Nuclear Power Development in Thailand Mr.Pricha - Nuclear... · 1961: Office of Atomic Energy for...
Transcript of Nuclear Power Development in Thailand Mr.Pricha - Nuclear... · 1961: Office of Atomic Energy for...
Nuclear Power Program Development Office
Ministry of Energy
Nuclear Power Development in Thailand
Assist. Prof. Pricha Karasuddhi
Former Technical Advisor
Advisor, Nuclear Society of Thailand
1954 : Thai Atomic Energy Commission was initiated.
1961 : Atomic Energy for Peace Act was enacted.
1961 : Office of Atomic Energy for Peace was established.
1966 : Nuclear Electricity Sub-committee was set up.
1976 : Cabinet approved NPP 600 MW.
(the project was opposed by public)
1984-88 : Economic aspect of NPP was studied with support from
IAEA.
1992-96 : NPP policy was put in the National Development Plan 7.
1997 : Study for NPP in Thailand was re-initiated,
NPP are not suitable during economic crisis.
2002 : Restructuring into Office of Atoms for Peace .
Nuclear Energy Development in Thailand
Contents
• NPP Infrastructure Development
• INIR Mission and Readiness
Report
• Current Challenges
• On-going Activities
3 Nuclear Power Plant Development in
Thailand
Nuclear Infrastructure
Development
Nuclear Power and National Energy Plan • PDP 2007 (2007-2021)
4x1,000-MWe NPP in 2020(2) and 2021(2)
• PDP 2007 Revision 2 (2007-2021)
2x1,000-MWe NPP in 2020 and 2021
• PDP 2010 (2010-2030)
5x1,000-MWe NPP in 2020-2021, 2024-2025 and 2028
• Revised PDP 2010(March 2011) After Fukushima Accident
• 4x1000-MWe NPP in 2023-2024 and 2027-2028
• Revised PDP 2010(December 2011)
2x1000-MWe NPP in 2026 and 2027
5 Nuclear Power Plant Development in
Thailand
PDP 2015 ( 2015-2036 )
2x 1000 MWe NPP in 2035 and 2036
NPP Infrastructure
Development
2007- 2011
Pre-Project Activities Phase (2008-2010)
Major activities include:
• Commence the work on infrastructure establishment to accommodate a nuclear program
• Survey potential sites for construction and perform initial environmental examination
• Complete nuclear power plant pre-feasibility study including human resources development plan
• Promote public communication and participation 7
Nuclear Power Plant Development in
Thailand
Pre-Project Activities Phase (2008-2010)
Major activities include:
• Commence the work on infrastructure establishment to accommodate a nuclear program
• Survey potential sites for construction and perform initial environmental examination
• Complete nuclear power plant pre-feasibility study including human resources development plan
• Promote public communication and participation 8
Nuclear Power Plant Development in
Thailand
Nuclear Power Plant Feasibility Study
1. Energy Economics and Financing
2. Technical and Safety Aspects of Nuclear
Power
3. Fuel Cycle and Waste Management
4. Reactor Technology, Reactor Supplier
and Fuel Supplier Selection
5. Site and Environmental Study
6. Human Resources Development and
Management Aspects
9
Human Resource Development
• Seminars, workshops, and trainings from
IAEA, nuclear vendors and EGAT’s
partners
• Fundamentals course
• Advanced course – Diploma program
• OJT – Belgium(GDF-SUEZ),
China(CGNPC), Japan (JAPC)
• Oversea Study – Master’s Degree
program (Korea)
Public Knowledge Program
Publi
c
International Co-operation
• IAEA
• Korea via ASEAN+3 nuclear co-
operation program
• JAPC – Japanese Utility
• CGNPC – Chinese Utility
• JAEA – Research Institute
• Hitachi – Nuclear Vendor
INIR Mission and Readiness
Report
Dec 13-18, 2010
19 Infrastructure Issues for INIR Mission
1. National position
2. Nuclear safety
3. Management
4. Funding and financing
5. Legislative framework
6. Safeguards
7. Regulatory framework
8. Radiation protection
9. Electrical grid
10. Human resources
development
14 Nuclear Power Plant Development in
Thailand
11. Stakeholder involvement
12. Site and supporting
facilities
13. Environmental protection
14. Emergency planning
15. Security and physical
protection
16. Nuclear fuel cycle
17. Radioactive waste
18. Industrial involvement
19. Procurement
Main Conclusion
“The INIR Mission Team reviewed all of the
19 issues based on the IAEA reference
documents. The Team concluded that based
on the progress in addressing 19 issues,
which will be included in Readiness Report,
Thailand can make a knowledgeable
decision on the introduction of nuclear
power.”
