Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St....

26
Tracking Number: 100284878 | Version 1.6 | Submied Date: (waing for outstanding consent forms and/or payment) Page 1 of 9 Noce of Work Halfway River Materials Source Tracking Number: 100284878 Applicant Informaon If approved, will the authorizaon be issued to an Individual or Company/Organizaon? Company/Organizaon What is your relaonship to the company/organizaon? Employee APPLICANT COMPANY / ORGANIZATION CONTACT INFORMATION Please enter the contact informaon of the Individual/Organizaon who is acng on behalf of the applicant. Name: Brish Columbia Hydro & Power Authority FW/2019 Doing Business As: Phone: 604-699-5178 Fax: Email: [email protected] BC Incorporaon Number: Extra Provincial Inc. No: Society Number: GST Registraon Number: Contact Name: Alexandra Gray Mailing Address: 9th Floor-1111 West Georgia Street Vancouver BC V6E 4M3 CORRESPONDENCE E-MAIL ADDRESS If you would like to receive correspondence at a different email address than shown above, please provide the correspondence email address here. If leſt blank, all correspondence will be sent to the above given email address. Email: Contact Name: Alex Gray TECHNICAL INFORMATION APPLICATION INFORMATION Type of Noce of Work: Quarry - Construcon Aggregate Is this a New Permit or an Amendment to an exisng permit for this property? New Permit MINE INFORMATION Do you have an exisng mine number? No Name of the property: Halfway River Materials Source Tenure Numbers: Crown Grant / District Lot Numbers: Direcons to site from nearest municipality: The Halfway River Materials Source is located adjacent to Halfway River just off of Highway 29, approximately 45 km west of Fort St. John. Geographic Coordinates of Mine: Latude: 56.2188000 Longitude: -121.4473000 Maximum Annual Tonnage Extracted: 155000 tonnes INFORMATION ABOUT PROPOSED ACTIVITIES Acvies to be undertaken: Access roads, trails, heli pads, air strips and boat ramps Camps, Bldgs, Staging Areas and/or Fuel / Lubricants Storage

Transcript of Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St....

Page 1: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 1 of 9

Notice of WorkHalfway River Materials Source

Tracking Number: 100284878

Applicant InformationIf approved, will the authorization be issued to an Individual or Company/Organization?

Company/Organization

What is your relationship to thecompany/organization?

Employee

APPLICANT COMPANY / ORGANIZATION CONTACT INFORMATIONPlease enter the contact information of the Individual/Organization who is acting on behalf of the applicant.

Name: British Columbia Hydro & Power Authority FW/2019Doing Business As:Phone: 604-699-5178Fax:Email: [email protected] Incorporation Number:Extra Provincial Inc. No:Society Number:GST Registration Number:Contact Name: Alexandra GrayMailing Address: 9th Floor-1111 West Georgia Street

Vancouver BC V6E 4M3

CORRESPONDENCE E-MAIL ADDRESSIf you would like to receive correspondence at a different email address than shown above, please provide the correspondence emailaddress here. If left blank, all correspondence will be sent to the above given email address.

Email:Contact Name: Alex Gray

TECHNICAL INFORMATIONAPPLICATION INFORMATION

Type of Notice of Work: Quarry - Construction AggregateIs this a New Permit or an Amendment to an

existing permit for this property?New Permit

MINE INFORMATION

Do you have an existing mine number? No Name of the property: Halfway River Materials SourceTenure Numbers:Crown Grant / District Lot Numbers:Directions to site from nearest

municipality:The Halfway River Materials Source is located adjacent to Halfway River just off ofHighway 29, approximately 45 km west of Fort St. John.

Geographic Coordinates of Mine: Latitude: 56.2188000 Longitude: -121.4473000Maximum Annual Tonnage Extracted: 155000 tonnes

INFORMATION ABOUT PROPOSED ACTIVITIES

Activities to be undertaken: Access roads, trails, heli pads, air strips and boat rampsCamps, Bldgs, Staging Areas and/or Fuel / Lubricants Storage

IzettEng
Highlight
Page 2: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 2 of 9

Sand & Gravel / Quarry Operations

FIRST AID

Proposed First Aid equipment on site: To be determined by the contractor. Equipment will be in accordance withthe Mines Health, Safety, and Reclamation Code.

Level of First Aid Certificate held by attendant: Occupational First Aid Level 3

DESCRIPTION OF WORK PROGRAMIf you prefer to upload a document, please enter "see attached document" and attach the document in the "Document Upload" steplater in the application under "Other".

Sufficient details of your work program to enable a good understanding of the types and scope of the activities that will beconducted:

Please see attached Activity Description.

TIME OF PROPOSED ACTIVITIESProposed start and end date: Aug 1, 2019 to Dec 31, 2023

Please remember that you need to give 10 days notice to the Inspector of Mines of your intention to start work, and 7 days notice ofyour intention to stop work.

ACCESSAccess presently gated: No

PRESENT STATE OF LANDPlease identify what the present state of the land is where you would like to undertake your activities. If some of the questions do notapply to you please enter n/a in the space provided.

Present condition of the land: The area was cleared and grubbed in winter 2019 in preparation for constructionactivities.

Type of vegetation: n/aPhysiography: The overall surface of the area is generally flat to gently undulating, ranging in elevation

from approximately 434 m to 438 m. The lower elevations were proximal to the edges ofthe Halfway River channel and related seasonal flood channels that bisect the areas fromnorthwest to southeast. The higher elevations are associated with a terrace area thatcomprises the approximate southwestern half of the site.

Current means of access: Access to the site will generally be from Highway 29 and the contractor will determine thelocation of internal roads including access to the material source.

Old equipment: n/aRecreational trails / use: n/a

ACCESS TO TENURE

Do you need to build a road, create streamcrossings or other surface disturbance thatwill not be on your tenure?

No

LAND OWNERSHIP

Application area in a community watershed: NoProposed activities on private land: No

Page 3: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 3 of 9

Proposed activities on Crown land: YesLicence of Occupation: No

Have you applied for a Licence of Occupation? YesFile number of application: 100285626

Activities in a park: No

CULTURAL HERITAGE RESOURCESCultural Heritage applies to a large spectrum of heritage resources that is defined as "an object, a site or the location of a traditionalsocietal practice that is of historical, cultural or archaeological significance to British Columbia, a community or an aboriginal people."

