Object Data Management Plant Engineering Life Cylcle Conference – April 11 th 2005 Camiel...
Transcript of Object Data Management Plant Engineering Life Cylcle Conference – April 11 th 2005 Camiel...
Object Data Management
Plant Engineering Life Cylcle Conference – April 11th
2005
Camiel Meijneken, project engineer at ProRail Infraprojects
ProRail - Ambitions in railinfra / 2
The world of ProRail:Railways and stations in The Netherlands
Ministry of Transport and
Public Works
Parliament
Local government
PRORAIL
Engineering companies Construction companies
Management
concession
Transport
concession
Railway companies
ProRail - Ambitions in railinfra / 3
DIFFICULTIES WITH PROJECTCONTROL
* more complex regulations (NL, EU)* complex decision making environment * outsourcing engineering & knowledge* new contracting methods in the building sector* more emphasis on controllability and assessment.
ProRail - Ambitions in railinfra / 4
REQUIREMENTS
CONTRACTS
DRAWINGS
COSTS
PERMITS
RISKS
ProRail - Ambitions in railinfra / 5
PROJECT CONTROL
* Objects form the hierarchical basis for projects
Systems Engineering“Expliciet Werken®” strategy (working explicitly)
ProRail - Ambitions in railinfra / 6
REQUIREMENTS
CONTRACTS
DRAWINGS
COSTS
PERMITS
RISKS
ProRail - Ambitions in railinfra / 7
REQUIREMENTS
CONTRACTS
DRAWINGS
COSTS
PERMITS
RISKS
OBJECTS
ProRail - Ambitions in railinfra / 8
PROJECT CONTROL, KEY-WORDS:
structure, controlability,unambigiousity, coherency, traceability, rapportability,transferability of information,auditability (public funds)
ProRail - Ambitions in railinfra / 9
ProRail’s “Expliciet Werken®” strategy (working explicitly)
Goal of EW: Ensure efficient and effective communication between people and parties
• Maximize transparency by explicit processes
• Guarantee that everybody is talking about the same thing/object
• Apply hierarchic structures for large amounts of information to obtain better traceability
• Faster, cheaper and quality controlled realization of projects
ProRail - Ambitions in railinfra / 10
PROJECT CONTROL -OBJECT DATA MANAGEMENT COUPLED TO OBJECTS:Requirements breakdown, permits, drawings, cost estimations, planning
OBJECTS CLASSED TO:contracts
ProRail - Ambitions in railinfra / 11
CONTRACTSREQUIREMENTSSPECIFICATIONS OBJECTS
DESIGN
PERMITSDRAWINGSDOCUMENTSRISKS
ProRail - Ambitions in railinfra / 12
ADDED VALUE OF ODM SYSTEM(as used until now, (14 projectdatabases))
* unambiguousity in data (in-/external)* Object related (parts of) specifications* ‘Blank spots’ in specifications* “Survival” of data
ProRail - Ambitions in railinfra / 13
NEAR FUTURE DEVELOPMENTS
* Web-based access to ODM databases* External parties demand for more accountability for tax payers money* Branch wide structurisation of information streams* Information-architecture of the Infra management & control department
ProRail - Ambitions in railinfra / 14
CIVIL INFRASTRUCTURE:
PRODUCT LIFECYCLE MANAGEMENT
ProRail - Ambitions in railinfra / 15
To support this way of working:
SMARTEAM ODM System
Based on SMARTEAM PLM platformCreated in close collaboration by:
ProRail - Ambitions in railinfra / 16
SUMMARIZING
• CHALLENGEMaintain integral control overincreasingly complicated processes
• SOLUTIONSystems Engineering methodologies,Supported and structured by anObject Data Management system and “Expliciet Werken®”
ProRail - Ambitions in railinfra / 17
END OF PRESENTATION
Screen views of the SMARTEAM application enclosed in the presentation on the Proceedings CD Rom.
Also: Information Market stand of IBM.
Time for questions / remarks?
ProRail - Ambitions in railinfra / 18
POSING
• An ODM system is essential to keep good control of complex projects
• Projects in the public domain are by definition complex, as well as implementing solutions
ProRail - Ambitions in railinfra / 19
How to contact ProRail:
ProRail Infraprojects, ProjectcentreCamiel Meijneken, Project Engineer
PO Box 20383500 GA Utrecht
ProRail - Ambitions in railinfra / 20
ProRail - Ambitions in railinfra / 21
ProRail - Ambitions in railinfra / 22