NWPC Procurement Manual (v3) Procureme… · methods of procurement as prescribed under RA 9184. As...
Transcript of NWPC Procurement Manual (v3) Procureme… · methods of procurement as prescribed under RA 9184. As...
N W P C Guide on Procurement
National Wages and Productivity Commission Department of Labor and Employment
A joint project of the
Review, Appeals and Legal Division
and the
Administrative Division
i
TABLE OF CONTENTS
TOPIC PAGE
I. Purpose 1
II. Definition of Terms 3
III. Background on Procurement 8
IV. Budget Preparation and Procurement Planning 10
V. Procurement Groups 14
a. Bids and Awards Committee (BAC) 14
b. Bids and Awards Committee Secretariat
(BAC Secretariat) 16
c. Technical Working Group (TWG) 18
d. Observers 18
VI. Procurement Procedure Flow Chart 22
VII. Procurement Modes 23
VIII. Procurement Mode: Competitive Bidding 23
a. Step 1: Preparation of Bidding Documents 24
b. Step 2: Advertisement of the Invitation to Bid 25
c. Step 3: Pre-bid Conference 29
d. Step 4: Submission and Receipt of Bids 30
e. Step 5: Opening of Bids/Evaluation of Bids 35
f. Step 6: Post Qualification 37
g. Step 7: Award of the Contract 40
IX. Protest Mechanism 45
X. Procurement Mode: Alternative Methods
of Procurement 47
a. Limited Source Bidding 48
b. Direct Contracting/Single Source Procurement 49
c. Repeat Order 50
d. Shopping 51
ii
e. Negotiated Procurement: 52
1. Two Failed Bidding 52
2. Emergency Cases 52
3. Take Over of Contracts 52
4. Adjacent or Contiguous 53
5. Agency-to-Agency 53
6. Procurement Agent 53
7. Highly Technical Consultants 53
8. Defense Cooperation Agreement 54
9. Small Value Procurement 54
10. Lease of Real Property 54
11. NGO Participation 54
12. Community Participation 55
13. United Nations Agencies 55
a. Terms and Conditions for the Use of Alternative Method 55
1
I. PURPOSE
Section 4.1 of the revised Implementing Rules and
Regulations (IRR) of Republic Act No. (RA) 91841 explicitly provides
that it shall apply to all procurement activities of any branch,
agency, department, bureau, office, or instrumentality of the
Government of the Philippines, including government owned
and/or controlled corporations (GOCCs), government financial
institutions (GFIs), state universities and colleges (SUCs), as well
as, local government units (LGUs). Hence, the National Wages and
Productivity Commission (NWPC), as an attached agency of the
Department of Labor and Employment and created under
Republic Act No. (RA) 6727, is not exempted from this
requirement. Thus, its procurement should be through public
bidding, as general rule, or through any of the alternative
methods of procurement as prescribed under RA 9184. As
provided for under Section 3 of R.A. 9184, government
procurement shall be governed by the principles of transparency,
competitiveness, streamlined procurement process, system of
accountability and public monitoring.
In line with this, there is a need for the crafting of a
procurement guide based on RA 9184 and its IRR and all other
Government Procurement Policy Board (GPPB) issuances and
other government issuances to provide the members of the
NWPC Bids and Awards Committee (BAC) with easy reference in
1 Government Procurement Reform Act; Signed by her Excellency President Gloria Macapagal-Arroyo on 10 January 2003, and was published on 11 January 2003, in two (2) newspapers of general nationwide circulation, namely, Manila times and Malaya. It took effect fifteen (15) days after its publication or on 26 January 2003.
2
the performance of their duties relative to the procurement of
goods and services.
This will contain the basic process flow for the
procurement of goods, general support services, and
infrastructure projects, beginning from the budget preparation all
the way to the award of the contract. Topics and concerns that
have not been tackled by the Procurement Guide can be
addressed through RA 9184 itself and its Revised Implementing
Rules and Regulations.
3
II. DEFINITION OF TERMS
2.1 Approved Budget for the Contract (ABC) - refers to the
budget for the contract duly approved by the Head of the
Procuring Entity, as provided for in the General Appropriations
Act (GAA) continuing, and automatic appropriations, in the case of
national government agencies (NGAs).
2.2 BAC - refers to the Bids and Awards Committee.
2.3 Bid - refers to a signed offer or proposal to undertake a
contract submitted by a bidder in response to and in consonance
with the requirements of the Bidding Documents.
2.4 Bidder - refers to an eligible contractor, manufacturer,
supplier, distributor and/or consultant, competing for the award
of a contract in any procurement by the Government of the
Philippines (GOP). A contractor, manufacturer, supplier,
distributor or consultant is said to be eligible if it meets all the
eligibility requirements issued by the procuring entity.
2.5 Bidding Documents - refer to the documents issued by the
Procuring Entity as the basis for bids, furnishing all information
necessary for a prospective bidder to prepare a bid for the
infrastructure projects, goods and/or consulting services required
by the Procuring Entity.
2.6 Bid Security – this shall serve as a guarantee that after
receipt of the Notice of Award, the winning bidder shall enter into
4
contract with the Procuring Entity within the stipulated time and
furnish the required performance security.2
2.7 Common-Use Supplies - refer to those goods, materials
and equipment that are used in the day-to-day operations of
Procuring Entities in the performance of their functions.
2.8 Consulting Service - refers to services for infrastructure
projects and other types of projects or activities of the GOP
requiring adequate external technical and professional expertise
that are beyond the capability and/or capacity of the GOP to
undertake such as, but not limited to: (i) advisory and review
services; (ii) pre-investment or feasibility studies; (iii)design; (iv)
construction supervision; (v) management and related services;
and (vi) other technical services or special studies.
2.9 Competitive Bidding - refers to a method of procurement
which is open to participation by any interested party and which
consists of the following processes: advertisement, pre-bid
conference, eligibility screening of prospective bidders, receipt
and opening of bids, evaluation of bids, post-qualification, and
award of contract.
2.10 Expendable supplies - refer to articles which are normally
consumed in use within one (1) year or converted in the process
of manufacture or construction, or those having a life expectancy
of more than one (1) year but which shall have decreased
substantially in value after being put to use for only one year (e.g.,
medicines, stationery, fuel, and spare parts.)