The Archaeology Branch of the Ministry of Forests, Land and Natural Resource Operations is responsible for the administration of theHeritage Conservation Act as it applies to archaeological sites. The Archaeology Branch has developed guidelines for companies engagedin natural resource extraction to aid in planning for and avoiding or managing impacts to protected archaeological sites.

Are you aware of any protected archaeological sitesthat may be affected by the proposed project?

No

FIRST NATIONS ENGAGEMENTIn making decisions on authorizations, the government will be fulfilling its responsibility to consult, and where appropriate,accommodate First Nations. The government takes this responsibility seriously and encourages the applicant to engage First Nationsearly and often as part of any planned development.

Establishing good relations with First Nations who might be affected by a proposed development is a key part of any successful miningoperation. The Ministry of Energy and Mines encourages applicants to engage and information share with First Nations that might beaffected by a proposed development prior to submitting an application. The earlier in the life of a proposed activity that the avenues ofcommunication are established the greater the likelihood that the relationships formed will be constructive and beneficial to all parties.A lack of information sharing and engagement by the applicant may result in extended timeframes for decision.

Applicants should keep a detailed record of information sharing and engagement with First Nations on their project in the event thegovernment needs to review it. Information on First Nations information sharing and engagement should include the following: a list ofFirst Nations contacted, whether the activity was modified based on feedback from First Nations, and whether the applicant has enteredinto any informal or formal agreements with First Nations in connection with the project.

The Consultative Areas Database Public Map Service is an online, interactive mapping tool that allows you to identify First Nations whohave treaty rights or asserted or proven rights or title on the land base. More information can be found at http://maps.gov.bc.ca/ess/sv/cadb/.

Have you shared information and engaged with FirstNations in the area of the proposed activity?

Yes

Please tell us about your engagements in the field below or attach a your record of engagement by uploading it at the "DocumentUpload" step later in the application process. If you are attaching your record later, please enter in the text box "See record attached".Please ensure your record does not contain an individual's personal information such as contact information.

Describe your First Nations engagement activities: Halfway River clearing and construction activities were described atPermitting Forum #10 held on September 11, 2018 in Fort St. John.The materials source will be described in further detail at theupcoming Permitting Forum #12 on May 2, 2019.

As a result of the engagement, are you aware of anycultural heritage resources in the area where thework is proposed?

No

CAMPS, BUILDINGS, STAGING AREAS AND FUEL / LUBRICANTS STORAGEThis section covers the construction of new camps and/or buildings as well as the storage of fuel/lubricants on the exploration/mine site.

Page 4: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 4 of 9

The construction and operation of industrial camps (where more than five people will be accommodated) are regulated under theHealth Act and its supporting regulations. Permits may be required for different aspects of camp operation. Contact the nearest RegionalHealth Authority to determine which requirements will apply to your camp.

You must also contact the BC Safety Authority and WorkSafe BC. For more information regarding Industrial Camp Regulation please seehttp://www2.gov.bc.ca/gov/content/health/keeping-bc-healthy-safe/industrial-camps.

If water for camp operations is withdrawn from either a surface water or groundwater source, a licence or an approval may be requiredunder the Water Sustainability Act. For further information please contact FrontCounter BC.

MAPSIf known, mark the locations of camps, buildings and fuel storage on the maps, show the distance of activity from known streams,wetlands or lakes on the map.You will upload the maps at the document upload step later in the application process.

If locations are not determined you must provide a location map with your start up notification at least 10 days prior to start-up. Camps,buildings and fuel storage must comply with riparian setbacks as set out in Section 9 of the Code and the guidance provided in theHandbook for Mineral & Coal Exploration.

CAMPSClick on the "Add Camp" button to add a camp. If you have multiple camps please give each camp a distinctive name like Camp 1 whichyou can reference on the maps you submit with your application.

BUILDINGSClick on the "Add Building" button to add a building. If you have multiple building please give each building a distinctive and descriptivename like "Shop" or "Storage 1" which you can reference on the maps and drawings you submit with your application. Please note thatall buildings must adhere to the following Codes, BC Building Code, BC Fire Code and CSA Standard M421-00 "Use of Electricity in Minesin conjunction with the Canadian Electrical Code. All plans must be submitted at least 60 days prior to the proposed start ofconstruction to the Inspector. The Inspector will advise if additional documents are required.

STAGING AREAClick on the "Add Staging Area" button to add a staging area. If you have multiple staging areas please give each staging area a distinctiveand descriptive name like "Area 1" or "Area 2" which you can reference on the maps and drawings you submit with your application.

Name Disturbed Area (ha)Merchantable timber

volume (m³)Area A4 13.00 0.00Area B 11.70 0.00Total: 24.70 0.00

FUEL / LUBRICANT STORAGEIf you are planning to handle, transport or store fuel and/or lubricants you must adhere to B.C. Environmental standards as detailed in"Summary of Environmental Standards and Guidelines for Fuel Handling, Transportation and Storage".

Do you propose to store fuel / lubricants on site? No

RECLAMATION PROGRAM

Describe the proposed reclamation andtiming for this specific activity:

In the period between extraction and inundation, the extraction areas will beprogressively reclaimed. The scope of reclamation works is anticipated toinclude slope stability, placement of stripping and overburden as a growingmedium, and seeding and preventative measures for invasive plants andnoxious weeds.

Estimated cost of reclamation activitiesdescribed above:

$0.00

ACCESS ROADS, TRAILS, HELI PADS, AIR STRIPS AND BOAT RAMPS

IzettEng
Highlight
Page 5: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 5 of 9

MAPSMark the locations of the proposed access roads and trails on the map. The maps will be uploaded at the document upload step later inthe application.

ACTIVITIESClick on the "Add Activity" button to add one or more activities. Select your activity out of the list and enter the length in km, the totaldisturbed area and total merchantable timber volume.

Activity Length (km) Disturbed Area (ha)Merchantable

timber volume (m³)Temporary Road - New 2.30 2.55 0.00Total: 2.30 2.55 0.00

BRIDGES, CULVERTS AND CROSSINGS

Are you proposing any bridges, culvertsand/or other river / stream crossings?

No

RECLAMATION PROGRAM

Describe the proposed reclamation andtiming for this specific activity:

n/a

Estimated cost of reclamation activitiesdescribed above:

$0.00

ADDITIONAL INFORMATIONPlease note that you may require a Special Use Permit under the Forest Practices Code of British Columbia Act or a Land Act tenure orother authorization under the legislation to use roads to access your tenure.

