Nubaria operation training mmmmmmmm
-
Upload
walid-salama -
Category
Education
-
view
668 -
download
4
Transcript of Nubaria operation training mmmmmmmm
OPERATION OF OPERATION OF
STEAM TURBINESTEAM TURBINE
GENERAL GENERAL ARRANGEMENTARRANGEMENT
HOT EXHAUST GAS
CTGHRSGHP SH
RH
IP SH
LP SH
LP STEAM
IP STEAM
HP STEAM
HPT
CONDENSER
IPT LPT GEN
HOTWELL PUMP
BOILER FEED WATER SYSTEM
IP-TBVIP-TBVHP-TBVHP-TBV
PROCESS OF STEAM PROCESS OF STEAM TURBINE START-UPTURBINE START-UP
AUX. EQUIPMENT OPERAITON
CTG & HRSG START UP
GLAND STEAM SERVICE IN
CONDENSER VACUUM UP
STG TURNING OPERATION
TURBINE RESET & SPEED UP
SYNCHRONIZATION
LOAD UP
CIRCULATING WATER SYSTEMCIRCULATING WATER SYSTEM
BEARING COOLING WATER SYSTEMBEARING COOLING WATER SYSTEM
CONDENSATE WATER SYSTEMCONDENSATE WATER SYSTEM
FEED WATER SYSTEMFEED WATER SYSTEM
and so on.and so on.
LIMIT ON OPERATION
VALVE TRANSFER
START-UP FOR OIL SYSTEMSTART-UP FOR OIL SYSTEM
1, CHECK THE MAIN OIL TANK LEVEL
2, START VAPOR EXTRACTOR FAN
3, START TURNING OIL PUMP (or MAIN OIL PUMP)
4, CHECK OPERATION STATUS LEAK CHECK , OIL TANK LEVEL , TANK INNER PRESSURELEAK CHECK , OIL TANK LEVEL , TANK INNER PRESSURE
OIL PRESSURES , TURNING GEAR SPRAY OIL PRESSURE , and so on.OIL PRESSURES , TURNING GEAR SPRAY OIL PRESSURE , and so on.
Double 3 Way Valve
To No5,6To No5,6 Brg.Brg.
To Thrust Brg.To Thrust Brg.
To No.1 To No.1 Brg.Brg. To No2 To No2
Brg.Brg.
To No3 To No3 Brg.Brg. To No.4 To No.4
Brg.Brg.
Turning GearTurning Gear
From AOPFrom AOP(For back up of MOP)(For back up of MOP) From EOPFrom EOP
(For Emergency(For Emergency Operation (AC Power Lost)Operation (AC Power Lost)
From TOPFrom TOP(For Turning Operation and(For Turning Operation andEmergency Operation)Emergency Operation)
From MOPFrom MOP(For Normal Operation)(For Normal Operation)
START UP OF TURBINE OIL SYSTEMSTART UP OF TURBINE OIL SYSTEM
TURNINIG OPERTIONTURNINIG OPERTIONTURNING OIL PRESS.> 0.3 bargECCENTRICITY < 0.075 mm
3rpm
START UP FOR GLAND STEAM SYSTEMSTART UP FOR GLAND STEAM SYSTEM
1, START GLAND STEAM CONDENSER FAN
2, START SERVICING FOR GLAND STEAM HEADER
3, START VACUUM PUMP
4, CLOSE VACUUM BREAKER
OTHER AUX. SYSTEM MUST BE IN SERVICE PRIOR TO START GLAND STEAM SYSTEM.
IT WILL TAKE A SHORT TIME FOR ESTABLISHING REQUIRED GLAND STEAM PRESSURE BECAUSE OF WARMING UP THE STEAM PIPE.
VACUUM BREAKER SHOULD BE CLOSED AFTER ESTABLISHING FOR SOME EXTENT OF VACUUM IN CONDENSER FOR PREVENTING UNEXPECTED PRESSURIZING ON CONDENSER.
CTG & HRSG START-UPCTG & HRSG START-UP
CTG HRSG
HP SH
RH
IP SH
LP SH
HP STEAM
HPT IPT LPT GEN
VE
NT
ST
AC
K
GLAND STEAM HEADER
TO STG
CTG must be started for supplying STG gland steam
GLAND STEAM GLAND STEAM FLOW DIAGRAMFLOW DIAGRAM
Press. : 0.3 barg
Temp. : 150 deg.C
(superheated 14deg.C
GLAND STEAM SETTING
GLAND STEAM HEADER
Gland Steam Condenser Fan
GLAND STEAM GLAND STEAM SYSTEM SYSTEM
LP GLAND STEAM FLOW
Start up mode Required gland steam temp
COLD START 160~180 deg.C or more
WARM START 200~240 deg.C or more
HOT START 300 deg.C more
GLAND STEAM CONDENSER
VACUUM UPVACUUM UP
VACUUM LOW SETTING
LOW TRIP. : 550mmHg
LOW ANN. : 635mmHg
VACUUM UP AREA
CONDENSER
HP/IP-LP TURBINE
HTR/LTR PIPE
CTGHRSGHP SH
RH
IP SH
LP SH
LP STEAM
IP STEAM
HP STEAM
HPT
CONDENSER
IPT LPT GEN
HOTWELL PUMP
BOILER FEED WATER SYSTEM
WARMING UP FOR STEAM PIPESWARMING UP FOR STEAM PIPES
VE
NT
ST
AC
K
CURTAIN SPRAY
Start up mode Stem Press Set. Main Steam Temp
COLD START 350~400 deg.C
WARM START 400~430 deg.C
HOT START
HP : 60baraIP : 12bara
430 deg.C more
REQUIRED STEAM CONDITION FOR REQUIRED STEAM CONDITION FOR STEAM ADDMISSION TO TURBINESTEAM ADDMISSION TO TURBINE
Steam pressure is controlled by HP and IP turbine by-pass valve at pre-determined set value.
