Note 3(2).pptx
Transcript of Note 3(2).pptx
-
8/11/2019 Note 3(2).pptx
1/63
Note 3
-
8/11/2019 Note 3(2).pptx
2/63
-
8/11/2019 Note 3(2).pptx
3/63
http://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdf
http://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdfhttp://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdf -
8/11/2019 Note 3(2).pptx
4/63
Book Rate of Return
Average income divided by average book value
over project life
Also called accounting rate of return
Components reflect tax and accounting figures,
not market values or cash flows
assetsbook
incomebookreturnofrateBook
-
8/11/2019 Note 3(2).pptx
5/63
Payback Period
Number of years before cumulative cash flow
equals initial outlay
Payback Rule
Only accept projects that pay back within desired
time frame
Ignores later year cash flows and present value offuture cash flows
-
8/11/2019 Note 3(2).pptx
6/63
Example
Find disadvantage of only taking projects with
payback period of two years or less
-
8/11/2019 Note 3(2).pptx
7/63
Example
Tool A costs $4,000. Investment will generate
$2,000 and $4,000 in cash flows for two years.
What is IRR?
0
)IRR1(
000,4
)IRR1(
000,2000,4NPV
21
%08.28IRR
-
8/11/2019 Note 3(2).pptx
8/63
-
8/11/2019 Note 3(2).pptx
9/63
Pitfall 1: Lending or Borrowing?
NPV of project increases as discount rate
increases for some cash flows
-
8/11/2019 Note 3(2).pptx
10/63
Pitfall 2: Multiple Rates of Return
Certain cash flows generate NPV = 0 at two
different discount rates
Following cash flow generates NPV = $A253 million atIRR% of 3.5% and 19.54%
-
8/11/2019 Note 3(2).pptx
11/63
-
8/11/2019 Note 3(2).pptx
12/63
Pitfall 2: Multiple Rates of Return
Project can have 0 IRR and positive NPV
-
8/11/2019 Note 3(2).pptx
13/63
Pitfall 3: Mutually Exclusive Projects
IRR sometimes ignores magnitude of project
-
8/11/2019 Note 3(2).pptx
14/63
Pitfall 4: More than One Opportunity Cost of Capital
Term Structure Assumption
Assume discount rates stable during term ofproject
Implies all funds reinvested at IRR
False assumption
-
8/11/2019 Note 3(2).pptx
15/63
While the internal rate of return (IRR) assumes thecash flows from a project are reinvested at the IRR,
the modified IRR assumes that positive cash flows
are reinvested at the firm's cost of capital, and theinitial outlays are financed at the firm's financing
cost.
Therefore, MIRR more accurately reflects the costand profitability of a project.
-
8/11/2019 Note 3(2).pptx
16/63
For example, say a two-year project with an initialoutlay of $195 and a cost of capital of 12%, will return$121 in the first year and $131 in the second year. Tofind the IRR of the project so that the net presentvalue (NPV) = 0:
NPV = 0 = -195 + 121/(1+ IRR) + 131/(1 + IRR)2
NPV = 0 when IRR = 18.66%
-
8/11/2019 Note 3(2).pptx
17/63
To calculate the MIRR of the project, we have to assume that the positivecash flows will be reinvested at the 12% cost of capital. So the futurevalue of the positive cash flows is computed as:
$121(1.12) + $131 = $266.52 = Future Value of positive cash flows at t = 2
Now you divide the future value of the cash flows by the present value ofthe initial outlay, which was $195, and find the geometric return for 2periods.
MIRR=sqrt($266.52/195) -1 = 16.91%
You can see here that the 16.91% MIRR is materially lower than the IRRof 18.66%. In this case, the IRR gives a too optimistic picture of thepotential of the project, while the MIRR gives a more realistic evaluation
of the project.
