Northern Burlington County Regional School District Board ...

38
Northern Burlington County Regional School District Board of Education Update 2018 Referendum Projects August 16, 2021

Transcript of Northern Burlington County Regional School District Board ...

Page 1: Northern Burlington County Regional School District Board ...

Northern Burlington County

Regional School District

Board of Education Update

2018 Referendum Projects

August 16, 2021

Page 2: Northern Burlington County Regional School District Board ...

Projects Status

Current Projects

•5086.3A – Phase 1 - Health and Training Center – 98% Complete

•5086.4 – Phase 2 - Main Addition (New construction)– Substantially Complete

•5086.4 – Phase 2 - Summer 2020 Renovations – Complete

•5086.5 – Phase 3 - 400/500 Connector – Substantially Complete

•5086.5 – Phase 3 – Summer 2021 Renovations – 60% Complete

•5086.6 – Phase 4 - HVAC Renovations – Complete

•5086.7 – Partial Reroofing –Substantially Complete

•5086.8 – Greenhouse – 80% Complete

•5086.9 – Parking Lot / Old Building Demo –

40% Complete

2

Page 3: Northern Burlington County Regional School District Board ...

Projects Status

Current Projects

• Construction Progress Meetings are held every other Thursday morning and are held in

the new Media Center

• All personnel on site have been instructed to wear masks whenever in proximity to

District Staff

3

Page 4: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.3A – Health and Training Center(Five Prime Contractors)

General Construction – Arthur Ogren

HVAC - Driscoll Mechanical

Structural Steel – Southern New Jersey Steel

Plumbing – Annese Mechanical

Electrical – QPI Electric

• Project is 98% complete – Waiting for wood doors and terrazzo

patching (currently underway)

• Interior renovations that are part of this contract are nearly

complete (Classroom renovations and restrooms)

4

Page 5: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.3A – Health and Training Center

Exterior View from Baseball Field

5

Page 6: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.3A – Health and Training Center

Inside View – Cleaning in Progress

6

Page 7: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.4 – Main Connector Addition/Renovations(Five Prime Contractors)

General Construction – Arthur Ogren

Structural Steel – Southern New Jersey Steel

Plumbing – Annese Mechanical

HVAC – Preferred Mechanical

Electric – QPI Electric

• Project is Substantially Complete

• Remaining new construction work to be complete this month (Site, Roof

Metal, Millwork)

7

Page 8: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.4 – Main Connector Additions

West Cafeteria Expansion Complete

8

Page 9: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.4 – Main Connector Addition

West Cafeteria Expansion

9

Page 10: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.4 – Main Connector Addition

West Cafeteria Expansion

10

Page 11: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.4 – Main Connector Addition

West Kitchen Expansion

11

Page 12: Northern Burlington County Regional School District Board ...

Project Photos

Front Entrance of Main Addition Final Metal Work

12

Page 13: Northern Burlington County Regional School District Board ...

Project Photos

New Media Center

13

Page 14: Northern Burlington County Regional School District Board ...

Project Photo

North Side of New Media Center

14

Page 15: Northern Burlington County Regional School District Board ...

Project Photos

Loading Dock at Rear of Main Addition

15

Page 16: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.5 – 400/500 Connector Addition(Five Prime Contractors)

General Construction – Arthur Ogren

Structural Steel – Mastercraft Iron

Plumbing – Three G’s Plumbing

Electric – QPI Electric

HVAC - Preferred Mechanical

• Addition is Substantially Complete with minor issues to address

16

Page 17: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.5 – Phase 3 (400/500 Connector) Addition

View from West Parking Lot

17

Page 18: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 (400/500 Connector) Addition

Finished Choral Room

18

Page 19: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 (400/500 Connector) Addition

Early Childhood Development Room

19

Page 20: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.5 – Phase 3 – Summer 2021 Renovations

• June 21, 2021 - Summer Renovation Work Began

• August 27, 2021 – Substantial Completion

Scope of Renovations

• Rooms 203, 205, 306, 307, and 308 are complete and have been

turned over to District

• New Guidance Offices have been turned over to the District

20

Page 21: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.5 – Phase 3 – Summer 2021 Renovations

• Extensive renovations continue in 100, 200, 300 and 700 Corridor

Classrooms

• 600 Corridor Restrooms (new) are 80% Complete

• HVAC renovations continue in East Cafeteria, Art Room and 700

Classrooms

21

Page 22: Northern Burlington County Regional School District Board ...

Project Scope

Project 5086.5 – Phase 3 – Summer 2021 Renovations

22

Page 23: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

700 Wing Renovation

23

Page 24: Northern Burlington County Regional School District Board ...

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

24

Page 25: Northern Burlington County Regional School District Board ...

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

25

Page 26: Northern Burlington County Regional School District Board ...

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

26

Page 27: Northern Burlington County Regional School District Board ...

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

27

Page 28: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

600 Wing Restroom Tile (Old Faculty Room)

28

Page 29: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

Old Media Center Conversion to Board Offices

29

Page 30: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

New Air Handler Unit in 500 Building

30

Page 31: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

Floor Trenches for Science Lab Utilities

31

Page 32: Northern Burlington County Regional School District Board ...

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

New Casework in Room 203

32

Page 33: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.6 – HVAC Renovations

HVAC - Preferred Mechanical

• Project is in close-out phase

• Systems are operating well

• Preferred Mechanical has responded quickly to a minimal number of issues

33

Page 34: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.7 – Partial Roof Replacement

Contractor - Winchester Roofing

• Project is Substantially Complete

• Contractor has some punch list items to complete and is working with the

HVAC Contractor flashing curbs for new roof top units

34

Page 35: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.8 – Greenhouse Project

Contractor – Aliano Brothers

• New Greenhouse is 80% - anticipated completion 9/1/2021

35

Page 36: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.8 – Greenhouse Project

36

Page 37: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.8 – Greenhouse Project

• Building concrete, masonry, framing and roofing are complete

• Exterior wall glazing is 85% complete

• Mechanical, Plumbing and Electrical rough-in are 50% complete

• Energy curtains are on site for installation

37

Page 38: Northern Burlington County Regional School District Board ...

Project Summary

Project 5086.9 – Parking Lot and Demolition of Old

Buildings

• Underground gas, sanitary and water lines are complete

• Rainwater piping is being installed

• Concrete curbs are being formed and poured

• Final paving and finishes may be completed