For further information please contact FrontCounter BC.

SAND & GRAVEL / QUARRY OPERATIONS

MAPSAll plans and sections must indicate the scale and orientation of the drawing and must include:

1) Plan View of Proposed Development illustrating:

- Property boundaries and set back of excavation from property boundary- Watercourses and drainage (wet, dry or intermittent) on the property and within 150 metres of its boundaries- All previous surface workings, the final boundaries of proposed excavation, and boundaries of excavation at the end of developmentdescribed in the Notice of Work- Access roads, including development roads within the pit and access to the public roads- All proposed and existing stockpiles (topsoil, overburden, product etc.)- All settling ponds (for both surface run off and process water) and source of process water- Buildings and other facilities (fuel/lubricant storage, sanitary facilities, weigh scale, etc.)- Sediment control structures and the location of any point discharges from the property- Fencing, berms and/or vegetative buffers.

2) Cross and longitudinal sections of Proposed Development illustrating:

- The orginial land surface and, if applicable, the groundwater table elevation- Typical configuration during mining, indicating angle of slope and, where applicable, bench locations- Proposed configuration on completion of reclamation

Page 6: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 6 of 9

3) A copy of the land title/crown land tenure map must be provided.

SOIL CONSERVATION

Average depth of overburden:Average depth of topsoil:Measures to stabilize soil overburden

stockpiles and control noxious weeds:

LAND USE

Is the site within the Agricultural Land Reserve? NoDoes the local government have a Soil Removal Bylaw? NoOfficial Community Plan for the site:Current land use zoning for the site:Proposed end land use is:Estimate total minable reserves over the life of the mine:Estimate annual extraction from site:

Application must be made to the Environmental Assessment Office if estimated extraction for sand/gravel production is 500,000tonnes/year or 1,000,000 tonnes over 4 years; or if estimated extraction is 250,000 tonnes/year for quarried product.

ACTIVITIESClick on the "Add Activity" button to add one or more activities. Select your activity out of the list and enter the tonnes, the totaldisturbed area and the total merchantable timber volume.

Please note that you must notify the Inspector at least two weeks before if you are planning to bring a crusher on site.

ActivityTotal Disturbed Area

(ha)Merchantable

timber volume (m³)Crushing 1.20 0.00Excavation of Pit Run 28.50 0.00Mechanical Screening 0.00 0.00Washing 1.00 0.00Total: 30.70 0.00

Is the work year round or only seasonal? Year roundBrief description of operation, including

proposed work schedule:Operations in the pit will generally be 6 days a week – 7:00am – 7:00pm. Depending on conditions and the contractor's schedule, work may occur 7 daysa week.

RECLAMATION PROGRAM

Describe the proposed reclamation and timing forthis specific activity:

In the period between extraction and inundation, the extraction areaswill be progressively reclaimed. The scope of reclamation works isanticipated to include slope stability, placement of stripping andoverburden as a growing medium, and seeding and preventativemeasures for invasive plants and noxious weeds. Progressive restorationwill be undertaken as the areas are mined. Progressive reclamation willbe in accordance with the Mines Health, Safety, and Reclamation code;MoTI SS165, and the Site C CEMP.

If backfilling of pits or pit slopes is proposed in thefinal configuration for reclamation, details ofmaterials to be used and placement procedures:

Estimated cost of reclamation activities describedabove:

$0.00

Will progressive reclamation be carried out? YesMaximum unreclaimed disturbance at any given

time:

Page 7: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 7 of 9

GROUNDWATER PROTECTION

Average depth to the high groundwater table at theproposed excavation:

433.0 m

Elevation of the groundwater table was determined from: Existing area wells Test pits Test wells drilled for this purpose Other:

Measures proposed to protect groundwater frompotential impacts of the proposed mining activity:

IMPACT MINIMIZATION

Shortest distance between proposed excavationto nearest residence:

Shortest distance between proposed excavationto nearest residential water source:

Measures proposed to prevent inadvertentaccess of unauthorized persons to the minesite:

Measures proposed to minimize noise impacts ofthe operation:

Measures proposed to minimize the dustimpacts of the operation:

Measures proposed to minimize visual impactsof the operation:

TIMBER CUTTING

Total merchantable timber volume: 0.00 m3

No TimberYou have indicated that there is no merchantable timber that will be cut. Therefore a Free Use Permit or a Licence to Cut isnot required. If this is not accurate, please correct your entries.

EQUIPMENTClick on the "Add Equipment" button to add one type of equipment at a time. All equipment must comply with the requirements of theHealth, Safety and Reclamation Code.

Quantity Type Size / Capacity5 Bulldozer/Crawler Tractors TBD2 Crusher TBD2 Excavator TBD4 Truck TBD4 Truck Dump trucks

SUMMARY OF RECLAMATIONBased on the information you have provided on the previous screens the Summary of Reclamation is:

ActivityTotal Affected area

(ha)Estimated cost of

reclamation ($)Access roads, trails, etc. 2.55 0.00Camps, Buildings, etc. 24.70 0.00Sand & Gravel / Quarry 30.70 0.00Subtotal: 57.95 0.00Unreclaimed disturbance from previous year: 0.00

Page 8: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 8 of 9

Disturbance planned for reclamation this year: 0.00Total: 57.95 0.00

OTHER CONTACTSPlease enter the contacts that are applicable to your application.

Contact Info Type of ContactName: BC Hydro Tenure HolderDoing Business As:Phone: 604-699-5178Fax:Email: [email protected] Inc. Number:Extra Provincial Number:Society Number:GST Registration Number:Contact Name:Mailing Address: 1111 W Georgia Street

Vancouver BC V6E 4G2

Name: BC Hydro PermitteeDoing Business As:Phone: 604-699-5178Fax:Email: [email protected] Inc. Number:Extra Provincial Number:Society Number:GST Registration Number:Contact Name:Mailing Address: 1111 W Georgia Street

Vancouver BC V6E 4G2

LOCATION INFORMATION

LAND DETAILSDo you have the legal description of the land or the civic address then click on 'Add Land Information'.

DRAWINGSAll applications must include the appropriate maps and applications received without maps will be returned. All maps must be in colour,computer generated, with a scale, north arrow and a detailed legend.