2 Section 27, RA 9184.
5
2.11 Goods - refer to all items, supplies, materials, and general
support services, except consulting services and infrastructure
projects, which may be needed in the transaction of public
businesses or in the pursuit of any government undertaking,
project or activity, whether in the nature of equipment, furniture,
stationery, materials for construction, or personal property of any
kind, including non-personal or contractual services, such as, the
repair and maintenance of equipment and furniture, as well as,
trucking, hauling, janitorial, security, and related or analogous
services, as well as procurement of materials and supplies
provided by the procuring entity for such services. The term
“related” or “analogous services” shall include, but not be limited
to, lease or purchase of office space, media advertisements,
health maintenance services, and other services essential to the
operation of the procuring entity.
2.12 Head of the Procuring Entity - refers to: (i) the head of the
agency or body, or his duly authorized official, for NGAs, and the
constitutional commissions or offices, and branches of
government; (ii) the governing board or its duly authorized official
for GOCCs, GFIs, and SUCs, or (iii) the local chief executive for
LGUs; Provided, however, That in an agency, department, or office
where the procurement is decentralized, the head of each
decentralized unit shall be considered as the Head of the
Procuring Entity, subject to the limitations and authority
delegated by the head of the agency, department, or office.
2.13 Non-expendable supplies - refer to articles which were
not consumed in use and ordinarily retain their original identity
during the period of use, whose serviceable life is more than one
6
(1) year and which add to the assets of the GOP (e.g. furniture,
fixtures, transportation and other equipment).
2.14 PhilGEPS - refers to the Philippine Government Electronic
Procurement System.
2.15 Procuring Entity - refers to any branch, constitutional
commission or office, agency, department bureau, office, or
instrumentality of the GOP (NGA), including GOCCs, GFIs, SUCs
and LGUs procuring goods, consulting services and infrastructure
projects.
2.16 Procurement - refers to the acquisition of Goods,
Consulting Services and the contracting for Infrastructure Projects
by the Procuring Entity. Procurement shall also include the lease
of goods and real estate. With respect to real property, its
procurement shall be governed by the provisions of R.A. 8974
entitled “An Act to Facilitate the Acquisition of Right-of-Way Site
or Location for National Government Infrastructure Projects and
for Other Purposes”, and other applicable laws, rules and
regulations.
2.17 Virtual Store - refers to an enhanced electronic catalogue
of the PhilGEPS that allows procuring entities to purchase
common-use supplies online that are available from the PS and its
depot.3
2.18 Single Largest Completed Contract Rule - Under this rule,
the bidder must have an experience of having completed within
the period specified in the Invitation to Bid, a single contract that 3 Section 3 (e) OP Administrative Order No. 17 dated 28 July 2011.
7
is “similar” to the contract to be bid, and whose value, adjusted to
current prices using the National Consumer Price Indices, must be
at least 50% of the ABC. However, in the case of Expendable
Supplies, said single contract must be at least 25% of the ABC. If,
at the outset, and after conducting market research, the
procuring entity can already determine that imposing the same
will likely to result to (a) failure of bidding or; (b) monopoly, the
bidder will instead be required of the following:
(a) Two (2) completed contracts similar to the contract being bid
out, and the aggregate contract amounts should be equivalent at
least to 50% or 25% as the case maybe of the ABC being bid out;
(b) The largest of these similar contracts must be equivalent to at
least half of 50% or 25%, as the case maybe, of the ABC being bid
out.
8
III. BACKGROUND ON PROCUREMENT
Republic Act No. 9184
Republic Act No. 9184 is the Government Procurement Reform
Act which prescribes the rules and regulations in the procurement
activities of the government to promote good governance
through the principle of transparency, accountability, equity,
efficiency, and economy.4
Procurements covered under RA 9184
Procurements cover the acquisition of goods , consulting services,
and the contracting of infrastructure projects, as well as mixed
procurements, where the nature of the procurement shall be
determined by the primary purpose of the contract.
Procurements not covered under RA 9184
The following procurements are not covered under RA 91845:
a) Procurement of goods, infrastructure projects, and
consulting services funded from Foreign Grants covered
by RA 8182, as amended by RA 8555, entitled “An Act
Excluding Official Development Assistance (ODA) from the
Foreign Debt Limit in order to Facilitate the Absorption
and Optimize the Utilization of ODA Resources, Amending
for the Purpose Paragraph 1, Section 2 of Republic Act No.
4860, As Amended”, unless the GOP and the foreign
4 Section 2, Rule I, Revised IRR, RA 9184. 5 Section 4.4, Revised IRR, RA 1984.
9
grantor/foreign or international financing institution agree
otherwise.
b) Acquisition of real property which shall be governed by RA
8974, entitled “An Act to Facilitate the Acquisition of
Right-of-Way Site or Location for National Government
Infrastructure Projects and for Other Purposes,” and
other applicable laws.
c) Public-Private sector infrastructure or development
projects and other procurement covered by RA 6957, as
amended by RA 7718, entitled “An Act Authorizing the
Financing, Construction, Operation and Maintenance of
Infrastructure Projects by the Private Sector; and for
Other Purposes,” as amended: Provided, however, That
for the portions financed by the GOP regardless of source
of funds, whether local or foreign, the provisions of the
IRR shall apply.
“Mixed procurements”
A “mixed procurement” is a procurement which is a combination
of procurement of goods, infrastructure projects and services.
Said procurements may be considered as procurement of goods,
infrastructure projects, or services depending on the nature of the
procurement. The Procuring Entity shall be in the best position to
determine the correct classification of its procurement activities,
whether goods, infrastructure projects or services ( GPPB Non-
Policy Matter No. 004-2014, dated 10 March 2014).
10
IV. BUDGET PREPARATION AND PROCUREMENT PLANNING
The following end-user units of the NWPC shall plan out all its
procurements and list them down in their respective Project
Procurement Management Plan (PPMP):
The different PPMPs shall be submitted to the Administrative
Division for consolidation and review. PPMPs shall be evaluated to
determine that only those necessary in the official discharge of
OED DED/DED
Policy Research
Service
Technical Services
Management
Support Services
Submission by the end-user units of their respective PPMPs to BUDGET
OFFICE for evaluation and inclusion in the NWPC’s BUDGET PROPOSAL
CONSOLIDATION by the BAC Secretariat of the
different PPMPs into a proposed APP
BUDGET PROPOSAL is approved by the Executive Director
WPRD PPRD PID TTSD AD FMD RALD
11
government functions shall be included in the Annual
Procurement Plan (APP). With regard to the procurement of office
supplies, the prior year consumption shall be considered. The
proposed APP shall then be submitted to the Budget Unit for
further evaluation of what should be included in the procuring
entity’s budget proposal to be approved by the Executive
Director.
Budget preparation should be done a year before the intended
year when the projects and activities will be carried out.
