NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer...

22
NUREG 1055 NUREG 1055 – Then and Then and Now Now

Transcript of NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer...

Page 1: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NUREG 1055 NUREG 1055 –– Then and Then and NowNow

Page 2: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

Overview of NUREG 1055Overview of NUREG 1055

BackgroundBackground

22

Application of NRC Lessons LearnedApplication of NRC Lessons Learned

Page 3: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

BackgroundBackground

Nuclear Construction at Zimmer ended in Nuclear Construction at Zimmer ended in 19821982

The scope of necessary corrective actionsThe scope of necessary corrective actions

33

The scope of necessary corrective actions The scope of necessary corrective actions became so extensive, the project was became so extensive, the project was abandoned after 10 years of construction abandoned after 10 years of construction and nearly $2 Billion in investment.and nearly $2 Billion in investment.

Page 4: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

What Were The Deficiencies?What Were The Deficiencies?Per NUREGPer NUREG--1055, quality of structures, systems, and 1055, quality of structures, systems, and components was indeterminate due to:components was indeterminate due to:

Inadequate quality Inadequate quality inspection documentationinspection documentation

Inadeq ate reporting ofInadeq ate reporting of

Inadequate procedures Inadequate procedures and instructionsand instructions

Proced re iolationsProced re iolations

44

Inadequate reporting of Inadequate reporting of nonconformancesnonconformances

Drawing deficienciesDrawing deficiencies

Inadequate specificationsInadequate specifications

Materials control Materials control deficienciesdeficiencies

Procedure violationsProcedure violations

Inadequate licensee Inadequate licensee auditsaudits

Inadequate corrective Inadequate corrective action programaction program

Page 5: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

What Are The Deficiencies?What Are The Deficiencies?What is being observed in current construction efforts:What is being observed in current construction efforts:

Inadequate QC Inadequate QC DocumentationDocumentation

Inadeq ate reporting ofInadeq ate reporting of

Inadequate procedures Inadequate procedures and instructionsand instructions

Proced re iolationsProced re iolations

55

Inadequate reporting of Inadequate reporting of nonconformancesnonconformances

Drawing deficienciesDrawing deficiencies

Inadequate specificationsInadequate specifications

Materials control Materials control deficienciesdeficiencies

Procedure violationsProcedure violations

Inadequate licensee Inadequate licensee auditsaudits

Inadequate corrective Inadequate corrective action programaction program

Page 6: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

What Are The Deficiencies?What Are The Deficiencies?What is being observed in current construction efforts:What is being observed in current construction efforts:

Vendors inexperienced in nuclear environmentsVendors inexperienced in nuclear environmentsConstruction craft and contractors inexperienced in Construction craft and contractors inexperienced in nuclear environmentsnuclear environmentsDifficulty managing multiple design control processesDifficulty managing multiple design control processesDifficulty managing multiple problem identification and Difficulty managing multiple problem identification and resolution (PI&R) programsresolution (PI&R) programs

66

resolution (PI&R) programsresolution (PI&R) programsProcurement specification issues Procurement specification issues –– beyond code but not beyond code but not enforcingenforcingVendor oversight challengesVendor oversight challengesInsufficient QA personnel for oversight activitiesInsufficient QA personnel for oversight activitiesLack of Commercial Grade Dedication understandingLack of Commercial Grade Dedication understandingLack of 10 CFR Part 21 understandingLack of 10 CFR Part 21 understanding

Page 7: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

Construction Program Management Issues Construction Program Management Issues

Identified in NUREG 1055Identified in NUREG 1055

Cincinnati Gas & Electric was a firstCincinnati Gas & Electric was a first--time nuclear plant owner.time nuclear plant owner.

Construction project management firm (Kaiser Co.) had no Construction project management firm (Kaiser Co.) had no experience in nuclear construction.experience in nuclear construction.

77

NRC requirements were rapidly evolving and increasingly more NRC requirements were rapidly evolving and increasingly more stringent.stringent.

Responsible managers did not realize until very late in the Responsible managers did not realize until very late in the construction project that a much more rigorous and formal approach construction project that a much more rigorous and formal approach was needed.was needed.

Page 8: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

Lessons Learned for the NRCLessons Learned for the NRCA mindset existed that there was no immediate A mindset existed that there was no immediate threat to the health and safety of the public until threat to the health and safety of the public until a planta plant became operational. became operational.

P t d d t lt i t i ti fP t d d t lt i t i ti f

88

Programs tended to result in categorization of Programs tended to result in categorization of nonconformances to the lowest action levels. nonconformances to the lowest action levels. There was an inability to categorize observed There was an inability to categorize observed issues to the correct thresholds for stronger issues to the correct thresholds for stronger enforcement action.enforcement action.