For Mineral, Coal and Placer applications you must provide a minimum of 3 maps:- A Location Map which must show the location of the property in relation to the nearest community with the access route from thecommunity to the work site clearly marked;- A Tenure Map which must show the boundaries of the tenure(s) and tenure numbers, at a scale of 1:20,000 or less;- A Map of Proposed Work which must show topography, water courses, existing access, existing disturbance, contour lines, knowncultural heritage resources and/or protected heritage property, at a scale of 1:10,000 or 1:5,000. For site specific applications thelocation of all proposed exploration activities must be shown; for area-based applications the work area must be shown as a polygon,with the location of all proposed exploration activities for year 1 shown, and shape files provided of the area.

Page 9: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Tracking Number: 100284878 | Version 1.6 | Submitted Date: (waiting for outstanding consent forms and/or payment) Page 9 of 9

For Sand & Gravel/Quarry applications you must provide a Plan View, Cross and Longitudinal Sections and a Land Title/Crown LandTenure Map. Details of these requirements are listed in the Sand & Gravel/Quarry Operations Activity sheet.

PRIVACY DECLARATIONPRIVACY NOTE FOR THE COLLECTION, USE AND DISCLOSURE OF PERSONAL INFORMATIONPersonal information is collected by FrontCounter BC under the legal authority of section 26 (c) and 27 (1)(a)(i) of the Freedom ofInformation and Protection of Privacy Act (the Act). The collection, use, and disclosure of personal information is subject to the provisions of the Act. The personal information collected byFrontCounter BC will be used to process your inquiry or application(s). It may also be shared when strictly necessary with partneragencies that are also subject to the provisions of the Act. The personal information supplied in the application package may be used forreferrals or notifications as required. Personal information may be used by FrontCounter BC for survey purposes.For more informationregarding the collection, use, and/or disclosure of your personal information by FrontCounter BC, please contact FrontCounter BC at1-877-855-3222 or at:FrontCounter BC Program DirectorFrontCounter BC, Provincial Operation441 Columbia StreetKamloops, BC V2C 2T3 Check here to indicate that you have read and agree to the privacy declaration stated above.

REFERRAL INFORMATIONSome applications may also be passed on to other agencies, ministries or other affected parties for referral or consultation purposes. Areferral or notification is necessary when the approval of your application might affect someone else's rights or resources or those of thecitizens of BC. An example of someone who could receive your application for referral purposes is a habitat officer who looks after thefish and wildlife in the area of your application. This does not apply to all applications and is done only when required.

Please enter contact information below for the person who would best answer questions about your application that may arise fromanyone who received a referral or notification.

Company / Organization: British Columbia Hydro & Power Authority FW/2019Contact Name: Alexandra GrayContact Address: 9th Floor-1111 West Georgia Street

Vancouver BC V6E 4M3Contact Phone: 604-699-5178Contact Email: [email protected]

I hereby consent to the disclosure of the information contained in this application to other agencies, government ministries orother affected parties for referral or First Nation consultation purposes.

APPLICATION AND ASSOCIATED FEESApplication and Associated Fees: $40000.00 CAD plus applicable taxes

OFFICE

Office to submit application to:

PROJECT INFORMATION

Is this application for an activity or project whichrequires more than one natural resourceauthorization from the Province of BC?

No

OFFICE USE ONLYOffice File Number Project Number

Disposition ID Client Number

Page 10: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

2019-04-29 Page 1 of 5

Site C Clean Energy Project Mines Act Notice of Work - Highway 29, Halfway River Materials Sources

Management Plan

1. INTRODUCTION

Highway 29 is two-lane rural arterial undivided highway under the jurisdiction of the British Columbia Ministry of Transportation and Infrastructure (MoTI) that connects Hudson’s Hope to Fort St. John. It runs along the north side of the Peace River. Segments of the highway will be inundated or rendered unstable by the Site C reservoir, resulting in the need to realign approximately 30 km of existing highway at Lynx Creek, Dry Creek, Farrell Creek, Halfway River, and Cache Creek. Construction of the Halfway River segment, including a new bridge over Halfway River, is planned to commence in fall 2019 and be complete by the end of 2022.

Embankment and road base material for the construction of the Halfway River realignment will be required and is planned to be excavated primarily from a future inundated area. The application area for the materials source will be between the existing highway and the Peace River, along the Halfway River, and above the existing highway as shown on Dwg No. 1016_N11_00471-1 and 1016_N11_00471-2.

The purpose of this document is to support BC Hydro’s Mines Act Notice of Work application for the Halfway River Inundated Materials Source. This document provides information on existing environmental conditions within the requested Notice of Work area, proposed activities and works, schedule of work, access and equipment, and future use of the area. Additional applications will be submitted under separate cover to support the construction of the realigned Halfway River section of Highway 29. These include:

Land Act Licence of Occupation for Halfway River Inundated Materials Source

Water Sustainability Act Application for Short Term Use of Water (WSA s.10)

Water Sustainability Act Applications for Changes In and About a Stream (WSA s.11)

Land Act Licence of Occupation for clearing and construction (issued January 2019)

Forest Act Occupant Licence to Cut (issued January 2019)

2. EXISTING CONDITIONS

The source area is comprised of a river terrace and point bar feature along the west side of the Halfway River, immediately north of and adjacent to the existing Highway 29 alignment, The planned new alignment for Highway 29 traverses the approximate center of the source area (Area A) in a generally southwest to northeasterly direction. The area will ultimately be inundated by the Site C reservoir. The overall surface of the area is generally flat to gently undulating, ranging in elevation from approximately 434 m to 438 m. The lower elevations were proximal to the edges of the Halfway River channel and related seasonal flood channels that bisect the areas from northwest to southeast. The higher elevations are associated with a terrace area that comprises the approximate southwestern half of the site. The area was cleared and grubbed in winter 2019 in preparation for construction activities.

Test pits were dug throughout the proposed gravel extraction area to determine the extent of the gravel deposits and the gravel properties. Drill holes were also completed along the proposed alignment. The test pits and drilling confirmed the presence of undulating shale

IzettEng
Highlight
Page 11: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Site C Clean Energy Project Mines Act Notice of Work - Highway 29, Halfway River Inundated Materials Source

Description of Activities and Works

2019-04-29 Page 2 of 5

bedrock underlying the site at depths ranging from approximately 6 to 8 m, depending on location. This corresponds to an approximate elevation range of 427 m to 431 m. Ground water was encountered within most of the test pits and all the drill holes. The depth to groundwater varied by location and the time of investigation. Generally, during the April-May 2017 investigation the groundwater was encountered at elevation 432.6 m to 434.2 m. In January 2018 the groundwater was encountered slightly lower, at elevation 431.8 to 433.5 m. In Area A-1, which is planned as the major excavation area, the thickness of the granular material encountered in the test pits ranged from 1.2 to 4.9m (average 2.8 m); however, all the test pits terminated in gravel and the gravel likely extends to depths encountered by the alignment drilling. The maximum depth of exploration was limited by the groundwater table which was encountered in most of the test pits.

