Note 3(2).pptx

download Note 3(2).pptx

of 63

Transcript of Note 3(2).pptx

  • 8/11/2019 Note 3(2).pptx

    1/63

    Note 3

  • 8/11/2019 Note 3(2).pptx

    2/63

  • 8/11/2019 Note 3(2).pptx

    3/63

    http://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdf

    http://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdfhttp://faculty.fuqua.duke.edu/~charvey/Research/Published_Papers/P67_The_theory_and.pdf
  • 8/11/2019 Note 3(2).pptx

    4/63

    Book Rate of Return

    Average income divided by average book value

    over project life

    Also called accounting rate of return

    Components reflect tax and accounting figures,

    not market values or cash flows

    assetsbook

    incomebookreturnofrateBook

  • 8/11/2019 Note 3(2).pptx

    5/63

    Payback Period

    Number of years before cumulative cash flow

    equals initial outlay

    Payback Rule

    Only accept projects that pay back within desired

    time frame

    Ignores later year cash flows and present value offuture cash flows

  • 8/11/2019 Note 3(2).pptx

    6/63

    Example

    Find disadvantage of only taking projects with

    payback period of two years or less

  • 8/11/2019 Note 3(2).pptx

    7/63

    Example

    Tool A costs $4,000. Investment will generate

    $2,000 and $4,000 in cash flows for two years.

    What is IRR?

    0

    )IRR1(

    000,4

    )IRR1(

    000,2000,4NPV

    21

    %08.28IRR

  • 8/11/2019 Note 3(2).pptx

    8/63

  • 8/11/2019 Note 3(2).pptx

    9/63

    Pitfall 1: Lending or Borrowing?

    NPV of project increases as discount rate

    increases for some cash flows

  • 8/11/2019 Note 3(2).pptx

    10/63

    Pitfall 2: Multiple Rates of Return

    Certain cash flows generate NPV = 0 at two

    different discount rates

    Following cash flow generates NPV = $A253 million atIRR% of 3.5% and 19.54%

  • 8/11/2019 Note 3(2).pptx

    11/63

  • 8/11/2019 Note 3(2).pptx

    12/63

    Pitfall 2: Multiple Rates of Return

    Project can have 0 IRR and positive NPV

  • 8/11/2019 Note 3(2).pptx

    13/63

    Pitfall 3: Mutually Exclusive Projects

    IRR sometimes ignores magnitude of project

  • 8/11/2019 Note 3(2).pptx

    14/63

    Pitfall 4: More than One Opportunity Cost of Capital

    Term Structure Assumption

    Assume discount rates stable during term ofproject

    Implies all funds reinvested at IRR

    False assumption

  • 8/11/2019 Note 3(2).pptx

    15/63

    While the internal rate of return (IRR) assumes thecash flows from a project are reinvested at the IRR,

    the modified IRR assumes that positive cash flows

    are reinvested at the firm's cost of capital, and theinitial outlays are financed at the firm's financing

    cost.

    Therefore, MIRR more accurately reflects the costand profitability of a project.

  • 8/11/2019 Note 3(2).pptx

    16/63

    For example, say a two-year project with an initialoutlay of $195 and a cost of capital of 12%, will return$121 in the first year and $131 in the second year. Tofind the IRR of the project so that the net presentvalue (NPV) = 0:

    NPV = 0 = -195 + 121/(1+ IRR) + 131/(1 + IRR)2

    NPV = 0 when IRR = 18.66%

  • 8/11/2019 Note 3(2).pptx

    17/63

    To calculate the MIRR of the project, we have to assume that the positivecash flows will be reinvested at the 12% cost of capital. So the futurevalue of the positive cash flows is computed as:

    $121(1.12) + $131 = $266.52 = Future Value of positive cash flows at t = 2

    Now you divide the future value of the cash flows by the present value ofthe initial outlay, which was $195, and find the geometric return for 2periods.

    MIRR=sqrt($266.52/195) -1 = 16.91%

    You can see here that the 16.91% MIRR is materially lower than the IRRof 18.66%. In this case, the IRR gives a too optimistic picture of thepotential of the project, while the MIRR gives a more realistic evaluation

    of the project.

