NuStart Efl ergysm - NRC: Home Page · 2012-11-29 · Documentation of borehole sampling and...
Transcript of NuStart Efl ergysm - NRC: Home Page · 2012-11-29 · Documentation of borehole sampling and...
NuStart Efl ergysm
NuStart Bellefonte NuclearProject
NRC Onsite ReviewSite Characterization Activities
July 10-11, 2006
NuStart Energy Development, LLC - All Rights Reserved
NuStart Energy,
Project Introduction & Agenda
" Project introduction - Peter Hastings (NuStart)
" Introductions
" Project Background and Status
" Site orientation - Jim Chardos (TVA)
" Site safety briefing
* Logistics
* Site tour
* Project Organization and QA - Joe Mancinelli (Enercon)
" Site Investigations Overview - Bill Godwin (WLA)
July 10-11, 2006 2
NuStartEnergym
Project Background
" December, 1974
" August, 2005
" September, 2005
" December, 2005
" April, 2006
- CP issued for Bellefonte Units 1 &2
- ABWR study of Bellefonte under DOE's NP2010 Program
- NuStart selects Grand Gulf & Bellefonte for COLAs
- TVA notifies NRC that Bellefonte 1 &2 in terminated status
- Site Geotechnical Activities Initiated
July 10-11, 2006 3
July 10-11, 2006 3
/__ • --- NuStart Energy, m
Overview of Current Status
" Site characterization underway
" Current geotechnical/groundwater activities as of July 2006
" Surface water sampling and other environmental baselining activities inprogress
" Meteorological data collection initiated May 2006
" Application submittal Fourth Quarter 2007
" NuStart Providing Leadership to Maximize Standardization for AP1000
COL Applications
July 10-11, 2006 4
NuStart Energy.
o o m no 1=s I=
Site Layout
* - NuStart Energy.
Plant StructuresExisting
NuStartEnergym
Project OrganizationSite Geotechnical Investigations
NuStart Energy
1--------- Tennessee ValleyAuthority
Enercon ServicesCOLA Development
II
WLASeismic & Geologic
Characterization
I
MACTECSite
GeotechnicalCharacterization
I
SupportSubcontractors
SupportSubcontractors
July 10-11, 2006 7
NuStartEnergysm
Project Organization ResponsibilitiesSite Geotechnical Investigations
" NuStart Energy
* Overall direction and management of COLA preparation
" Tennessee Valley Authority
* Site owner; interface as necessary with NuStart Energy
" Enercon Services, Inc.
* COL Application contractor for NuStart Energy
* Providing QA oversight for geotechnical investigation activities as well asmanaging interface with site owner
" Enercon Subcontractors
" William Lettis & Associates, Inc. (WLA) - Provides Overall Technical Directionfor Geological, Geotechnical and Seismological Consultants
* MACTEC Engineering and Consulting - Implementation of Site InvestigationActivities, Laboratory Testing and Geotechnical Analyses
July 10-11, 2006 8
SNuStartEnergy.m
Project Organization ResponsibilitiesSite Geotechnical Investigations (cont'd)
" MACTEC and WLA share field project management responsibilities for
geotechnical and geologic data collection tasks
" MACTEC Site Coordinator provides supervision of the day-to-day field
activities
" The Rig Geologist has full-time assignment with a drill rig operation
The Rig Geologist duties include:[] Ensure that drilling or testing operations are conducted in
conformance with specified proceduresDocumentation of borehole sampling and testingMaintaining field log for boring, including classification of materialsrecovered and recovery and RQD measurements for rock coreChain-of-custody document preparation and logging samples
July 10-11, 2006 9
1111- NuStartEnergy.