Existing baseline conditions are further described in the Fish and Fish Habitat, Vegetation and Ecological Communities, Wildlife Resources and Heritage Resources, are described in the Site C Project’s EIS Volume 2 Sections 12, 13 and 14, and Volume 4 Section 32, respectively.

Activities related to the realignment of Highway 29 at Halfway River may affect bear dens, beaver lodges/bank dens and rare plant occurrences. As outlined in the Site C Project’s Construction Environmental Management Plan1 (CEMP), any active bear den will be buffered by 200 m. The buffer will be retained until the den is no longer occupied. Beaver dens/dams will be removed as required as per the conditions laid out in Wildlife Act Permit FJ14-1540052 and the Water Sustainability Act Notification 9000138. Mitigation for the loss of rare plant occurrences is described in the Site C Vegetation and Wildlife Mitigation and Monitoring Plan V1, June 5, 2015.3

3. DESCRIPTION OF WORK

Highway 29 realignment at Halfway River will require relocation of a 3.7 kilometer section of highway and include the construction of river crossing. MoTI will be tendering and managing the construction contract for the relocation and bridge. Gravel and borrow material is required for the contract including embankment construction over the length of the project.

The inundated material source would supply the highway and bridge projects with gravel and borrow material as well as provide the contractors an area for their operations. This area would also be used for stockpiling of material and waste disposal and may be used for staging and a temporary work camp.

The Halfway River inundated materials source areas have been cleared during the February/March 2019 under a separate tenure. The highway construction contractor is anticipated to arrive on site in fall 2019 after the clearing is complete. The construction contractor’s first activities will be stripping the areas that will be mined. The stripping material will be stockpiled within the site limits and used for progressive reclamation. The highway contractor will primarily source material from the designated borrow area, but may utilize the stockpile area, contractor area, or waste area if required. Screening and/or crushing may begin in fall 2019. Some crushed material will be stockpiled for use as pavement and crush gravel. The contractor will also need to screen or crush the pit run to meet a specified gradation for

1 Site C Clean Energy Project Construction Environmental Management Plan. 2016. Revision 4: July 26, 2016. Available from:

https://www.sitecproject.com/sites/default/files/construction-environmental-management-plan-aug-2.pdf. 2

Wildlife Act Permit FJ14-154005, issued July 6, 2015. Available from: https://www.sitecproject.com/sites/default/files/Wildlife%20Act%20Permit%20for%20Beaver%20and%20Muskrat%20Removal.pdf 3 BC Hydro. 2015. Site C Clean Energy Project Vegetation and Wildlife Mitigation and Monitoring Plan. June 5, 2015. Available

from https://www.sitecproject.com/sites/default/files/Veg_and_Wildlife_Mit_and_Mon_Plan.pdf

IzettEng
Highlight
IzettEng
Highlight
Page 12: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Site C Clean Energy Project Mines Act Notice of Work - Highway 29, Halfway River Inundated Materials Source

Description of Activities and Works

2019-04-29 Page 3 of 5

embankment purposes. The crushing and screening operations will include excavators, loaders, trucks and a crushing or screening plant. The location of the crushing operation will be determined by the contractor. The material will also be tested on site to ensure it meets specifications. The processed granular material will then be loaded and hauled to the construction site using trucks. A new access road to the borrow area will be constructed within the permit boundary.

A contractor area within the permit application boundary will be designated for use as a laydown or staging site. The contractor may utilize this location for a small temporary worker camp. If the contractor plans a camp at this location all relevant permits will be applied for and in place prior to its establishment. As part of the Highway 29 re-alignment at Halfway River, in order to provide a cost-effective and reliable concrete supply for construction, there is potential to establish a batch concrete plant on-site. See Appendix A - technical memo titled “Site C Clearing Energy Project – Road and Bridge Infrastructure (Highway 29) Halfway River Concrete Batch Plant Specifications” and Appendix B - Pit Development Plan R3-329-601 for further details and proposed layout. These Plans serve to outline the general technical specifications (including plant footprint and servicing requirements) for the potential concrete batch plant and pit layout. Site specific requirements will ultimately be determined by the chosen contractor.

All operations will be in accordance with the applicable MoTI Standard Construction Specification 165 (SS165)4, the Mines Act, and the Health, Safety, and Reclamation code5.

4. SCHEDULE OF PROPOSED WORK

Site preparation in the Halfway River area started in February 2019 with clearing and grubbing of commercial and non-commercial vegetation. Construction is expected to commence for the Halfway River segment in fall 2019 and is scheduled to be completed by fall 2022.

Mining for gravel and borrow for the highway realignment at Halfway River would commence in fall 2019 and may be required until 2023. Material from the borrow area will primarily be used for construction at Halfway River, but may also be required for other Project needs.

A detailed schedule will be developed closer to the start of works. All works will begin only on receipt of relevant permits and approvals.

5. ACCESS AND EQUIPMENT

Access to the site will generally be from Highway 29 and the contractor will determine the location of internal roads including access to the material source

Access to the Halfway River construction site will be gated and locked when the construction site, including the area to be mined, is active.

All access roads within the Halfway River site boundary will be considered temporary as this area will ultimately be inundated by the Site C reservoir.

4 Ministry of Transportation and Infrastructure, 2011. 2012 Standard Specifications for Highway Construction. Adopted November 1,

2011. Section 165 – Protection of the Environments. Available from: http://www2.gov.bc.ca/assets/gov/driving-and-transportation/transportation-infrastructure/engineering-standards-and-guidelines/highway-specifications/volume_1_ss2012.pdf 5 Health, Safety and Reclamation Code for Mines in British Columbia. Available from: http://www2.gov.bc.ca/assets/gov/farming-

natural-resources-and-industry/mineral-exploration-mining/documents/health-and-safety/code-review/health_safety_and_reclamation_code_2017.pdf

Page 13: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Site C Clean Energy Project Mines Act Notice of Work - Highway 29, Halfway River Inundated Materials Source

Description of Activities and Works

2019-04-29 Page 4 of 5

Equipment required at site will include bulldozers, excavators, dump trucks, scrapers, fuel trucks and fuel storage facilities, service vehicles and other typical highway construction machinery.

