NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Facilities Construction
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION
2010 BOND
July 2014
Boldt Elementary School
BERNAL MIDDLE SCHOOL (Formerly STEVENS RANCH AREA MIDDLE SCHOOL)
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke, Inc. Construction Budget - $41,408,415.00 Construction Period - January 2013 – May 2014 Project Scope – New 1200 Student Middle School (97% Complete) Project was substantially complete on June 2, 2014. Punch list completion is in progress.
ELLISON ELEMENTARY SCHOOL (Formerly CIELO VISTA SOUTH ELEMENTARY)
Architect – Garza Bomberger Architects Project Architect – Roy Lewis, AIA NISD Project Manager – Marilyn Sevedge CM @ Risk Contractor – Joeris General Contractor Construction Budget - $19,877,127.00 Construction Period - February 2013 – May 19, 2014 (98% Complete) Project Scope – 800 Student Elementary School Certificate of Occupancy issued May 20, 2014. Intrusion alarm installed. Additional PR’s in progress. 100% Completion of Substantial Completion Punch List, Landscaping and Commissioning in Progress.
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH)
Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Thomas Curiel Contractor – Joeris General Contractor Construction Budget - $20,000,000.00 Construction Period – February 2014 – May 22, 2015 (7% Complete) Project Scope – New 800 Student Elementary School Building layout, steel erection and building pad in progress.
INSELMANN BASEBALL FIELD (Replacement of Existing Facilities)
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis, AIA NISD Project Manager – Christopher Parker Contractor – D. Wilson Construction Construction Budget - $2,700,000.00 Construction Period – May 2014 – December 2014 (3% Complete) Project Scope – Replacement of Existing Field and associated Facilities.
Demolition complete. Site work in Progress.
OAK HILLS ELEMENTARY SCHOOL - Art Room
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – Rohde General Contracting Construction Budget - $300,000.00 Construction Period – May 2014 – August 2014 (5% Complete) Project Scope – Provide a new Art Room to meet current NISD standards Schematic Design Approved by Building Committee. Construction started June 9, 2014.
Demolition is complete. Plumbing rough-in in progress. Electrical in progress and interior framing is complete. Exterior concrete in progress.
SPORTS GYM
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $19,000,000.00 Construction Period - October 2014 – October 2015 Project Scope – Provide a District-Wide Sports Gymnasium at the Farris Complex. Design only project at this time.
Funding - Project to be funded from 2010 Bond Savings.
KALLISON RANCH HIGH SCHOOL
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor Estimated Construction Budget - $105,000,000.00 Tenative Construction Period – September 2014 – May 2017 Project Scope – New 2800 Student High School Design is 95% complete. Construction Budget - $105,000,000.00 in 2014 Bond