NZS 6808:2010 Acoustics – Wind farm noise · 2017. 8. 6. · Wind energy and the RMA > Project...
Transcript of NZS 6808:2010 Acoustics – Wind farm noise · 2017. 8. 6. · Wind energy and the RMA > Project...
NZS 6808:2010Acoustics –Wind farm noise
Programme
• Introduction• Wind farm acoustics 101• Key changes to NZS 6808• NZ projects and prospects• Example • Questions
Introduction
White Hill
Motorimu
• NZS 6808:1998• SNZ review (Nov 2004)
• NZWEA / EECA Review (May 2007)
• SNZ scoping workshop (Nov 2007)
Timeline
Committee
• Energy Efficiency and Conservation Authority• Executive of Community Boards• Local Government New Zealand• Massey University• Ministry for the Environment• Ministry of Health• New Zealand Acoustical Society• New Zealand Institute of Environmental Health Inc.• New Zealand Wind Energy Association• Resource Management Law Association• University of Auckland
• NZS 6808:1998• SNZ review (Nov 2004)
• NZWEA / EECA Review (May 2007)
• SNZ scoping workshop (Nov 2007)
• Committee (Jul-Dec 2008)
• Consultation (Mar-Apr 2009)
• Committee (May-Oct 2009)
• NZS 6808:2010
Timeline
Process
• Review research and current practice
• Propose method based on the evidence
• Test and debate proposed method
• Reach consensus position
Potential effects
• Infrastructure
• Visual
• Construction phase
• Noise
Wind farm acoustics 101
Sound
Pressure changes
(Pascals)
decibels (dB)
Sound levels
NZS 6808
decibels
• 1 dB + 1 dB = 4 dB• 35 dB + 35 dB = 38 dB
• + 3 dB audible difference
• + 10 dB doubling of subjective loudness
Frequencies
• Human hearing – less sensitive to low frequencies
• A-weighting approximates human hearing
L90
30 dB
40 dB
50 dB
60 dB
70 dB
Time
L90
Sources of sound
• Blade aerodynamic sound• Gearbox, generator, hydraulics mechanical sound• Transformer electrical sound
Key changes to NZS 6808
40 dB
45 dB
25 dB
50 dB
35 dB
Noise limits
High amenity noise limit
30
35
40
45
50
55
20 25 30 35 40 45Background sound level, dB
Noi
se li
mit,
dB
Noise limit
Noise limits
High amenity noise limit
West WindLess than 25 dBLess than 1.5 m/s NZS 6808:2010
6 m/s or less
Cumulative effects
• Noise Limits apply to total sound from:– all wind farms– all stages of a wind farm
0
10
20
30
40
50
60
70
80
90
100
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2
Wind speed relative to 10 m
Heigh
t (m)
Wind speed height
Predictions
Ground attenuationScreening
terrain, foliage, buildingsOctave-bands
DistanceAir absorption
ISO 9613
30 dB
40 dB
50 dB
60 dB
70 dB
Time
L95
L90
Measurements
Special Audible Characteristics
• Tonality
• Impulsiveness
• Amplitude Modulation
Small wind turbines
• Less than 200 m2 swept rotor area– approximately 8 m blade length
• District plan limits
• On/off tests
Alleged health effects
• Literature reviewed
• No causative link shown to exist
• Inaudibility not justified
• Attitude influences perception of noise
Consent conditions
• Recommended conditions in NZS 6808:2010
• Procedural details not required
Wind DirectionsAn update on New Zealand’s wind energy activity
Fraser Clark, Chief ExecutiveRMLA NZS6808 Roadshow, Palmerston North, 29 March 2010
Outline> Wind energy – the technology> Why wind energy> The industry today> Where we’re headed
About NZWEA> Represents over 80 organisations:
> Generators and developers> Transpower and lines companies> Wind turbine manufacturers> Consultancies, financiers and legal firms.
> Policy & regulatory advocacy, public awareness and industry development.
