Nuclear I&C Activities in Hungary 2011-2012 · assessed in the case of permanent loss of electric...
-
Upload
hoangkhanh -
Category
Documents
-
view
215 -
download
2
Transcript of Nuclear I&C Activities in Hungary 2011-2012 · assessed in the case of permanent loss of electric...
Vienna, May 22, 2013
Nuclear I&C Activities in Hungary
2011-2012
Presented by Tamás Túri
Vienna, May 22, 2013
Contents
• Paks NPP
• Centre for Energy Research
• Technical University of Budapest
• Suggested topics for the IAEA
3
Paks Nuclear Power Plant
Status of nuclear energy in Hungary
Unit-1
1982
Unit-2
1984
Unit-3
1986
Unit-4
1987
4 x PWR 500 MWe
Paks Nuclear Power Plant
Paks Nuclear Power Plant
Paks Nuclear Power Plant
Turbine Monitoring
• 4x2=8 turbogenerator
• The original system is soviet design from the 70s
• 2001 December, insurance assessment
• Public procurement, Emerson selected
• Installation
– Unit 1 2011
– Unit 2 2012
– Unit 3 2013
– Unit 4 2014
10
Stress test
• European Commission and the European Nuclear Safety
Regulators' Group (ENSREG) agreed on 25 May 2011
on voluntary tests for the EU's 143 nuclear power
reactors
• The Hungarian National Action Plan was completed on
December 18, 2012.
• April 22 – 26, 2013 ENSREG meeting on action plans of
the 17 countries involved.
20
I&C related actions in the Natioanl Action Plan:
• In the frame of the reconstruction project of the seismic instrumentation, which is
in preparatory phase, the question of automatic shutdown shall be revised
• Resistance against electromagnetic effects shall be reevaluated
• The adequacy of the emergency related on-site and off-site radiation monitoring
devices for earthquakes and loss of power supply shall be revised.
• Installation of the severe accident instrumentation has been taking place for
Paks NPP and it had been decided before the accident of Fukushima Dai ichi
NPP.
• A software-based severe accident training simulator shall be developed
• The methods to guarantee the conditions for radio communication shall be
assessed in the case of permanent loss of electric power and earthquakes
21
Stress test
Sever accident management
22
2011 2012 2013 2014 2016 2018
1.Installation of hydrogen burners in the
containment
U1-4
2.Flooding the reactor cavity and cooling the
reactor pressure vessel from outside
U1 U2 U3 U4
3.Prevention of loss of coolant of the spent fuel
storage pool
U1 U2, U4 U3
4.Installation of an autonomous electric power
supply system for designated consumers of SAM
U1-4
5.Installation of a severe accident monitoring
system
U1 U2 U3, U4 U4
6.Setup of a technical support center STSC TSC
Main I&C projects in progress
23
• Over all I&C system refurbishment – Feasibility study 2011, Control Room upgrade studies,
• Control rod driving system and the Reactor
power controller – Specification for tendering 2012, waiting for approval
• On-line chemical measuring system – Basic design is ready, license is issued, first installation is planned in 2013.