  • 8/11/2019 Note 3(2).pptx

    18/63

  • 8/11/2019 Note 3(2).pptx

    19/63

    investment

    NPVindexityProfitabil

  • 8/11/2019 Note 3(2).pptx

    20/63

    Example

    Select best projects for $300,000

    Project NPV Investment PI

    A 230,000 200,000 1.15

    B 141,250 125,000 1.13

    C 194,250 175,000 1.11D 162,000 150,000 1.08

  • 8/11/2019 Note 3(2).pptx

    21/63

    Project NPV Investment PI

    A 230,000 200,000 1.15

    B 141,250 125,000 1.13

    C 194,250 175,000 1.11

    D 162,000 150,000 1.08

  • 8/11/2019 Note 3(2).pptx

    22/63

    Example, continued

    Select projects with highest weighted average PI WAPI (BD) = 1.01

    WAPI (A) = 0.77

    WAPI (BC) = 1.12

    Project NPV Investment PI

    A 230,000 200,000 1.15

    B 141,250 125,000 1.13

    C 194,250 175,000 1.11

    D 162,000 150,000 1.08

  • 8/11/2019 Note 3(2).pptx

    23/63

    Capital Rationing

    Limit set on amount of funds available for

    investment

    Soft Rationing

    Imposed by management

    Hard Rationing

    Imposed by unavailability of funds in capitalmarket

  • 8/11/2019 Note 3(2).pptx

    24/63

    Rule 1: Only Cash Flow Is Relevant

    Capital Expenses

    Record capital expenditures when they occur

    To determine cash flow from income, add back

    depreciation and subtract capital expenditure

    Working Capital

    Difference between companys short-termassets and liabilities

  • 8/11/2019 Note 3(2).pptx

    25/63

    Rule 2: Estimate Cash Flows on an IncrementalBasis

    Include taxes, salvage value, incidental

    effects, and opportunity costs Do not confuse average with incremental

    payoffs

    Forecast sales today, recognize after-salescash flow to come later

    Forget sunk costs

    Beware of allocated overhead costs

  • 8/11/2019 Note 3(2).pptx

    26/63

    Rule 3: Treat Inflation Consistently

    Use nominal interest rates to discount

    nominal cash flows

    Use real interest rates to discount real cashflows

    Same results from real and nominal figures

  • 8/11/2019 Note 3(2).pptx

    27/63

    Inflation

    Example

    Project produces real cash flows of -$100 in year zero andthen $35, $50, and $30 in three following years. Nominaldiscount rate is 15% and inflation rate is 10%. What isNPV?

    045.110.1

    15.11rateinflation+1

    ratediscountnominal+1

    =ratediscountReal

  • 8/11/2019 Note 3(2).pptx

    28/63

  • 8/11/2019 Note 3(2).pptx

    29/63

    Inflation

    ExampleReal figures

    50.5$

    26.29=30345.79=502

    33.49=351

    [email protected]%FlowCashYear

    3

    2

    1.045

    30

    1.045

    50

    1.045

    35

    =

  • 8/11/2019 Note 3(2).pptx

    30/63

    Separate Investment and Financing Decisions

    Regardless of financing, treat cash outflows

    required for project as coming from investors

    Regardless of financing, treat cash inflows as

    going to investors

  • 8/11/2019 Note 3(2).pptx

    31/63

  • 8/11/2019 Note 3(2).pptx

    32/63

  • 8/11/2019 Note 3(2).pptx

    33/63

  • 8/11/2019 Note 3(2).pptx

    34/63

    NPV Using Nominal Cash Flows

    $3,520,000or,520,3

    20.1

    444,3

    20.1

    110,6

    20.1

    136,10

    20.1

    685,10

    20.1

    205,6

    20.1

    381,2

    20.1

    630,1600,12NPV

    76

    5432

  • 8/11/2019 Note 3(2).pptx

    35/63

  • 8/11/2019 Note 3(2).pptx

    36/63

  • 8/11/2019 Note 3(2).pptx

    37/63

  • 8/11/2019 Note 3(2).pptx

    38/63

    Problem 1: Investment Timing Decision

    Some projects are more valuable if undertaken in

    the future

    Examine start dates (t) for investment and

    calculate net future value for each date

    Discount net values back to present

  • 8/11/2019 Note 3(2).pptx

    39/63

    Problem 2: Choice between Long- and Short-Term Equipment

    Example

    Given the following cash flows from operating two

    machines and a 6% cost of capital, which machine hasthe higher value using the equivalent annual annuitymethod?

    Year

    Machine 0 1 2 3 PV@6% E.A.A.A +15 +5 +5 +5 28.37 10.61

    B +10 +6 +6 21.00 11.45

    E =

    1(1+)

  • 8/11/2019 Note 3(2).pptx

    40/63

    Equivalent Annual Cash Flow, Inflation, andTechnological Change

    Inflation increases nominal costs of operatingequipment, but real costs remain unchanged

    Real cash flows are not always constant

  • 8/11/2019 Note 3(2).pptx

    41/63

    Equivalent Annual Cash Flow and Taxes

    Lifetime costs should be calculated after tax

    Operating costs are tax-deductible Capital investment generates depreciation tax

    shields

  • 8/11/2019 Note 3(2).pptx

    42/63

    Problem 3: When to Replace an Old Machine

    Example

    A machine is expected to produce a net inflow of $4,000this year and $4,000 next year before breaking. You canreplace it now with a machine that costs $15,000 and willproduce an inflow of $8,000 per year for three years.Should you replace now or wait a year?