(Example: the PPMP and APP for 2015 should be prepared in
2014)
When the General Appropriations Act (GAA) becomes final, the
different end-user units shall revise and adjust the PPMP to
reflect the budgetary allocation for the respective projects and
activities.6
6 Section 7.3.5, Revised IRR, RA 9184.
12
Wage Policy and
Research Division
Productivity Policy
and Research Division
APPROVAL by the Executive Director of the APP
UPDATING OF APP by the BAC at least every 6 months.
In case of additional procurements, issuance of a SUPPLEMENTAL APP
containing the amended portion of the APP, to be approved by Executive
Director
Planning and
Information Division REVISION of PPMPs by the END-USER
UNITS
CONSOLIDATION by the BAC Secretariat (Admin
Division) of the different final PPMPs into a APP
OED DED/DED
Technical Services
Policy Research
Service
Management
Support Services
PID TTSD AD FMD RALD PPRD WPRD
13
Remember, procurements should always be carried out in
accordance with what is indicated in the PPMP, and accordingly in
the APP. Thus, in view of the requirement that no government
procurement shall be undertaken unless it is in accordance with
an approved APP7, the NWPC is mandated to update the
individual PPMPs, and correspondingly, the APP at least every 6
months or as often as may be required. It is the end-user units’
responsibility to update their respective PPMPs, while it is the
BAC Secretariat’s (Admin Division) responsibility to update the
APP accordingly.8
The ABC as reflected in the APP and PPMP should also be
consistent with the appropriations for the project authorized in
the GAA, continuing, and automatic appropriations.
NOTE: In preparing the APP, the BAC shall indicate the mode of
procurement (i.e. Public bidding or any of the alternative
methods of procurement) to be used and shall execute the same
accordingly. The APP shall indicate the timelines from which the
procurement activity shall be carried out starting from the
posting of the Invitation to Bid all the way to the
Implementation of the contract.
7 Government Procurement Policy Board (GPPB) Non-Policy Matter Opinion No. 137-2004. 8 Section 7.4, Revised IRR, RA 9184.
14
V. PROCUREMENT GROUPS:
a) Bids and Awards Committee (BAC)
b) Bids and Awards Committee Secretariat (BSC Secretariat)
c) Technical Working Group (TWG)
d) Observers
a) Bids and Awards Committee (BAC) -
The Executive Director shall designate to the BAC at least five (5)
but not more than seven (7) members of unquestionable integrity
and procurement proficiency. The members shall serve for a
period of one (1) year. In no case shall the Head of the Procuring
Entity and/or the approving authority be the Chairman or a
member of the BAC.9
The regular members are as follows:
(1) Chairperson, who is at least a third ranking permanent official
of the NWPC;
(2) An officer who is at least a 5th ranking permanent official, with
knowledge , experience and/or expertise in procurement who, to
the extent possible, represents the legal or administrative area of
the NWPC.
9 Section 11.2.5, Rule V, Revised IRR, R.A. 9184.
15
(3) An officer who is at least a 5th ranking permanent official with
knowledge, experience and /or expertise in procurement who, to
the extent possible, represents the finance area of the NWPC.
NOTE: The Vice-chairperson shall be a regular member. The term
'permanent' shall refer to plantilla positions within the
procuring entity.10
The provisional members are as follows:
(4) An officer who has technical expertise relevant to the
procurement at hand (i.e. Procurement of goods, consulting
services or infrastructure projects), and to the extent possible, has
knowledge, experience, and expertise in procurement.
(5) A representative from the end-user unit.
NOTE: A majority of the total BAC composition shall constitute a
quorum for the transaction of business, provided that the
presence of the Chairperson or Vice-Chairperson shall be
required.11 The Chairperson, or in his absence, the Vice-
Chairperson, shall preside at all meetings of the BAC. The
decision of at least a majority of those present at a meeting
where there is a quorum shall be valid and binding as an act of
the BAC provided that the Chairperson or, in his absence, the
Vice-Chairperson , shall vote only in case of a tie.12
10 Section 11.2.2 (last paragraph), Rule V, Revised IRR, R.A. 9184. 11 Section 12.3, Rule V, Revised IRR, R.A. 9184. 12 Section 12.4, Rule V, Revised IRR, R.A. 9184.
16
The BAC shall have the following functions:
a) advertise and/or post the invitation to bid/request for
expressions of interest;
b) conduct pre-procurement and pre-bid conferences;
c) determine the eligibility of prospective bidders;
d) receive bids;
e) conduct of bid evaluation;
f) undertake post-qualification;
g) resolve motions for reconsideration;
h) recommend award of contracts to the Head of the Procuring
Entity (Executive Director) or duly authorized representative;
i) recommend imposition of sanctions;
j) recommend use of alternative methods of procurement.
k) perform other necessary related functions including the
creation of the Technical Working Group.
b) Bids and Awards Committee Secretariat (BAC Secretariat)
BAC Secretariat shall be created by the Head of the Procuring
Entity which will serve as the main support unit of the NWPC BAC;
the Administrative Division is always designated as BAC
Secretariat. Its functions are as follows:
17
(1) Provide administrative support;
(2) Organize and make all necessary arrangements for BAC
meetings and conferences;
(3) Prepare minutes of the meetings and resolutions;
(4) Take custody of procurement documents and other records;
(5) Manage the sale and distribution of bidding documents to
interested parties;
(6) Advertise and/or post bidding opportunities, including bidding
documents and notices of awards;
(7) Assist in managing the procurement processes;
(8) Monitor procurement activities and milestones for proper
reporting to relevant agencies when required.
(9) Consolidate PPMPs from various units of the procuring entity
to make available for review;
(10) Act as the central channel of communications for the BAC
with end users, PMOs, other units of the line agency, other
government agencies, providers of goods, infrastructure projects,
and consulting services, observers, and the general public.
NOTE: The head of the Secretariat in the NWPC shall be at least a
5th ranking permanent employee or, if not available, a
permanent official of the next lower rank.13
13 Section 14.2, Rule V, Revised IRR, R.A. 9184.
18
c) Technical Working Group (TWG)-
Then TWG shall be created by the BAC to assist in the
procurement process, particularly in the eligibility screening,
evaluation of bids, and post-qualification.14
d) Observers-
Qualified observers, who shall be invited in all stages of the
procurement process, at least three (3) calendar days before the
date of the procurement stage/activity to sit in the proceedings,
shall consist of the following:
1) Representative from COA
2) At least one (1) representative from a duly recognized
private group in a sector or discipline relevant to the
procurement at hand:
a) For infrastructure projects, national associations of
constructors duly recognized by the Construction
Industry Authority of the Philippines (CIAP):
i. Philippine Constructors Association
ii. National Constructors Association of the
Philippines, Inc.
iii. Philippine Institute of Civil Engineers (PICE).
b) For goods, a specific relevant chamber-member of the
Philippine Chamber of Commerce and Industry.