> Utility scale generation only
Main components of a wind turbine
Siemens SWT-2.3-82> West Wind> 2.3 MW rated output> 9,500 MWh/yr
(~1,150 homes)> 40 metre blade length> 67 metre high tower
Tower
Nacelle
Hub
Blades
Foundation (underground)
Main components of a wind turbine
Windflow 500> Te Rere Hau> 0.5 MW rated output> 1,300 MWh/yr
(~160 homes)> 16.2 metre blade length> 30 metre high tower
Tower
Nacelle
Hub
Blades
Foundation (underground)
How it works…
Wind direction
Electricity to grid (via substation)
Not an aeroplane propeller, but it does have wings…
How big?
BrooklynMost new wind farms
Drivers of increasing size include higher yields and reduced infrastructure
Windflow/Te Rere Hau
Selection of size & model depends on specific site characteristics
When is a wind farm a wind farm?> 1 to 100+ turbines> 30 to 100 m high towers> 2 or 3 blades> Arrangement influenced by wind conditions, terrain,
turbine size/spacing
Source: Transpower
1.6m residential consumers (33%)
0.2m commercial consumers (23%)
0.1m industrial consumers (44%)
Electricity:a national system…
… with national significance
Significance is acknowledged in case law
“Electricity is a vital resource for New Zealand. There can be no sustainable management of natural and physical resources without energy, of which electricity is a vital component “
Genesis Power Ltd. And Anor v Franklin District Council (‘Awhitu’), A148/05 at [64]
Why wind energy?> No fuel price
> No fuel risk
> No carbon risk
> Portfolio and location diversity
> Proven technology
> Plenty of energy
Source: Contact Energy HY Results
Source: Contact Energy HY Results
Meridian Energy “Choices, Options,
Decisions 2009 Update”
Competitive with other technologies
Contributing to the economy> Price taker – does not cause electricity price rises
(actually reduces spot prices).> Ongoing regional economic benefits &
employment ($150m+ at construction).> Low-risk, long-term infrastructure
(no fuel price, dependable fuel supply, no carbon emissions).
Contributing to security of supply> West Wind
> Voltage support> Local generation kept the lights on during substation fire
> Energy supply during dry years(i.e. White Hill during 2008).
> Technology improvements mean that wind farms can provide some ancillary services.
Other advantages for NZ> No greenhouse gas emissions> No fuel price or supply risk> World-leading wind resource> Potential sites nation-wide> Scaleable> Hydro base increases flexibility of use> Reduces dry year supply risk> Existing land use retained
Wind Energy now
Planned
Operating and under construction
Up to 630 MWHigh Court
??? MWUnder Investigation
Up to 1,150 MWEnvironment Court/
Board of Inquiry
Up to 1,016 MWConsented
577.8 MWInstalled by end 2011
80.4 MWUnder Construction
497.4 MWInstalled CapacityWaikato
11%
Manawatu 52%
Wellington & Wairarapa 26%
Marlborough & Canterbury 0.2%
Southland & Otago10%
Recent highlights> Project West Wind and 2 small wind farms> 500 MW installed capacity> 4-5% of NZ’s electricity
Future opportunity
38,00040,00042,00044,00046,00048,00050,00052,00054,000
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Year
GW
h Demand Growth
Dry years,Fuel risk,Retirements
Recession?
How much? How soon? How fast?> Electricity demand growth estimate: 1.5% per year
> 42,245 GWh generated in 2008
> 30% increase needed by 2025 (54,410 GWh)
How much? How soon? How fast?> Electricity demand growth estimate: 1.5% per year
> Reducing supply and price risks> “Dry year” risk
> Fuel supply and price risks
> Introduction of carbon price
How much? How soon? How fast?> Electricity demand growth estimate: 1.5% per year
> Reducing supply and price risks
> 90% renewable electricity by 2025 target> Up from 65% now
> With demand increasing, 70-100% increase in renewable generation
How much? How soon? How fast?
> Electricity demand growth estimate: 1.5% per year
> Reducing supply and price risks
> 90% renewable electricity by 2025 target
Wind energy in 20 years:
> 2,500 to 3,000 MW, up from 500 MW
> 20% of our electricity, up from about 4%
> Variety of small and large-scale projects throughout NZ
In line with international trends
Rapid global wind energy growth is being facilitated by support schemes…
…while in New Zealand projects proceed on a purely economic basis.
