NUCLEAR POWER IN INDIA
K. Koshy Head NRRF
Nuclear Power Corporation of India Limited (NPCIL)
INDIA
![Page 2: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/2.jpg)
NUCLEAR POWER CORPORATION OF INDIA LTD.
(NPCIL)
A PUBLIC SECTOR ENTERPRISE
UNDER THE ADMINISTRATIVE CONTROL
OF
DEPARTMENT OF ATOMIC ENERGY
![Page 3: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/3.jpg)
Organisation
![Page 4: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/4.jpg)
NPCIL - MANY COMPANIES IN ONE
•Siting
•Design
•Construction
•Commissioning
•Operation & Maintenance
•R&M & Upgrades
•Life Extension
•Waste Management
![Page 5: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/5.jpg)
INDIAN ENERGY SCENARIO
![Page 6: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/6.jpg)
Fuel Shares in Electricity Generation
INSTALLED CAPACITY 271722.17 MW
(As on 31.03.2015)
Source: Central Electricity Authority, GOI
![Page 7: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/7.jpg)
Demand Projections (based on 8% GDP Growth)
By 2050, the required Installed Capacity is estimated to be 1300 GW
Source: Integrated Energy Policy, Planning Commission, GoI
![Page 8: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/8.jpg)
Amount Electricity Potential¤
GWe-yr
Coal 38-BT 7614
Hydrocarbon 12 –BT# 5,833
Uranium-Metal 61,000 -T
- In PHWR 328
- In Fast Breeders 42,231
Thorium-Metal
(In Breeders) 2,25,000 –T 155,502
Hydro 150 -GWe 69 GWe-yr / yr
Non-conv. Ren. 100 -GWe 33 GWe-yr / yr
India’s Energy Resource Base
¤ Assuming entire resource is used for generating electricity.
# Currently known resources (including coal bed methane) are 3 BT.
Source: Strategy for growth of Electrical Energy in India – DAE, GoI
![Page 9: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/9.jpg)
Meeting the Demand
• Optimal Deployment of all sources
• Emphasis on Nuclear Power for long term
energy security & sustainability
• Setting up Nuclear Power Reactors based on Indigenous Nuclear Power Programme
International cooperation
![Page 10: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/10.jpg)
STAGE 1 STAGE 2 STAGE 3
U - 233
ELECTRICITY
Depleted U
Pu
300 GWe
Pu FUELLED FAST BREEDERS
Th
Huge
ELECTRICITY U - 233 FUELLED
BREEDERS
Natural Uranium
ELECTRICITY
PHWR
10 GWe
Th
Pu
U - 233
Indian Nuclear Power Programme Indigenous Three-stage Programme
Additionalities (LWRs with International
cooperation)
155000 Gwe-yr
![Page 11: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/11.jpg)
Narora, U.P.2X220 MWRawatbhata Raj. .
100+200+4X220 MW
2X700 MW
Kudankulam, T.N .
1X1000 MW1X1000 MW
Kaiga, Karnataka4X 220 MW
Kalpakkam, T.N.2X220 MW 1X500 MW*
Kakrapar, Gujarat2X220 MW2X700 MW
Tarapur, Maharashtra2X160+2X540 MW
IN OPERATION
(21 reactors, 5780 MW
UNDER CONSTRUCTION
(6 reactors, 4300 MW)
*Implemented by BHAVINI
Nuclear power plants in Operation & under Construction
![Page 12: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/12.jpg)
RAJASTHAN 1 to 6
(100+200+4X220 MW) MADRAS 1&2
(2X220 MW)
NARORA 1&2
(2X220 MW)
KAKRAPAR 1&2
(2X220 MW)
KAIGA 1 to 4
(4X220 MW)
Operating Nuclear Power Plants in India TARAPUR 1&2
(2X160MW)
TARAPUR 3&4
(2X540 MW) 5780 MW
12
KUDANKULAM 1
(1000 MW)
3380 MW under IAEA Safeguards
![Page 13: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/13.jpg)
Construction of Nuclear Power Plants in India
remained alive over the last 45 years.
Simultaneous construction of 6 Reactors.
Vendors specializing in manufacture and supply
of exacting standards equipment and supplies
are developed .
