NUMO's Safety Strategy for implementing Geological ... · facilities Underground ... R&D/ design/...
Transcript of NUMO's Safety Strategy for implementing Geological ... · facilities Underground ... R&D/ design/...
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.0
NUMO’s Safety Strategyfor implementing
Geological Disposal Project
Nuclear Safety Research Forum 2010
Tokyo, Japan23 February, 2010
Hiroyuki TsuchiNuclear Waste Management
Organization of Japan (NUMO)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.1
Uranium mine
Fuel fabrication
Nuclear power generation
HLW (approx. 5%)Fuel
Spent fuel
MOX fabrication
Recovery of uranium/ plutonium (approx. 95%)
Reprocessing
LLW for geological disposal
Nuclear fuel cycle
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.2
Generation point Category Example of disposal
Nuclear power plant
LLW
Nuclear pow
er plant w
aste
VLLW
Near-surfaceLLW
HLLW Sub-surface
Uranium enrichment/ fuel fabrication plants
Uranium waste
Near-surface
Sub-surface
Geological (undecided)
Reprocessing/ MOX fabrication plants
TRU waste
Near-surface
Sub-surface
Geological
Reprocessing plant HLW Geological
Disposal method
Depth[m]0 Low
Trench disposal
25
300
100
50
Radioactivity
High
TRU
waste
Nuclear pow
er plant w
aste
Uranium
waste
HLW
Sub-surface disposal
Geological disposal in more than 300m deep
underground
Pit disposal
Classification of radioactive wastes & disposal methods
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.3
Classification of specified radioactive wastes
HLW
Specific 1st
radioactive Waste
TRU
air
Spent silver adsorbent
air
Hull,and Ends
Slice
Dry and pellet
Nitric acid drain
High concentration radioactive wasteSpecific 2nd
radioactive Waste
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.4
Layout example of disposal facilities
CoastalSurfacefacilities
UndergroundFacilities(HLW)
Disposal panel
Ramp
Connecting Tunnel
Connecting Tunnel
Inland
UndergroundFacilities(TRU)
Disposal panel
Connecting Tunnel
Ramp
Surfacefacilities
UndergroundFacilities(TRU)
Shaft Shaft
UndergroundFacilities(HLW)
Ramp
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.5
Three Stages of the Selection Process
Selection of PIAsby Literature Surveys
Selection of DIAs by Surface-based Preliminary Investigation• Geophysical survey• Borehole drilling, etc
Final Selection of Repository Site by Detailed Investigation including measurements and tests in the underground facility
Preliminary Investigation Areas (PIAs)
Detailed Investigation Areas (DIAs)
Repository Site (RS)
Volunteer Areas
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.6
Sele
ctio
n of
PIA
s
Design concept Basic Design & Safety Assessment
Stepwise Refinement of the Safety Case
Report on the Final Selection of the Rep.Site
Detailed Design & Safety Assessment
Sele
ctio
n of
RS
Sele
ctio
n of
DIA
sSiting Factors for DIAs
NSC Basic Guidelines for Safety Review
NSC Guidelines for Safety Review
Siting Factors for RS
Siting Factors for PIAs
Literature Survey
Preliminary Investigation
Detailed Investigation
Lice
nsin
g
Nomination
OpenSolicitation
Safety Case 1 Safety Case 2 Safety Case 3
Supporting Documents Supporting
DocumentsSupporting Documents
NSC: Nuclear safety Commission
Report on theSelection of DIAs
Report on theSelection of PIAs
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.7
NUMO’s R&D Roles
Fundamental R&D Coordination Executives
The Government’s fundamental R&D
・ JAEA and other R&D organizations
NUMO’s R&D
Practicality/ sophistication
Systematization
Demonstration
Rationalization/ efficiency
Application of the fundamental R&D
results
Impro
vem
ent o
f safety an
d reliability
NUMO: R&D for safe implementation of the repository with improved technology from economic and practical perspectives
The Government & relevant organizations including JAEA: R&D for establishing the safety-regulation framework, other fundamental issues related to safety assessment, geoscientific studies, and improving repository technology from the viewpoint of increasing confidence
Role allocation of R&D on the geological disposal in line with the Framework for Nuclear Energy Policy
Suggest needs
Utilize results
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.8
Close cooperation with R&D organizations
NUMONecessary technology based on the progress of repository programme
R&D Planning
R&D Implementation
Evaluation of achievements
JAEA and other R&D organizations
Fundamental R&D Coordination Executives
The Government’s fundamental R&D
plan etc outcomes
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.9
Reflection of NUMO needs in Government’s fundamental R&D
Objective:
For implementing the geological disposal in line with the recommendation by the Advisory Committee on the Evaluation of Framework for Nuclear Energy Policy of AEC, NUMO develops and reflects its R&D needs to the Government’s fundamental R&D plan, from the perspective of the implementer.
