November 12, 2010 Regional Planning Group Long-Term System Assessment Project Update Warren Lasher...
-
Upload
claud-carson -
Category
Documents
-
view
214 -
download
0
Transcript of November 12, 2010 Regional Planning Group Long-Term System Assessment Project Update Warren Lasher...
November 12, 2010
Regional Planning Group
Long-Term System AssessmentProject Update
Warren LasherManager, Long-Term Planning and Policy
Jonathan RosePlanning Engineer
2 Regional Planning GroupNovember 12, 2010
Purpose of the Long-Term Plan
To Inform Near-Term Planning with Potential Solutions that Meet Long-Range System Needs
• Intent is not to select new circuits to recommend
• Rather, the intent is to provide a selection of alternatives through scenario analysis that can be considered when developing solutions for near-term congestion or reliability needs
• To meet the NERC TPL Requirements for development of 10-year transmission plan
3 Regional Planning GroupNovember 12, 2010
Specific Focus
The focus of this study is to look for:• Long-Lead-Time Projects – projects that may
require 5 or more years to bring on-line• Large Projects – short-term analyses tend to
focus on short-term solutions. A long-term perspective can indicate larger projects that both solve short-term issues but also meet long-term system needs more cost-effectively.
• This analysis will also provide implementation experience for some of the new tools and processes being developed for long-term planning.
4 Regional Planning GroupNovember 12, 2010
Scope
• Study Years: 2020 – 2030• Load growth based on extrapolating current
ERCOT Long-Term Load Forecast• 2020 Peak Load: ~86,500 MW• 2030 Peak Load: ~102,000 MW
• All generation currently on-line (and expected to maintain operation) plus all units with signed IAs as of 9/1/2010
• Generation Expansion by Scenario• Report will be submitted to PUCT by end of 2010
5 Regional Planning GroupNovember 12, 2010
Methodology
First Step: Simplify the ERCOT Transmission Network
6
Motivation
• LTSA and DOE project are long-range studies.
• Due to uncertainties over a long time scale, different focus from near-term planning:– Scenario-based rather than typical year– Simplified model to highlight long-term
concerns while de-emphasizing issues better dealt with as they arise in the near-term.
November 12, 2010 Regional Planning Group
7
Example: A 2030 Load-Flow Case
• Starting from the latest ERCOT five-year planning case
• Increase loads from 70+GW to ~102 GW• For initial testing purposes, add proxy generators to
fulfill load at existing sites and other obvious transmission locations
• Resulting case has 1400 N-1 overloads.• Why? Twenty years of transmission upgrades have
not been modeled.
November 12, 2010 Regional Planning Group
8
Example of 2030 Case
• Such a high number of overloads is prohibitively large to examine manually.
• Case simplification helps “filter” the overloads.
• Many overloads are on easily upgradable lines (generally short 69 kV). These aren’t the study’s focus, thus should be hidden from view.
November 12, 2010 Regional Planning Group
9
Case Simplification Steps
• Process Code written by Dave Matthews (AEP) and Jonathan Rose (ERCOT)
• Remove 69-kV network.• Remove 138-kV radial buses.• Remove 138-kV inline buses.• Raise rating of “short” rural lines.
– Definition of “short” is subject to tuning.
November 12, 2010 Regional Planning Group
10
Remove 69-kV Network
• Move all generators to nearest 138-kV bus.– POI bus is also moved, so bus number and name are
preserved for recognition.
• “Move loads”: Measure flow at the 138 / 69 kV autos and represent these flows by loads at the 138-kV buses.
• Remove 69-kV network.
November 12, 2010 Regional Planning Group
11
Remove Radials and Inlines
• Move load and switched shunts to neighboring bus.
• Three-winding transformers with a radial leg are converted to two-winding transformers. Radial load and switched shunt moved to high side.
November 12, 2010 Regional Planning Group
12
After Simplification
• Bus count reduced 6000 2000 (approx)• Line count reduced 6000 2000 (approx)• Flows on 138-kV and 345-kV bulk
transmission network mostly unchanged.• Example simplified system will be posted on
the Planning and Operations web-site
November 12, 2010 Regional Planning Group
13 Regional Planning GroupNovember 12, 2010
Methodology
Next Steps:• Generation Expansion Analysis
– Scenarios being evaluated:• Business as Usual• Coal Generation Expansion• Gas Generation Expansion• High Renewables
• Evaluate transmission projects that meet system needs
14 Regional Planning GroupNovember 12, 2010
Summary
• Study focus is on identification of long-lead-time projects through scenario analysis that can be considered when developing solutions for near-term congestion or reliability needs
• Designed to meet the NERC TPL Requirements for development of 10-year transmission plan
• This analysis will provide implementation experience for some of the new tools and processes being developed for long-term planning.
15 Regional Planning GroupNovember 12, 2010
Questions?