Mike Cummens, MD Semantic Interoperability - 15 August, 2006.
NSIS Interoperability Meeting 12-13 October 2006
-
Upload
regina-gilmore -
Category
Documents
-
view
21 -
download
0
description
Transcript of NSIS Interoperability Meeting 12-13 October 2006
NSIS Interoperability Meeting
12-13 October 2006
University of Coimbra Portugal
209/11/2006
Summary
Participants Implementations Tests Methodology Issues Conclusions
309/11/2006
Participants
University of Coimbra (UoC) Luís Cordeiro Luís Conceição (GIST) David Palma (QoS NSLP & QSPEC) Rui Vilão (NATFW NSLP) Vitor Bernardo
University of Göttingen (UoG) Bernd Schloer (QoS NSLP) Henning Peters (NATFW NSLP)
University of Karlsruhe (UKA) Roland Bless Matthias Friedrich
409/11/2006
Participants
Roke Alan Ford
Ericsson Ferenc Pintér Attila Bader
University of Twente Rudd Klaver (remotely only)
Total of 13 persons from 6 organizations
509/11/2006
Implementations
GIST UoC v11 UoG v11 UKA v11 Roke v09 UoT v09 (remotely only)
QoS NSLP UoC v11 UoG v11 UKA v09 Ericsson v06
[using UoG GIST]
NATFW UoC v12 UoG v11 UKA v12
609/11/2006
Tests done/scheduled GIST
Stateless mode D-Mode Handshake C-Mode Handshake (TCP) C-Mode Handshake (SCTP) C-Mode Handshake (TCP) with TLS/SSL Timers Error messages Packages torture:
Header MRI
State refresh IPv6 Multiple flows in parallel in D-Mode Multiple flows in parallel in C-Mode (with
association reuse) Multiple nodes (message interception)
QoS NSLP Create sessions Update sessions Remove sessions Receiver initiated reservation Query probe Error cases Multiple sessions in parallel Multiple nodes Packages torture
NATFW NSLP Create Update Remove Trace Error cases Proxy mode Lifetime maintenance Asynchronous termination Packages torture
Different subsets of these tests were done depending on the implementations interacting
The interacting team chose the tests to perform depending on their concerns
A detailed list of tests and methodology MUST
be made to the next interop
709/11/2006
Important Issues
GIST Use of Stack-Configuration-Data and MA-Protocol-
Options MA-Hold-Time issues GIST Hop count
QoS NSLP: Receiver initiated methods Is notify required to acknowledge every refresh
message?
All issues have been taken to the mailing list
Many spec clarification issues were taken directly to the author
809/11/2006
Conclusions
GIST Several implementation issues were discovered and most of them
solved on site Not all features were tested
Only back-to-back tests were made Few package torture were made
There are interoperable implementations The spec is clear and "simple" enough to produce running and
interoperable code.
NSLPs Several implementation issues were discovered and most of them
solved on site There are interoperable implementations There are still some issues with the spec
909/11/2006
Conclusions
Interop meetings are very good to: Fast testing Fast debugging Discuss implementation issues Discuss specification unclear parts
New interop is needed Should have more days (3-4) Have a very detail methodology and test sequence defined All intervenient should have the same spec version implemented Roland Bless offered University of Karlsruhe (Germany) to held
the next interop When?