Site Investigation/Data ColletionQuality Assurance
tart"E"''R Enercon QA Program
MACTEC QA Program
FEnercon QAPPD
Project Geotechnical - GeotechnicalDCP Work Plan
WorkInstructions----- Contracted to perform work under Enercon QA program
- Qualification of contractor/subcontractor QA program-- - Review of Quality Assurance Plan
Flowdown of requirementsInterrelationship between documents
I PNuStart Energysm
Quality Assurance" NuStart contracted Enercon Services to perform COLA development under the
Enercon Services' QA Program
" COLA work by Enercon Services is performed under the Enercon Services'
Quality Assurance Project Plan Document
" Engineering analysis performed by William Lettis & Associates and MACTEC is
performed under the Enercon Services' Quality Assurance Project Plan Document
" Enercon qualified the MACTEC Quality Assurance Program
Enercon reviewed and approved MACTEC's Project Quality Assurance Plan
* Geotechnical field investigation and laboratory testing by MACTEC is performed
under the MACTEC Quality Assurance Project Document
* Geotechnical field work by William Lettis & Associates is performed under the
MACTEC Quality Assurance Project Document
July 10-11, 2006 11
2 NuStartEnlergym
Site Geotechnical Investigatio sUData Collection Objectives
* Confirm and demonstrate applicability of field data from previous
limited exploration
m Limited data in current proposed location
* Obtain new data in safety related areas to meet
" Updated NRC guidelines
* Vendor DCD requirements
" Soil Structure Interaction (SSI) requirements
* Collect new data on certain non-safety related areas
* Surface water sampling for characterization and quality
* Groundwater sampling
Site characterization
Current conditions
July 10-11, 2006 12
NuStartEnergym.
Three Well Cluster - Under Construction
NuStartEnergym
Sampling Operations
_ ______NuStart Energy.m
Geologic & Geotechnical SiteCharacterization Scope
" Perform geological, geotechnical and geophysical exploration program to
confirm and refine:
" site stratigraphy and groundwater conditions" static and dynamic soil and rock properties" site geohazards and foundation conditions
" Evaluate variability of site conditions and soil and rock parameters
" Evaluate site suitability with respect to regulatory guidance and reactor
vendor DCD
" Update, as required, site soil profile, site response, and SSE
* Characterize possible seismic and/or geotechnical hazards and evaluate
mitigating measures
July 10-11, 2006 15
NuStartEnergy.
Regional Geologic Setting
BUo.,te Sits
N
A
NuStartEnerg.
Site Geology
- I~c
A
c-)CrfNt
I ,
Y
'Reservoir
AN
0 875 1=750•~Feet
NuStartEnergy,
Field Exploration Methods
" Standard Penetration Testing (SPT)
" Rock Coring (NQ, HQ sizes)
" Borehole Goodman Jack Testing
(3 completed)
" Seismic downhole and P-S Suspension
velocity measurements (8 planned)
" Borehole Televiewer Profiles (18
planned, 10 completed)
" Seismic Refraction and Gravity
(14,000 LF planned, 6000LF
underway)
* Spectral Analysis Of Surface Waves
(SASW) (13 planned)
* Borehole Packer Testing (16 planned,
7 completed)
* Cone Penetration Test (CPT) Soundings
(15 static and 2 seismic planned)
" Monitoring Wells (Observation Wells)
(17 clusters installed)
" Geologic Mapping
" Test Pit Excavation and Mapping
(16 planned)
July 10-11, 2006 20
NuStart Energym
Geotechnical Laboratory Testing
" Geotechnical Index Measurement
" Geotechnical Strength Testing
" Dynamic Testing (UTEX)
July 10-11, 2006 21
NuStartEnergy.m
Lab Testing Program
GEOTECHNICAL INDEX
Moisture Content
Specific Gravity
X-Ray Diffraction/Mineralogy
Grain size Mechanical
Grain size
Atterberg Limits and Indices (soil)
Slaking Durability (core)
Organic Content
SOIL DYNAMIC TESTING
X-ray of UD Samples Prior to Shipping to Austin
Resonant Column/Torsional Shear Testing(performed at the University of Texas - Austin)
July 10-11, 2006 22
NuStartEnergy,
Lab Testing Program (Cont'd)
GEOTECHNICAL PROPERTIES GEOTFC(7INICAL PROPERTIES
Petrographic Thin Section
Unconfined Compression (core)
Unconfined Compression with modulus
(core)
Unit Weight (core)
Triaxial CU (3-point)
Triaxial SCUE (3-point) - Remolded
Direct Shear (3-point)
v • v •
Consolidation
Corrosion
Proctor
California Bearing Ratio (CBR) Test
