![Page 1: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/1.jpg)
Falsework & Formwork Section 3.1
January, 2018 1
Falsework & FormworkSection 3
Falsework Construction00540.42
![Page 2: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/2.jpg)
Falsework & Formwork Section 3.1
January, 2018 2
Falsework
Temporary construction used to support the permanent structure until it becomes self supporting.
Falsework must support the weight of the Forms, Fresh concrete, and Construction equipment.
All falsework to be in accordance with the contractor’s reviewed falsework plans.
Falsework Construction00540.42
• Construct per AASHTO Construction Handbook for Bridge Temporary Works
• Do not place concrete until the falsework design engineer inspects work.
![Page 3: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/3.jpg)
Falsework & Formwork Section 3.1
January, 2018 3
Falsework
Falsework Foundations
Piling is often used.
The inspector should verify that bearing has been reached.
![Page 4: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/4.jpg)
Falsework & Formwork Section 3.1
January, 2018 4
Falsework Foundations
Mudsills may be used with the approval of the engineer.
Watch for excessive settlement.
Falsework Foundations
![Page 5: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/5.jpg)
Falsework & Formwork Section 3.1
January, 2018 5
Falsework
Support System:
• Rigid vertical posts and diagonal braces
• Secure fasteners
Look for items not matching the approved falsework plans.
Vertical 4x4’s?
Falsework
![Page 6: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/6.jpg)
Falsework & Formwork Section 3.1
January, 2018 6
Vertical 4x4 supports?
Falsework EOR site visit before placing concrete
Falsework
Wedges Under Beam
Hardwood wedges
Used in pairs with only one additional block allowed
Toenail after adjustment
![Page 7: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/7.jpg)
Falsework & Formwork Section 3.1
January, 2018 7
Pier Falsework
Falsework Bent
![Page 8: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/8.jpg)
Falsework & Formwork Section 3.1
January, 2018 8
Falsework Footings
Set Telltales from Deck Forms to Ground
Near Interior Falsework Bents To Measure Settlement
![Page 9: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/9.jpg)
Falsework & Formwork Section 3.1
January, 2018 9
Telltale from Deck Forms to Ground
Mark Before & After Pour To Determine The Total Settlement & Crush
Compare To EOR’s Estimate
Deck Falsework
Deck overhang brackets – they are designed to support the cantilevered deck overhangs.
![Page 10: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/10.jpg)
Falsework & Formwork Section 3.1
January, 2018 10
Deck Falsework
Deck Falsework
![Page 11: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/11.jpg)
Falsework & Formwork Section 3.1
January, 2018 11
Deck Falsework
Falsework
![Page 12: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/12.jpg)
Falsework & Formwork Section 3.1
January, 2018 12
Screwjacks
Adjusted to Grade with Uniform Bearing
Case StudyHwy 149 @ Hwy 70, Oroville, CA
![Page 13: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/13.jpg)
Falsework & Formwork Section 3.1
January, 2018 13
Falsework
Cable removed.
Thoughts?
Falsework Collapse
![Page 14: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/14.jpg)
Falsework & Formwork Section 3.1
January, 2018 14
Falsework Collapse
Hwy 149 @ Hwy 70, Oroville, CA
July 30, 2007
Fatalities: 0
Injuries: 2
Hwy 149 @ Hwy 70
![Page 15: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/15.jpg)
Falsework & Formwork Section 3.1
January, 2018 15
Hwy 149 @ Hwy 70
Hwy 149 @ Hwy 70
![Page 16: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/16.jpg)
Falsework & Formwork Section 3.1
January, 2018 16
Causes
• Falsework erection plan not followed by
Contractor.
• Contractor told Inspector they would be working several spans away from this area.
• Cable bracing for falsework removed without permission from engineer.
Formwork Construction00540.45
![Page 17: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/17.jpg)
Falsework & Formwork Section 3.1
January, 2018 17
Pier Formwork
![Page 18: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/18.jpg)
Falsework & Formwork Section 3.1
January, 2018 18
Formwork Construction
• Check forms for correct dimensions and shapes.
• Forms to be mortar tight.
• Internal tie rods or snap-ties have 1” recess (2” within 25 miles of ocean).
2x4 Imprint On Outside Of Exterior Stemwall?
Any Shape Inside The Forms Will Not Be Poured Concrete
![Page 19: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/19.jpg)
Falsework & Formwork Section 3.1
January, 2018 19
Deck Forms Against Stemwall
Overhang of Deck Forms?
![Page 20: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/20.jpg)
Falsework & Formwork Section 3.1
January, 2018 20
Nylon Mesh to Make Forms Mortar Tight?
Nylon Mesh?
![Page 21: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/21.jpg)
Falsework & Formwork Section 3.1
January, 2018 21
Gap Under Plywood?
Excess Foam?
![Page 22: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/22.jpg)
Falsework & Formwork Section 3.1
January, 2018 22
Support at Hole?
Drip Strip Nailed Sideways on Form? Note Clearance, Too.