14 Section 12.1, Rule V, Revised IRR, R.A. 9184.
19
c) For consulting services, a project-related professional
organization accredited or duly recognized by the
Professional Regulation Commission or the Supreme
Court:
i. PICE
ii. Philippine Institute of Certified Public Accountants
(PICPA)
iii. Confederation of Filipino Consulting Organizations
3) At least another representative from a non-government
organization (NGO)
Qualifications of an Observer:
1) The observer shall come from an organization duly
registered with the SEC or CDA;
2) The observers should meet the following criteria:
a) Have knowledge, experience or expertise in
procurement or in the subject matter to be bid;
b) Absence of actual or potential conflict of interest in the
contract to be bid
c) Any other relevant criteria may be determined by the
BAC.
Responsibilities of Observers:
1) To prepare the report either jointly or separately
indicating their observations made on the procurement
activities conducted by the BAC for submission to the
Executive Director, copy furnished the BAC Chairperson.
20
2) To submit their report to the NWPC and furnish a copy to
the GPPB and Office of the Ombudsman/Resident
Ombudsman. If no report is submitted by the observer,
then it is understood that the bidding activity conducted
by the BAC followed the correct procedure.
3) To immediately inhibit and notify in writing the NWPC of
any actual or potential interest in the contract to be bid.
Documents to which Observers are Allowed Access to:
Observers shall be allowed access to the following documents
upon request subject to signing of a confidentiality agreement:
1) Minutes of the BAC meetings
2) Abstract of Bids
3) Post-qualification Summary Report
4) APP and related PPMP
5) Opened Proposals
Observers not entitled to honoraria
To ensure independence “observers should not be granted
honoraria by the procuring entity for its participation in
the procurement process.” (GPPB Non-Policy Matter
Opinion No. 11-2005, dated 10 February 2005)
Non-attendance of the observers
21
Absence of observers will not nullify the BAC proceedings,
provided that they have been duly notified in writing.15
Observers are required to be invited during the post-
qualification stage of the Bidding Process
Observers shall be invited in all stages of the procurement
stage, which shall include the post-qualification stage of a
bidding process.16
15 Section 13.3, Revised IRR, R.A. 9184. 16 Section 13.1, Revised IRR, R.A. 9184.
22
VI.PROCUREMENT PROCEDURE FLOW CHART
PPMPs consolidated into
APP
Issuance of Purchase Request corresponding
to Procurements reflected in the APP
Procurement Process (Follow Procurement Mode indicated in the APP): Either COMPETITIVE BIDDING or any of the ALTERNATIVE
MODES OF PROCUREMENT (Public Bidding or
Alternative Method of
Procurement)
NOTICE OF AWARD issued to the
winning Bidder/Supplier
Issuance of CONTRACT/PURCHASE/JOB ORDER
Delivery/Inspection/Acceptance
PAYMENT
23
VII. PROCUREMENT MODES
Competitive Bidding
Alternative Methods
Limited Source Bidding or Selective Bidding
Direct Contracting or Single Source Procurement
Repeat Order
Shopping
Negotiated Procurement
VIII. PROCUREMENT MODE: Competitive Bidding
All procurement shall be done through Competitive Bidding,
except as provided for in Article XVI (Alternative Methods) of R.A.
9184.
STEPS in conducting procurement through Competitive
Bidding
STEP 1: Preparation of Bidding Documents
STEP 3: Pre-bid Conference
STEP 4: Submission and Receipt of Bids
STEP 5: Opening of Bids /Evaluation of Bids
STEP 6: Post-qualification
STEP 7: Award of the Contract
STEP 2: Advertisement of the Invitation to Bid
24
STEP 1: PREPARATION OF BIDDING DOCUMENTS
1) BAC Secretariat shall prepare the Bidding
Documents in cooperation with the End-User
concerned, who shall provide the technical
specifications for the goods/service to be procured.
The Documents shall be in accordance with the
standard forms prescribed by the Government
Procurement Policy Board (GPPB).
2) The Bidding Documents shall include the
following:
Approved Budget for the contract
Invitation to Bid/Request for Expression of
Interest
Eligibility Requirements
Instructions to Bidders
Terms of Reference (TOR) for consulting
services
Scope of work, where applicable
Plans/Drawing and Technical Specifications
Form of Bid, Price Form and List Goods or
Bill of Quantities
Delivery Time or Completion Schedule
Form, Amount and Validity Period of Bid
Security
25
Form, Amount and Validity of Performance
Security and Warranty
Form of Contract and General and Special
Conditions of Contract
3) A PRE-PROCUREMENT CONFERENCE shall be
conducted in order to ensure that the Bidding
Documents and Invitation to Bid is well in order and is
conducted prior to the posting of the Bidding
Documents and Invitation to Bid. The pre-procurement
conference may not be required for small
procurements where the ABC is 2 Million and below
(for procurement of goods), 5 Million and below (for
procurement of infrastructure projects) and 1 Million
and below (for consulting services).17
STEP 2: ADVERTISEMENT OF THE INVITATION TO BID
1) The invitation shall provide prospective bidders
the following information:
For the procurement of:
Goods, the name of the contract to be
bid and a brief description of the goods
to be procured
Infrastructure projects, the name and
location of the contract to be bid, the
project background and other relevant
information;
17 Section 20, Revised IRR, R.A. 9184.
26
Consulting services, the name of the
contract to be bid, a general description
of the project and other relevant
information;
A general statement on the criteria to be used
by the Procuring Entity;
The date, time and place of the deadline for the
submission and receipt of the eligibility
requirements, the pre-bid conference if any,
the submission and receipt of bids and the
opening of bids;
ABC to be bid;
The source of funding;
The period and place of availability of the
Bidding Documents;
The contract duration or delivery schedule;
The name, telephone number, address (fax, e-
mail and website), and designated contact
person of the Procuring Entity; and
Other relevant information
2) The Invitation to Bid shall be posted by the BAC
Secretariat in accordance with the scheduled timelines
indicated in the APP.
3) The Invitation to Bid shall be posted in the
following:
(a) At least once in one (1) newspaper of general
nationwide circulation which should be regularly
27
published for at least two (2) years before the date
of issue of the advertisement;
(b) Posted continuously in the PhilGEPS website, the
website of the NWPC for seven (7) calendar days
starting from the day of advertisement.
