North Shore Wastewater Treatment PlantPROJECT UPDATE
Joan LiuSENIOR PROJECT ENGINEER
Tom Sadleir POLICY COORDINATOR, PUBLIC INVOLVEMENT
North Shore Waterfront Liaison Committee, September 14, 2017
North Shore Waterfront Liaison Committee
October 22,2015
Lions Gate Secondary Wastewater Treatment Plant
PROJECT UPDATEAndrea Winkler, Program Manager, Public Involvement
Paul Dufault, P.Eng., Project Manager
3
Regulatory Driven
• Integrated Liquid Waste and
Resource Management Plan - 2011
• Wastewater Systems Effluent
Regulations – 2012
• Secondary Treatment by
December 31, 2020
4North Shore Wastewater Treatment Program
3 Components:• North Shore WWTP
• New Conveyance
(Pump Station + Pipes)
• Decommissioning of existing
LGWWTP
5
• Acciona Infrastructure Canada
• Operating in Canada since 2001
• Head Office in Vancouver
• 9 Major Infrastructure Projects in Canada including 5 P3 Projects worth over $ 4.3 Billion
• Acciona Agua S.A.
• Design, Build, Finance and Operation of Water and Wastewater Plants
• Over 300 WWTPs
• 35 P3 Type water sector projects
ADApT Consortium
6
7
Remediation
8
Stone Column
9
NSWWTP Project Schedule
10
Conveyance
11
Pump Station
12
Pipes
13
Request for Qualification
• The purpose is to invite interested parties to submit responses indicating their interest in, and qualifications for the Project.
• Based on the responses a shortlist of up to 3 Proponents will be invited to participate in the Request for Proposals stage
Closing
Aug 17 2017
14
Request for Proposals
• Shortlisted Respondents from the RFQ stage will be invited to submit proposals that will include technical and financial aspects of the project.
• RFP Process is to include collaborative discussion relating to technical and commercial matters.
• The objective is to select the Preferred Proponent who may be offered the opportunity to enter in to the Project Agreement
Sep 27 2017
Activity
NSWWTP Design Build Finance RFP
NSWWTP Design Build
Secondary Effluent
NSWWTP Commissioning and
Handover
Conveyance Indicative Design
Property Acquisition
Conveyance Design Build RFQ
Conveyance Design Build RFP
Pump Station Design/Construction
Pipeline Design/Construction
Conveyance System Commissioning
Decommissioning Existing Lions Gate
WWTP
2020 20212016 2017 2018 2019
Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Overall Program Schedule
Consultation and Communications
North Shore Wastewater Treatment Plant
Metro Vancouver activity since October 2015• Dec 2015 Education Workshop• Feb 2016 Norgate Open House – Project Update• Dec 2016 Newsletter – Project Update• Apr 2017 Letters to First Nations
Lions Gate Public Advisory Committee – Phase 2• 6 meetings to April 2017 (plant design and opportunities; tour of US facility;
construction mitigation, traffic management)
Consultation and Communications
North Shore Wastewater Treatment Plant (continued)
April 2017: Project Agreement with ACCIONA• ACCIONA assumes responsibility for communications planning,
community relations, consultation
ACCIONA• Introduced at final LGPAC meeting• May 18, 2017 Open House – Public Impact Mitigation Plan• June 21, 2017 Open House – DNV Development Permit process• Pre-construction activity notification• Ongoing communications
18
Pump Station + Pipes
Questions