World-class performance
Source: NZWEA calculations from MED data, Windstats Newsletter
NZ has a significant wind resource…
Source: Electricity Commission ‘Transmission to Enable Renewables’ Report
“Tranche 1”=31,230 GWh
“Tranche 1”=19,550 GWh
NZ has a significant wind resource…
…but not all of it is:
* Accessible* Available* Consentable* Economically viable
Wind in the Manawatu
Source: Electricity Commission ‘Transmission to Enable Renewables’ Report
Wind in Taranaki and the Hawkes Bay
Wind in Taranaki and the Hawkes Bay
Wind energy in the Manawatu
Seeking consent
288MWMighty River Power
Tararua RangesTuritea
Operating/ seeking consent
32.5MW (76.5MW)
NZ Wind Farms
Tararua RangesTe Rere Hau
StatusSizeOperatorLocationWind farm
Tararua Ranges
Ruahine Ranges
Operating161MWTrustPowerTararua
Operating90.8MWMeridian Energy
Te Apiti
And a bit beyond
Consented225MWHawkes Bay Wind Farms
Hawkes BayHawkes Bay Wind Farm
Consented48MWUnison & Roaring 40s
Hawkes BayTitiokura
Consented130MWMeridian EnergyTaihapeCentral Wind
Other sites under investigation
Seeking consent
177MWContact EnergyDannevirkeWaitahora
Operating8.7MWGenesis EnergySouthern WairarapaHau Nui
Policy environment> No feed-in tariffs, renewables obligations, tax
credits, capital subsidies, etc.> Price on carbon expected to allow all generation
sources to compete directly.> Non-legislated target of 90% renewable
electricity by 2025 (as long as this does not compromise ‘security of supply’).
Carbon – a view to the futureis emerging through the smog
> Electricity sector enters ETS 1st July 2010.
> 50% allocation and $25/t price cap to end-2012.
> Equivalent to fixed price $12.50/t – unlikely to be enough to drive immediate investment.
> UN Negotiations & review of ETS in 2011 means uncertainty remains.
Wind energy and the RMA
> Project Hayes adds to a sequence of inconsistent consent decisions> Experience to date with ‘call-in’ is a possible disincentive to its use in
future> Timing and decision uncertainty, together with high costs are a
potential disincentive to both developers and turbine OEMs.> RMA reform?
> balancing national & regional benefits against localised effects> resolving tension between the economic & social benefits of
infrastructure development and its environmental effects
What the industry is doing…> Establish ‘best practice’ as a route to
consistency & certainty.> Industry guidelines> Non-statutory guidance (i.e. QP)> Standards (i.e. NZS6808)
> Also seeking more robust & consistent landscape character assessment.
> Stakeholder participation critical
www.windenergy.org.nz
29-31 March, Palmerston North
Example
Process
Predict 35 dB contour
Check plan provisions
Measure background
Determine noise limits
Refine predictions
Prepare a report
Measure wind farm
Statutory processesand construction
Fictitious wind farm
District plan maps
• High country (rural) zone• Village is township zone
District plan rules
• No reference to wind farms• Reference to NZS 6802 for general noise• NZS 6802:2008 excludes wind farms
• No reference to special acoustic amenity
• NZS 6808:2010 appropriate standard
35 dB contour
Background soundBa
ckgr
ound
L A90(
10mi
n)(d
B)
Wind farm hub-height wind speed (m/s)
Noise limitsBa
ckgr
ound
L A90(
10mi
n)(d
B)
Wind farm hub-height wind speed (m/s)
Report
• Sound level contours (35 dB and 40 dB)
• Background sound measurements
• Noise limits
• Predictions at individual receivers
Post-installation measurements
• Repeat procedure as for background sound
• Check regression curve below noise limit
• On/off testing if necessary
• Compliance report
Summary
You now know:
• when and why there was a revision
• the project included all the key stakeholders
• the key changes between the 1998 original and 2010 revision
NZS 6808:2010 is available as a pdf or hard copy fromStandards New Zealand - www.standards.co.nz
Questions