(c) Posted at any conspicuous place reserved for this
purpose in the premises of the NWPC for seven (7)
calendar days.
Advertisement in a newspaper of general
nationwide circulation shall no longer be
necessary18 in the following:
i. For procurement of goods where the ABC is 2
Million pesos and below;
ii. For procurement of infrastructure projects where
the ABC is 5 Million pesos and below;
iii. For procurement of consulting services, where the
duration is 4 months or less or 1 Million and
below.
4) The hard copy of the Bidding Documents should
be made available as of first posting until deadline for
submission and receipt of bids. Also, the soft copy
should be made available at the NWPC website and
PhilGEPS website as of first posting.
18 Section 21.2.2. Revised IRR, R.A. 9184.
28
The BAC is mandated to post all its bidding documents
on both its website and the PhilGEPS. (GPPB NPM 14-
2010, dated 21 May 2010)
5) The bidders may be asked to pay for the Bidding
Documents to recover the cost of its preparation and
development.
The cost of the bidding documents shall correspond to
the ABC ratings as indicated in GPPB Resolution No.
04-201219 (Guidelines of the Sale of Bidding
Documents):
ABC Maximum Cost of Bidding Documents
500,000 and below P500.00
More than 500,000 up to 1 Million
P1,000.00
More than 1 Million up to 5 Million
P5,000.00
More than 5 Million up to 10 Million
P10,000.00
More than 10 Million up to 50 Million
P25,000.00
More than 50 Million up to 500 Million
P50,000.00
More than 500 Million P75,000
19 Took effect on 20 August 2012.
29
STEP 3: PRE-BID CONFERENCE
1) Pre-bid conference shall be required in
procurements where the ABC is 1 Million or more. For
contracts with an approved budget of less than 1
Million, pre-bid conference may be conducted at the
discretion of the BAC.
2) It shall be conducted by the BAC as scheduled in
the Invitation to Bid which should be at least twelve
(12) calendar days before the scheduled deadline for
submission and receipt of bids. If the Procuring Entity
determines that, by reason of the method, nature or
complexity of the contract to be bid or when
international participation will be more advantageous
to the GOP, a longer period for the preparation of bids
is necessary, the pre-bid conference shall be held at
least thirty (30) calendar days before the deadline for
the submission and receipt of bids20.
3) The pre-bid conference shall discuss the eligibility
requirements and the technical and financial
components of the contract to be bid. Attendance of
the bidders shall not be made mandatory.21
4) BAC Secretariat shall prepare the Minutes of the
Pre-bid Conference and should be made available to
all the participants not later than three (3) calendar
days after the pre-bid conference.
20 Section 22.2, Rule VII, Revised IRR, R.A. 9184. 21 Section 22.3, Rule VII, Revised IRR, R.A. 9184.
30
5) Likewise, any statement made during the pre-bid
conference shall not modify the terms of the Bidding
Documents, unless such statement is specifically
identified in writing as an amendment and issued in a
Supplement/Bid Bulletin.
STEP 4: SUBMISSION AND RECEIPT OF BIDS
1) Eligible Participants:22
(a) Duly licensed Filipino citizens/sole proprietorship;
(b) Partnerships duly organized under the laws of the
Philippines and of which at least 60% of the interest
belongs to citizens of the Philippines (for procurement
of goods and consulting services) or at least 75% of the
interest belongs to citizens of the Philippines in the
case of procurement of infrastructure projects;
(c) Corporations duly organized under the laws of the
Philippines of which at least 60% of the outstanding
capital stock belongs to Filipino citizens (for
procurement of goods and consulting services), or at
least 75% Filipino owned (procurement of
infrastructure projects)
(d) Cooperatives duly organized under the laws of the
Philippines of which at least 60% belongs to Filipinos
(for procurement of goods and consulting services), or
at least 75% belongs to Filipinos (procurement of
infrastructure projects)
22 Sections 23.5 and 24.3, Rule VIII, Revised IRR, R.A. 9184
31
(e) Persons/entities forming themselves into a joint
venture, the ownership of which shall be 60% Filipino
for procurement of goods/consulting services or 75%
for infrastructure.
2) Foreign bidder may be eligible to participate in a
public bidding in any of the following circumstances:
a) When provided for under a Treaty or International
Agreement
b) When the foreign supplier is a citizen, corporation,
cooperation or association of a country, the laws or
regulations of which grant reciprocal rights to Filipinos.
c) When the goods sought to be procured are not
available from the local supplier.
d) When there is a need to prevent situations that defeat
competition or restraint of trade.
3) A bidder’s bid shall consist of two (2) envelopes,
namely the Technical Component of the Bid including the
eligibility requirements under Section 23.1 of the IRR (1st
Envelope)23; and the Financial Component of the Bid (2nd
Envelope).
4) The Technical Component shall contain the
following documents:
Legal Documents (Mayor’s Permit, Registration
Certificate, Tax Clearance) 23 Section 25.2, Rule VIII, Revised IRR, R.A. 9184.
32
Technical Documents (Statement of all on-going
government and private contracts and one (1)
completed contract complying with the “Single
Largest Completed Contract Rule, PCAB License
and Registration for procurement of Infrastructure
Projects.
Bid Security shall be returned only after the
bidder with the Lowest Calculated Responsive Bid
has signed the contract and furnished the
performance security except to those declared by
the BAC as failed or post-disqualified (Section
27.4, Rule VIII, IRR). In no case shall bid security be
returned later than the expiration of the bid
validity period (Section 27.6, Rule VIII, IRR).
Technical Specifications
Sworn statement by the prospective bidder as to
the following:
It is not blacklisted;
The documents submitted are authentic
copies of the original with the information
provided therein being true and correct;
It is authorizing the Procuring Entity to
verify all the documents;
Signatory is duly authorized with notarized
Secretary’s Certificate attesting to such
fact if bidder is a corporation, partnership,
cooperative or joint venture;
It complies with the disclosure provision
under Section 47 of the Act;
33
It complies with the responsibilities of a
prospective bidder;
It complies with existing labor laws and
standards;
It did not give or pay any amount to any
personnel of the government in relation to
the procurement activity.
5) Financial Component of the Bid shall contain the
Audit Financial Statements stamped “received” by the BIR
and the Net Financial Contracting Capacity or NFCC.24
6) Credit Line Commitment is not an available
option, as a financial eligibility document, for the bidder.
Thus, the bidder is required to submit an Audited Financial
Statement and a net financial Contracting Capacity.25
7) The Bid Validity Period cannot exceed 120 days
counted from the opening of bids.26 Should it become
necessary to extend the validity of the bids and bid
securities beyond 120 calendar days, the procuring entity
shall request in writing all those who submitted bid for
such extension before the expiration date thereof.