July 10-11, 2006 23
NuStartEnergy.m
Geotechnical Borehole Procedure" Work Instructions issued to drilling companies and Rig Geologists defining duties
" Boring Assignments for each borehole prepared by MACTEC Site Coordinator
with Principal (WLA/MACTEC) review; Boring assignments specify:
* Boring location and Type* Boring depth and required testing* Boring Completion
" TVA personnel review drill site and provide excavation permit
" Rig Geologist directs Drill Crew to prepare drill site and instructs drill crew to
prepare and perform as per Boring Assignment
" Rig Geologist monitors drilling, describes samples, maintains field log
" Modifications to Boring Assignment instructions, if needed, reviewed and approved
by Site Coordinator
" Samples transported to site storage facility at end of day
July 10-11, 2006 24
NuStart Energym
Monitoring Wells Installation Procedure
" Hydrology Lead directs boring layout using GPS methods
" TVA personnel provide clearance for drilling
" Site Coordinator prepares Boring Assignment for lithologic boring and gives to Rig
Geologist
" Rig Geologist and drill crew executes the Boring Assignment using procedures referenced
in Work Plan, logging boring and submitting samples and cores for on-site storage
" Hydrology Lead reviews boring logs for well design and provides well construction plan to
Site Coordinator
" Site Coordinator prepares Boring Assignment for monitoring well installation and gives to
well crew and Enercon observer
" Drill crew installs under Enercon observation
July 10-11, 2006 25
/- NuStartEnergym
Beginning of Day Activities
" Daily group safety briefing at field office before leaving for assignment
" Rig Geologist conducts morning crew safety meeting and inspection of
equipment with operator
" Rig Geologist completes safety inspection checklist
" Review Work Assignments for the day
July 10-11, 2006 26
NuStartEnergysm
End of Day Activities
" Return field records and all samples to the on-site storage facility
* Complete sample inventory forms and place samples in Storage Facility
" Partially completed field records copied to assure data backup
" Completed originals remain in locked file cabinets until checked,
duplicated for site file, and original record transported to secure file
cabinet at MACTEC's Raleigh, NC office
July 10-11, 2006 27
______NuStart Energysm
Data Transmittal
* At appropriate intervals (generally at end of each 10-day shift), Site
Coordinator prepares package of collected data and transmits or
transports originals to secure file cabinet at MACTEC's Raleigh, NC
office
* Selected soil and rock specimens are transported under Chain of Custody
to appropriate laboratory for testing
July 10-11, 2006 28
/ • NuStart Energy•
Current Site Activities
(week of 10 July 2006)
[] Geotechnical Borings* 4 Borings in progress (Power Block and general yard areas)* 80 of 100 borings complete
" P-S Suspension Logging
E B-1005 (Unit 3) and B-1034 (Unit 4)
" Surface Geophysics
" Phase 1 seismic refraction (night shift)* Micro-gravity survey to start soon
" Groundwater Monitoring and Sampling
m 49 monitoring wells have been installed in 17 clustersN 10 wells are being sampled
a All monitoring wells will have GW level measurements* 12 observation wells installed for pump testing
July 10-11, 2006 29
/___ •NuStartEnergy,•
Boreholes B-1005 and B-1034
" B-1005 and B-1034 are power block borings that:
* Centered in containment structures of nuclear island" Obtain new data to meet
" Updated NRC guidelines" Vendor DCD requirement
" Soil Structure Interaction (SSI) requirements
" The following geotechnical tests are planned for B-1005 and B-1034
m Seismic downhole velocity measurements (P-S logging)
" In-situ testing on nearby primary borings
" Borehole Televiewer profiles" Borehole Packer testing* Goodman Jack testing
July 10-11, 2006 30
______NuStart Energ•y. m
SUMMARY
" Schedule
c] Started field exploration April, complete mid-August, ahead of schedule
" Safety
o First Priority-No significant incidents or injuries
* No Unanticipated Conditions
* Project Organization
o Communication and oversight at management and field level
* Quality Assurance
o Data Collection Objectives and Implementation
July 10-11, 2006 31
July 10-11, 2006 31