6. SITE RESTORATION AND STABILIZATION OF TEMPORARY DISTURBANCES

The materials source areas at Halfway River will be inundated by the Site C reservoir. Disturbed areas will be stabilized following the completion of field investigations in a manner that complies with the MoTI Standard Construction Specification 165 (SS165), Site C CEMP and the Contractor’s Environmental Protection Plan (EPP).

In the period between extraction and inundation, the extraction areas will be progressively reclaimed. The scope of reclamation works is anticipated to include slope stability, placement of stripping and overburden as a growing medium, and seeding and preventative measures for invasive plants and noxious weeds. Progressive restoration will be undertaken as the areas are mined. Progressive reclamation will be in accordance with the Mines Health, Safety, and Reclamation code; MoTI SS165, and the Site C CEMP. The highway contractor will provide a progressive reclamation plan.

7. ENVIRONMENTAL MANAGEMENT AND MONITORING

In the following sub-sections, component measures are described, followed by a description of general approaches to environmental management. An environmental protection plan (EPP) will be prepared by the highway contractor ahead of development described herein. The EPP will be required to meet MoTI and Site C CEMP requirements and hence will provide a description of site-specific measures to be implemented. Works will not begin until MoTI and BC Hydro accept the contractor’s EPP.

Air Quality

Air quality control, including dust and silica, will be completed under an approved EPP implemented by the highway contractor in accordance with MoTI SS165 and the Site C CEMP requirements. Air quality management may include control of emissions of fine particulate matter, pollution prevention, temporary barriers and smoke management.

Noise

Noise monitoring and mitigation will be completed under an approved EPP implemented by the highway contractor in accordance with BC MoTI SS165 and the Site C CEMP requirements.

Materials Management

A waste disposal area has been designated for the highway and bridge contractor. Unsuitable material will be stockpiled and capped with 0.6m pit run upon completion of the highway works and prior to inundation. Potential Acid Generating (PAG) rock may be encountered during the highway and bridge pile excavation. PAG rock will be disposed of in an engineered and controlled manner in accordance with the “Potential Acid Generating Rock Controlled Disposal”, see Appendix C. The contractor will provide a disposal plan for PAG in accordance with these provisions.

General Guidance on Management and Monitoring

Page 14: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Site C Clean Energy Project Mines Act Notice of Work - Highway 29, Halfway River Inundated Materials Source

Description of Activities and Works

2019-04-29 Page 5 of 5

Environmental management will comply with the MoTI’s SS165 “Protection of the Environment” and the Site C Project’s CEMP.

An archaeological overview assessment has been completed for the entire highway footprint and material source area and any archaeological resources identified from sites will be recovered before construction begins. The contractor will follow chance find procedures if additional artifacts are discovered during construction. Work in the area will be stopped until recovery is completed.

8. FUTURE USE

The newly aligned highway will be permanent. Access roads, laydown areas, and borrow sites will be reclaimed in accordance with the EPP, Site C CEMP and MoTI’s SS165. The material source locations at Halfway River will be permanently under water when the reservoir is full.

Closure Karen von Muehldorfer Regulatory Manager Site C Clean Energy Project

alegray
Stamp
Page 15: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

1016-N11-00471-1 R 0Apr 23, 2019Cons truction of the Site C Clean Energy Project is s ubject to required regulatory and permitting approvals.

Date DWG NO

Map Notes:1. Datum: NAD832. Projection: UTM Zone 10N3. Base Data: Province of B.C.4. Imagery: ESRI Online Basemapping.

1:12,000

Path:

X:\A

rcGISP

rojec

ts\Pe

rmitti

ng\C

onstr

uctio

n\High

ways

\Half

way_

Rive

r\Half

wayR

iver_N

OW_IM

S_De

tail_1

016_

N11_

0047

1-1.m

xd

© BC Hydro 2019 – all rights reserved. This map is for information purposes only and accuracy is not guaranteed.

Halfway River

Peace

River

Sources: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community

³

!.

!.

!.

!.

!(29

!(97

Taylor

Hudson's Hope

Fort St. John

Map 1: Detail Map Mines Act Notice of Work for Inundated Material Sources - Halfway River

0 100 200 300 400 50050 mLegendHalfway River Inundated Material Sources - Notice of Work Application Area (Area = Approx 128 hectares)Land Act License of Occupation Application AreaHighway Realignment CenterlineAccess Road

Index

Page 16: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Peace RiverHalfway River

Cache Creek

1016-N11-00471-2 R 0Apr 17, 2019Cons truction of the Site C Clean Energy Project is s ubject to required regulatory and permitting approvals.

Date DWG NO

Map Notes:1. Datum: NAD832. Projection: UTM Zone 10N3. Base Data: Province of B.C.

Path:

X:\A

rcGISP

rojec

ts\Pe

rmitti

ng\C

onstr

uctio

n\High

ways

\Half

way_

Rive

r\Half

wayR

iver_N

OW_IM

S_Ov

erview

_101

6_N1

1_00

471-2

.mxd

© BC Hydro 2019 – all rights reserved. This map is for information purposes only and accuracy is not guaranteed.

³

!.

!.

!.

!.

!(29

!(97

Taylor

Hudson's Hope

Fort St. John

Map 2: Overview Map Mines Act Notice of Workfor Inundated Material Sources - Halfway River

Index

0 2 4 61Km1:100,000

¬«29

³

LegendHalfway River Inundated Material Sources - Notice of Work Application Area (Area = Approx 128 hectares)Highway Realignment Centerline

Page 17: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Appendix A

Page 18: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

TECHNICAL MEMO

Tetra Tech Canada Inc.117-877 Goldstream Avenue

Victoria, BC V9B 2X8Tel 250.915.2000 Fax 250.915.2009

ISSUED FOR REVIEW

To: John Bodnarchuk Date: March 15, 2019 c: Alex Izett, P.Eng. File: 705-1188230207-MEM-C0231-00

From: Dayna Alexander, P.Eng.

Subject: Site C Clean Energy Project – Road and Bridge Infrastructure (Highway 29) Halfway River Concrete Batch Plant Specifications

1.0 INTRODUCTION

As part of the Highway 29 re-alignment at Halfway River (associated with the Site C Clean Energy Project), in order to provide a cost-effective and reliable concrete supply for construction, there is potential to establish a batch concrete plant on-site at Halfway River. To support permitting, this memorandum serves to outline the general technical specifications (including plant footprint and servicing requirements) for the potential concrete batch plant.