Bidders, however, shall have the right to refuse to grant
such extension without forfeiting their bid security.27
8) Forms of Bid Security
24 Section 23, Rule VIII, Revised IRR, R.A. 9184. 25 GPPB Resolution No. 20-2013, took effect on 12 March 2014. 26 Section 28.1, Rule VIII, Revised IRR, R.A. 9184. 27 Section 28.2, Rule VIII, Revised IRR, R.A. 9184.
34
Form of Bid Security Amount to be paid
Cash/Cashier’s Manager’s Check 2% of the ABC
Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank
2% of ABC
Surety Bond callable upon demand by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security.
5% of ABC
Any combination of the foregoing
Proportionate to share of form with respect to total amount of security
A bidder can modify its bid provided that this is done before the
deadline for submission and receipt of bids. When the bidder
modifies its bid, it is not allowed to retrieve its original bid, but
shall only be allowed to send another bid equally sealed, properly
identified, linked to its original bid and marked as “modification”.
Bid modifications received after the applicable deadline for
submission and receipt of bids shall not be considered and shall
be returned to the bidder unopened.28
28 Section 26.1, Rule VIII, Revised IRR, R.A. 9184.
35
STEP 5: OPENING OF BIDS/EVALUTATION OF BIDS
1) The BAC shall open the bids immediately after the
deadline for the submission and receipt of bids.
2) The Technical Component shall be opened first.
3) The BAC, through the BAC Secretariat shall check
the documents in the Technical Component and shall
determine whether the documents are present using
the “pass-fail” criterion.
4) Bidders who have a complete set of documents
present in the Technical Component shall be
considered “PASSED”.
5) Only those bidders who are considered “PASSED”
shall proceed with the opening of the Financial
Component.
6) In the opening of the Financial Component, the
bidders’ Financial Offer shall be evaluated and the BAC
shall determine whether or not the computation
leading to the bid price is accurate. Only bids that are
determined to contain all the bid requirements for
both components shall be rated “passed” and shall be
considered for evaluation and comparison.
36
7) The bidder with a bid price higher than the ABC
shall be automatically disqualified. Once the Financial
Offers are evaluated, the BAC shall rank the bidders
based on their evaluated bid price, from the lowest
calculated bid to the highest calculated bid.
In the event of a tie breaker amongst the lowest
evaluated bid prices, the bidders with the lowest
evaluated bid prices are to all undergo post-
qualification. In the event that more than one bidder is
post-qualified, the bidders are to undergo a non-
discretionary process based on sheer luck, in order to
determine the winning bidder.
The Procuring Entity is advised at the onset, to
prescribe in its Bidding Documents the method of
breaking the tie. In the event that there is no
prescribed method mentioned in the Bidding
Documents, the bidders shall have to agree to a
method of breaking the tie. 29
8) The BAC Secretariat shall prepare the Abstract of
Bids which shall contain the following:
Name of the contract and its location, if
applicable
Time, date, and place of bid opening
29 GPPB Circular No. 06-2005, dated 5 August 2005.
37
Names of bidders and their corresponding
calculated bid prices arranged from lowest to
highest, the amount of bid security and the name
of issuing entity.
STEP 6: POST QUALIFICATION
1) The Lowest Calculated Bid/Highest Rated Bid shall
undergo post-qualification in order to determine
whether the bidder concerned complies with and is
responsive to all the requirements and conditions
as specified in the Bidding Documents.
2) The BAC Secretariat shall notify the bidder with
the Lowest Calculated Bid/Highest Rated Bid that it
shall be subject to post-qualification and shall be
required to submit the following post-qualification
documents within three (3) calendar days from
receipt:30
(a) Latest Income tax returns and business tax
returns;
(b) Certificate of PhilGEPS registration;
(c) Other licenses and permits required by law and
stated in the Bidding Documents
Failure to submit the above requirements on time
or a finding against the veracity of such shall be
30 Section 34.2, Rule X, Revised IRR, R.A. 9184.
38
ground for the forfeiture of the bid security and
disqualify the bidder for award.
3) The post-qualification shall verify, validate, and
ascertain all statements made and documents
submitted by the bidder with the Lowest Calculated
Bid/Highest Rated Bid, using non-discretionary criteria,
as stated in the Bidding Documents.
4) If it is determined that the bidder passes all the
criteria for post-qualification, the BAC shall declare the
said bid as the LOWEST CALCULATED RESPONSIVE BID
(LCRB)/Highest Rated Responsive Bid, and recommend
to the Head of the Procuring Entity, through a BAC
Resolution, the award of the contract.
5) If it is determined, however, that the bidder with
the Lowest Calculated Bid fails the criteria, the BAC
shall immediately notify the said bidder in writing of its
post-disqualification and the grounds for it.
Immediately thereafter, the notwithstanding any
pending request for reconsideration, the BAC shall
initiate and complete the same post-qualification
process on the bidder with the second Lowest
Calculated Bid/Highest Rated Responsive Bid.
6) If the second lowest calculated bidder fails to
post-qualify, the procedure is repeated for the bidder
next lower and so on until a bidder is post-qualified.
39
7) The post-qualification process shall be completed
in not more than seven (7) calendar days from the
determination of the lowest calculated bid. The post-
qualification stage may be extended but in no case
shall the aggregate period exceed 30 calendar days.31
8) Failure of Bidding. The BAC shall declare the
bidding a failure when:
No Bids are received;
All prospective bidders are declared
ineligible;
All bids fail to comply with all the bid
requirements or fail post-qualification or in the
case of consulting services, there is no
successful negotiation; or
The bidder with the Lowest Calculated
Responsive Bid/Highest Rated Responsive Bid
refuses, without justifiable cause, to accept
the award of contract and no award is made in
accordance with Section 40 of the Act and the
IRR.
31 Section 34.8, Rule X, Revised IRR, R.A. 9184.
40
STEP 7: AWARD OF THE CONTRACT
1) The BAC shall recommend to the Head of the
Procuring Entity the award of the contract to the
bidder with the Lowest Calculated Responsive
Bid/Highest Rated Responsive Bid.
2) In facilitating the award of the contract, the BAC
shall submit the following:
(a) Resolution of the BAC recommending award;
(b) Abstract of Bids
(c) Duly approved program of work or delivery
schedule, and Cost estimates;
(d) Document issued by appropriate entity
authorizing the Procuring Entity to incur
obligations for a specified amount
(e) Other pertinent documents required by
existing laws, rules and/or procuring entities
concerned.