Basic policy:
Develop NUMO’s R&D needs systematically, in particular, focusing on the detailed investigation phase which involves important decision making;
Cover a wide distribution of geo-environmental conditions, considering the situation where the sites for investigation cannot be identified due to the volunteer siting approach;
Determine overpack materials, emplacement methods among other important judgments to be made during the detailed investigation period;
The site-specific needs will be additionally evaluated as appropriate after volunteer applications received.
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.10
Important NUMO needs (tentative) – 1/2
From viewpoint of “engineering feasibility”
Knowledge accumulation on long-term behaviors/ interactions of the engineered barriers(e.g. re-establishment of overpack corrosion rate; assessment technology of corrosion resistance of welded parts, etc.)
Alternative technologies of the engineered barrier system (e.g. alternative solidification method of TRU waste, etc.)
R&D for improving engineering feasibility of fabrication/ transportation/ emplacement of the engineered barriers(e.g. sophistication of element technologies on transportation/ emplacement of engineered barriers using PEM/ block/ pellet)
Confirmation/ demonstration of technologies for investigation/ assessment of geological environment(e.g. applicability of technologies for deep geological investigation in coastal/ marine areas)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.11
Important NUMO needs (tentative) – 2/2
Needs from viewpoint of “safety assessment”
R&D on the performance assessment scenarios based on probability
R&D on the performance assessment considering the long-term evolution of geological environment (e.g. standardization/ validation of conditions for performance assessment)
Needs from viewpoint of “long-term safety assessment of geological environment”
Review on methods/concepts of extremely long-term assessment(e.g. more than 100,000 years)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.12
Overview of R&D system
・Information exchange・Joint research
・Suggest needs・Confirm outcomes
・Technical support
・Teaching
Utilities
Implementers (JNFL/NAGRA/SKB/
POSIVA, etc.)
Consultants, Engineering and construction companies
Agency for Natural Resources and Energy (ANRE)
R&D organizations (JAEA/CRIEPI/AIST)
Geological investigation /assessment
Design/ production of the engineered barrier system
Design/ construction of facilities/ installments
Repository operation/ closure
Performance/ safety assessments
Implementation of these activities
R&D required for their implementation
Universities
Nuclear Safety Commission (NSC)
Nuclear and Industrial Safety Agency (NISA)
Supervision Regulation
Guideline
National budget
Atomic Energy Commission (AEC)
Basic policy
・Suggest needs・Provide outcomes
Fundamental R&D
Coordination Executives
Implementation of repository project
R&D from waste-producer perspective
Fundamental research
Fundamental R&D
R&D/ design/ construction
・R&D・Construction orders/ implementation
NUMO
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.13
Evaluations and advices by third-partyPromote the project getting evaluations and advices about the issues such as promotion of public understanding from domestic and international experts.
NUMO-hosted international meetings ITM(International Tectonics Meeting)
Example of achievement; Probabilistic assessment of magmatism
Evaluations and advices for NUMO’s activitiesby domestic and international experts
ITAC ( International Technical Advisory Committee)DTAC(Domestic Technical Advisory Committee)Example of achievement; Information Package(「Repository Concepts」,「Siting Factors for the Selection of Preliminary Investigation Area」)
Technical Reports(「Technology and Safety of High Level Radioactive Waste Geological Disposal Background and
Technical Justification of Siting Factor for the Selection of Preliminary Investigation Area」)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.14
Schedule of implementation and R&D of NUMO
Literature Survey
Preliminary Investigation
Detailed Investigation
Construction, Operation, Closure
Selection ofPIAs▼
Selection ofDIAs▼
Selection of a repository site▼
▼LicensingOpen solicitation▼
now▼
Detailed investigations in research galleries
Research on the deep geological environment at URLs in Horonobe and Mizunami
Improving the reliability of disposal technologies at Tokai R&D center
Investigation from the surface
Investigation during excavation
Site-specificGeneric
Impl
emen
tatio
nFu
ndam
enta
l R
&D
(JA
EA
)NUMO is driving to implement the deep geological disposal by doing NUMO’s R&D.
NU
MO
’s R
&D
2000 2002
Establishment of NUMO▼
For open solicitation
- Siting factors for PIAs’ selection- Repository concepts for volunteer siting environment, etc.