  • 8/11/2019 Note 3(2).pptx

    43/63

    Problem 3: When to Replace an Old Machine

    Example, continued

  • 8/11/2019 Note 3(2).pptx

    44/63

    Problem 4: Cost of Excess Capacity

    Example

    A computer system costs $500,000 to buy andoperate at a discount rate of 6% and lasts fiveyears

    Equivalent annual cost of $118,700

    Undertaking project in year 4 has a present value of118,700/(1.06)4, or about $94,000

  • 8/11/2019 Note 3(2).pptx

    45/63

    Types of Analysis

    Sensitivity Analyzes effects of changes in sales, costs, etc., on project

    Scenario Project analysis given particular combination of assumptions

    Simulation Estimates probabilities of different outcomes

    Break Even Level of sales (or other variable) at which project breaks even

  • 8/11/2019 Note 3(2).pptx

    46/63

    Example

    Given expected cash-flow forecasts for Otobai

    Companys Motor Scooter project, determine theNPV of project given changes in cash- flow

    components using 10% cost of capital. Assume

    constant variables, except the one you are

    changing.

  • 8/11/2019 Note 3(2).pptx

    47/63

    Example, continued

    315-FlowCashNet

    3.0flowcashOperating

    1.5after taxProfit

    1.550%@Taxes

    3.0profitPretax

    1.5onDepreciati

    3costsFixed

    30costsVariable

    37.5Sales

    15-Investment

    10-1Years0Year

  • 8/11/2019 Note 3(2).pptx

    48/63

    Example, continued

    bil2bil3bil4costFixed

    275,000300,000360,000costUnit var380,000375,000350,000priceUnit

    .16.1.04shareMarket

    mil1.1mil1.0mil.9sizeMarket

    OptimisticExpectedcPessimistiVariable

    Outcomes

  • 8/11/2019 Note 3(2).pptx

    49/63

    Example, continued

    NPV calculationsOptimistic scenario

    3.3815-FlowCashNet

    3.38flowcashOperating

    1.88after taxProfit

    1.8850%@Taxes

    3.75profitPretax

    1.5onDepreciati

    3costsFixed

    33costsVariable

    41.25Sales15-Investment

    10-1Years0Year

  • 8/11/2019 Note 3(2).pptx

    50/63

    Modeling Process

    Step 1: Model Project

    Step 2: Specify Probabilities

    Step 3: Simulate Cash Flows

    Step 4: Calculate Present Value

  • 8/11/2019 Note 3(2).pptx

    51/63

    Decision Trees

    Diagram of sequential decisions and possible

    outcomes

    Help companies analyze options by showingvarious choices and outcomes

    Option to avoid a loss or produce extra profit has

    value Ability to create option has value that can be

    bought or sold

  • 8/11/2019 Note 3(2).pptx

    52/63

  • 8/11/2019 Note 3(2).pptx

    53/63

    Real Options

    Option to expand

    Option to abandon

    Timing option

    Flexible production facilities

  • 8/11/2019 Note 3(2).pptx

    54/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)$ 100 (.80)

    $ 0 (.20)

    InvestYes / No

    NPV= ?

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

  • 8/11/2019 Note 3(2).pptx

    55/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= ?

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

  • 8/11/2019 Note 3(2).pptx

    56/63

    $700 (.80)

    $ 0 (.20)

    $ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes /

    NoNPV= ?

    -$18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    56020.080.700

  • 8/11/2019 Note 3(2).pptx

    57/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)$ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= ?

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    295

    096.1

    560130(upside)NPV

    3

    NPV = $295

  • 8/11/2019 Note 3(2).pptx

    58/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= ?

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    NPV = $295

    NPV = $52

    NPV = - $69(do not invest, so NPV = 0)

  • 8/11/2019 Note 3(2).pptx

    59/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= ?

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    NPV = $295

    NPV = $52

    NPV = - $69(do not invest, so NPV =

    0)

    83$

    096.1)25.295()5.52()25.0(NPV 2

    NPV = $83

  • 8/11/2019 Note 3(2).pptx

    60/63

    $700 (.80)

    $ 0 (.20)$ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= $19

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    NPV = $295

    NPV = $52

    NPV = - $69(do not invest, so NPV = 0)

    NPV = $83

    19$

    )056(.)8344(.18NPV

  • 8/11/2019 Note 3(2).pptx

    61/63

    $700 (.80)

    $ 0 (.20)

    $ 300 (.80)

    $ 0 (.20)

    $ 100 (.80)

    $ 0 (.20)

    560

    240

    80

    InvestYes / No

    NPV= $19

    - $18

    - $130

    - $130

    - $130

    .25

    .50

    .25

    $ 0

    .44

    .56

    NPV = $295

    NPV = $52

    NPV = - $69(do not invest, so NPV = 0)

    NPV = $83

  • 8/11/2019 Note 3(2).pptx

    62/63

    Boyne mountain resort

  • 8/11/2019 Note 3(2).pptx

    63/63

    Chapter 5

    9, 12, 14 15

    Chapter 6 19, 21,26