3) Within seven (7) calendar days from receipt of the
recommendation of the BAC, the Head of the
Procuring Entity shall either approve or disapprove the
recommendation. Within the prescribed period, the
BAC shall notify all losing bidders.32
32 Section 37.1.2, Rule XI, Revised IRR, R.A. 9184.
41
4) In case of approval, the Head of the Procuring Entity
shall immediately issue the Notice of Award (NOA) to
the bidder with the Lowest Calculated Responsive Bid.
In case of disapproval, such disapproval shall be based
only on valid, reasonable, and justifiable grounds to be
expressed in writing. The NOA shall be posted within
three (3) calendar days in the PhilGEPS website,
website of the Procuring Entity, and conspicuous
places within the premises of the Procuring Entity.
5) Aside from the NOA, the bidder recommended for
award is required to comply with the following:
Submission of a valid Joint venture agreement,
in case the bidder consist of a group of entities
which signified their intention to enter into a
joint venture once identified as the winning
bidder;
Posting of a performance security
Signing of the contract within ten (10) days
from receipt by the bidder of the NOA.
Approval by higher authority as provided in
Section 37.3 of the IRR
6) Documents forming part of the contract
Contract Agreement
Bidding Documents
42
Winning bidder’s bid, including the Eligibility
requirements, Technical and Financial Proposals,
and all other documents/statements submitted;
Performance Security
Credit Line
Notice of Award of the Contract
Other contract documents that may be required
by existing laws and/or the NWPC
7) Notice to Proceed
Where applicable, the procuring entity shall issue the
Notice to Proceed together with a copy of the
approved contract to the successful bidder within
three (3) calendar days from the date of the approval
of the contract by the appropriate government
approving authority.
8) Performance Security is a security to guarantee
faithful performance by the winning bidder of its
obligations under the contract in accordance with the
Bidding Documents.
Forms of Performance Security:
Forms Amount
Cash or Cashier’s or Manager’s Check
5% (Goods) 10% (Infrastructure Projects)
Bank draft/guarantee or 5% (Goods) 10%
43
irrevocable letter of credit issued by a Universal or Commercial Bank; provided, however, that it shall be confirmed or authenticated by a universal or commercial bank, if issued by a foreign bank
(Infrastructure Projects)
Surety bond callable upon demand issued by a surety or insurance company duly certified by the insurance commission as authorized to issue such security.
30%
Any combination of the foregoing
Proportionate to share of form with respect to total amount of security
9) The performance security shall be valid until the
issuance by the Procuring Entity of a Certificate of
Acceptance.
10) Reservation Clause.
The Head of the Procuring Entity reserves the right to
reject any and all bids, declare a failure of bidding or
not to award the contract in the following situations:
a) There is prima facie evidence of collusion between
appropriate public officers or employees of the
Procuring Entity.
44
b) The BAC is found to have failed in following the
prescribed bidding procedures.
c) For any justifiable and reasonable ground, where the
award of the contract will not redound to the benefit
of the GOP, as follows:
i. If the physical and economic conditions
have significantly changed so as to
render the project no longer
economically, financially, or technically
feasible, as determined by the Head of
the Procuring Entity;
ii. If the project is no long necessary as
determined by the Head of the
Procuring Entity; and
iii. If the source of funds for the project
has been withheld or reduced through
no fault of the Procuring Entity.
45
IX. PROTEST MECHANISM33
Decisions of the BAC at any stage of the procurement process
may be questioned by filing a request for reconsideration within
three (3) calendar days upon receipt of the written notice or
upon verbal notification.
The BAC shall decide on the request for reconsideration within
seven (7) calendar days.
In the event that the request for reconsideration is denied, the
bidder can file within seven (7) calendar days, a PROTEST in the
form of a verified position paper, accompanied by a non-
refundable PROTEST FEE.
Protest fee
ABC Range Protest Fee Cost
50 Million pesos and below
0.75% of the ABC
More than 50 Million pesos to 100 Million pesos
P500,000
More than 100 Million pesos to 500 Million pesos
0.5% of the ABC
More than 500 Million pesos to 1 Billion pesos
P2,500,000
More than 1 Billion pesos to 2 Billion pesos
0.25% of the ABC
More than 2 Billion P5,000,000.00
33 Section 55, Rule XVII, Revised IRR, RA 9184.
46
pesos to 5 Billion pesos
More than 5 Billion pesos
0.1% of the ABC
47
X.PROCUREMENT MODE: Alternative Methods of Procurement
When justified by the conditions, these methods are resorted to
in order to promote economy and efficiency. However, they are
subject to the prior approval of the Head of Procuring Entity. The
Procuring Entity shall ensure that the most advantageous price for
the Government is obtained.
(1) Limited Source Bidding
(2) Direct Contracting*
(3) Repeat Order*
(4) Shopping*
(5) Negotiated Procurement:
Two Failed Bidding*
Emergency Cases*
Take Over of Contracts
Adjacent or Contiguous
Agency-to-Agency
Procurement Agent
Highly Technical Consultants*
Defense Cooperation Agreement
Small Value Procurement*
Lease of Real Property*
NGO Participation
Community Participation
United Nations Agencies
48
*Commonly used kinds of Negotiated Procurement
LIMITED SOURCE BIDDING OR SELECTIVE BIDDING
1) This involves direct invitation to bid by the Procuring
Entity from the list of pre-selected suppliers or consultants
with known experience and proven capability on the
requirements of the particular contract. This may be
employed under any of the following:
Procurement of highly specialized goods (example
– sophisticated defense equipment, complex air
navigation systems, coal) and consulting services
where only a few suppliers or consultants are
known to be available, such that resorting to the
public bidding method will not likely result in any
additional suppliers or consultants; or
Procurement of major plant components where it
is deemed advantageous to limit the bidding to
known qualified bidders.
2) The pre-selected suppliers or consultants shall be those
appearing in a list maintained by the relevant government
authority that has expertise in the type of procurement
concerned.
3) The pre-selection shall be based upon the capability and
resources of the bidders to perform the contract.
49
4) The BAC shall directly invite all the suppliers or
consultants appearing in the pre-selected list.
5) All other procedures for competitive bidding shall be
undertaken except for the advertisement of Invitation to
Bid/Request for Expression of Interest under Section
21.2.1 of the IRR.