-
8/11/2019 Note 3(2).pptx
18/63
-
8/11/2019 Note 3(2).pptx
19/63
investment
NPVindexityProfitabil
-
8/11/2019 Note 3(2).pptx
20/63
Example
Select best projects for $300,000
Project NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11D 162,000 150,000 1.08
-
8/11/2019 Note 3(2).pptx
21/63
Project NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11
D 162,000 150,000 1.08
-
8/11/2019 Note 3(2).pptx
22/63
Example, continued
Select projects with highest weighted average PI WAPI (BD) = 1.01
WAPI (A) = 0.77
WAPI (BC) = 1.12
Project NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11
D 162,000 150,000 1.08
-
8/11/2019 Note 3(2).pptx
23/63
Capital Rationing
Limit set on amount of funds available for
investment
Soft Rationing
Imposed by management
Hard Rationing
Imposed by unavailability of funds in capitalmarket
-
8/11/2019 Note 3(2).pptx
24/63
Rule 1: Only Cash Flow Is Relevant
Capital Expenses
Record capital expenditures when they occur
To determine cash flow from income, add back
depreciation and subtract capital expenditure
Working Capital
Difference between companys short-termassets and liabilities
-
8/11/2019 Note 3(2).pptx
25/63
Rule 2: Estimate Cash Flows on an IncrementalBasis
Include taxes, salvage value, incidental
effects, and opportunity costs Do not confuse average with incremental
payoffs
Forecast sales today, recognize after-salescash flow to come later
Forget sunk costs
Beware of allocated overhead costs
-
8/11/2019 Note 3(2).pptx
26/63
Rule 3: Treat Inflation Consistently
Use nominal interest rates to discount
nominal cash flows
Use real interest rates to discount real cashflows
Same results from real and nominal figures
-
8/11/2019 Note 3(2).pptx
27/63
Inflation
Example
Project produces real cash flows of -$100 in year zero andthen $35, $50, and $30 in three following years. Nominaldiscount rate is 15% and inflation rate is 10%. What isNPV?
045.110.1
15.11rateinflation+1
ratediscountnominal+1
=ratediscountReal
-
8/11/2019 Note 3(2).pptx
28/63
-
8/11/2019 Note 3(2).pptx
29/63
Inflation
ExampleReal figures
50.5$
26.29=30345.79=502
33.49=351
[email protected]%FlowCashYear
3
2
1.045
30
1.045
50
1.045
35
=
-
8/11/2019 Note 3(2).pptx
30/63
Separate Investment and Financing Decisions
Regardless of financing, treat cash outflows
required for project as coming from investors
Regardless of financing, treat cash inflows as
going to investors
-
8/11/2019 Note 3(2).pptx
31/63
-
8/11/2019 Note 3(2).pptx
32/63
-
8/11/2019 Note 3(2).pptx
33/63
-
8/11/2019 Note 3(2).pptx
34/63
NPV Using Nominal Cash Flows
$3,520,000or,520,3
20.1
444,3
20.1
110,6
20.1
136,10
20.1
685,10
20.1
205,6
20.1
381,2
20.1
630,1600,12NPV
76
5432
-
8/11/2019 Note 3(2).pptx
35/63
-
8/11/2019 Note 3(2).pptx
36/63
-
8/11/2019 Note 3(2).pptx
37/63
-
8/11/2019 Note 3(2).pptx
38/63
Problem 1: Investment Timing Decision
Some projects are more valuable if undertaken in
the future
Examine start dates (t) for investment and
calculate net future value for each date
Discount net values back to present
-
8/11/2019 Note 3(2).pptx
39/63
Problem 2: Choice between Long- and Short-Term Equipment
Example
Given the following cash flows from operating two
machines and a 6% cost of capital, which machine hasthe higher value using the equivalent annual annuitymethod?
Year
Machine 0 1 2 3 PV@6% E.A.A.A +15 +5 +5 +5 28.37 10.61
B +10 +6 +6 21.00 11.45
E =
1(1+)
-
8/11/2019 Note 3(2).pptx
40/63
Equivalent Annual Cash Flow, Inflation, andTechnological Change
Inflation increases nominal costs of operatingequipment, but real costs remain unchanged
Real cash flows are not always constant
-
8/11/2019 Note 3(2).pptx
41/63
Equivalent Annual Cash Flow and Taxes
Lifetime costs should be calculated after tax
Operating costs are tax-deductible Capital investment generates depreciation tax
shields
-
8/11/2019 Note 3(2).pptx
42/63
Problem 3: When to Replace an Old Machine
Example
A machine is expected to produce a net inflow of $4,000this year and $4,000 next year before breaking. You canreplace it now with a machine that costs $15,000 and willproduce an inflow of $8,000 per year for three years.Should you replace now or wait a year?