2.0 REFERENCES AND LINKS

The following documents may be beneficial from a permitting perspective: BC Environmental Management Act – Code of Practice for the Concrete and Concrete Products Industry

(http://www.bclaws.ca/EPLibraries/bclaws_new/document/ID/freeside/16_329_2007) Concrete Plant Standards of the Concrete Plant Manufacturers Bureau

(http://www.cpmb.org/images/ConcretePlantStandards.pdf) Recommended Guide Specifications for Batching Equipment and Control Systems in Concrete Batch Plants

(http://www.cpmb.org/images/RecommendedGuideSpecs.pdf)

3.0 DISCUSSION

The 50% Detailed Design for the Halfway River bridge includes a Pit Development Plan that provides a potential location for a concrete plant (as well as an aggregate crusher and asphalt plant). The proposed location for the Halfway River Pit is on the west bank of the river, northwest of the existing Highway 29 Halfway River bridge, as shown on Drawing R3-329-601 (attached to this memo). The concrete volumes required for the Halfway River bridge (per the 50% Detailed Design) are as shown on the adjacent table. In total, the project will require approximately 15,000 m3 of concrete for construction. Concrete batch plants range in capacity (low to high), complexity (manual to full automated batching), and mobility (portable to stationary), and are available for either dry transit mix or wet central mix concrete. As the current plan

Halfway River Bridge Element Quantity

Deck Concrete 2,540 m3

Substructure Concrete 10,700 m3

Hollow Pier Concrete 1,740 m3

Total 14,980 m3

Page 19: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

HALFWAY RIVER CONCRETE BATCH PLANT SPECIFICATIONS FILE: 705-1188230207-MEM-C0231-00 | MARCH 15, 2019 | ISSUED FOR REVIEW

2705-1188230207-MEM-C0231-00 Halfway River Concrete Batch Plant Specs.docx

is to install the batch plant at the proposed Halfway River Pit, and the concrete requirements for bridge construction, the following assumptions have been made regarding selection of a batch plant for Halfway River: Capacity

On the low-end of capacity, small, highly-transportable and mobile concrete batch plants can produce wet concrete in the range of 10 to 50 m3 per hour, with individual concrete batch sizes less than 0.5 m3 for the smallest plants. On the high-end, large, stationary concrete batch plants can produce wet concrete in the range of 200 to 250 m3

per hour, with individual concrete batch sizes over 12 m3 for the largest plants. The Halfway River bridge requires a significant volume of concrete for construction and capacity will likely be the primary criteria in selecting an appropriate batch plant for the project. For critical concrete pours for bridge elements (and especially the deck pours), a high hourly output of concrete will be necessary. It is estimated that the potential batch plant will therefore require an output capacity upwards of 100 m3 per hour. Mobility

Some construction projects, such as concrete paving, use highly mobile batch plants, positioning the plant as close as possible to the concrete placement and relocating the plant as work progresses. With size being an obvious limiting factor in a plant’s mobility and transportability, concrete productivity is limited for mobile batch plants and the highest output concrete plants will be stationary. As noted above, capacity is likely to be the primary factor in selecting an appropriate plant for Halfway River which would likely eliminate most small, mobile facilities. Further, there is no project requirement for the batch plant at Halfway River to be mobile, with the proposed Halfway River Pit plant location intended for the duration of the work. Note that mobile batch plants need not be completed excluded, however, as there are those available that may meet capacity requirements. Automation

Automation of batching generally goes hand-in-hand with plant capacity. Small concrete batch plants may not have any automation; measuring of aggregate, cement, etc. for batching is completed manually. While the high-output, larger plants will be fully automated. In consideration of the volume of concrete required for Halfway River, and in view of the concrete mix requirements necessary for bridge construction, fully-automated batching is expected to be necessary for Halfway River. Transit vs. Central Mix

The difference between transit and central mix batch plants are where the concrete ingredients are mixed. Transit mix batch plants will load all the concrete ingredients into the concrete truck, with the truck itself acting as the concrete mixer i.e. truck mixer. Central mix batch plants mix the concrete at a stationary mixer before loading to trucks, i.e. a plant mixer. Transit mix allows for some of the mixing to take place during travel to site which may be an advantage, but transit mix can result in inconsistent concrete quality across truck loads and as well as being hard on the truck drums. Central mix batch plants are more expensive and may be harder to maintain, however, their advantage is consistent concrete quality across truck loads as well as higher production rates. When reviewing manufacturer’s products, transit mix batch plants are simply the base model of batch plant and can be upgraded to a central mix batch plant by adding on a plant mixer. The proposed Halfway River Pit plant location means there will be a relatively short distance for concrete to travel to site and there is therefore little advantage to mixing concrete in transit. Further, the quality requirements for bridge

Page 20: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

HALFWAY RIVER CONCRETE BATCH PLANT SPECIFICATIONS FILE: 705-1188230207-MEM-C0231-00 | MARCH 15, 2019 | ISSUED FOR REVIEW

3705-1188230207-MEM-C0231-00 Halfway River Concrete Batch Plant Specs.docx

construction may necessitate central mixing. It is therefore expected that a central mix batch plant will be required for Halfway River.

4.0 CONCRETE BATCH PLANT – ASSUMED SPECIFICATIONS

Based on the discussion in the previous section, the following batch plant models are considered feasible for Halfway River: BMH Systems EG-10 Series (http://www.bmhsystems.com/img/brochure/EG-10MX_EN_Datasheet_V2_2018-

10-15.pdf) Vince Hagan HSM-10 Series (https://www.vincehagan.com/product-brochures/wet-startionary-concrete-batch-

plants-brochure.pdf) Vince Hagan HT Series (https://www.vincehagan.com/product-brochures/dry-mobile-concrete-batch-plant-

brochure.pdf) Cemco Model 275 (http://www.cemcoinc.com/our-products/mobile-concrete-batch-plant/) Besser ULC-IV (https://besser.com/masonry-hardscape/batching-mixing/complete-concrete-batch-plants/ulc-

iv/) A summary the rough specification expected for these concrete batch plants are as shown in the Table below:

Criteria Approximate

Specifications

Notes

Concrete Output Capacity 100 to 200 m3 per hour N/A Concrete Type Central Mix N/A Dimensions Length: 15 to 20 m

Width: 3.5 to 5.0 m Height: Up to 15 m

N/A

Servicing Water All plants require water supply, with the size of water meters variable.