- Software supporting for LS- Software developing of repository concepts based on literature information, etc.
For LS and selection of PIAs >>>
For PI and selection of DIAs >>>- Siting factors for DIAs’ selection- Systematization of geological environmental investigation and evaluation- Improvement of repository design and performance assessment, etc.
For DI and selection of a repository site Demonstration
For promotion of long-term project
2nd report (H12)
- Important issues of construction, operation and closure- Requirement management system, etc.
2020 2040
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.15
Current situation of NUMO’s R&DOn-going R&D activities
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.16
Case1: Improvement of assessment technology for seismic/fault activities
Characteristics of deep-underground seismic motion
Identification of relevant active fold zones
Surface facility
repository
Hypocenter property
Deep rock formation
Shallow rock formation
Seismic-resistant design for NPP
+
Require designing and assessment of seismic motion
specific to ‘deep underground’
Propagation property
EL-1000m
Accelaration (gal)
Repository:
□ 5m × 5m
20 rows × 2 tiers
repository
EL-500m
Surface
Master faultFault caused by folding
Branching of fault
Objective: Establish methods for designing seismic-resistant repository; assessing active folds
Model experiment using CT- scanner
Seismic response identified by 2D dynamic analysis
L(km)10001001010.10.1
1
10
100
1000
Wav
e gr
owth
ratio
per
1km
(m/1
06 yrs
)2m
L
H
Wave growth ratio
HL 106yrs=
Shinjo, Niigata
Sedimentary layer
Wave length
105yrs
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.17
Corrosion test in low alkaline environment, using carbon fiber material –alternative for steel material (photo images: production of test material)
Waste package
Combination of PEM and the capsule transportation system
BufferExternal container
overpack
Concrete plugtunnel support
Bentonite plug
Bentonite buffer
Grout
fracture
Collaborative research on tunnel support, plug, etc. (e.g. NUMO, CRIEPI)
Collaborative research on applicability to grout (e.g. NUMO, SKB, POSIVA, Nagra)
Fabrication in the surface
facility
Case2: Improvement of technologies for construction/operation systems
Objective: Review comparison of waste emplacement methods; applicability of low alkaline c e m e n t
Assessment of vertical/ horizontal emplacement using the Prefabricated EBS Module (PEM)
Vertical emplacement
Horizontal emplacement
Block type Pellets type
Repository construction technology using low alkaline cement
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.18
1.0E-03
1.0E-02
1.0E-01
1.0E+00
1.0E+01
1.0E+02
1.0E+03
1.0E+04
1.0E+05
1.0E+06
1.0E+01 1.0E+02 1.0E+03 1.0E+04 1.0E+05 1.0E+06 1.0E+07 1.0E+08
時間 [y]
Cs-
135
の移
行率
[Bq/y]
EBS
NBS
1.0E-03
1.0E-02
1.0E-01
1.0E+00
1.0E+01
1.0E+02
1.0E+03
1.0E+04
1.0E+05
1.0E+06
1.0E+01 1.0E+02 1.0E+03 1.0E+04 1.0E+05 1.0E+06 1.0E+07 1.0E+08
時間 [y]
Cs-
135の
移行
率 [B
q/y]
EBS
NBS
Vertical emplacement
Horizontal emplacement
断層 断層
3D model
1.E-08
1.E-07
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
0 10 20 30 40 50 60 70 80 90 100
坑道方向位置[m]
規格
化し
た移
行率
の最
大値
[1/
y]EBS
NBS
は断層を示す
1.E-08
1.E-07
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
0 10 20 30 40 50 60 70 80 90 100
坑道方向位置[m]
規格
化し
た移
行率
の最
大値
[1/y
]
EBS
NBS
は断層を示す
はプラグを示す
Without plug With plug at crossing of fault and tunnel
Cross-sectional flow velocity distribution
Case 3: Improvement of repository design by 3D analysis of radionuclide migration
Objective: Develop the 3D analysis code of radionuclide migration, which allows simulation ofits detailed behaviors, to study their effects on different repository designs
Comparison of release between different waste emplacement methods
Effect of plug for a fault – groundwater flow analysis
faultfault
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.19
Case 4: Development of Requirements Management System
Developments of NUMO-RMSDevelopments of NUMO-RMS•Original system suitable for RM in NUMO and the stepwise program.
Info. exchange with oversea organizations
Info. exchange with oversea organizations
“RMS2010” held in Tokyo at 26/Jan./2010
Works and RM process for the stepwise program.