Experience in Construction of NPPs
![Page 14: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/14.jpg)
Reactors under Commissioning
KKNPP - 2 (1000 MW) Expected completion - 2015-16
![Page 15: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/15.jpg)
Reactors under Construction
KAPP 3&4 (2X700MW)
Physical Progress – 64.6% (KAPP 3 – 71.0%, KAPP 4 – 57.26%)
Expected Completion 2017 / 18
RAPP 7&8 (2X700MW)
Physical Progress – 48.2% (RAPP 7 – 53.42, RAPP 8 – 42.18%)
Expected Completion 2018 / 2019
![Page 16: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/16.jpg)
The 500MWe Prototype Fast Breeder Reactor is in the advanced
stage of construction and is getting poised for commissioning.
physical progress of 97.64 %
Bharatiya Nabhikiya Vidyut Nigam Limited
![Page 17: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/17.jpg)
Sites for Future Projects
Projects to be implemented on twin unit basis, in phases at a site
![Page 18: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/18.jpg)
Planned New Starts by 2017
Project Location Capacity (MW)
Indigenous Reactors
GHAVP 1&2 Gorakhpur, Haryana 2 x 700
CMAPP 1&2 Chutka, Madhya Pradesh 2 x 700
Mahi Banswara, 1&2 Mahi Banswara, Rajasthan 2 x 700
Kaiga 5&6 Kaiga, Karnataka 2 x 700
Reactors with Foreign Cooperation
KKNPP 3&4 (Russian Federation) Kudankulam, Tamilnadu 2 x 1000
JNPP 1&2 (France) Jaitapur, Maharashtra 2 x 1650
Kovvada 1&2 (USA) Kovvada, Andhra Pradesh 2 x 1500
Chhaya Mithi Virdi 1&2 (USA) Chhaya Mithi Virdi, Gujarat 2 x 1100
GHAVP 1&2 and KKNPP 3&4 accorded financial sanction by the government and are being
readied for launch in this year. Pre-project activities are in progress at remaining sites.
![Page 19: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/19.jpg)
Future Plans
Start of Work Pre-Project Activities on
• 8 more indigenous PHWRs of 700 MW each
• 8 LWRs of 1000 MW or larger size based on international cooperation
• 2 Fast Breeder Reactors(500MW)
• To reach 63000 MW by 2032 based on indigenous
reactors & LWRs with international cooperation
![Page 20: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/20.jpg)
Considerations for Setting up LWRs
• Viable Tariff
• Progressive Indigenization to optimize Cost
• Cooperation between Indian Industries & Foreign
Technology Partners
• Life time fuel supply guarantees
![Page 21: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/21.jpg)
Our Experience in setting up LWRs
2 VVERs at Kudankulam (KK 1&2 – 2 X 1000 MW)
1 Unit commissioned and 2nd at advanced stage of commissioning
Implementation Model Role of Technology Partner Role of NPCIL
•Design Construction
•Supply of Equipment Erection
•Evaluation of Personnel Commissioning
Training
Training of Personnel :Carried out in Three Phases
Phase-1 in India : Induction in Nuclear Technology
Phase-2 in Russia : Simulator and Technology Specifics
Phase-3 in India : Commissioning and Systems operation
Evaluation by Technology Partners
![Page 22: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/22.jpg)
Tour To KKNPP
KK 1 – 100%
-Commercial operation started in Dec 2014
-Cumulative Generation so far - 6500 MUs
KK 2 – 98.01%
-Hot Run Completed
-Criticality and synchronization to follow
A few glimpses ……..