Power Varies by manufacturer BMH Systems EG-10: Power panel 480 or 575

volts Vince Hagan HSM-10 Series: 230 or

460V/3PH/60HZ Vince Hagan HSM-10 Series: 460V/3PH/60HZ Cemco Model 275: 10A 120V, plant has a

mounted diesel engine Besser ULC-IV: 330A 220V 3P

Page 21: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

HALFWAY RIVER CONCRETE BATCH PLANT SPECIFICATIONS FILE: 705-1188230207-MEM-C0231-00 | MARCH 15, 2019 | ISSUED FOR REVIEW

4705-1188230207-MEM-C0231-00 Halfway River Concrete Batch Plant Specs.docx

5.0 CLOSURE

We trust this technical memo meets your present requirements. If you have any questions or comments, please contact the undersigned. Respectfully submitted, Tetra Tech Canada Inc.

Prepared by: Dayna Alexander, P.Eng. Civil Design Lead Direct Line: 250.915.2002 [email protected] Attachments

R3-329-601 Halfway River Pit Development Plan (50% Detailed Design)

Page 22: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Appendix B

Page 23: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting
Page 24: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Appendix C

Page 25: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

Appendix C: Potential Acid Generating Rock Controlled Disposal

i) Disposal of Excavated Rock

Rock excavated from the pile rock sockets is Potential Acid Generating rock and will be disposed at the designated disposal site within 5 days of its excavation. The excavated rock will have to be managed for the construction period and disposed of permanently at the designated disposal site. The temporary storage location and the permanent storage location may be the same but any other PAG disposal site must not be disturbed. The Contractor will design and maintain the disposal site for the excavated rock, including perimeter drainage works to keep the excavated rock dry from surface drainage, and maintain a temporary membrane over the rock to keep the rock dry from precipitation and not in contact with the atmosphere. The storage design for the temporary condition shall, at a minimum, include the following:

(a) The disposal location for the PAG rock must be stripped clear of any organic rich surface soils.

(b) The disposal site shall be underlain by a low permeability clay or clay/silt liner with a minimum thickness of 0.3m of clay or clay/silt with a fines content greater than 50% that has been placed and compacted to the compaction specifications of BC Ministry of Transportation and Infrastructure Standard Specification (SS) 201.37 in at least two lifts. The clay or clay silt liner must cover the site to the ditch in all directions and be graded toward the ditch in all directions at a minimum of 2%.

(c) The Contractor will construct and maintain for the duration of the Work a perimeter V-shaped ditch at least 1.0m deep and berm. The ditch will outlet while maintaining a minimum of 0.2m of water in the ditch when drainage is occurring. The ditch grade will have to be designed and constructed so that it does not erode. The ditch must include an outer berm designed to divert surface drainage around the site, or from entering the ditch.

(d) The excavated rock will be placed a minimum of 2m from the ditch edge but the permanent condition may require a greater distance to allow for a final clay or clay/silt cover depending on the sampling system designed.

(e) The excavated rock may be placed at a maximum slope of 2H:1V.

(f) Not later than 1 day following placement at any location all excavated rock at that location will be covered with an impermeable membrane.

(g) The membrane will be low density polyethylene such as Enviroflex 20 mil or approved equivalent. Any approved equivalent must have a design life of at least 2 years.

(h) Any plateau surface of the pile will be graded in a manner that maintains surface drainage off the membrane away from adjacent uncovered newly placed rock.

(i) The membrane may be overlapped at the top of a pile. The membrane may be overlapped on the sides of a pile provided 2m of overlap is used and graded in a manner to flow away from the overlap.

(j) The membrane must be weighted down with sand bags or equivalent to protect from wind. Piercing the membrane with anchors is not acceptable.

(k) The membrane must cover the excavated rock and end at an elevation lower than the adjacent rock so that water flows off the membrane into the ditch, without contacting the rock.

(l) Any breach of the membrane must be repaired by the Contractor within 12 hours of discovery.

Page 26: Notice of Work - British Columbia...Permitting Forum #10 held on September 11, 2018 in Fort St. John. The materials source will be described in further detail at the upcoming Permitting

(m) For the duration of the contract the Contractor must sample the water discharged from the perimeter ditch monthly and provide the results to the Ministry Representative within one week of the test results being available. Water discharged from the location of the PAG disposal site must meet the water quality requirements of the CEMP.

The permanent storage shall, at a minimum, include the following:

(n) In all directions the excavated rock pile will be graded with positive drainage away from the pile and towards the ditch at a slope of greater than 2 %.

(o) The Contractor will construct and maintain for the duration of the Work a perimeter V-shaped ditch or perforated pipe sampling system at least 1.0m deep. The ditch will outlet to the drainage system while maintaining a minimum of 0.2m of water in the ditch when drainage is occurring. The ditch grade will have to be designed and constructed so that it does not erode. The Contractor may maintain the ditch as a water quality sampling location or may maintain a perforated pipe system or alternate collections system to allow long-term water quality sampling.

(p) The excavated PAG rock will be placed below elevation 456m.

(q) The final excavated PAG rock storage pile will be covered at the top and sides with a minimum thickness of 2.0m of clay or clay/silt with a fines content greater than 50% that has been placed and compacted to the compaction specifications of SS 201.37. The clay or clay/silt cover may not be placed in freezing conditions or during rain.

(r) The membrane may not be left in place in the permanent condition. The excavated rock may not be left exposed to the atmosphere or to precipitation for more than 5 days without either the membrane or the clay or clay/silt cover of at least 2.0m thickness.

(s) In all directions the clay or clay/silt cover will be graded with positive drainage away from the pile and towards the ditch at a slope of greater than 2% but less than 20%. The top of the clay must be lower than elevation 458m. If the clay or clay/silt covers the former ditch location a perforated pipe, or alternative system, must be maintained for long-term water quality sampling.

(t) The surface of the clay or clay/silt cover will be covered with a 450 mm thick layer of gravel placed without compaction other than by placement.

(u) For the duration of the contract the Contractor must sample the water discharged from the perimeter ditch monthly and provide the results to the Ministry Representative within one week of the test results being available. Water discharged from the location of the PAG disposal site must meet the water quality requirements of the CEMP.