Preparation of e-contentsPreparation of e-contents•Contents for “repository design at each site-selection stage•Trial use of the outcomes of the fundamental R&D (e.g. JAEA-KMS)
Conceptualization of requirements management
and engineering works
Conceptualization of requirements management
and engineering works
NUMO, SKB, POSIVA, ONDRAF/NIRAS, Nagra,domestic organizations
RWMC(2005)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.20
Background of 2010 Technical Report
NUMO
Implementation of the repository project
YR 2000• Published the JNC 2nd Report
• Establishment of the Final Disposal Act• Establishment of NUMO
YR 2000• Published the JNC 2nd Report
• Establishment of the Final Disposal Act• Establishment of NUMO
NUMO became the implementer of the LLW geological disposal
NUMO became the implementer of the LLW geological disposal
Preparation for the Literature SurveyPreparation for the Literature Survey
Amendment of the Final Disposal Act
Development of the Nuclear Reactor Act
Launch solicitation of nationwide municipalities using volunteer approach
Launch solicitation of nationwide municipalities using volunteer approach
Progress of overseas/domestic R&D
Development of overseas programmes
For siting & PR support
2010 Technical Report(tentative)
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.21
Objectives of 2010 Technical Report
For building public confidence in NUMO’s repository project,
Clarify NUMO’s safety concepts (precedent publication in 2009):
Specify the safety measures
Express NUMO’s policies on its technical activities for ensuring safety
Demonstrate Japanese technology advancement, which supports NUMO’s safety concept
Incorporate NUMO’s R&D and the Government’s fundamental R&D activities since 2000
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.22
2010 Technical Report - Main2010 Technical Report - MainSafety Report 2009Safety Report 2009
Technical Reports
2010 Technical Report 2010 Technical Report
PR version of the NUMO 2010 Report
PR version of the NUMO 2010 Report
Report
Summary
Brochure
SummarySummary
Pick-up useful information to support PR activities
ProjecProjec
TechnologiesTechnologies
Main report
Series of the NUMO 2010 Report group
NUMO’s policyNUMO’s policy
Leaflet
Sim
ple
Detail
NUMO manifesto
Transfer technical policies on safety
IntegrationIntegration
FY2010FY2009
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.23
Structure of the Safety Report 2009
Global Global aimaim
Achievement of safe geological disposal
AimsAims
MeasuresMeasures
Long-term safety
(1I Site selection and confirmation
(2) Engineering measures
(3) Evaluation of long-term safety
(1) Avoid non nuclear accident
(2) Avoid radiation accident
(3) Conservation of natural environment
Section 4.1
Chapter 4: Detail Chapter 4: Detail descriptionsdescriptions
Safety during implementation
Chapter 2: Breakdown of the structure of safetyChapter 2: Breakdown of the structure of safety
Chapter 3: Policies and measures for implementation of safety geChapter 3: Policies and measures for implementation of safety geological disposal projectological disposal project
PoliciesPolicies
Implementation by step-wise decision making based on repetitious confirmation of safety
Implementation by credible (reliable) technologies
Technical works toward public confidence building
Implementation by step-wise decision making based on the advance planning
Repetitious confirmation of safety by coordination between 3 measures
Ensuring safety during implementation
Well planned R&DQA of technical informationOrganizational
Implementation based on understanding of safety by local residence
Information disclosure (e.g. demonstration of technologies)Consideration for future generation
Breakdown of policyBreakdown of policy
Section 4.2
Section 4.3
Policy 1
Policy 2
Policy 3
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.24
Drat schedule for production of the 2009 & 2010 Report
FY 2009 FY 2010 FY 2011
▽
Mid Workshop &Symposium▽
2010R main Workshop▽
▽▽
Completion of the 2009R
AESJ review ▽Review report
Workshop
Safety Report 2009
(2009R)
2010 Report
(2010R)
Modifications
Review by AESJ etc. ▽Review report
2010R International
workshop
Modifications
PR version of 2010R
▽
▽▽
Completion of the 2010R
Safety Report2009 Workshop
Draft production
Draft production
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.25
SummaryPreparation for the literature survey has completed.
- Reliability improvement by showing recent findings -
Develop & publish the 2010 Technical Report for obtaining the public confidence toward NUMO’s repository project and its safety; promoting its project implementation
In regards to stepwise research & technical development, their comprehensive visions and progress will be laid out to the general public in an easily understood manner;
For ensuring the transfer of NUMO’s technology, the required human resources will be secured and fostered with the mid and long term vision.
Nuclear Safety Research Forum Tokyo ,Japan 23 February 2010 P.26
Thank youfor your attention
For further information:www.numo.or.jp/en/index.html