![Page 23: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/23.jpg)
Falsework & Formwork Section 3.1
January, 2018 23
Chamfer Strip on Beam?
Form Construction00540.45
• Provide a ¾″ chamfer on all exposed concrete edges.
• Apply form release oil.
![Page 24: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/24.jpg)
Falsework & Formwork Section 3.1
January, 2018 24
Chamfer Strips on Exposed Edges
Chamfer Strips on Exposed Edges
![Page 25: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/25.jpg)
Falsework & Formwork Section 3.1
January, 2018 25
Abutment & Retaining Wall With Chamfers
Wingwall With vs. Deck Without Chamfers
![Page 26: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/26.jpg)
Falsework & Formwork Section 3.1
January, 2018 26
“E” Beam Without Chamfers @ Shear Block
Top Of Wingwall Spalling
Is There Preformed Joint Material?
No Chamfers
![Page 27: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/27.jpg)
Falsework & Formwork Section 3.1
January, 2018 27
Chamfer @ Wingwall
Abutment with Chamfers At Cold Joint?
![Page 28: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/28.jpg)
Falsework & Formwork Section 3.1
January, 2018 28
Form Construction Cont’d
• Remove sawdust, dirt, excess water and other foreign materials prior to placement.
• Saturate with water immediately before placement and keep damp during placement.
Debris at Abutment Cold Joint
![Page 29: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/29.jpg)
Falsework & Formwork Section 3.1
January, 2018 29
Debris Between Beam & Deck
Look for Good Lines and Shapes
![Page 30: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/30.jpg)
Falsework & Formwork Section 3.1
January, 2018 30
Shape of Collar?
Collar Shape
![Page 31: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/31.jpg)
Falsework & Formwork Section 3.1
January, 2018 31
Odd Lines?
Access for Inspection
![Page 32: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/32.jpg)
Falsework & Formwork Section 3.1
January, 2018 32
Inspection Facilities(00150.20 (b))
The Contractor shall furnish walkways, railings, ladders, tunnels, platforms and other facilities necessary to permit The Engineer to have safe access to the Work to be inspected.
Safe Access?
![Page 33: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/33.jpg)
Falsework & Formwork Section 3.1
January, 2018 33
Safe Access?
Safe Access?
![Page 34: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/34.jpg)
Falsework & Formwork Section 3.1
January, 2018 34
Protected Access to Deck
Stairway Access
![Page 35: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/35.jpg)
Falsework & Formwork Section 3.1
January, 2018 35
Ladder Access
Ladder Supported
![Page 36: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/36.jpg)
Falsework & Formwork Section 3.1
January, 2018 36
Abutment Access
Work Platform for Abutment
![Page 37: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/37.jpg)
Falsework & Formwork Section 3.1
January, 2018 37
Check Form Placement(Are Forms Squared Up?)
Pythagorean Theorem
a2 + b2 = c2a
b
c
c = a2 + b2
![Page 38: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/38.jpg)
Falsework & Formwork Section 3.1
January, 2018 38
Footing Example
32 + 42 = c23
4
c
c = 9 + 16
c = 32 + 42
c = 5
Footing Exercise
A footing is 6′ wide by
8′ long. What is the
diagonal distance “c”? 6
8
c
![Page 39: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/39.jpg)
Falsework & Formwork Section 3.1
January, 2018 39
Footing Exercise Key
62 + 82 = c26
8
c
c = 36 + 64
c = 62 + 82
c = 10
Similar Triangles
10
3
4
5
8
6
![Page 40: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/40.jpg)
Falsework & Formwork Section 3.1
January, 2018 40
Right Triangle Exercise
Law of Sines
Sin A Sin B Sin CB
CA
a
b
c= =
a b c
![Page 41: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/41.jpg)
Falsework & Formwork Section 3.1
January, 2018 41
Law of Cosines
c2 = a2 + b2 – 2abCosCB
CA
a
b
c
Other Types of Checks
• Measure Chord Distances (Bent Checks)
• Measure Middle Ordinates (Edge of Deck Checks)
![Page 42: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/42.jpg)
Falsework & Formwork Section 3.1
January, 2018 42
Bridge In 10° Curve(How To Check Forms Are
Positioned Correctly?)
Rebar and stem wall layout marked on bottom slab forms.