![Page 23: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/23.jpg)
THEN
NOW
KKNPP
![Page 24: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/24.jpg)
![Page 25: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/25.jpg)
KK 1&2 Panoramic View
![Page 26: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/26.jpg)
Unit-1: Criticality of Reactor on 13.7.2013
![Page 27: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/27.jpg)
7 JUN 2014: KK-1 reached 1000MWe Power
![Page 28: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/28.jpg)
Night view from the Sea
![Page 29: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/29.jpg)
Intake & Break water Dyke Structure
![Page 30: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/30.jpg)
View from sea
![Page 31: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/31.jpg)
View from North
![Page 32: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/32.jpg)
View of Turbine Generator
![Page 33: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/33.jpg)
Control Room
![Page 34: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/34.jpg)
Desalination Plant
![Page 35: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/35.jpg)
View of KKNPP 3 to 4 area from KKNPP 1&2
KKNPP 3 to 4 AREA
![Page 36: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/36.jpg)
Visit of Dignitaries
![Page 37: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/37.jpg)
Visit of Dignitaries
![Page 38: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/38.jpg)
Visit of Dignitaries
![Page 39: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/39.jpg)
Preparedness for large Capacity Addition
• Sites made available – Pre project activities in
progress
• Augmentation of existing capacity & capability
of Indian industry initiated • Joint Ventures / Consortia between Indian and foreign
companies
• Companies setting up manufacturing facilities being facilitated
• Joint Venture Company between NPCIL & Indian companies
• Structured development of human resources The experience with the Training model adopted for KKNPP has
been good. Same model is planned to be followed for each new
technology.
![Page 40: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/40.jpg)
Supply Chain
• Nuclear Island (NI)
• Balance of Nuclear Island (BNI)
• Conventional Island (CI)
• Balance of Conventional Island (BCI)
• Balance of Plant (BOP)
![Page 41: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/41.jpg)
India - Future Nuclear Industry Hub
• Country having an alive small and Medium reactor
technology with excellent safety and performance
record
• Cost advantage with technology expertise of
Indian industry
• Availability of Large pool of trained Human
Resource
![Page 42: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/42.jpg)
Conclusion
• India has a robust Nuclear Power Programme
• Stage is set for nuclear power capacity
expansion to meet its huge electricity
demand through indigenous technologies
and with international cooperation
• India poised to be the future global nuclear
industry hub
![Page 43: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/43.jpg)
NPCIL Performance
![Page 44: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/44.jpg)
Performance
• Excellent Safety Record
– No accident or incident of release of radioactivity beyond stipulated limits in public domain
– Radiation dose around nuclear power plants a negligible fraction of natural background
• Excellent Safety Culture
• High Plant Load Factors and Availability Factors, long continuous run
• Viable Tariffs
• Environment Protection
• Neighbourhood Inclusion
![Page 45: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/45.jpg)
Safety
• Excellent Safety Record
– No accident or incident of release of radioactivity beyond stipulated limits in public domain in over 45 years of operation
– Radiation dose around nuclear power plants a negligible fraction of natural background
• Excellent Safety Culture
Average Radiation Dose
![Page 46: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/46.jpg)
Performance - Operation
• Growing Generation
• High Availability Factors
• Increasing Plant Load Factors
• Long continuous runs – RAPS-5 second longest in the world of
765 days
– Continuous runs longer a year (365 days) registered 18 times
14927
18831
26473
32455 32863
3533337835
0
10000
20000
30000
40000
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
MU
NPCIL Generation
82
9289
91 90 88 88
0
20
40
60
80
100
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
NPCIL Availability Factor (%)
50
61
71
79 8083 82
0
20
40
60
80
100
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
MU
NPCIL Plant Load Factor (%)
![Page 47: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/47.jpg)
Neighbourhood Inclusion
Healthcare Education
Infrastructure Skill Development
Sanitation – Toilets Swatch Bharat Abhiyaan
![Page 48: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/48.jpg)
• Structured action plan with monitoring mechanism
• Focus on Capacity building, Media, state officials, peoples representatives, students and faculty .
• Partnership with 21 Professional Agencies and Government organizations
• Multipronged Approach
o Permanent Exhibition Centres
o Single sheet publications
o Short films
o Radio jingles
o TV Commercials
o Digital Media – Cinema & Cable TV
o Comic Books
o Animation Films
o Web based Awareness
o Press Meets
o Visits to Plants
o Briefing Opinion makers
Public Awareness
48
![Page 49: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/49.jpg)
Environment Stewardship - Safety first Environment foremost
49 P khot
![Page 50: NUCLEAR POWER IN INDIA2015.atomexpo.ru/mediafiles/u/files/materials/1/Koshi...765 days –Continuous runs longer a year (365 days) registered 18 times 14927 18831 26473 32455 32863](https://reader034.fdocuments.us/reader034/viewer/2022042116/5e942587af9c075387580653/html5/thumbnails/50.jpg)
Thank You