Start up mode HP turbine 1st Stage Metal Temp
COLD START < 120 deg.C
WARM START 120~350 deg.CHOT START 350 deg.C more
REQUIRED STEAM CONDITION
TURBINE START UP MODE
EXAMPLE OF LIMIT ON EXAMPLE OF LIMIT ON OPERATION -(1)OPERATION -(1)
APPLICATION ALARM TRIPVibration 125um 250um Int.
Journal Brg. Metal Temp. 107deg.C 113deg.C Man.
Thrust Brg. Metal Temp. 99deg.C 107deg.C Man.
Brg. Oil Drain Temp 77deg.C - -
Rotor Position ± 0.9mm ± 1.0mm Man
Eccentricity 75um<50 um @ 0~600rpm
-
HP -11.4 ~ +5.3mm -Differential Expansion
LP -9.7 ~ +15.5mm -
Man. : Manual Trip , Int. : Interlock Trip
APPLICATION ALARM TRIPVacuum 635 mmHg 550 mmHg Int.
80 deg.C 120deg.C Man.Exhaust Steam Temp.Exhaust Spary Set : 70 deg.C
Bearing Oil Press < 0.75barg 0.45~0.55barg Int.HP Control Oil Press 16 barg - -HP/IP Upper - LowerTemp. Diff Temp
42 deg.C 66 deg.C Man
Flange – Bolt Diff Temp 110 ~ -30 deg.C -……and so on.
Man. : Manual Trip , Int. : Interlock Trip
EXAMPLE OF LIMIT ON EXAMPLE OF LIMIT ON OPERATION -(2)OPERATION -(2)
EVENTS AT SPEED UP & WARMINGEVENTS AT SPEED UP & WARMING
TURNING WITH VACUUMTURBINE RESET (GV & RSV FULLY OPENED)
SPEED UP
HEAT SOAK
RUB CHECK
500rpm
SPEED UP COMPLETION
3000rpm
2000rpm
SYNCHRO
INIT. LOAD HOLDING
SPEED UP RATELOAD UP RATE
START UP SCHEDULE AND START UP SCHEDULE AND PARAMETERSPARAMETERS
APPLICATION (unit) COLD WARM HOT
Speed Up Rate rpm/min 150 300 300
Rub Check Time @500rpm min 15 0 0
Heat Soak Time @2000rpm min 180 0 0
Initial Load Holding Time min 30 20 0
%/min 0.5 0.5 1.0Load Up Rate
Init. Load 5% 5% 10%
Medium Load Holding Time Min 30 20 0Load Up Rate(Mid load to full load) 1.0 1.0 2.0
TURBINE RESETTURBINE RESETAND SPEED UPAND SPEED UP
TURNING WITH VACUUM TURBINE RESETSPEED UP
RUB CHECK500rpm
HP-CV & RSV
HP-SV & ICV
HP-CVHP-SV
RSV ICV
100%
VALVE OPENING
RESET SPEED UP
CONTROL OJBECTS
TURBINE SPEED : Controlled by HP-SV and ICV
INITIAL PRESSURE : Controlled by HP/ IP Turbine By-Pass Valve
HEAT SOAK AND HEAT SOAK AND CRITICAL SPEEDCRITICAL SPEED
HEAT SOAK
2000rpm
PURPOSE OF HEAT SOAK
In order to avoid excess thermal stress in the rotor, it is important to have 2hours holding time at 2000rpm at cold start up.
STRESS CONTROLLER
Temp. Diff (Rotor Outer Surface - Rotor Mean ) > 70 deg.C
[SPEED UP HOLD COMMAND][SPEED UP HOLD COMMAND]
CRITICAL SPEED
1000rpm 3000rpm2000rpm
900~1050rpm
1150~1600rpm
1850~1950rpm
2050~2150rpm
2300~2800rpm
VALVE TRANSFERVALVE TRANSFER
HP-SVHP-CV
HP-CVHP-SV
RSV ICV
100%
VALVE OPENING
SYNCHRO VALVE TRANSFER
CONTROL OJBECTS
LOAD : Controlled by HP-CV and ICV
INITIAL PRESSURE : Controlled by HP/ IP Turbine By-Pass Valve
3000rpm
VALVE TRANSFERSYNCHRO
LOAD UP PROCESSLOAD UP PROCESS
HP-CV / ICV
100%
Tubine by-pass valve program close
HP/iP Turbine By-pass Valve
STG Load
CTG LOAD UP
Main Steam PressTotal CTG Load
Initial Press control by STG governor
Load up depending on CTG load
HP-CV and ICV shall be fully opened above approx. 40% of rated load.
From 1-CTG on 1-STGFrom 1-CTG on 1-STG
to 2-CTG on 1-STGto 2-CTG on 1-STG
LP STEAM
IP STEAM
HP STEAM
HOT EXHAUST GAS
CTGHRSG
HP SH
RH
IP SH
LP SH
HPT
CONDENSER
IPT LPT GEN
HOTWELL PUMPHOT EXHAUST GAS
CTGHRSG
HP SH
RH
IP SH
LP SH
Before opening of 2nd HRSG Stop Valve, 1st and 2nd HRSG temp. difference should be within ±50deg.C