-
8/11/2019 Note 3(2).pptx
43/63
Problem 3: When to Replace an Old Machine
Example, continued
-
8/11/2019 Note 3(2).pptx
44/63
Problem 4: Cost of Excess Capacity
Example
A computer system costs $500,000 to buy andoperate at a discount rate of 6% and lasts fiveyears
Equivalent annual cost of $118,700
Undertaking project in year 4 has a present value of118,700/(1.06)4, or about $94,000
-
8/11/2019 Note 3(2).pptx
45/63
Types of Analysis
Sensitivity Analyzes effects of changes in sales, costs, etc., on project
Scenario Project analysis given particular combination of assumptions
Simulation Estimates probabilities of different outcomes
Break Even Level of sales (or other variable) at which project breaks even
-
8/11/2019 Note 3(2).pptx
46/63
Example
Given expected cash-flow forecasts for Otobai
Companys Motor Scooter project, determine theNPV of project given changes in cash- flow
components using 10% cost of capital. Assume
constant variables, except the one you are
changing.
-
8/11/2019 Note 3(2).pptx
47/63
Example, continued
315-FlowCashNet
3.0flowcashOperating
1.5after taxProfit
1.550%@Taxes
3.0profitPretax
1.5onDepreciati
3costsFixed
30costsVariable
37.5Sales
15-Investment
10-1Years0Year
-
8/11/2019 Note 3(2).pptx
48/63
Example, continued
bil2bil3bil4costFixed
275,000300,000360,000costUnit var380,000375,000350,000priceUnit
.16.1.04shareMarket
mil1.1mil1.0mil.9sizeMarket
OptimisticExpectedcPessimistiVariable
Outcomes
-
8/11/2019 Note 3(2).pptx
49/63
Example, continued
NPV calculationsOptimistic scenario
3.3815-FlowCashNet
3.38flowcashOperating
1.88after taxProfit
1.8850%@Taxes
3.75profitPretax
1.5onDepreciati
3costsFixed
33costsVariable
41.25Sales15-Investment
10-1Years0Year
-
8/11/2019 Note 3(2).pptx
50/63
Modeling Process
Step 1: Model Project
Step 2: Specify Probabilities
Step 3: Simulate Cash Flows
Step 4: Calculate Present Value
-
8/11/2019 Note 3(2).pptx
51/63
Decision Trees
Diagram of sequential decisions and possible
outcomes
Help companies analyze options by showingvarious choices and outcomes
Option to avoid a loss or produce extra profit has
value Ability to create option has value that can be
bought or sold
-
8/11/2019 Note 3(2).pptx
52/63
-
8/11/2019 Note 3(2).pptx
53/63
Real Options
Option to expand
Option to abandon
Timing option
Flexible production facilities
-
8/11/2019 Note 3(2).pptx
54/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)$ 100 (.80)
$ 0 (.20)
InvestYes / No
NPV= ?
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
-
8/11/2019 Note 3(2).pptx
55/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= ?
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
-
8/11/2019 Note 3(2).pptx
56/63
$700 (.80)
$ 0 (.20)
$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes /
NoNPV= ?
-$18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
56020.080.700
-
8/11/2019 Note 3(2).pptx
57/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= ?
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
295
096.1
560130(upside)NPV
3
NPV = $295
-
8/11/2019 Note 3(2).pptx
58/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= ?
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
NPV = $295
NPV = $52
NPV = - $69(do not invest, so NPV = 0)
-
8/11/2019 Note 3(2).pptx
59/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= ?
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
NPV = $295
NPV = $52
NPV = - $69(do not invest, so NPV =
0)
83$
096.1)25.295()5.52()25.0(NPV 2
NPV = $83
-
8/11/2019 Note 3(2).pptx
60/63
$700 (.80)
$ 0 (.20)$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= $19
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
NPV = $295
NPV = $52
NPV = - $69(do not invest, so NPV = 0)
NPV = $83
19$
)056(.)8344(.18NPV
-
8/11/2019 Note 3(2).pptx
61/63
$700 (.80)
$ 0 (.20)
$ 300 (.80)
$ 0 (.20)
$ 100 (.80)
$ 0 (.20)
560
240
80
InvestYes / No
NPV= $19
- $18
- $130
- $130
- $130
.25
.50
.25
$ 0
.44
.56
NPV = $295
NPV = $52
NPV = - $69(do not invest, so NPV = 0)
NPV = $83
-
8/11/2019 Note 3(2).pptx
62/63
Boyne mountain resort
-
8/11/2019 Note 3(2).pptx
63/63
Chapter 5
9, 12, 14 15
Chapter 6 19, 21,26