7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
1/24
East-West Gateway Council of GovernmentsSeptember 26, 2007
Northside and SouthsideMajor Transit Improvements
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
2/24
Summary of Northside Alignments
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
3/24
Summary of Downtown Alignments
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
4/24
Summary of Southside Alignments
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
5/24
Community Engagement
40 stakeholderinterviews
100+ outreachpresentations to 1,700citizens
Three rounds of publicopen houses
E-mail list of 600
Three issues ofnewsletter to 1,650citizens
300+ written comments
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
6/24
Street-Running LRT
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
7/24
Street-Running LRT
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
8/24
Street-Running LRT
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
9/24
Prototypical Station Plans In Roadway ROW, Far-Side Platforms
Street-Running LRT Stations
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
10/24
Prototypical Station Section in 100+ ROW
Street-Running LRT Station
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
11/24
Northside
Natural Bridge Avenue/14th
Street Alternative
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
12/24
Northside:Key Differentiators
Runs through core of Northside residential,commercial development
Existing new development and LRT can worktogether to promote future development
Serves only significant Northside employmentcenter, Union-70
Provides good connectivity to future westernextension
No major right-of-way impacts
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
13/24
Downtown
9th
Street/10th
Street Couplet Alternative
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
14/24
Downtown:Key Differentiators
Provides most direct north-south travel in
downtown
Avoids track, operational complexity
Serves existing residences and businesses Provides direct access to employment and
activity centers
Provides transit access to developmentssouth of Market
Avoids serious property impacts
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
15/24
Southside -
Jefferson Avenue/Interstate-55Alternative
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
16/24
Existing development strongly transit-
supportive (high-densityresidential/neighborhood commercial)
Major transit-supportive development projects
planned or under construction
Strong transit-dependent markets
Serves development along Chouteau
Most direct end-to-end access
High speed along I-55 improves travel times,attractiveness for extension
Southside:Key Differentiators
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
17/24
Capital Costs (2007 Million $)
Total cost for LPA $971 Million
Route miles 16.8 Miles
Cost/route mile $57.8 Million
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
18/24
Ridership:Process
Aggregate Rail Ridership Forecasting (ARRF)
Application of the TransEval model
Preliminary ridership forecasts
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
19/24
Rail Ridership Forecasting
No Special Events
Draft
FTA review
Northside/Downtown/Southside Alignment:
9,300-12,700 weekday boardings
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
20/24
LPA: Northside
Potential Development Opportunity at North
Florissant Boulevard and St. Louis Avenue
Existing Conditionson North Florissant Boulevard
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
21/24
LPA: Downtown
Potential Development Opportunity at
Convention Plaza and Tucker Boulevard
Existing Conditionson Convention Plaza
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
22/24
LPA: Southside
Potential Development Opportunity at
Gravois Road and Jefferson Avenue
Existing Conditions at intersectionof Gravois and Jefferson
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
23/24
Locally-Preferred Alternative:Key Points
Recommendation October 31 Single LPA
Not necessarily next LRT extension
Getting LRT to Northside
Ridership subject to revision; FTA review
Street-running LRT: new operationalparadigm
-
7/29/2019 Northside and Southside Major Transit Improvements: East-West Gateway Council of Governments September 26, 2007
24/24
Potential Next Steps
Draft Environmental Impact Statement
New Starts application
Preliminary engineering