DIRECT CONTRACTING OR SINGLE SOURCE PROCUREMENT
1) It does not require elaborate Bidding Documents. The
supplier is simply asked to submit a price quotation or a
pro-forma invoice together with the conditions of sale. The
offer may be accepted immediately or after some
negotiations. This may be resorted to by concerned
Procuring Entity under any of the following conditions:
Procurement of goods of propriety nature which
can be obtained only from the propriety source, i.e.
when patents, trade secrets, and copyrights
prohibit others from manufacturing the same item;
When the procurement of critical components
from a specific supplier is a condition precedent to
hold a contractor to guarantee its project
performance, in accordance with the provisions of
its contract; or
50
Those sold by an exclusive dealer or manufacturer
which does not have sub-dealers selling at lower
prices.
REPEAT ORDER
1) This is procurement of goods from the previous winning
bidder, whenever there is a need to replenish goods
procured under a contract previously awarded through
Competitive Bidding. It shall be subject to the following
conditions:
Unit prices of the repeat order must be the same as
or lower than those in the original contract,
provided that such prices are still the most
advantageous to the GOP after price verification;
It will not result in splitting of contracts,
requisitions, or purchase orders, as provided for in
Section 54.1 of this IRR;
Except in cases duly approved by the GPPB, it shall
be availed of only within six (6) months from the
contract effectivity date stated in the Notice to
Proceed arising from the original contract;
It shall not exceed twenty-five percent (25%) of the
quantity of each item in the original contract.
51
SHOPPING
1) This involves request by the Procuring Entity for the
submission of price quotations for readily available off-
the-shelf goods or ordinary/regular equipment to be
procured directly from suppliers of known qualifications.
This shall be employed in any of the following cases:
When there is an unforeseen contingency
requiring immediate purchase: Provided, however,
That the amount shall not exceed the thresholds
prescribed;
Procurement of ordinary or regular office supplies
and equipment not available in the Procurement
Service involving an amount not exceeding the
thresholds prescribed.34
2) The phrase “ordinary or regular office supplies” shall be
understood to include those supplies, commodities, or
materials which, depending on the Procuring Entity’s
mandate and nature of operations, are necessary in the
transaction of its official businesses, and consumed in the
day-to-day operations of said Procuring Entity. Office
supplies shall not include services such as repair and
maintenance of equipment and furniture, as well as
trucking, hauling, janitorial, security, and related or
analogous services.
34 Section 52.1.b, Rule XVI, Revised IRR, R.A. 9184.
52
3) At least three (3) price quotations from bona fide
suppliers shall be obtained for procurement of office
supplies under Section 52.1.b of the Revised IRR.
NEGOTIATED PROCUREMENT
1) This involves direct negotiation of a contract with a
technically, legally, and financially capable supplier,
contractor, or consultant in any of the following cases:
Two Failed Biddings. Where there has been failure
of public bidding for the second time.
Emergency Cases. In case of imminent danger to
life or property during a state of calamity, or when
time is of the essence arising from natural or man-
made calamities or other causes where immediate
action is necessary to prevent damage to or loss of
life or property, or to restore vital public services,
infrastructure facilities and other public utilities.
Take-Over of Contracts. Take-over of contracts,
which have been rescinded or terminated for
causes provided for in the contract and existing
laws, where immediate action is necessary to
prevent damage to or loss of life or property, or to
restore vital public services, infrastructure facilities
and other public utilities.
53
Adjacent or Contiguous. Where the subject
contract is adjacent or contiguous to an on-going
Infrastructure Project or Consulting Service where
the consultants have unique experience and
expertise to deliver the required service.
Agency-to-Agency. Procurement of infrastructure
projects, consulting services, and goods from
another agency of the GOP, such as the PS-DBM,
which is tasked with a centralized procurement of
Common-Use Supplies for the GOP.
Procurement Agent. In order to hasten project
implementation, Procuring Entities which may not
have the proficiency or capability to undertake a
particular procurement, as determined by the
Head of the Procuring Entity concerned, may
request other GOP agencies to undertake such
procurement for them, or at their option, recruit
and hire consultants or procurement agents to
assist them directly and/or train their staff in the
management of the procurement function.
Highly Technical Consultants. This is the case of
individual consultants hired to do work that is (i)
highly technical or proprietary; or (ii) primarily
confidential or policy determining, where trust and
confidence are the primary consideration for the
hiring of the consultant: Provided, however, that
the term of the individual consultants shall, at the
54
most, be on a six month basis, renewable at the
option of the appointing Head of the Procuring
Entity but in no case shall exceed the term of the
latter.
Defense Cooperation Management. Upon prior
approval by the President of the Philippines, and
when the procurement for use by the AFP involves
major defense equipment or materiel and/or
defense-related consultancy services, when the
expertise or capability required is not available
locally, and the Secretary of National Defense has
determined that the interests of the country shall
be protected by negotiating directly with an agency
or instrumentality of another country with which
the Philippines has entered into a defense
cooperation agreement or otherwise maintains
diplomatic relations.
Small Value Procurement. Where the procurement
does not fall under Shopping and the amount
involved does not exceed the thresholds
prescribed.
Lease of Real Property. Lease of privately owned
real property and venue for official use.
NGO Participation. When an appropriation law or
ordinance earmarks an amount to be specifically
contracted out to Non-Governmental
Organizations (NGOs), the Procuring Entity may
55
enter into a Memorandum of Agreement with an
NGO.
Community Participation. Where, in the interest of
project sustainability or to achieve certain specific
social objectives, it is desirable in selected projects,
or its components, to call for participation of local
communities in the delivery of goods, including
non-consulting services, and simple infrastructure
projects.
United Nations Agencies. Procurement from
specialized agencies of the United Nations of any of
the following: (a) small quantities of off-the-shelf
goods, primarily in the fields of education and
health; and (b) specialized products where the
number of suppliers is limited, such as vaccines or
drugs.
TERMS AND CONDITIONS FOR THE USE OF ALTERNATIVE METHODS
Splitting of contract is not allowed.
Advertisement and posting as prescribed in Section
21.2.1 of the Revised IRR may be dispensed with:
Provided, that the BAC, through its Secretariat, shall post
the invitation or request for submission of price
quotations for Shopping under Sections 52.1 (b) and
56
Negotiated Procurement under Sections 53.1 (two-failed
biddings), 53.9 (small value procurement); and 53.11 (NGO
Participation) of the IRR in the PhilGEPS website, the
website of the Procuring Entity concerned, if available, and
at any conspicuous place reserved for this purpose in the
premises of the procuring entity for a period of seven (7)
calendar days.
In all instances of alternative methods of procurement,
the BAC, through the Secretariat, shall post, for
information purposes, the Notice of Award in the PhilGEPS
website, the website of the Procuring Entity concerned, if
available, and at any conspicuous place reserved for this
purpose in the premises of the Procuring Entity.