Page 9: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

Lessons Learned for the NRCLessons Learned for the NRC

Inspection procedures …as guidance and Inspection procedures …as guidance and reliance placed on the engineering judgment of reliance placed on the engineering judgment of the inspector and Regional Office the inspector and Regional Office management for proper implementation. management for proper implementation. Th d f i tiTh d f i ti

99

The degree of inspection program The degree of inspection program implementation was varied across the Regions implementation was varied across the Regions dependent upon management's approach to dependent upon management's approach to regulations and the capability of personnel. regulations and the capability of personnel. Inspector training in quality assurance and Inspector training in quality assurance and performing inspections was insufficient.performing inspections was insufficient.

Page 10: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

Lessons Learned for the NRC Lessons Learned for the NRC

The legal base for direct NRC inspection of vendors The legal base for direct NRC inspection of vendors and any resultant enforcement action was not clearly and any resultant enforcement action was not clearly addressed in regulations. addressed in regulations.

1010

The vendor inspection program did not include The vendor inspection program did not include material manufacturers or material suppliers, sources material manufacturers or material suppliers, sources of many material related problems during construction.of many material related problems during construction.

Page 11: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons LearnedLearned

Establish a nearEstablish a near--constant presenceconstant presenceApply more attention to design activitiesApply more attention to design activitiesMinimize diversions of inspectors for the Minimize diversions of inspectors for the purpose of investigating allegationspurpose of investigating allegations

1111

Enforcement programs need to encourage Enforcement programs need to encourage conformance to commitmentsconformance to commitmentsDevelop capability to detect Quality Assurance Develop capability to detect Quality Assurance Program breakdownsProgram breakdownsInIn--process QC inspections and NRC’s ability to process QC inspections and NRC’s ability to inspect oninspect on--going construction activitiesgoing construction activities

Page 12: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons

LearnedLearned

Today’s construction inspection strategy Today’s construction inspection strategy includes placement of qualified inspectors on includes placement of qualified inspectors on site to conduct direct observations of site to conduct direct observations of construction activities (SECYconstruction activities (SECY--0606--0114)0114)

1212

construction activities (SECYconstruction activities (SECY 0606 0114)0114)

The formal inspection planning process is The formal inspection planning process is ensuring direct inspections are scheduled for ensuring direct inspections are scheduled for Resident, Regional, and Headquarters Resident, Regional, and Headquarters inspections staff.inspections staff.

Page 13: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons LearnedLearned

PresentPresent--day inspections of the MOX Fuel Fabrication day inspections of the MOX Fuel Fabrication Facility and the LES National Enrichment Facility have Facility and the LES National Enrichment Facility have included specific inspections of design development.included specific inspections of design development.

1313

Per SECYPer SECY--0606--0114, the use of certified designs for 0114, the use of certified designs for reactors requires NRC staff to inspect and review the reactors requires NRC staff to inspect and review the adequacy of design early, possibly beginning soon after adequacy of design early, possibly beginning soon after receipt of the licensing application.receipt of the licensing application.

Page 14: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons LearnedLearned

ITAAC strategies identify minimum resource ITAAC strategies identify minimum resource requirements for accomplishing scheduled inspections.requirements for accomplishing scheduled inspections.

U h d l d i ti t dd t iU h d l d i ti t dd t i

1414

Unscheduled inspections to address emergent issues Unscheduled inspections to address emergent issues such as allegations are scheduled separately or with such as allegations are scheduled separately or with supplemental personnel.supplemental personnel.

Page 15: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons

LearnedLearned

Licensees are not compelled to establish hold points for Licensees are not compelled to establish hold points for NRC. NRC.

NRC Construction Projects staff are developing anNRC Construction Projects staff are developing an

1515

NRC Construction Projects staff are developing an NRC Construction Projects staff are developing an inspection schedule management tool that will address inspection schedule management tool that will address this area. The EPM system will establish links with this area. The EPM system will establish links with licensee construction schedule systems to assure licensee construction schedule systems to assure inspectors’ presence onsite to observe critical activities.inspectors’ presence onsite to observe critical activities.

Page 16: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons LearnedLearned

Guidance for evaluating the significance of Guidance for evaluating the significance of findings and apparent violations in respect to findings and apparent violations in respect to minor / more than minor is currently being minor / more than minor is currently being

1616

evaluated for revision to ensure clear and evaluated for revision to ensure clear and consistent conclusions. consistent conclusions.

NRO has developed an assessment process NRO has developed an assessment process complete with a Construction Response Table complete with a Construction Response Table for assessing NRC response to findings.for assessing NRC response to findings.

Page 17: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

NRC Response to Identified Lessons NRC Response to Identified Lessons

LearnedLearned

The Center for Construction Inspection The Center for Construction Inspection now inspects different aspects of the licensee’s QA program over the entire project schedule. Inspections include verifications of program implementation during the performance of construction-related work.

