW– Pre-existing FIT applicants prior to
June 5, 2010
• Expansion Stream– NUG or HCI contracted facilities– Procurement for expansion potential at
existing facility
16
17
Questions and Resources
Questions regarding FIT or microFIT, including application questions:
Questions regarding your existing FIT or microFIT contract:
Where to find additional information:
fit.powerauthority.on.ca
microfit.powerauthority.on.ca
ontario.ca/refo