Bottom Slab Form of PT Box
![Page 43: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/43.jpg)
Falsework & Formwork Section 3.1
January, 2018 43
Curve Data
Curve Data
![Page 44: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/44.jpg)
Falsework & Formwork Section 3.1
January, 2018 44
Curve Data
Curve Defined As D = 1°
D=
L
100′
360°
1°=
2πR
100′
▲
R = 5,729.578′
Curve Data▲ / L = D / 100ft
▲ = The Subtended Angle Of The CurveD = Degree Of Curve
(Subtended Angle Of 100′ Of Arc)L = Length Of CurveR = Radius Of Curve
▲ = D(L) / 100ft
R = 5,729.578 / D
![Page 45: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/45.jpg)
Falsework & Formwork Section 3.1
January, 2018 45
Trig Functions
Sin ▲ = O / H
Cos ▲ = A / H
Tan ▲ = O / A
O
HA
▲
Check Chord Distance
![Page 46: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/46.jpg)
Falsework & Formwork Section 3.1
January, 2018 46
Chord Distance
Sin(½ ▲) = ½ C / R
R Sin(½ ▲) = ½ C
2R Sin(½ ▲) = C
Chord Distance = 2R Sin(½ ▲)
½ C
R▲
2
Chord Distance Example
D = 10° Bent 1 @ 10+00
Bent 2 @ 12+00
What is the chord distance between Bents 1&2?
L = (12+00)-(10+00) = 200ft
▲= D(L)/100ft = 10°(200ft)/100ft = 20°
R= 5,729.578 / D = 5,729.578 / 10° = 572.958ft
C = 2R Sin(1/2 ▲)
C = 2(572.958ft)Sin(1/2(20°)) = 198.99ft
![Page 47: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/47.jpg)
Falsework & Formwork Section 3.1
January, 2018 47
Chord Distance Exercise
D = 5°
Bent 1 @ 10+00
Bent 2 @ 11+50
What is C?
Chord Distance Exercise Key
D = 5°
Bent 1 @ 10+00
Bent 2 @ 11+50
L = (11+50)-(10+00) = 150ft
▲= D(L)/100ft = 5° (150ft)/100ft = 7.5°
R= 5,729.578 / D = 5,729.578 / 5° = 1,145.916ft
C = 2(1,145.916ft)Sin(1/2(7.5°)) = 149.89ft
![Page 48: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/48.jpg)
Falsework & Formwork Section 3.1
January, 2018 48
Middle Ordinate Check
Curve Data
![Page 49: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/49.jpg)
Falsework & Formwork Section 3.1
January, 2018 49
Middle Ordinate Distance
Cos(½ ▲) = A / R
A = R(Cos(½ ▲))
M = R - A
M = R - R(Cos(½ ▲))
Middle Ordinate = R(1 - Cos(½ ▲))
½ C
R▲
2
R
M
A
Middle Ordinate Example
M = R(1 - Cos(1/2 ▲))
Example: D = 10o Bent 1 @ 10+00
Bent 2 @ 12+00
L = (12+00)-(10+00) = 200ft
▲= D(L)/100ft = 10° (200ft)/100ft = 20°
R= 5,729.578 / D = 5,729.578 / 10° = 572.958ft
M = 572.958ft(1 - Cos(1/2(20°)) = 8.70ft
![Page 50: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/50.jpg)
Falsework & Formwork Section 3.1
January, 2018 50
Middle Ordinate Exercise
D = 5o
Bent 1 @ 10+00
Bent 2 @ 11+50
What is M?
Middle Ordinate Exercise Key
D = 5°
Bent 1 @ 10+00
Bent 2 @ 11+50
L = (11+50)-(10+00) = 150ft
▲= D(L)/100ft = 5°(150ft)/100ft = 7.5°
R= 5,729.578 / D = 5,729.578 / 5 °= 1,145.916ft
M = 1,145.916ft(1 - Cos(1/2(7.5°)) = 2.45ft
![Page 51: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/51.jpg)
Falsework & Formwork Section 3.1
January, 2018 51
Form & Falsework Removal
Form & Falsework Removal
• No forms or falsework may be removed until approved by the Engineer.
• All forms and falsework must eventually be removed unless there is no permanent access, e.g., box girder bridge.
![Page 52: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/52.jpg)
Falsework & Formwork Section 3.1
January, 2018 52
Field Cured Cylinders (00540.52)
• Need to verify strength
• In like conditions or worse
• Coolers are for Lab cured cylinders
Table 00540-1
![Page 53: o03 Falsework Formwork - oregon.gov · Falsework & Formwork Section 3.1 January, 2018 2 Falsework Temporary construction used to support the permanent structure until it becomes self](https://reader034.fdocuments.us/reader034/viewer/2022052206/5cb349ef88c993fa708c48a7/html5/thumbnails/53.jpg)
Falsework & Formwork Section 3.1
January, 2018 53
Form Removal & Loading Exercise
Situation: Crossbeam poured @ 4 p.m. the day before with 4,000 psi concrete.
Can side forms be removed at 6 a.m. the next day? _______
What is the minimum concrete strength to remove the bottom forms? _______
7 days later concrete strength is 3,000 psi and the contractor wants to set girders on top of the crossbeam. Is this acceptable? _______
Form Removal & Loading Exercise KeySituation: Crossbeam poured @ 4 p.m. the day before
with 3,000 psi concrete.
Can side forms be removed at 6 a.m. the next day?No
What is the minimum concrete strength to remove the bottom forms?
3,200 psi
7 days later concrete strength is 3,000 psi and the contractor wants to set girders on top of the crossbeam. Is this acceptable?
No