15 Nuclear Power Plant Development in
Thailand
Major Gaps (1)
1. No official statement demonstrating the
Government’s commitment to the safe, secure
and peaceful (non-proliferation) implementation
of nuclear power for the long term
2. No official plan for the completion of the
national nuclear legislation
3. Necessary elements for joining the relevant
international legal instruments are not included
in national legislation, and the government has
not yet formalized the plan to address this issue
16 Nuclear Power Plant Development in
Thailand
Major Gaps (2)
4. No evidence of commitment to ensure
appointment of leaders with appropriate
training and experience for leadership
and the management of safety
5. No evidence showing understanding of
the ultimate responsibility of the operator
for safety.
6. Office of Atoms for Peace Human
Resources Development Plan is not
sufficiently detailed for Milestone 1 17
Nuclear Power Plant Development in
Thailand
Examples of Good Practices
18 Nuclear Power Plant Development in
Thailand
1. Utility’s studies for inclusion of an NPP into the
existing and future national electrical grid, which
covers all the necessary aspects and are well
documented
2. The Utility’s HRD Plan, which has considerable
scope and depth, addressing all elements required
by Milestone 1 and has already included nuclear
familiarization training for many staff
3. “Study on Strategic Environmental and Siting
Assessment for Nuclear Power Plant Project” by
Chulalongkorn University, which is a
comprehensive report addressing the
environmental issues and siting
Current Challenges
• National position
– Political instability
– Government commitment
• Public acceptance
– Promoting understanding and participation
– Site survey and data collection
• Infrastructure Preparation
– Laws and regulations for nuclear power
– Independent and capable nuclear regulatory
body 19
Nuclear Power Plant Development in
Thailand
Pre-Project Activities Phase
• Public communication, education and
participation
• Lessons learned from Fukushima Accidents
– NPP Technical and Safety Reviews
– NPP Site Selection Reviews
– Emergency Preparedness and Response
• Infrastructure Preparation
– Laws and regulations for nuclear power
– Setting up nuclear regulatory body
• Human resource development
20 Nuclear Power Plant Development in
Thailand
Pre-Project Activities Phase (2008-2010)
Major activities include:
• Commence the work on infrastructure establishment to accommodate a nuclear program
• Survey potential sites for construction and perform initial environmental examination
• Complete nuclear power plant pre-feasibility study including human resources development plan
• Promote public communication and participation 21
Nuclear Power Plant Development in
Thailand
INIR Mission (Integrated Nuclear Infrastructure Review)
• Thailand had carried out the self-
evaluation and submitted a report to
IAEA in October 2010
• IAEA experts had come to Thailand
during Dec 13-18, 2010 to conduct an
INIR mission
22 Nuclear Power Plant Development in
Thailand
Readiness Report (1)
• NPIECC and sub-committees had prepared
Readiness Report to submit to National Energy
Policy Council (NEPC) for consideration to
proceed to Phase 2 (Project Implementation)
23
Contents 1 – Thailand NPP Policy and Development
2 – Evaluation of Thailand Infrastructure for
Supporting
NPP Project
– Self-Evaluation of Infrastructure
– INIR Mission
3 – Activities in the Next Phases
4 – Conclusions and Suggestions
Power Generation by Fuel Type in 2015
Energy Generation 183,377 GWh ( 3.3%)
Peak Demand 27,346 MW ( 1.5%)
Renewables 1.5%
Coal Import
8.2%
Electricity Generation 2009 (Based on type of fuel)
Oil 0.4%
Lignite 11.6%
Water 4.8%
From Loas
1.6% From Malasia
0.1 %
Diesel 0.03 %
Natural Gas
71.8 % 145,233 GWhr
Source : IAEA Nuclear Energy Series No. NG-T-3.2
Infrastructure development program
2007 2011 2014 2020
Infrastructure Development Program (IAEA Milestones)
1st 2035
Thailand
Thank You for Your Attention