• Meteorological measuring system – Desing is in progress, installation is planned in 2013
24
Hungarian Academy of Sciences
Centre for Energy Research
János Végh
Centre for Energy Research
Control room modernization: Plant Control Centre 1/2
• Replacement of the conventional scheme-wall and
furniture
• Activities completed in 2010:
Preparation of requirements specification document
Conceptual studies for a video-wall with large overview displays
Modernization concept for the whole PCC control room
KFKI AEKI and CGM AB (Borås, Sweden) were selected to perform
conceptual control room and HMI design studies
SCADANET Ltd. performed the video-wall studies
PCC staff was involved in data collection, conceptual design and review
activities
Centre for Energy Research
Control room modernization: Plant Control Centre 2/2
• Activities completed in 2011: Finalization of the new PCC control room design (CGM AB)
Selection of the video-wall concept and technology (Scadanet)
Development of large overview display prototypes (KFKI AEKI)
• Activities completed in 2012: Selection of system integrator and video-wall supplier (EyeVis, Germany)
Preparation of site installation plan
Procurement and installation at FAT site
FAT was completed in November 2012 (Budapest)
Site installation and SAT performed in December 2012 (Paks)
• The new PCC control room with the new video-wall
started successfully its regular operation in January 2013
Centre for Energy Research
View of the old scheme-wall in the Plant Control Centre control room ( Paks NPP)
Centre for Energy Research
View of the new video-wall in the Plant Control Centre control room ( Paks NPP)
Centre for Energy Research
Preparation of Bid Invitation Specification for Paks 5&6
• Lévai Project (MVM Ltd.) – conducting BIS preparation
• Activities completed in 2011 and 2012 (BIS chapters by CER):
I&C functional analysis and task analysis
Requirements for I&C design, I&C functions and architecture
Application of human factor engineering principles in I&C design
Requirements for process control and instrumentation
Requirements for safety I&C (e.g. RPS)
Requirements for safety-related I&C
Requirements and specifications for human-system interface components,
control rooms and other control points
Specifications for full-scope simulator and training programmes
Emergency preparedness infrastructure requirements
Centre for Energy Research
Modernization of Paks NPP process computer (PCS)
• The present PCS is 15 years old obsolete hardware and
operating system (Windows NT) maintenance problems
• Conceptual plan for the modernization
• Main proposals and recommendations:
Application of the “virtual machine” concept to facilitate hardware independence of
the new process computer system
Application of unidirectional “data diodes” and “mirror servers” to separate internal
and external computer networks in a secured way
Provision of the same HSI for the internal and external users
Provision of a plant-level data archive with central data storage
Continuation of the basic PCS architecture: Windows operating system + iFIX Scada
application software + Intel-based servers
Upgrading and renewal activities at
the Training Reactor of
the Budapest University of Technology and
Economics
Bálint Szabó
31
32
• Education and research reactor
• Commissioned in 1971
• Located in the university campus
Training reactor at BME
• Pool-type reactor
• Pmax: 100 kWth
• Fuel: 10 % enriched UO2
Training reactor at BME
33
• Reactor control and safety rod drives – completed
• Primary circuit measurement system
(T, p, water level, etc.) – in design phase
I&C Reconstruction activities
34
Control and safety rod drives
New rod drives
• Stepper motor
• Proximity sensors
• Spiral cabled magnet
power supply
• High reliability
connectors
Old rod drive
• DC motor
• Micro switches
• Sliding contactor
magnet power supply
• Standard connectors
36
Control and safety rod drives
Suggested topics for the IAEA
for 2013-2016
Suggested topics for the IAEA 2013-2016 1/2
• Role of I&C in BDBA and SA situations – I&C designs to cope with BDB and severe accidents
– Improved (“hardened”) instrumentation and process monitoring
– Improved emergency response capabilities, including
• on-site support (with the capability to handle multi-unit accidents)
• off-site support (with simulation, planning + prediction capabilities)
• improved training (with advanced simulation + visualization tools)
• Harmonization of I&C standards and safety regulations – Focusing on safety I&C requirements for new plants
– International co-operation to establish a reference safety I&C architecture for LWR
plants
• Computer security protection measures
40
Suggested topics for the IAEA 2013-2016 2/2
• Special considerations for the I&C design of the new plants – Relatively long time between bidding and commissioning and very short life cycle of
the I&C (How to avoid obsolescence already at commissioning?)
– Design for easy refurbishment during the long service life of the plant
– Design for supporting configuration management
– Design tools in general, and integration of the tools of different areas
– The role of the simulators in the design of I&C
• Technical missions to the different stakeholders – Nuclear I&C training for utilities and regulators,
– IERICS to the utilities, evaluating design solutions prior to installation,
– ICSAS missions,
41