1717

QA measures exercised in the development of the application for an early site permit are addressed.

Early verifications of the licensee’s QA manual and quality procedures are being implemented by appropriately trained and qualified staff.

Page 18: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

ReferencesReferencesNUREGNUREG--0969, 0969, Report of the NRC Evaluation Team on Report of the NRC Evaluation Team on the Quality of Construction at the Zimmer Nuclear Power the Quality of Construction at the Zimmer Nuclear Power StationStation, published April 1983, published April 1983NUREGNUREG--1055, 1055, Improving Quality and the Assurance of Improving Quality and the Assurance of Quality in the Design and Construction of Nuclear Power Quality in the Design and Construction of Nuclear Power Plants A Report to CongressPlants A Report to Congress published May 1984published May 1984

1818

Plants, A Report to CongressPlants, A Report to Congress, published May, 1984, published May, 1984Article by Robert T. Grieves, TIME magazine, dated Article by Robert T. Grieves, TIME magazine, dated 10/31/198310/31/1983Article, New York Times newspaper, dated 01/24/1984Article, New York Times newspaper, dated 01/24/1984IMC 2503, Construction Inspection Program: Inspections IMC 2503, Construction Inspection Program: Inspections of ITAAC Related Workof ITAAC Related Work

Page 19: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

References (cont’d)References (cont’d)IMC 2504, Construction Inspection Program: NonIMC 2504, Construction Inspection Program: Non--ITAAC ITAAC InspectionsInspections

IMC 2517, Watts Bar Unit 2 Construction Inspection IMC 2517, Watts Bar Unit 2 Construction Inspection ProgramProgram

IMC 0616, Fuel Cycle Safety And Safeguards Inspection IMC 0616, Fuel Cycle Safety And Safeguards Inspection ReportsReports

1919

IP 88107, Quality Assurance: Design And Documentation IP 88107, Quality Assurance: Design And Documentation Control (PreControl (Pre--licensing And Construction)licensing And Construction)

SECYSECY--0606--0114, “Description Of The Construction 0114, “Description Of The Construction Inspection Program For Plants Licensed Under 10 CFR Inspection Program For Plants Licensed Under 10 CFR PART 52,” Enclosure 1PART 52,” Enclosure 1

Page 20: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

ADAMS NUMBERS FOR LES NEF INSPECTION ADAMS NUMBERS FOR LES NEF INSPECTION REPORTSREPORTS DOCKET: 70DOCKET: 70--3103 (FY 08 3103 (FY 08 –– 09)09)

IR 2008IR 2008--001, ML081160345001, ML081160345IR 2008IR 2008--002, ML081930118002, ML081930118In Office Review, ML080670488In Office Review, ML080670488IR 2008IR 2008--003, ML083040618003, ML083040618

2020

IR 2008IR 2008--004, ML083540709004, ML083540709IR 2008IR 2008--005, ML090610203005, ML090610203IR 2008IR 2008--006, ML090790642006, ML090790642IR 2009IR 2009--001, ML090850669001, ML090850669IR 2009IR 2009--002, ML091770643002, ML091770643

Page 21: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

ADAMS NUMBERS FOR MOX INSPECTION REPORTSADAMS NUMBERS FOR MOX INSPECTION REPORTS

DOCKET: 70DOCKET: 70--30983098 (FY08(FY08--09)09)

IR 2008IR 2008--001, ML081210717001, ML081210717IR 2008IR 2008--002, ML082120091002, ML082120091IR 2008IR 2008--003, ML083050388003, ML083050388IR 2008IR 2008--004, ML090300246004, ML090300246IR 2008IR 2008 005 ML081340672005 ML081340672

2121

IR 2008IR 2008--005, ML081340672005, ML081340672IR 2009IR 2009--001, ML091200733001, ML091200733IR 2009IR 2009--002, ML092110728002, ML092110728IR 2009IR 2009--005, ML091000358005, ML091000358IR 2009IR 2009--006, ML091550287006, ML091550287IR 2009IR 2009--007&008, ML091310674007&008, ML091310674

Page 22: NUREG 1055 NUREG 1055 –– Then and Then and NowWhat Were The Deficiencies? Per NUREGPer NUREG--1055, quality of stru1055, quality of structures, systems, and components was indeterminate

ADAMS NUMBERS FOR VENDOR INSPECTION ADAMS NUMBERS FOR VENDOR INSPECTION REPORTSREPORTS

Consolidated Power Supply Consolidated Power Supply --ML081160345ML081160345

Energy and Process Energy and Process -- ML081410040ML081410040

BF Sh / J h O t C tiBF Sh / J h O t C ti

2222

BF Shaw / Joseph Oat Corporation BF Shaw / Joseph Oat Corporation --ML091310674ML091310674